1.3 OSHA Electrical Safety Standards (29 CFR 1926/1910)

Oklahoma Journeyman Electrician Exam

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: Oklahoma Licensing Laws, Board Rules & Safety

1.1 Oklahoma Electrical License Act & CIB Regulations 1.2 OK Journeyman Exam Format, PSI Logistics & Codebook Navigation 1.3 OSHA Electrical Safety Standards (29 CFR 1926/1910) 1.4 NFPA 70E Electrical Safety in the Workplace & Arc Flash 1.5 Permits, Inspections, Structural Integrity & Job Estimating 1.6 Oklahoma's Adopted 2023 NEC: OUBCC Amendments You Must Know 1.7 OSHA 29 CFR 1926 Job-Site Safety: Sanitation, Signage, Ladders, Scaffolds & Fall Protection

2 Chapter 2: General Electrical Theory & Calculations

2.1 Ohm's Law, Watt's Law & DC Series/Parallel Circuits 2.2 AC Theory, Reactance, Impedance & Power Factor 2.3 Three-Phase Power Systems (Delta & Wye Configurations) 2.4 Electrical Units, Formulas & Conversions 2.5 Cost of Power in a Circuit, Efficiency & Troubleshooting/Test Instruments

3 Chapter 3: General Installation Requirements (NEC Article 110)

3.1 Examination, Identification, Installation & Use of Equipment (110.3) 3.2 Electrical Connections, Terminations & Torque Requirements (110.14) 3.3 Working Space, Clearances & Guarding of Live Parts (110.26 & 110.27) 3.4 Enclosure Types, Markings & Available Fault Current (110.24 & 110.28) 3.5 Installations Over 600 Volts: Article 110 Part III, Article 490 & Medium-Voltage Cable

4 Chapter 4: Branch Circuits & Feeders (NEC Articles 210, 215 & 225)

4.1 Branch Circuit Ratings, Multiwire Branch Circuits & Identification (210.3–210.10) 4.2 Ground-Fault Circuit-Interrupter (GFCI) Protection (210.8) 4.3 Arc-Fault Circuit-Interrupter (AFCI) Protection & Receptacle Outlets (210.12 & 210.52) 4.4 Outside Branch Circuits and Feeders (Article 225) & Feeder Sizing (Article 215)

5 Chapter 5: Services & Service Equipment (NEC Article 230)

5.1 Service Clearances, Overhead & Underground Service-Drop Requirements (230.9, 230.24 & 230.30) 5.2 Service-Entrance Conductors, Sizing & Installation (230.40–230.54) 5.3 Service Equipment Disconnecting Means, Overcurrent Protection & Emergency Disconnects (230.70–230.95)

6 Chapter 6: Electrical Load Calculations (NEC Article 220)

6.1 General Lighting, Small Appliance & Laundry Loads (NEC 220.41, 220.42, 220.45 & 220.52) 6.2 Standard Dwelling Unit Feeder & Service Calculations (NEC Article 220 Part III) 6.3 Optional Dwelling Unit Feeder & Service Calculations (NEC Article 220 Part IV) 6.4 Commercial & Multi-Family Load Calculations (Cooktops, Dryers, HVAC & Stores)

7 Chapter 7: Overcurrent Protection & Tap Rules (NEC Article 240)

7.1 Overcurrent Protection Fundamentals & Standard Ampere Ratings (240.4 & 240.6) 7.2 Feeder & Branch Circuit Tap Rules (NEC 240.21) 7.3 Ground-Fault Protection of Equipment & Selective Coordination (NEC 240.13, 240.86 & Article 245)

8 Chapter 8: Grounding and Bonding (NEC Article 250)

8.1 General Grounding Principles, System Grounding & Grounded Conductors (NEC 250.4, 250.20 & 250.24) 8.2 Grounding Electrode System & Grounding Electrode Conductor (GEC) Sizing (NEC 250.50, 250.52 & 250.66) 8.3 Equipment Grounding Conductors (EGC) Sizing & Installation (NEC 250.118, 250.120 & 250.122) 8.4 Bonding Requirements, Main/System Bonding Jumpers & Separately Derived Systems (NEC 250.28, 250.30 & 250.102)

