Study guide

10.2 Nonmetallic Raceways (PVC, RTRC, Liquidtight) & Cable Trays (NEC Articles 352, 356, 392)

Oklahoma Journeyman Electrician Exam

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: Oklahoma Licensing Laws, Board Rules & Safety

1.1 Oklahoma Electrical License Act & CIB Regulations 1.2 OK Journeyman Exam Format, PSI Logistics & Codebook Navigation 1.3 OSHA Electrical Safety Standards (29 CFR 1926/1910) 1.4 NFPA 70E Electrical Safety in the Workplace & Arc Flash 1.5 Permits, Inspections, Structural Integrity & Job Estimating 1.6 Oklahoma's Adopted 2023 NEC: OUBCC Amendments You Must Know 1.7 OSHA 29 CFR 1926 Job-Site Safety: Sanitation, Signage, Ladders, Scaffolds & Fall Protection

2 Chapter 2: General Electrical Theory & Calculations

2.1 Ohm's Law, Watt's Law & DC Series/Parallel Circuits 2.2 AC Theory, Reactance, Impedance & Power Factor 2.3 Three-Phase Power Systems (Delta & Wye Configurations) 2.4 Electrical Units, Formulas & Conversions 2.5 Cost of Power in a Circuit, Efficiency & Troubleshooting/Test Instruments

3 Chapter 3: General Installation Requirements (NEC Article 110)

3.1 Examination, Identification, Installation & Use of Equipment (110.3) 3.2 Electrical Connections, Terminations & Torque Requirements (110.14) 3.3 Working Space, Clearances & Guarding of Live Parts (110.26 & 110.27) 3.4 Enclosure Types, Markings & Available Fault Current (110.24 & 110.28) 3.5 Installations Over 600 Volts: Article 110 Part III, Article 490 & Medium-Voltage Cable

4 Chapter 4: Branch Circuits & Feeders (NEC Articles 210, 215 & 225)

4.1 Branch Circuit Ratings, Multiwire Branch Circuits & Identification (210.3–210.10) 4.2 Ground-Fault Circuit-Interrupter (GFCI) Protection (210.8) 4.3 Arc-Fault Circuit-Interrupter (AFCI) Protection & Receptacle Outlets (210.12 & 210.52) 4.4 Outside Branch Circuits and Feeders (Article 225) & Feeder Sizing (Article 215)

5 Chapter 5: Services & Service Equipment (NEC Article 230)

5.1 Service Clearances, Overhead & Underground Service-Drop Requirements (230.9, 230.24 & 230.30) 5.2 Service-Entrance Conductors, Sizing & Installation (230.40–230.54) 5.3 Service Equipment Disconnecting Means, Overcurrent Protection & Emergency Disconnects (230.70–230.95)

6 Chapter 6: Electrical Load Calculations (NEC Article 220)

6.1 General Lighting, Small Appliance & Laundry Loads (NEC 220.41, 220.42, 220.45 & 220.52) 6.2 Standard Dwelling Unit Feeder & Service Calculations (NEC Article 220 Part III) 6.3 Optional Dwelling Unit Feeder & Service Calculations (NEC Article 220 Part IV) 6.4 Commercial & Multi-Family Load Calculations (Cooktops, Dryers, HVAC & Stores)

7 Chapter 7: Overcurrent Protection & Tap Rules (NEC Article 240)

7.1 Overcurrent Protection Fundamentals & Standard Ampere Ratings (240.4 & 240.6) 7.2 Feeder & Branch Circuit Tap Rules (NEC 240.21) 7.3 Ground-Fault Protection of Equipment & Selective Coordination (NEC 240.13, 240.86 & Article 245)

8 Chapter 8: Grounding and Bonding (NEC Article 250)

8.1 General Grounding Principles, System Grounding & Grounded Conductors (NEC 250.4, 250.20 & 250.24) 8.2 Grounding Electrode System & Grounding Electrode Conductor (GEC) Sizing (NEC 250.50, 250.52 & 250.66) 8.3 Equipment Grounding Conductors (EGC) Sizing & Installation (NEC 250.118, 250.120 & 250.122) 8.4 Bonding Requirements, Main/System Bonding Jumpers & Separately Derived Systems (NEC 250.28, 250.30 & 250.102)

