1 Introduction & Exam Overview

1.1 Current Exam Facts 1.2 Open-Reference Strategy & Permitted Materials 1.3 Electrician Registration Pathway & Limits of Work 1.4 Which Editions Apply: ESR Schedule 2 & the 13 November 2025 Update

2 Electricity Act & EWRB Framework

2.1 Electricity Act 1992 Framework 2.2 EWRB Role, Register & Registration Classes 2.3 Practising Licence & Electrician Limits of Work

3 Electricity (Safety) Regulations 2010

3.1 ESR 2010 Structure & Key Definitions 3.2 Electrically Safe & Electrically Unsafe 3.3 Duties of Electrical Workers & Competence 3.4 Certification Timeframes & Notification Duties under ESR

4 Prescribed Electrical Work

4.1 What Is Prescribed Electrical Work 4.2 PEW Risk Categories: Low, General, High 4.3 Who May Carry Out and Supervise PEW 4.4 High-Risk Work & Electrical Inspector Requirements

5 Certification Documents (CoC, ESC, RoI)

5.1 Certificate of Compliance (Regulation 65) 5.2 Electrical Safety Certificate (Safe to Connect / Use) 5.3 Record of Inspection (Regulation 72) 5.4 Record-Keeping, Retention & the Certification Chain 5.5 Record-Keeping Duties & the Statutory Clocks (regs 72A, 74E–74H)

6 AS/NZS 3000 Fundamentals

6.1 Structure of AS/NZS 3000 & Open-Book Navigation 6.2 Multiple Earthed Neutral (MEN) System 6.3 Basic Protection vs Fault Protection 6.4 Protective Devices, Discrimination & Coordination

7 RCDs, Shock Protection & Disconnection Times

7.1 RCD Shock-Protection Requirements 7.2 RCD Types, Classification & Installation Contexts 7.3 Disconnection Times (0.4 s / 5 s) & Earth Fault Path 7.4 Damp Situations & Additional Protection

8 Circuits, Maximum Demand & Voltage Drop

8.1 Division of Circuits & Final Subcircuits 8.2 Maximum Demand Principles 8.3 Voltage Drop Requirements & Worked Examples

9 Testing & Verification Core

9.1 Visual Inspection Before Testing 9.2 Continuity of Earthing & Protective Bonding 9.3 Insulation Resistance Testing (500 V DC, 1 MΩ) 9.4 Polarity & Correct Circuit Connections

10 EFLI, RCD Tests & Verification Sequence

10.1 Earth Fault Loop Impedance 10.2 RCD Operation Tests & Prospective Fault Current 10.3 Mandatory Test Sequence & Documentation

11 Safe Isolation & Personal Safety

11.1 Physiological Effects of Current & Shock Factors 11.2 Prove–Test–Prove Safe Isolation 11.3 Lock-Out/Tag-Out & Safety Tag System 11.4 Live-Work Controls, Fault Finding & Unsafe Installations

12 Electrical Codes of Practice & Schedule 2

12.1 NZECP 34 Electrical Safe Distances 12.2 NZECP 50 Repair of Domestic Electrical Equipment 12.3 NZECP 51 Electrical Wiring Work in Domestic Premises 12.4 NZECP 54 Recessed Luminaires & Auxiliary Equipment 12.5 ESR Schedule 2 & Companion Standards Overview

13 Installation Requirements

13.1 Consumer Mains, Point of Supply & Switchboards 13.2 Conductor Identification, Isolation, Labelling & IP Ratings 13.3 Cable Selection (AS/NZS 3008.1.2 NZ Conditions) 13.4 Construction Sites, Appliance Testing & Special Installations 13.5 Periodic Assessment, Warrants of Electrical Fitness & AS/NZS 3019

14 Exam Strategy & Key Numbers

14.1 Must-Know Numbers, Times & Thresholds 14.2 Exam Tactics & Common Traps

5.1 Certificate of Compliance (Regulation 65)

Key Takeaways Explain This Topic AI

A CoC certifies that PEW is lawful, electrically safe, and complies with ESR 2010 and applicable standards—not that a network company or inspector has finished their separate roles

Regulation 65 requires a CoC for ALL general-risk and high-risk PEW; low-risk PEW generally does not use CoC as the primary compliance certificate

The authorised electrical worker who did or supervised and verified the work issues the CoC—false certification of unverified work is a serious breach

CoC content themes cover what work, where, who, standards applied, and supporting verification—not invoice-only fields

  • A CoC is not a substitute for an ESC after connection, nor for an RoI on high-risk PEW
  • Last updated: August 2026

5.1 Certificate of Compliance (Regulation 65)

On the EWRB electrician registration regulations exam, certification is not “paperwork after the real job.” The Certificate of Compliance (CoC) is the primary legal instrument that says prescribed electrical work (PEW) was carried out lawfully, safely, and in accordance with the Electricity (Safety) Regulations 2010 (ESR) and the applicable standards. Regulation 65 is the usual open-book anchor for when a CoC is required and what it is meant to certify. Candidates who mix CoC, Electrical Safety Certificate (ESC), and Record of Inspection (RoI) roles lose easy marks—so learn each document’s purpose before memorising form layouts.

What a CoC certifies

A CoC certifies that the PEW:

was carried out in accordance with the ESR 2010 and any other applicable requirements under the Electricity Act framework

complies with the applicable standards cited for that work (commonly AS/NZS 3000 and related Schedule 2 instruments where they apply)

is electrically safe as that concept is used in the Regulations—not merely “the customer is happy” or “it powered up once”

In plain exam language: the CoC is the worker’s formal statement that the work itself is compliant and safe. It is not a network company connection application, not a building consent, and not the independent inspector’s record used for high-risk PEW.