9 Chapter 9: Wiring Methods & Materials (NEC Articles 300–314)

9.1 General Requirements for Wiring Methods, Underground Clearances & Firestopping (NEC Article 300) 9.2 Conductor Ampacity Ratings, Temperature Correction & Bundling Adjustments (Article 310 & Table 310.16) 9.3 Nonmetallic-Sheathed Cable (Type NM), Metal-Clad Cable (Type MC) & Armored Cable (Type AC) 9.4 Outlet, Device, Pull & Junction Boxes Sizing and Box Fill Calculations (NEC Article 314) 9.5 Temporary Installations (Article 590), Cranes & Hoists (Article 610), Elevators & Escalators (Article 620)

10 Chapter 10: Raceways, Tubing, Conduit Fill & Underground Systems

10.1 Rigid Metal Conduit (RMC), Intermediate Metal Conduit (IMC) & Electrical Metallic Tubing (EMT) 10.2 Nonmetallic Raceways (PVC, RTRC, Liquidtight) & Cable Trays (NEC Articles 352, 356, 392) 10.3 Conduit Fill Calculations (Chapter 9 Tables 1, 4 & 5, Annex C) & Pull Box Sizing (NEC 314.28)

11 Chapter 11: Motors, Controllers & Air Conditioning (NEC Articles 430 & 440)

11.1 Motor Full-Load Current (FLC), Branch Circuit Conductor Sizing & Disconnects (430.6, 430.22 & 430.102) 11.2 Motor Overload Protection & Motor Branch Circuit Short-Circuit/Ground-Fault Protection (430.32 & 430.52) 11.3 Motor Feeder Conductor Sizing & Feeder Overcurrent Protection (430.24 & 430.62) 11.4 Air Conditioning & Refrigeration Equipment (NEC Article 440: MCA, MOCP & Disconnects)

12 Chapter 12: Transformers & Equipment (NEC Articles 450, 410, 422 & 424)

12.1 Transformer Sizing, Protection & Voltage Calculations (NEC Article 450 & Table 450.3(B)) 12.2 Luminaires, Lampholders & Lamps Installation (NEC Article 410) 12.3 Appliances & Electric Water Heaters (NEC Article 422) 12.4 Fixed Electric Space-Heating Equipment (NEC Article 424) 12.5 Snow-Melting & De-Icing Equipment (Article 426) and Pipeline & Vessel Heating (Article 427) 12.6 Electric Signs & Outline Lighting (Article 600) and Lighting Systems 30 Volts or Less (Article 411)

13 Chapter 13: Special Occupancies & Hazardous Locations (NEC Articles 500–517)

13.1 Hazardous (Classified) Locations: Class I, II, and III (Articles 500, 501, 502 & 503) 13.2 Commercial Garages, Repair Facilities & Fuel Dispensing Facilities (Articles 511 & 514) 13.3 Health Care Facilities: Patient Care Spaces & Wiring Methods (Article 517) 13.4 Agricultural Buildings & Manufactured/Mobile Homes (Articles 547 & 550) 13.5 Bulk Storage Plants (Article 515) and Spray Application, Dipping & Coating (Article 516)

14 Chapter 14: Special Equipment, Swimming Pools & Low-Voltage Systems

14.1 Swimming Pools, Spas, Hot Tubs & Hydromassage Bathtubs (Article 680) 14.2 Emergency Systems, Legally Required & Optional Standby Systems (Articles 700, 701 & 702) 14.3 Class 1, 2, 3 & Class 4 Power-Limited Circuits (NEC Articles 722, 724, 725 & 726) and Fire Alarms (NEC Article 760) 14.4 RV Parks (Article 551), Floating Buildings (Article 553) & Marinas/Docking Facilities (Article 555)

1.3 OSHA Electrical Safety Standards (29 CFR 1926/1910)

Key Takeaways Explain This Topic AI

OSHA regulates electrical safety under 29 CFR 1926 Subpart K for construction sites and 29 CFR 1910 Subpart S for general industry facilities.

