9.5 Temporary Installations (Article 590), Cranes & Hoists (Article 610), Elevators & Escalators (Article 620)

Oklahoma Journeyman Electrician Exam

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: Oklahoma Licensing Laws, Board Rules & Safety

1.1 Oklahoma Electrical License Act & CIB Regulations 1.2 OK Journeyman Exam Format, PSI Logistics & Codebook Navigation 1.3 OSHA Electrical Safety Standards (29 CFR 1926/1910) 1.4 NFPA 70E Electrical Safety in the Workplace & Arc Flash 1.5 Permits, Inspections, Structural Integrity & Job Estimating 1.6 Oklahoma's Adopted 2023 NEC: OUBCC Amendments You Must Know 1.7 OSHA 29 CFR 1926 Job-Site Safety: Sanitation, Signage, Ladders, Scaffolds & Fall Protection

2 Chapter 2: General Electrical Theory & Calculations

2.1 Ohm's Law, Watt's Law & DC Series/Parallel Circuits 2.2 AC Theory, Reactance, Impedance & Power Factor 2.3 Three-Phase Power Systems (Delta & Wye Configurations) 2.4 Electrical Units, Formulas & Conversions 2.5 Cost of Power in a Circuit, Efficiency & Troubleshooting/Test Instruments

3 Chapter 3: General Installation Requirements (NEC Article 110)

3.1 Examination, Identification, Installation & Use of Equipment (110.3) 3.2 Electrical Connections, Terminations & Torque Requirements (110.14) 3.3 Working Space, Clearances & Guarding of Live Parts (110.26 & 110.27) 3.4 Enclosure Types, Markings & Available Fault Current (110.24 & 110.28) 3.5 Installations Over 600 Volts: Article 110 Part III, Article 490 & Medium-Voltage Cable

4 Chapter 4: Branch Circuits & Feeders (NEC Articles 210, 215 & 225)

4.1 Branch Circuit Ratings, Multiwire Branch Circuits & Identification (210.3–210.10) 4.2 Ground-Fault Circuit-Interrupter (GFCI) Protection (210.8) 4.3 Arc-Fault Circuit-Interrupter (AFCI) Protection & Receptacle Outlets (210.12 & 210.52) 4.4 Outside Branch Circuits and Feeders (Article 225) & Feeder Sizing (Article 215)

5 Chapter 5: Services & Service Equipment (NEC Article 230)

5.1 Service Clearances, Overhead & Underground Service-Drop Requirements (230.9, 230.24 & 230.30) 5.2 Service-Entrance Conductors, Sizing & Installation (230.40–230.54) 5.3 Service Equipment Disconnecting Means, Overcurrent Protection & Emergency Disconnects (230.70–230.95)

6 Chapter 6: Electrical Load Calculations (NEC Article 220)

6.1 General Lighting, Small Appliance & Laundry Loads (NEC 220.41, 220.42, 220.45 & 220.52) 6.2 Standard Dwelling Unit Feeder & Service Calculations (NEC Article 220 Part III) 6.3 Optional Dwelling Unit Feeder & Service Calculations (NEC Article 220 Part IV) 6.4 Commercial & Multi-Family Load Calculations (Cooktops, Dryers, HVAC & Stores)

7 Chapter 7: Overcurrent Protection & Tap Rules (NEC Article 240)

7.1 Overcurrent Protection Fundamentals & Standard Ampere Ratings (240.4 & 240.6) 7.2 Feeder & Branch Circuit Tap Rules (NEC 240.21) 7.3 Ground-Fault Protection of Equipment & Selective Coordination (NEC 240.13, 240.86 & Article 245)

8 Chapter 8: Grounding and Bonding (NEC Article 250)

8.1 General Grounding Principles, System Grounding & Grounded Conductors (NEC 250.4, 250.20 & 250.24) 8.2 Grounding Electrode System & Grounding Electrode Conductor (GEC) Sizing (NEC 250.50, 250.52 & 250.66) 8.3 Equipment Grounding Conductors (EGC) Sizing & Installation (NEC 250.118, 250.120 & 250.122) 8.4 Bonding Requirements, Main/System Bonding Jumpers & Separately Derived Systems (NEC 250.28, 250.30 & 250.102)

