Study guide

3.1 Stormwater Sizing & Flow Calculations to AS/NZS 3500.3 & E1/AS1

NZ PGDB Certifying Drainlayer Registration Examination Exam

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: Foul-Water Drainage System Design

1.1 Separated Drainage Systems & Cross-Connection Prevention 1.2 Drain Layout, Junctions, Bends & Sweep Connections 1.3 Gully Traps, Water Seals & Overflow Relief Gullies (ORG) 1.4 Boundary Connections, Inspection Shafts & Public Sewer Interface

2 Chapter 2: Drainage Ventilation & Commercial Waste Systems

2.1 Drainage Ventilation Systems, Relief Vents & Air Admittance Valves (AAVs) 2.2 Discharge Unit & Fixture Unit Sizing under G13/AS2 & AS/NZS 3500.2 2.3 Commercial Grease Interceptors & Oil/Grit Separators 2.4 Pumped Drainage Systems, Sumps & Rising Mains

3 Chapter 3: Stormwater Drainage & Surface Water Management

3.1 Stormwater Sizing & Flow Calculations to AS/NZS 3500.3 & E1/AS1 3.2 Stormwater Pits, Sumps, Silt Traps & Inlets 3.3 Soakage Systems, Retention & Detention Tanks 3.4 Overland Flow Paths & Secondary Flow Protection

4 Chapter 4: Drainage Testing & Quality Verification

4.1 Hydrostatic (Water) Testing Methods & Pressure Limits 4.2 Pneumatic (Air) Testing, Vacuum Testing & Leak Detection 4.3 CCTV Inspection, Defect Identification & As-Built Verification

5 Chapter 5: Trenching Safety & Confined Spaces

5.1 Excavation & Trenching Safety: Shoring, Battering & Benching 5.2 Confined Space Entry, Atmospheric Monitoring & Hazardous Gases 5.3 Underground Service Locating & Utility Strike Prevention 5.4 Site Health & Safety Management under the Health and Safety at Work Act 2015

6 Chapter 6: The Legislative & Regulatory Framework

6.1 Plumbers, Gasfitters, and Drainlayers Act 2006 & Board Functions 6.2 Licensing Classes, Registration Competencies & Annual Practising Licences 6.3 Disciplinary Regime, Offences, Complaints & Board Powers

7 Chapter 7: Certifying Drainlayer Authority & Site Supervision

7.1 Certifying Authority, Producer Statements & Records of Work 7.2 Supervision Principles: Direct vs General Supervision & Trainee Ratios 7.3 Professional Ethics, Continuing Professional Development (CPD) & Quality Assurance

8 Chapter 8: On-Site Wastewater System Design

8.1 AS/NZS 1547 Framework, Site Assessment & Soil Classification 8.2 Primary Treatment: Septic Tank Sizing, Baffles & Effluent Filters 8.3 Secondary Treatment: Aerated Wastewater Treatment Systems (AWTS) & Media Filters

9 Chapter 9: Land Application Systems & Environmental Protection

9.1 Land Application Systems: Absorption Trenches, Beds & Subsurface Drip Irrigation 9.2 Design Loading Rates (DLR), Reserve Areas & Hydraulic Sizing 9.3 Environmental Setbacks, Groundwater Protection & Resource Consents

10 Chapter 10: Pipe Materials, Jointing & Transitions

10.1 DWV Pipe Materials: uPVC, Vitrified Clay, PE & Concrete 10.2 Jointing Technologies: Solvent Cementing & Rubber Ring Joints 10.3 Dissimilar Material Adaptors, Flexible Couplings & Expansion Management

11 Chapter 11: Trench Bedding, Support & Backfill

11.1 Bedding Classes & Material Specifications under AS/NZS 3500.2 11.2 Cover Depths, Loading Conditions & Encasement Protection 11.3 Trench Backfill, Compaction Standards & Pipe Flotation Prevention

12 Chapter 12: Gradients, Invert Levels & Setting Out

12.1 Gradient Standards & Self-Cleansing Velocities under G13 & AS/NZS 3500.2 12.2 Fall, Grade & Run Calculations 12.3 Invert Level Calculations & Datum Relationships 12.4 Setting Out Methods: Laser Levels, Optical Instruments & Boning Rods

13 Chapter 13: Building Code Compliance & Service Separation

13.1 NZ Building Code Architecture: Clause G13, Clause E1 & Compliance Pathways 13.2 Service Separation: Clearances Between Foul Water, Stormwater & Other Utilities 13.3 Building Consent Authorities (BCAs), Code Compliance Certificates (CCC) & Council Inspections

14 Chapter 14: Examination Blueprint & Integrated Certifying Practice

14.1 Official Examination 9198 Blueprint, Logistics & Source Strategy 14.2 Plans, Specifications, Material Lists, Patterns, Tools & Equipment 14.3 Sustainability, Water Quality, Structural Integrity, Seismic & Geotechnical Resilience

3.1 Stormwater Sizing & Flow Calculations to AS/NZS 3500.3 & E1/AS1

Key Takeaways Explain This Topic AI

E1/AS1 minimum gradients are 1:90 for 85 mm, 1:120 for 100 mm, 1:200 for 150 mm, and 1:350 for 225 mm drains.