When a CoC is required (reg 65 pathway)

Under the ESR risk-category model taught for this exam:

PEW risk category CoC required? Typical companion documents

Low-risk Generally not required as the main compliance certificate ESC may still apply when the work is connected/energised

  • General-risk Yes — reg 65 pathway for all general-risk PEW CoC + ESC when connected
  • High-risk Yes — reg 65 pathway for all high-risk PEW CoC + RoI (inspector) + ESC when connected

The hard rule for exam stems: a CoC is required for all general-risk and high-risk PEW . If a stem describes everyday installation work such as adding circuits, altering wiring, or other general-risk PEW, “no certificate needed” is almost always wrong. If the stem is high-risk (for example new mains, certain submain or main-switchboard work on a new installation—confirm exact high-risk definitions in ESR), a CoC is still required in addition to the inspector pathway.

Who issues the CoC

The CoC is issued by the authorised electrical worker who carried out or supervised the PEW and who is entitled to certify that work under their EWRB registration class and current practising licence. Key implications:

You certify work you did or supervised and verified —not work you never saw, never tested, or only “helped on for an hour.”

A trainee does not complete certification alone; supervisory arrangements matter for who can lawfully sign.

Issuing a CoC for work you did not do or cannot verify is false certification —a regulatory breach that can attract EWRB discipline, not a “admin shortcut.”

Open-book exam technique: if the stem asks who may issue, open ESR wording on certification responsibility and match it to registration class (electrician for typical installation PEW; Electrical Inspector for RoI, not as a substitute CoC issuer for someone else’s un-supervised work).

Content themes: what the CoC must cover

Exact field lists live in the current ESR / approved forms, but exam and industry teaching consistently expect CoC content themes around:

What work — identify the PEW performed (scope: new circuit, alteration, switchboard work, etc.).

Where — identify the installation/location so the record can be audited later.

Who — identify the certifier (registration/licence details of the authorised worker).

Standards applied — confirm compliance with the Regulations and applicable standards used for the work.

Evidence of safety/compliance — relevant test and verification results that support the certification (verification detail is expanded in the testing chapters; here, know that results support the CoC).

A CoC that only names a price and a date is not a valid compliance record. Treat “minimum information” stems as: work + place + person + standards/compliance + supporting verification , not commercial invoice fields.

Relationship to “safe to connect” before energising

Do not confuse compliance of the work with safe to connect / use after connection :

CoC → the PEW complies with ESR and applicable standards (reg 65 pathway).

ESC → after connection (where required), the work is safe to use and does not leave other parts unsafe (regs 74A / 74C pathway—detailed in section 5.2).

Verification tests (AS/NZS 3000 section 8 sequence) → technical evidence that underpins both instruments before you energise or certify.

Practically, authorised workers verify before connection, issue the CoC for general/high-risk PEW, and only treat connection/energisation as complete when the full chain for that risk category is satisfied. For high-risk PEW, independent inspection/RoI sits in that chain before connection as applicable—CoC alone does not “clear” high-risk work.

What a CoC is not

Exam traps often rephrase the same mistakes:

  • Trap statement Why it fails
  • “CoC replaces ESC after connection” ESC is a separate safe-to-use/connect instrument
  • “CoC replaces RoI for high-risk PEW” RoI is independent inspector evidence under reg 72
  • “CoC is only needed if the customer asks” Reg 65 duties are positive obligations for general/high-risk PEW
  • “Any worker on site can sign any CoC” Only the authorised certifier for that PEW may issue
  • “Low-risk and high-risk use identical CoC rules” Risk category changes which documents are mandatory
  • Timeframes and supply to the client (preview)

Section 3.4 covered ESR time limits after completion. For exam flow with CoC content:

Issue the CoC promptly after the PEW is completed, and give the client a copy within 20 days after completing the work (reg 74E(2) — calendar days, not working days).

Provide the certificate to the person who contracted for the work (client/person entitled to receive it).

Retain a copy for at least 7 years (reg 74E(3)), and produce it within 10 working days of an authorised request (reg 74E(4)); full chain in section 5.4 and every clock in section 5.5.

Exam scenario patterns for reg 65

Pattern A — General-risk PEW finished. Expect CoC (and ESC when connected). “ESC only” is incomplete if the stem is general-risk PEW requiring compliance certification.

Pattern B — High-risk PEW finished. Expect CoC plus inspector RoI before the high-risk chain is complete; ESC when energised/connected. “CoC alone finishes high-risk” is a classic wrong answer.

Pattern C — Low-risk PEW. Do not invent a CoC if ESR does not require one for that category—but do not assume “no documents at all”; ESC may still apply.

Pattern D — False certification. Options that allow certifying untested work, someone else’s unsupervised PEW, or unsafe work as compliant are always wrong.

Open-book checklist for CoC items

Is the activity PEW ?

What risk category (low / general / high)?

If general or high → CoC required (reg 65).

Who is the authorised certifier for that work?

Does the stem also need ESC (connection/use) or RoI (high-risk inspection)?

Confirm issue timing and client copy duties in ESR under time pressure.

Master the CoC as compliance of PEW by the authorised worker for general- and high-risk work , and the rest of the certification suite becomes much easier to place.