9 Chapter 9: Wiring Methods & Materials (NEC Articles 300–314)

9.1 General Requirements for Wiring Methods, Underground Clearances & Firestopping (NEC Article 300) 9.2 Conductor Ampacity Ratings, Temperature Correction & Bundling Adjustments (Article 310 & Table 310.16) 9.3 Nonmetallic-Sheathed Cable (Type NM), Metal-Clad Cable (Type MC) & Armored Cable (Type AC) 9.4 Outlet, Device, Pull & Junction Boxes Sizing and Box Fill Calculations (NEC Article 314) 9.5 Temporary Installations (Article 590), Cranes & Hoists (Article 610), Elevators & Escalators (Article 620)

10 Chapter 10: Raceways, Tubing, Conduit Fill & Underground Systems

10.1 Rigid Metal Conduit (RMC), Intermediate Metal Conduit (IMC) & Electrical Metallic Tubing (EMT) 10.2 Nonmetallic Raceways (PVC, RTRC, Liquidtight) & Cable Trays (NEC Articles 352, 356, 392) 10.3 Conduit Fill Calculations (Chapter 9 Tables 1, 4 & 5, Annex C) & Pull Box Sizing (NEC 314.28)

11 Chapter 11: Motors, Controllers & Air Conditioning (NEC Articles 430 & 440)

11.1 Motor Full-Load Current (FLC), Branch Circuit Conductor Sizing & Disconnects (430.6, 430.22 & 430.102) 11.2 Motor Overload Protection & Motor Branch Circuit Short-Circuit/Ground-Fault Protection (430.32 & 430.52) 11.3 Motor Feeder Conductor Sizing & Feeder Overcurrent Protection (430.24 & 430.62) 11.4 Air Conditioning & Refrigeration Equipment (NEC Article 440: MCA, MOCP & Disconnects)

12 Chapter 12: Transformers & Equipment (NEC Articles 450, 410, 422 & 424)

12.1 Transformer Sizing, Protection & Voltage Calculations (NEC Article 450 & Table 450.3(B)) 12.2 Luminaires, Lampholders & Lamps Installation (NEC Article 410) 12.3 Appliances & Electric Water Heaters (NEC Article 422) 12.4 Fixed Electric Space-Heating Equipment (NEC Article 424) 12.5 Snow-Melting & De-Icing Equipment (Article 426) and Pipeline & Vessel Heating (Article 427) 12.6 Electric Signs & Outline Lighting (Article 600) and Lighting Systems 30 Volts or Less (Article 411)

13 Chapter 13: Special Occupancies & Hazardous Locations (NEC Articles 500–517)

13.1 Hazardous (Classified) Locations: Class I, II, and III (Articles 500, 501, 502 & 503) 13.2 Commercial Garages, Repair Facilities & Fuel Dispensing Facilities (Articles 511 & 514) 13.3 Health Care Facilities: Patient Care Spaces & Wiring Methods (Article 517) 13.4 Agricultural Buildings & Manufactured/Mobile Homes (Articles 547 & 550) 13.5 Bulk Storage Plants (Article 515) and Spray Application, Dipping & Coating (Article 516)

14 Chapter 14: Special Equipment, Swimming Pools & Low-Voltage Systems

14.1 Swimming Pools, Spas, Hot Tubs & Hydromassage Bathtubs (Article 680) 14.2 Emergency Systems, Legally Required & Optional Standby Systems (Articles 700, 701 & 702) 14.3 Class 1, 2, 3 & Class 4 Power-Limited Circuits (NEC Articles 722, 724, 725 & 726) and Fire Alarms (NEC Article 760) 14.4 RV Parks (Article 551), Floating Buildings (Article 553) & Marinas/Docking Facilities (Article 555)

9.5 Temporary Installations (Article 590), Cranes & Hoists (Article 610), Elevators & Escalators (Article 620)

Key Takeaways Explain This Topic AI

NEC 590.3(B) limits temporary wiring for holiday decorative lighting and similar purposes to 90 days, while 590.3(A) permits temporary wiring for the period of construction, remodeling, maintenance, repair, or demolition, and 590.3(D) requires removal immediately upon completion.