Electrocution is one of OSHA's Construction 'Fatal Four'; overhead power lines require a mandatory minimum approach distance of 10 feet for voltages up to 50 kV (plus 0.4 inches per kV over 50 kV under 1926.1408).

Lockout/Tagout (LOTO) under 29 CFR 1910.147 mandates a strict 6-step de-energization sequence, zero-energy state verification, and live-dead-live testing prior to physical contact.

Job site temporary wiring requires either 100% GFCI protection on all 120V 15A/20A receptacles or a written Assured Equipment Grounding Conductor Program (AEGCP) with quarterly continuity testing.

ASTM D120 voltage-rated rubber insulating gloves (Classes 00 to 4) require daily visual and manual air inflation inspections and mandatory laboratory dielectric re-testing every six (6) months in service.

Last updated: August 2026

1.3 OSHA Electrical Safety Standards (29 CFR 1926/1910)

Occupational electrical safety in the United States is governed under federal law by the Occupational Safety and Health Administration (OSHA) . For electricians, two distinct standards dictate workplace safety requirements:

29 CFR 1926, Subpart K (Electrical, §§ 1926.400 – 1926.449): Applies to all construction, alteration, demolition, and renovation job sites.

29 CFR 1910, Subpart S (Electrical, §§ 1910.301 – 1910.399): Applies to general industry, industrial manufacturing plants, commercial maintenance, and ongoing facility operations.

Mastery of OSHA standards is essential not only for passing the Oklahoma Journeyman licensing exam, but for preventing catastrophic workplace fatalities and severe arc flash or electrocution injuries.

1. Electrocution & OSHA's Construction "Fatal Four"

OSHA identifies electrocution as one of the construction industry's Fatal Four leading causes of workplace fatalities (alongside falls, struck-by hazards, and caught-in/between hazards). The majority of electrical fatalities stem from four primary hazard scenarios:

Direct or indirect contact with overhead high-voltage power lines.

Contact with energized conductors or busbars due to failure to isolate and lock out equipment.

Missing, damaged, or discontinuous equipment grounding conductors.

Improper use of flexible cords, temporary lighting, and non-ground-fault protected power sources.

Overhead Power Line Clearances (29 CFR 1926.1408 & 1926.403)

Contact with energized overhead distribution and transmission lines is the single largest contributor to electrical fatalities on construction sites. +-----------------------------------------------------------------------------+

  • | OSHA OVERHEAD POWER LINE MINIMUM CLEARANCE |
  • | |
  • | VOLTAGE LEVEL (Line to Ground) MINIMUM CLEARANCE DISTANCE |
  • | ----------------------------------- -------------------------- |
  • | Up to 50,000 Volts (50 kV) 10 Feet (3.05 Meters) |
  • | Over 50 kV (Up to 200 kV) 10 Feet + 4 Inches for each 10 kV |
  • | (or 0.4 inches per 1 kV over 50 kV)|
  • | Over 200 kV (e.g., 345 kV, 500 kV) Calculated Engineering Clearance |
  • +-----------------------------------------------------------------------------+

[!CRITICAL] The 10-Foot Rule: For all distribution voltages up to 50 kV , unqualified workers, ladders, scaffolds, mobile cranes, and conductive equipment must maintain a continuous minimum clearance boundary of 10 feet . Never assume a line is insulated or de-energized unless verified by the utility operator.