Use the rainfall intensity, duration, AEP, climate allowance, catchment, and runoff coefficient required by the consent and territorial authority.

The Rational Method in square-metre units is Q = C I A / 3600, producing litres per second when I is millimetres per hour.

Pipe capacity must be checked from an accepted hydraulic method rather than an uncited generic table.

Last updated: October 2026

Stormwater sizing and flow calculations

Stormwater design begins with the performance requirement and the approved site information. Clause E1 requires surface water to be disposed of without creating nuisance or damage, but a pipe diameter cannot be selected from that sentence alone. The calculation needs a design event, catchment, runoff response, approved outfall, hydraulic grade, and secondary-flow strategy.

Rainfall and catchment

Use the rainfall source required by the territorial authority or consent. Record the annual exceedance probability, storm duration, location, and any prescribed climate-change allowance. Do not copy a generic city rainfall table into another district. Duration matters because the critical intensity depends on the time of concentration and storage response.

Divide the site into defensible catchments. Roof, paving, compacted yard, and landscaped ground can have different runoff coefficients. In square-metre units, the Rational Method may be written as Q = C I A / 3600, where Q is litres per second, C is dimensionless, I is millimetres per hour, and A is square metres. Check units every time.

For a 420 square metre roof, C = 1.0, and an approved intensity of 120 mm/h, Q = 1.0 × 120 × 420 / 3600 = 14 L/s. That is the catchment peak used for the next design step; it is not proof that a particular pipe will carry it.

E1/AS1 drain gradients

E1/AS1 gives these minimum gradients for drains: 85 mm at 1:90, 100 mm at 1:120, 150 mm at 1:200, and 225 mm at 1:350. The draft value 1:90 for a 100 mm drain confuses the 85 mm row with the 100 mm row. State nominal size and grade together.

After selecting a tentative size and grade, determine capacity using the method and roughness assumptions accepted for the project. Check inlet control, outlet tailwater, junction and bend losses, partial flow, and surcharge where relevant. A table of free-discharge barrel capacities cannot by itself prove a complete network.

Primary and secondary systems

A primary network manages the selected frequent event. A secondary route manages exceedance, blockage, or surcharge. Map where water will go if every inlet is blocked. Preserve overland routes and check finished-floor protection under the site’s approved flood information. E1/AS1 uses 150 mm separation above adjacent ground, road crown, or the lowest site boundary for its applicable housing conditions; it does not create a universal 225 mm unpaved-ground rule or a universal 500 mm flood freeboard.

Inlets and outfalls

E1/AS1 requires a surface-water inlet grating with at least 35 percent open area and a maximum smaller opening dimension of 35 mm. Provide suitable space below the outlet for sediment, but the Acceptable Solution does not prescribe one universal 300 mm-deep sump for every inlet. Size the grate for approach flow and blockage appropriate to the site.

Confirm the outfall is lawful and hydraulically available. A public connection needs network approval; soakage requires field investigation and territorial-authority acceptance; discharge to land or water may involve regional rules. Never assume an invert shown on GIS is construction-grade survey data.

Calculation record

A reviewable record includes the rainfall source and date, AEP and duration, climate factor, catchment plan, coefficients, calculated flows, inlet schedule, pipe sizes and grades, loss assumptions, outfall condition, secondary route, and as-built verification. If the final installed grade differs from the design, recalculate; do not merely relabel the drawing.

Independent source-check exercise

For 3.1 Stormwater Sizing & Flow Calculations to AS/NZS 3500.3 & E1/AS1 , practise answering from evidence rather than recall. Write the controlling source, its edition or effective date, its scope, and the exact paragraph, table, figure, or manufacturer instruction that supports the decision. Then state the site inputs that can change the result. In this section those inputs include E1/AS1 minimum gradients are 1:90 for 85 mm, 1:120 for 100 mm, 1:200 for 150 mm, and 1:350 for 225 mm drains.; Use the rainfall intensity, duration, AEP, climate allowance, catchment, and runoff coefficient required by the consent and territorial authority.; The Rational Method in square-metre units is Q = C I A / 3600, producing litres per second when I is millimetres per hour..

Build a four-column check: proposed condition, source requirement, evidence observed, and action. Test the answer with one changed assumption. A different pipe size, discharge-unit load, ground condition, licence status, authority, compliance path, or consent condition may produce a different result. If it does, explain why; if it does not, show which requirement remains controlling.

Finish with a field-verification plan. Name what must be inspected before concealment, what instrument or record demonstrates it, who has authority to accept a change, and what appears on the as-built or completion file. This exercise turns an open-book fact into certifying-level judgement. It also exposes accidental mixing of standards: if the source for a dimension differs from the source for the test or approval, either return to one complete compliance path or document the proposal as an Alternative Solution. Do not promote an example value into a national rule.

Loading diagram... Stormwater design sequence