NEC 590.6(A) requires GFCI protection for personnel on all 125-volt, single-phase, 15-, 20-, and 30-ampere receptacle outlets that are not part of the permanent wiring, with an assured equipment grounding conductor program permitted only for receptacles outside that description.

Crane and hoist conductors are sized from Table 610.14(A) using short-time motor ratings and are generally not smaller than 16 AWG, and Table 610.14(E) supplies demand factors where several motors share the same conductors.

A crane or monorail hoist disconnect under 610.32 must be within sight of the crane or hoist, readily accessible and operable from the ground or floor level, and lockable in the open position.

NEC 620.85 requires GFCI protection for 125-volt, single-phase, 15- and 20-ampere receptacles installed in elevator pits, hoistways, on car tops, in escalator and moving walk wellways, and in machine rooms, machinery spaces, control rooms, and control spaces.

Last updated: August 2026

9.5 Temporary Installations (Article 590), Cranes & Hoists (Article 610), Elevators & Escalators (Article 620)

The PSI outline hides three complete NEC articles inside the General Electrical Knowledge subject area as sub-topics (j) temporary wiring , (k) cranes and hoists , and (l) elevators and escalators . Each is a Chapter 5 or Chapter 6 article whose rules supplement or modify the general Chapter 3 wiring rules, and each has two or three numbers the exam reliably asks for.

1. Article 590 — Temporary Installations

Article 590 is a relaxation, not a loophole. It permits methods that would be unacceptable permanently, and pays for that relaxation with time limits and mandatory GFCI protection.

590.3 Time constraints

Subsection Permitted use Time limit

590.3(A) During the period of construction, remodeling, maintenance, repair, or demolition The period of the work

590.3(B) Holiday decorative lighting and similar purposes 90 days

590.3(C) Emergencies and for tests, experiments, and developmental work The duration of the emergency, test, or developmental work

590.3(D) — Temporary wiring must be removed immediately upon completion of construction or the purpose for which it was installed

590.4 General requirements

Services are installed in conformance with Article 230, exactly as they would be permanently.

Feeders must originate in an approved distribution center and may be run as multiconductor cord or cable assemblies or, where not subject to physical damage, as single insulated conductors supported by the messenger or in a raceway.

Branch circuits originate in an approved power outlet or panelboard.

Receptacles must be of the grounding type and must be connected to an equipment grounding conductor; on construction sites, receptacles may not be installed on any branch circuit that supplies temporary lighting.

Lamp protection. Lamps for general illumination must be protected from accidental contact by a suitable luminaire or lampholder with a guard; brass shell, paper-lined, and unprotected sockets are prohibited.

Support. Cable assemblies and flexible cords may not be laid on the floor, must be protected where they pass through doorways or are subject to vehicle traffic, and — outside of the 590.3(B) holiday allowance — may not be supported by vegetation .

Splices made without a box are permitted for nonmetallic multiconductor cord or cable assemblies, provided the equipment grounding continuity is maintained (590.4(G)).

590.6 Ground-fault protection for personnel — the rule that gets tested

590.6(A)(1): All 125-volt, single-phase, 15-, 20-, and 30-ampere receptacle outlets that are not part of the permanent wiring and are in use by personnel must have GFCI protection . There is no AEGCP substitute here.

590.6(A)(2): Receptacles other than those in (A)(1), up to 250 volts, must also have GFCI protection where used by personnel.

590.6(A)(3): Receptacles on 15 kW or smaller portable generators are addressed separately.

590.6(B): For receptacles other than the 125-volt 15/20/30-ampere ones, an assured equipment grounding conductor program may be used in place of GFCI protection — with written program documentation, a designated competent person, continuity testing of every cord and receptacle, and testing intervals (before first use, after repair, after suspected damage, and at least every three months).

590.7: A disconnecting means must be provided to allow the disconnection of all ungrounded conductors of each temporary circuit.

2. Article 610 — Cranes and Hoists

Crane motors run on short-time duty , so crane conductors are sized from a duty-specific table rather than from Table 310.16:

610.14(A) sends you to Table 610.14(A) for the ampacities of insulated conductors used with short-time-rated crane and hoist motors, indexed by conductor size, temperature rating, and the duty cycle (30-minute, 60-minute, or continuous).