2. Lockout/Tagout (LOTO) & The Control of Hazardous Energy (29 CFR 1910.147)

Under 29 CFR 1910.147 (General Industry) and 29 CFR 1926.417 (Construction) , servicing, maintaining, or modifying electrical circuits and machinery requires the complete isolation, de-energization, and locking out of all hazardous energy sources. +-----------------------------------------------------------------------------+

  • | OSHA 6-STEP DE-ENERGIZATION & LOTO SEQUENCE |
  • | |
  • | [STEP 1: PREPARATION FOR SHUTDOWN] |
  • | - Identify all energy sources (Electrical, Mechanical, Pneumatic, Springs)|
  • | | |
  • | v |
  • | [STEP 2: NOTIFICATION OF AFFECTED EMPLOYEES] |
  • | - Inform machine operators and affected personnel of pending shutdown. |
  • | | |
  • | v |
  • | [STEP 3: EQUIPMENT SHUTDOWN] |
  • | - Execute normal stopping procedure (stop button, control switch). |
  • | | |
  • | v |
  • | [STEP 4: ENERGY ISOLATION (DISCONNECT)] |
  • | - Open circuit breakers, disconnect switches, pull fuses, close valves. |
  • | | |
  • | v |
  • | [STEP 5: APPLY LOTO DEVICES] |
  • | - Attach individual lockout padlocks and standardized danger tags. |
  • | | |
  • | v |
  • | [STEP 6: STORED ENERGY DISSIPATION & ZERO-ENERGY VERIFICATION] |
  • | - Discharge capacitors, bleed hydraulic/air pressure, block gravity loads.|
  • | - TEST CONDUCTORS: Live-Dead-Live verification on calibrated meter. |
  • +-----------------------------------------------------------------------------+

LOTO Roles & Key Protocols:

Authorized Employee: A qualified individual who physically applies lockout or tagout devices to machines or electrical equipment to perform servicing or maintenance.

Affected Employee: An employee whose job requires operating equipment on which servicing is being performed, or whose work requires them to be in the area.

Group Lockout Protocol: When multiple trades or workers service complex equipment, each authorized employee must attach their personal lockout padlock to a group lockout hasp or master lockbox. No worker may rely on another worker's lock.

Emergency Lock Removal (1910.147(e)(3)): A lockout device may only be removed by the person who applied it. If that person is absent, the employer may remove the lock ONLY after: (1) verifying the employee is off-site, (2) making documented reasonable efforts to notify the employee, and (3) ensuring the employee is informed of the removal before resuming work.

3. Job Site Ground-Fault Protection: GFCI vs. AEGCP (29 CFR 1926.404(b)(1))

On construction job sites, temporary electrical power is exposed to moisture, physical abrasion, rough handling, and dynamic loads. OSHA mandates ground-fault protection for all temporary receptacle outlets through one of two methods: +-----------------------------------------------------------------------------+

  • | OSHA TEMPORARY RECEPTACLE GROUND-FAULT PROTECTION |
  • | |
  • | +-----------------------------------+ |
  • | | CONSTRUCTION SITE RECEPTACLES | |
  • | | (120V, Single-Phase, 15A & 20A)| |
  • | +-----------------------------------+ |
  • | | |
  • | +--------------------+--------------------+ |
  • | | | |
  • | v v |
  • | +-----------------------------+ +-----------------------------+ |
  • | | OPTION 1: MANDATORY | | OPTION 2: ASSURED EQUIP | |
  • | | GFCI PROTECTION | --OR--| GROUND CONDUCTOR PROGRAM | |
  • | | | | (AEGCP) | |
  • | | - Class A GFCI on all outlets| | - Written site procedure | |
  • | | - Trips at 4 to 6 mA | | - Designated Competent Person| |
  • | | - 25 millisecond trip speed | | - Visual check before shift | |
  • | | - Replaces AEGCP complexity | | - 3-Month Continuity Test | |
  • | +-----------------------------+ +-----------------------------+ |
  • +-----------------------------------------------------------------------------+
  • Option 1: Ground-Fault Circuit-Interrupters (GFCI)

All 120-volt, single-phase, 15- and 20-ampere receptacle outlets that are not part of the permanent structure's wiring must have approved Class A GFCI protection for personnel.