9 Chapter 9: Wiring Methods & Materials (NEC Articles 300–314)

9.1 General Requirements for Wiring Methods, Underground Clearances & Firestopping (NEC Article 300) 9.2 Conductor Ampacity Ratings, Temperature Correction & Bundling Adjustments (Article 310 & Table 310.16) 9.3 Nonmetallic-Sheathed Cable (Type NM), Metal-Clad Cable (Type MC) & Armored Cable (Type AC) 9.4 Outlet, Device, Pull & Junction Boxes Sizing and Box Fill Calculations (NEC Article 314) 9.5 Temporary Installations (Article 590), Cranes & Hoists (Article 610), Elevators & Escalators (Article 620)

10 Chapter 10: Raceways, Tubing, Conduit Fill & Underground Systems

10.1 Rigid Metal Conduit (RMC), Intermediate Metal Conduit (IMC) & Electrical Metallic Tubing (EMT) 10.2 Nonmetallic Raceways (PVC, RTRC, Liquidtight) & Cable Trays (NEC Articles 352, 356, 392) 10.3 Conduit Fill Calculations (Chapter 9 Tables 1, 4 & 5, Annex C) & Pull Box Sizing (NEC 314.28)

11 Chapter 11: Motors, Controllers & Air Conditioning (NEC Articles 430 & 440)

11.1 Motor Full-Load Current (FLC), Branch Circuit Conductor Sizing & Disconnects (430.6, 430.22 & 430.102) 11.2 Motor Overload Protection & Motor Branch Circuit Short-Circuit/Ground-Fault Protection (430.32 & 430.52) 11.3 Motor Feeder Conductor Sizing & Feeder Overcurrent Protection (430.24 & 430.62) 11.4 Air Conditioning & Refrigeration Equipment (NEC Article 440: MCA, MOCP & Disconnects)

12 Chapter 12: Transformers & Equipment (NEC Articles 450, 410, 422 & 424)

12.1 Transformer Sizing, Protection & Voltage Calculations (NEC Article 450 & Table 450.3(B)) 12.2 Luminaires, Lampholders & Lamps Installation (NEC Article 410) 12.3 Appliances & Electric Water Heaters (NEC Article 422) 12.4 Fixed Electric Space-Heating Equipment (NEC Article 424) 12.5 Snow-Melting & De-Icing Equipment (Article 426) and Pipeline & Vessel Heating (Article 427) 12.6 Electric Signs & Outline Lighting (Article 600) and Lighting Systems 30 Volts or Less (Article 411)

13 Chapter 13: Special Occupancies & Hazardous Locations (NEC Articles 500–517)

13.1 Hazardous (Classified) Locations: Class I, II, and III (Articles 500, 501, 502 & 503) 13.2 Commercial Garages, Repair Facilities & Fuel Dispensing Facilities (Articles 511 & 514) 13.3 Health Care Facilities: Patient Care Spaces & Wiring Methods (Article 517) 13.4 Agricultural Buildings & Manufactured/Mobile Homes (Articles 547 & 550) 13.5 Bulk Storage Plants (Article 515) and Spray Application, Dipping & Coating (Article 516)

14 Chapter 14: Special Equipment, Swimming Pools & Low-Voltage Systems

14.1 Swimming Pools, Spas, Hot Tubs & Hydromassage Bathtubs (Article 680) 14.2 Emergency Systems, Legally Required & Optional Standby Systems (Articles 700, 701 & 702) 14.3 Class 1, 2, 3 & Class 4 Power-Limited Circuits (NEC Articles 722, 724, 725 & 726) and Fire Alarms (NEC Article 760) 14.4 RV Parks (Article 551), Floating Buildings (Article 553) & Marinas/Docking Facilities (Article 555)

10.2 Nonmetallic Raceways (PVC, RTRC, Liquidtight) & Cable Trays (NEC Articles 352, 356, 392)

Key Takeaways Explain This Topic AI

Schedule 80 PVC is required where rigid nonmetallic conduit is exposed to physical damage; Schedule 40 PVC, ENT, and LFNC are not permitted in those locations.

