5.3 Record of Inspection (Regulation 72)
NZ EWRB Electrician Registration Regulations
Track your progress as you read
Finished sections get a check mark.
1 Introduction & Exam Overview
1.1 Current Exam Facts 1.2 Open-Reference Strategy & Permitted Materials 1.3 Electrician Registration Pathway & Limits of Work 1.4 Which Editions Apply: ESR Schedule 2 & the 13 November 2025 Update
2 Electricity Act & EWRB Framework
2.1 Electricity Act 1992 Framework 2.2 EWRB Role, Register & Registration Classes 2.3 Practising Licence & Electrician Limits of Work
3 Electricity (Safety) Regulations 2010
3.1 ESR 2010 Structure & Key Definitions 3.2 Electrically Safe & Electrically Unsafe 3.3 Duties of Electrical Workers & Competence 3.4 Certification Timeframes & Notification Duties under ESR
4 Prescribed Electrical Work
4.1 What Is Prescribed Electrical Work 4.2 PEW Risk Categories: Low, General, High 4.3 Who May Carry Out and Supervise PEW 4.4 High-Risk Work & Electrical Inspector Requirements
5 Certification Documents (CoC, ESC, RoI)
5.1 Certificate of Compliance (Regulation 65) 5.2 Electrical Safety Certificate (Safe to Connect / Use) 5.3 Record of Inspection (Regulation 72) 5.4 Record-Keeping, Retention & the Certification Chain 5.5 Record-Keeping Duties & the Statutory Clocks (regs 72A, 74E–74H)
6 AS/NZS 3000 Fundamentals
6.1 Structure of AS/NZS 3000 & Open-Book Navigation 6.2 Multiple Earthed Neutral (MEN) System 6.3 Basic Protection vs Fault Protection 6.4 Protective Devices, Discrimination & Coordination
7 RCDs, Shock Protection & Disconnection Times
7.1 RCD Shock-Protection Requirements 7.2 RCD Types, Classification & Installation Contexts 7.3 Disconnection Times (0.4 s / 5 s) & Earth Fault Path 7.4 Damp Situations & Additional Protection
8 Circuits, Maximum Demand & Voltage Drop
8.1 Division of Circuits & Final Subcircuits 8.2 Maximum Demand Principles 8.3 Voltage Drop Requirements & Worked Examples
9 Testing & Verification Core
9.1 Visual Inspection Before Testing 9.2 Continuity of Earthing & Protective Bonding 9.3 Insulation Resistance Testing (500 V DC, 1 MΩ) 9.4 Polarity & Correct Circuit Connections
10 EFLI, RCD Tests & Verification Sequence
10.1 Earth Fault Loop Impedance 10.2 RCD Operation Tests & Prospective Fault Current 10.3 Mandatory Test Sequence & Documentation
11 Safe Isolation & Personal Safety
11.1 Physiological Effects of Current & Shock Factors 11.2 Prove–Test–Prove Safe Isolation 11.3 Lock-Out/Tag-Out & Safety Tag System 11.4 Live-Work Controls, Fault Finding & Unsafe Installations
12 Electrical Codes of Practice & Schedule 2
12.1 NZECP 34 Electrical Safe Distances 12.2 NZECP 50 Repair of Domestic Electrical Equipment 12.3 NZECP 51 Electrical Wiring Work in Domestic Premises 12.4 NZECP 54 Recessed Luminaires & Auxiliary Equipment 12.5 ESR Schedule 2 & Companion Standards Overview
13 Installation Requirements
13.1 Consumer Mains, Point of Supply & Switchboards 13.2 Conductor Identification, Isolation, Labelling & IP Ratings 13.3 Cable Selection (AS/NZS 3008.1.2 NZ Conditions) 13.4 Construction Sites, Appliance Testing & Special Installations 13.5 Periodic Assessment, Warrants of Electrical Fitness & AS/NZS 3019
14 Exam Strategy & Key Numbers
14.1 Must-Know Numbers, Times & Thresholds 14.2 Exam Tactics & Common Traps
5.3 Record of Inspection (Regulation 72)
Key Takeaways Explain This Topic AI
An RoI is required for high-risk PEW only (reg 72)—not for low-risk or ordinary general-risk PEW
A registered Electrical Inspector issues the RoI after independent inspection; it is not the installer’s CoC under another name
High-risk completion/connection chains require CoC plus RoI (and ESC when connected)—CoC alone does not finish high-risk PEW
The RoI’s purpose is an independent inspection record for safety, audit, and connection—not a substitute ESC or network billing form
- Never treat RoI, CoC, and ESC as interchangeable labels on exam stems
- Last updated: August 2026
5.3 Record of Inspection (Regulation 72)
High-risk prescribed electrical work sits at the top of the ESR risk ladder because faults can have severe consequences for people and property. The Record of Inspection (RoI) is the document that proves an independent Electrical Inspector has inspected that high-risk PEW. Regulation 72 is the standard open-book anchor for RoI duties. If you only remember one RoI sentence for the exam, remember this: RoI is for high-risk PEW only, issued by a registered Electrical Inspector after inspection—not by the installing electrician as a substitute CoC.