Operating Parameters: A Class A GFCI is defined by UL 943 as a device that will trip when the current to ground is 6 mA or higher and will not trip when it is less than 4 mA . Its clearing time is not a single number — UL 943 sets a maximum trip time that shortens as fault current rises, following T = (20 ÷ I)^1.43 seconds with I in milliamperes. That yields the familiar 25 milliseconds (1/40 second) at the high fault currents of a real line-to-earth contact, and a longer permitted time near the 6 mA threshold.

Option 2: Assured Equipment Grounding Conductor Program (AEGCP)

If an employer chooses not to provide GFCIs, they must implement a comprehensive, written AEGCP covering all cord sets, receptacles, and cord-and-plug connected equipment:

Written Program: Documented procedure kept on site and managed by a designated Competent Person .

Daily Visual Inspection: Inspect cords, plugs, and receptacles for crushed jackets, missing ground prongs, exposed copper, and strain relief damage prior to each day's use.

Mandatory Testing Schedule: Conduct electrical continuity tests and verify correct polarity/terminal connections:

Before first use on site.

Before returning equipment to service following any repair.

After any suspected damage or incident.

At recurring intervals not exceeding three (3) months (quarterly) .

Color-Coded Logging: Tested cords must be logged and tagged using standard quarterly color tape (e.g., White = Q1, Green = Q2, Red = Q3, Orange = Q4).

4. Personal Protective Equipment & ASTM D120 Insulating Rubber Gloves

Electrical personal protective equipment (PPE) acts as the final line of defense against shock and electrocution. Under OSHA 1910.137 and ASTM D120, voltage-rated rubber insulating gloves are classified into six distinct performance tiers:

  • Glove Class Color Tag / Label Maximum AC Use Voltage Maximum DC Use Voltage Proof-Test Voltage (AC)
  • Class 00 Beige 500 Volts AC 750 Volts DC 2,500 Volts AC
  • Class 0 Red 1,000 Volts AC 1,500 Volts DC 5,000 Volts AC
  • Class 1 White 7,500 Volts AC 11,250 Volts DC 10,000 Volts AC
  • Class 2 Yellow 17,000 Volts AC 25,500 Volts DC 20,000 Volts AC
  • Class 3 Green 26,500 Volts AC 39,750 Volts DC 30,000 Volts AC
  • Class 4 Orange 36,000 Volts AC 54,000 Volts DC 40,000 Volts AC
  • Mandatory Inspection & Dielectric Re-Test Intervals (OSHA 1910.137(c)(2))

Daily Field Air Test: Prior to each work shift, the electrician must visually inspect gloves for cuts, cracks, chemical degradation, or ozone checking, and perform a manual air inflation test (rolling the gauntlet tightly to trap air and listening/feeling for pinhole leaks).

Leather Protectors: Rubber insulating gloves must always be worn with outer leather protector gloves to shield the rubber from mechanical punctures, cuts, and abrasions. (Leather provides no dielectric shock protection).

Mandatory Laboratory Dielectric Testing:

In-service rubber insulating gloves must undergo laboratory dielectric testing at least once every six (6) months .

Unissued/stored gloves in original packaging must be retested every twelve (12) months .

5. Portable Electric Tools & Double-Insulation Standards

Under OSHA 29 CFR 1926.404(f) and 1910.304:

Grounding Prongs: All cord-and-plug connected tools with exposed metal housings must be equipped with a 3-conductor cord and an intact grounding prong plugged into an approved grounded receptacle.

Double-Insulated Tools: Portable electric tools are exempt from grounding requirements only if they are approved and marked as Double Insulated .

Marking: Double-insulated tools feature the international symbol—a square within a square (□)—or are explicitly marked "Double Insulated". Double insulation uses non-conductive composite housings and isolated internal drive mechanisms to prevent internal electrical faults from energizing the outer casing.

Loading diagram... OSHA Lockout/Tagout & Electrical Verification Workflow