NEC 352.44 requires an expansion fitting wherever the calculated length change between securely mounted points is 0.25 inch or more, computed from Table 352.44 at 4.06 inches per 100 feet per 100°F.

Listed LFMC may serve as the sole equipment grounding conductor only within the length and overcurrent limits of 250.118(6); beyond 6 feet in the ground return path or above the stated overcurrent rating, a wire-type EGC is required.

Single conductors in cable tray must be 1/0 AWG or larger and marked for cable tray use (NEC 392.10(B)(1)).

Type FMT is limited to dry locations and lengths not exceeding 6 feet and is not a recognized equipment grounding conductor; surface nonmetallic raceway may not be used above 300 volts between conductors unless it has a metal cover.

Last updated: August 2026

Nonmetallic Raceways (PVC, RTRC, Liquidtight) & Cable Trays (NEC Articles 352, 356, 392)

Nonmetallic raceways and cable tray systems offer superior corrosion resistance, chemical immunity, and lightweight structural support in commercial, industrial, and utility environments. However, nonmetallic materials exhibit high coefficients of thermal expansion and lack the innate conductivity of steel raceways, requiring dedicated equipment grounding conductors (EGCs) and carefully engineered expansion joints. Understanding the specific installation boundaries for Schedule 40 vs Schedule 80 PVC, Reinforced Thermosetting Resin Conduit (RTRC), Liquidtight Flexible Conduit (LFMC/LFNC), and Cable Tray systems is critical for passing the Oklahoma Journeyman Electrician examination.

1. Rigid Polyvinyl Chloride Conduit (PVC - NEC Article 352)

Rigid PVC conduit is the most widely installed underground and corrosive-environment raceway. It is impervious to moisture, acids, alkalis, and soil chemicals. +---------------------------------------------------------------------------------------------------------+

  • | SCHEDULE 40 VS. SCHEDULE 80 PVC COMPARISON |
  • | |
  • | Feature / Parameter Schedule 40 PVC (Article 352) Schedule 80 PVC (Article 352) |
  • | ----------------------------- ----------------------------------- -------------------------------- |
  • | Wall Thickness Standard wall thickness Thick heavy-duty wall |
  • | Internal Cross-Sectional Area Larger internal area Smaller internal area (less fill)|
  • | Physical Damage Rating Normal / moderate conditions SUBJECT TO PHYSICAL DAMAGE |
  • | Emerging from Earth (300.5(D)) Requires protection where exposed Approved for physical protection |
  • | Direct Burial Cover Depth 18 inches (general soil) 18 inches (general soil) |
  • | Underground under Driveways 24 inches (commercial driveways) 24 inches (commercial driveways) |
  • +---------------------------------------------------------------------------------------------------------+
  • Schedule 40 vs. Schedule 80 Selection Rules (NEC 352.10(F))

Schedule 40 PVC: Permitted underground, direct-buried, encased in concrete, in walls/floors, and exposed in locations not subject to physical damage.

Schedule 80 PVC (Physical Damage Requirement): Where conduit is installed in areas subject to physical damage , Schedule 80 PVC is mandatory (NEC 352.10(F)). Examples include conduit emerging from grade on the exterior of commercial buildings, service riser poles, warehouse traffic aisles, and parking garages where vehicles or forklifts operate.

Conduit Fill Caution: Because Schedule 80 PVC has a much thicker wall, its inside diameter is significantly smaller than Schedule 40. Always use NEC Chapter 9 Table 4 (Schedule 80 PVC) when calculating conductor fill, as fewer conductors can fit into Schedule 80 than Schedule 40 of the same trade size.