Minimum size: conductors used in crane and hoist circuits are generally not smaller than 16 AWG , with narrow allowances for control circuits and for multiconductor cable within listed assemblies.

610.14(E) provides demand factors for conductors supplying more than one motor on a crane or hoist — the same principle as a motor feeder, adapted to intermittent hoisting duty.

610.13 governs the conductor types permitted, and 610.11 the wiring methods; flexible connections to moving parts use listed flexible cord or cable in a strain-relieving arrangement.

610.21 covers contact (collector) conductors — the rigid runway conductors or festooned cable that feed a moving bridge — including support spacing, clearance from the crane bridge, and guarding against accidental contact.

610.31 requires a runway conductor disconnecting means — a readily accessible, lockable disconnect, operable from the ground or floor, that opens all ungrounded runway conductors.

610.32 requires a disconnecting means for the crane or monorail hoist itself , located within sight of the crane or hoist, readily accessible and operable from the ground or floor level, lockable in the open position, and opening all ungrounded conductors simultaneously.

610.41 covers overcurrent protection of the contact conductors and the crane branch circuits.

610.61 requires the crane or hoist frame to be grounded . Moving parts other than removable accessories having metal-to-metal bearing surfaces are considered electrically connected through those surfaces, and the trolley and bridge frames are considered grounded through the bridge and trolley wheels and their tracks unless conditions such as paint or grease prevent reliable metal-to-metal contact — in which case a separate bonding conductor is required.

3. Article 620 — Elevators, Dumbwaiters, Escalators, Moving Walks, Platform Lifts, and Stairway Chairlifts

Article 620 is where an electrician most often works alongside another trade, and its separation-of-circuits rules exist so that an elevator mechanic is never dependent on the building electrician to get light in a pit.

Branch circuits that must stand alone

Requirement Section Detail

Car lights, receptacles, ventilation 620.22(A) A separate branch circuit supplies the car lights, receptacle(s), auxiliary lighting, and ventilation on each elevator car

Machine room / control room 620.22(B) A separate branch circuit supplies the lighting and receptacles in each machine room, control room, machinery space, and control space; the required lighting switch must be located at the point of entry

Machine room lighting and receptacle 620.24 At least one 125-volt, single-phase, 15- or 20-ampere duplex receptacle and a means of illumination are required in machine rooms, control rooms, machinery spaces, and control spaces; lighting may not be connected to the load side of a GFCI device

Pit lighting and receptacle 620.23 At least one 125-volt, single-phase, 15- or 20-ampere duplex receptacle and permanent lighting in the pit, with a light switch accessible from the pit access door

Conductor sizing and demand

620.13 sizes feeders and branch circuits from the motor and controller ratings, accounting for the intermittent duty of the elevator machine. Where a single feeder supplies more than one elevator, 620.14 and Table 620.14 provide demand factors that recognize that not every car accelerates at the same instant.

Disconnecting means and coordination

620.51 requires a single means for disconnecting all ungrounded main power supply conductors for each unit: an enclosed externally operable fused motor circuit switch or circuit breaker, lockable in the open position , and located where it is readily accessible to qualified persons and visible from the controller (with provisions for remote machine rooms).

620.51(C) prohibits that disconnect from disconnecting the car lighting, receptacle, and ventilation circuits — those have their own disconnect under 620.53 , which must also be lockable in the open position.

620.62 requires selective coordination : where more than one driving machine disconnecting means is supplied by a single feeder , the overcurrent protective devices in each disconnecting means must be selectively coordinated with any other supply-side overcurrent protective device. One stalled car may not take the whole bank down.

620.85 requires GFCI protection for 125-volt, single-phase, 15- and 20-ampere receptacles installed in pits, hoistways, on car tops, and in escalator and moving walk wellways , as well as in machine rooms, machinery spaces, control rooms, and control spaces.

Important

The hoistway is not a chase. Under 620.21, only wiring and equipment used directly in connection with the elevator may be installed inside a hoistway, machine room, control room, machinery space, or control space. Running a building lighting circuit or a data cable through a hoistway because it is a convenient vertical path is a violation and a rejected inspection.