Purpose of the RoI
The RoI exists to provide an independent inspection record that supports:
- Safety — a second competent set of eyes on the highest-risk PEW categories
- Audit / accountability — a clear trail that inspection occurred and was recorded
Connection completion — high-risk PEW is not treated as freely complete/connectable until the inspection/certification chain the regulations require is satisfied
Independence matters. The RoI is not the installer re-labelling their own CoC. The inspector’s role is a distinct registration class with additional competence expectations.
When an RoI is required
PEW category RoI required?
- Low-risk No — RoI is not the low-risk document set
- General-risk No — CoC (+ ESC when connected); no independent RoI as standard
- High-risk Yes — RoI after inspection by an Electrical Inspector (reg 72)
High-risk examples taught for electrician regulations prep commonly include work such as new mains , or certain work on a submain or main switchboard of a new installation (always match the stem to the current ESR high-risk definition rather than inventing categories). Everyday like-for-like switch replacements and many minor alterations are not high-risk and do not attract an RoI.
Who issues the RoI
Only a person registered and licensed as an Electrical Inspector (the inspector class) carries out the independent inspection of high-risk PEW and issues the RoI. Exam implications:
An electrician issues the CoC for the high-risk PEW they carry out or supervise; they do not issue the RoI as if they were inspecting their own high-risk work in the inspector’s place (unless they also hold the inspector registration and are acting in that independent inspection capacity under the rules).
An Electrical Appliance Serviceperson , trainee, or associated tradesperson does not issue RoIs for high-risk installation PEW.
The inspector’s RoI does not erase the installer’s duty to do compliant work and issue a CoC.
Relationship to CoC and connection
For high-risk PEW, think in layers:
Do the PEW to ESR and AS/NZS 3000 (and other applicable standards).
Verify (inspection and testing) as required before certification/connection.
Issue the CoC (reg 65) for the high-risk PEW.
Obtain independent inspection and RoI (reg 72).
Connect only when the high-risk chain allows connection as applicable.
Issue the ESC after connection (reg 74A pathway) when connection/use certification applies.
Teaching shorthand used throughout this guide and EWRB-style toolboxes:
High-risk: CoC → RoI → connect → ESC
The RoI is required with the CoC before high-risk PEW is considered complete / before connection as applicable. Exact sequencing nuances (what must exist before connection versus what completes the file) should be confirmed in current ESR wording under open-book conditions—but exam options that say “CoC alone finishes high-risk” or “connect first, maybe inspect later if someone complains” are wrong.
Do not confuse RoI with CoC or ESC
- Document Issuer (typical) Risk trigger Core message
- CoC Authorised worker for the PEW General + high PEW complies with ESR/standards; electrically safe work
ESC Authorised worker for connection/use certification When connected (incl. low-risk path) Safe to use; does not make other parts unsafe
RoI Electrical Inspector High-risk only Independent inspection recorded
Common mix-ups and the correction:
“RoI replaces CoC” → No. High-risk needs both .
“RoI replaces ESC” → No. ESC still applies when connected.
“RoI is needed for all PEW” → No. High-risk only.
“Electrician’s CoC is the same as inspection” → No. Independence is the point of reg 72.
What the RoI is not
Not a building consent or council producer statement by another name (though building processes may interact on some projects).
Not a network company livening form (though network processes may require evidence of compliance/inspection).
Not optional “extra QA” the customer can decline for true high-risk PEW—the Regulations impose the inspection pathway.
Not a substitute for competent installation and verification by the PEW worker.
Practical coordination on high-risk jobs
Real jobs and exam narratives often include coordination failures. Good candidate thinking:
Plan high-risk PEW so an inspector is available before connection deadlines.
Do not energise high-risk work on the assumption that “paperwork will catch up.”
Keep CoC, RoI, ESC, and test results as a set for the installation file.
If the stem describes incomplete inspection, treat the high-risk PEW as not complete for regulatory purposes.
Exam scenario patterns for reg 72
Pattern A — New mains / high-risk installation PEW. Expect CoC + RoI; ESC when connected. Correct issuer of RoI = Electrical Inspector.
Pattern B — Like-for-like light switch. Low-risk style work: no RoI; do not over-certify with inspector documents.
Pattern C — High-risk PEW with CoC only, connected immediately. Missing RoI (and possibly premature connection) — non-compliant chain.
Pattern D — Who inspects? Options naming EAS, trainee, or “any electrician on site” as RoI issuer are wrong; choose Electrical Inspector .
Pattern E — Purpose question. If asked why RoI exists, answer independent inspection record for high-risk PEW safety/audit/connection , not “to set electricity prices” or “to replace all other certificates.”
Open-book checklist for RoI items
Is the PEW high-risk under ESR?
If no → RoI not required; pick CoC/ESC as applicable.
If yes → Electrical Inspector inspects and issues RoI (reg 72).
Confirm CoC still required (reg 65).
Confirm connection only after the high-risk chain allows it.
Confirm ESC after connection when applicable.
Reject any option that treats RoI, CoC, and ESC as interchangeable labels.
Master RoI as high-risk + inspector + independence , and you will separate it cleanly from the worker’s CoC and the post-connection ESC every time.