Thermal Expansion & Contraction (NEC 352.44 & Table 352.44)

PVC has a high coefficient of thermal expansion ( 3.06 × 10 − 5 in./in. / ∘ F 3.06 \times 10^{-5}\text{ in./in.}/^\circ\text{F} 3.06 × 1 0 − 5 in./in. / ∘ F ). In outdoor environments with seasonal temperature swings, long PVC conduit runs expand and contract dramatically, pulling out of boxes or buckling off walls if expansion joints are omitted. Δ L = ( Length in Feet 100 ) × ( Δ T in ∘ F 100 ) × 4.06 inches \Delta L = \left( \frac{\text{Length in Feet}}{100} \right) \times \left( \frac{\Delta T \text{ in } ^\circ\text{F}}{100} \right) \times 4.06\text{ inches} Δ L = ( 100 Length in Feet ​ ) × ( 100 Δ T in ∘ F ​ ) × 4.06 inches +-----------------------------------------------------------------------------+

  • | PVC EXPANSION FITTING TRIGGER RULE |
  • | (NEC 352.44) |
  • | |
  • | If the total estimated change in length (ΔL) between securely mounted |
  • | boxes or anchor points is 0.25 INCHES (6 mm) OR GREATER, an expansion |
  • | fitting MUST be installed! |
  • +-----------------------------------------------------------------------------+
  • Worked Example: Rooftop Solar PVC Expansion Calculation

An electrician installs an 80-foot continuous exposed run of Schedule 40 PVC conduit across an Oklahoma commercial rooftop. The expected winter low is − 10 ∘ F -10^\circ\text{F} − 1 0 ∘ F and the summer rooftop high is 130 ∘ F 130^\circ\text{F} 13 0 ∘ F .

Calculate Temperature Differential ( Δ T \Delta T Δ T ): Δ T = 130 ∘ F − ( − 10 ∘ F ) = 140 ∘ F \Delta T = 130^\circ\text{F} - (-10^\circ\text{F}) = 140^\circ\text{F} Δ T = 13 0 ∘ F − ( − 1 0 ∘ F ) = 14 0 ∘ F

Determine Expansion from Table 352.44: From NEC Table 352.44, PVC expands 4.06 inches 4.06\text{ inches} 4.06 inches per 100 ft 100\text{ ft} 100 ft per 100 ∘ F 100^\circ\text{F} 10 0 ∘ F temperature change.

Calculate Total Expansion Length ( Δ L \Delta L Δ L ): Δ L = ( 80 ft 100 ) × ( 140 ∘ F 100 ) × 4.06 in. = 0.80 × 1.40 × 4.06 = 4.55 inches \Delta L = \left(\frac{80\text{ ft}}{100}\right) \times \left(\frac{140^\circ\text{F}}{100}\right) \times 4.06\text{ in.} = 0.80 \times 1.40 \times 4.06 = 4.55\text{ inches} Δ L = ( 100 80 ft ​ ) × ( 100 14 0 ∘ F ​ ) × 4.06 in. = 0.80 × 1.40 × 4.06 = 4.55 inches

Conclusion: Since 4.55 inches ≥ 0.25 inches 4.55\text{ inches} \ge 0.25\text{ inches} 4.55 inches ≥ 0.25 inches , an expansion fitting is required. A listed expansion fitting providing at least 5 inches of travel (or two smaller fittings) must be installed.

Support Spacing for PVC Conduit (NEC Table 352.30)

  • Conduit Trade Size Maximum Support Spacing
  • 1/2 in. through 1 in. 3 feet (900 mm)
  • 1-1/4 in. through 2 in. 5 feet (1.5 m)
  • 2-1/2 in. through 3 in. 6 feet (1.8 m)
  • 3-1/2 in. through 5 in. 7 feet (2.1 m)
  • 6 in. 8 feet (2.4 m)

Note: PVC conduit must also be securely fastened within 3 feet (900 mm) of each box, cabinet, or termination fitting.

2. Reinforced Thermosetting Resin Conduit (RTRC / Fiberglass - NEC Article 355)

Reinforced Thermosetting Resin Conduit (RTRC), commonly known as fiberglass conduit, is an engineered nonmetallic raceway manufactured from wound fiberglass filaments impregnated with thermosetting epoxy resin. +-----------------------------------------------------------------------------+

  • | RTRC CLASSIFICATIONS (NEC 355) |
  • | |
  • | [Type RTRC-AG (Above Ground)] - Standard wall for exposed/concealed |
  • | [Type RTRC-BG (Below Ground)] - Thinner wall for direct burial/duct |
  • | [Type RTRC-XW (eXtra-Wall)] - Heavy-wall listed for SEVERE PHYSICAL |
  • | DAMAGE & Class I, Div 2 locations |
  • +-----------------------------------------------------------------------------+

Key Advantages & Code Applications:

Thermal Stability: Coefficient of thermal expansion is significantly lower than PVC ( 1.37 × 10 − 5 in./in. / ∘ F 1.37 \times 10^{-5}\text{ in./in.}/^\circ\text{F} 1.37 × 1 0 − 5 in./in. / ∘ F — less than half that of PVC).

Severe Physical Damage: Type RTRC-XW is specifically listed for installations where subject to severe physical damage (NEC 355.10(F)), such as highway bridges, railway overpasses, wastewater treatment plants, and coastal marine docks.

Low Smoke Zero Halogen (LSZH): Unlike PVC (which releases toxic hydrogen chloride gas when burned), RTRC releases non-toxic combustion products, making it ideal for transit tunnels and mining.

3. Flexible Conduits: FMC, LFMC & LFNC

Flexible raceways are designed to isolate vibration at motors, transformers, and HVAC equipment, and to facilitate routing through tight architectural obstructions. +---------------------------------------------------------------------------------------------------------+

  • | FLEXIBLE RACEWAYS COMPARISON & LIMITATIONS |
  • | |
  • | Raceway Type Article Permitted Environments Max Support Interval Securing from Enclosure |
  • | ---------------- ------- ---------------------- -------------------- ----------------------- |
  • | FMC (Flex) 348 Dry only (indoor) 4.5 feet (1.4 m) Within 12 in. (300 mm) |
  • | LFMC (Sealtite) 350 Wet / outdoor / oily 4.5 feet (1.4 m) Within 12 in. (300 mm) |
  • | LFNC (Nonmetallic) 356 Wet / corrosive / burial 3.0 feet (900 mm) Within 12 in. (300 mm) |
  • +---------------------------------------------------------------------------------------------------------+

Equipment Grounding Limitations for Flexible Conduits (NEC 250.118):

FMC (NEC 250.118(5)): Listed FMC is permitted as an equipment grounding conductor ONLY if:

The total length of the ground return path does not exceed 6 feet (1.8 m) .

The circuit conductors are protected by overcurrent devices rated at 20 amperes or less .

Listed fittings are used. (If over 20A or > 6 ft, a separate copper EGC must be pulled inside!).

LFMC (NEC 250.118(6)): Listed LFMC is permitted as an EGC ONLY if:

Total length does not exceed 6 feet (1.8 m) .

Overcurrent protection is rated ≤ 20 A \le 20\text{A} ≤ 20 A (for 3/8"–1/2" trade size) or ≤ 60 A \le 60\text{A} ≤ 60 A (for 3/4"–1-1/4" trade size).

For runs > 6 ft > 6\text{ ft} > 6 ft or higher overcurrent ratings, a dedicated equipment grounding conductor is mandatory.

Support Exceptions for Flexible Raceways:

Luminaire Taps (NEC 348.30(A) Ex. 3 & 350.30(A) Ex. 3): Lengths up to 6 feet (1.8 m) from an outlet box to a luminaire above an accessible drop ceiling are permitted without intermediate supports.

Flexibility at Terminals: Lengths up to 3 feet (900 mm) for LFNC or 3 feet for FMC/LFMC are permitted without support where flexibility is required at motor terminals or vibrating equipment.

4. Cable Trays (NEC Article 392)

Cable trays are rigid structural support systems designed to carry insulated conductors, power cables, control cables, and optical fiber cables in commercial and industrial facilities. +-----------------------------------------------------------------------------+

  • | CABLE TRAY SYSTEM TYPES |
  • | |
  • | [Ladder Tray] [Ventilated Trough] [Solid Bottom Tray] |
  • | Two longitudinal side Perforated steel/Al base Solid sheet metal base |
  • | rails joined by rungs; providing partial bottom providing maximum EMI |
  • | maximum heat dissipation support & ventilation shielding & drop prot |
  • +-----------------------------------------------------------------------------+

Permitted Cable Types (NEC 392.10(A)):

  • Metal-Clad Cable (Type MC)
  • Power and Control Tray Cable (Type TC)
  • Mineral-Insulated Metal-Sheathed Cable (Type MI)
  • Instrumentation Tray Cable (Type ITC)
  • Armored Cable (Type AC)
  • Optical Fiber Cables and Communication Cables

Single-Conductor Cable Rules in Cable Trays (NEC 392.10(B)(1)):

Minimum Conductor Size: Single conductors installed in cable tray must be size 1/0 AWG or larger and marked for cable tray use (marked "CT" or "for CT use"). Conductors smaller than 1/0 AWG are prohibited as single conductors in cable tray (they must be in multiconductor cables).

Single Layer Installation (NEC 392.22(B)(1)): Where single-conductor cables are sizes 1/0 AWG through 4/0 AWG, they must be installed in a single layer in ladder or ventilated trough cable trays.

Metal Cable Trays as Equipment Grounding Conductors (NEC 392.60(B)):

Steel or aluminum cable trays are permitted to be used as Equipment Grounding Conductors (EGCs) provided ALL of the following four conditions are met:

Marking: The cable tray sections and fittings are identified and marked with their minimum cross-sectional area.

Minimum Cross-Sectional Area: The total cross-sectional area of metal meets or exceeds the requirements of NEC Table 392.60(A) based on the largest rating of overcurrent device protecting circuits in the tray.

Bonding Jumpers: All tray joints, expansion splices, and mechanical connections are bonded using listed bonding jumpers sized per NEC 250.102(D) or listed mechanical bonding splice plates.

Qualified Maintenance: In industrial establishments where conditions of maintenance and supervision ensure that only qualified persons service the installation.

5. The Remaining Raceway Articles the PSI Outline Lists

The Raceways and Boxes subject area enumerates 22 sub-topics but carries only 7 scored items , so the Code expects you to recognize each raceway type and know its one defining limitation rather than to master every article. The types not covered above:

Raceway Article The limitation that defines it

Type FMT — Flexible Metallic Tubing 360 Dry locations only, and permitted only in lengths not exceeding 6 feet . Manufactured in trade sizes ½ and ¾ only. Not permitted in hoistways, in storage battery rooms, in hazardous (classified) locations, underground, embedded in concrete or aggregate, or where subject to physical damage. FMT is not an equipment grounding conductor — an EGC must be installed in the tubing.

Surface Metal Raceway 386 Dry locations only. Not permitted where subject to severe physical damage, where corrosive vapors exist, in hoistways, or in classified locations except as specifically permitted. Where it is a combination raceway with separate compartments for power and signal conductors, the compartments must be identified by stamping, imprinting, or color coding the interior surface.

Surface Nonmetallic Raceway 388 Dry locations only, and additionally barred from concealed locations, from ambient temperatures above the listing, and from circuits where the voltage exceeds 300 volts between conductors unless the raceway has a metal cover.

Underfloor Raceway 390 Permitted under the floor surface with defined cover; not permitted where corrosive vapors are present, in hazardous locations except as permitted, or in commercial garages other than for supplying outlets under the floor. Junction boxes must be level with the floor and sealed against water.

Auxiliary Gutter 366 A wiring supplement , not a distribution raceway: it may not extend more than 30 inches beyond the equipment it supplements except in specific industrial cases, and conductor fill is limited (generally 20 percent, with a 30-conductor current-carrying limit before derating).

Busway 368 A listed assembly of busbars in a protective housing, supported at defined intervals; totally enclosed busway may be run vertically through floors and horizontally through dry walls with specific firestopping and length conditions.

Metal and Nonmetallic Wireway 376 / 378 A sheet-metal or nonmetallic trough with a hinged or removable cover: conductor fill is limited to 20 percent of the interior cross-sectional area, and 30 current-carrying conductors is the point at which adjustment factors begin to apply.

Important

Three numbers from this table earn their keep on exam day. FMT is capped at 6 feet . Surface nonmetallic raceway is barred above 300 volts between conductors unless it has a metal cover. Wireways and auxiliary gutters share the 20 percent fill / 30 current-carrying conductor pair — the same two figures, applied to two different articles.

Loading diagram... Nonmetallic Raceways & Cable Tray Decision Tree (NEC Articles 350, 352, 355, 356, 392)