Planting plans, stock sizes, and quantity takeoffs
Oregon Landscape Contractor License Study Guide 2026
Track your progress as you read
Finished sections get a check mark.
1 1. Licensing and business: 1
Exam structure, reference use, and license routes Oregon jurisdiction, license phases, and eligibility Bonds, insurance, and financial responsibility
2 2. Licensing and business: 2
Employee status, paid work, and payroll calculations Hiring, breaks, sick time, and workplace protections Contracts, cancellation, guarantees, and liens
3 3. Licensing and business: 3
LCP supervision and clear project communication Direct costs and overhead allocation Margin, markup, changes, and job costing
4 4. Site safety and utilities
Excavation safety and hazard controls Oregon 811 notices and utility protection
5 5. Soil science and site preparation: 1
Soil texture, structure, and pore space Density, regional profiles, and soil water Soil pH, diagnosis, and exchange capacity
6 6. Soil science and site preparation: 2
Amendments and fertilizer calculations Compaction, decompaction, and topsoil protection Topsoil placement, finish grades, and weeds
7 7. Plants, turf, and establishment: 1
Planting plans, stock sizes, and quantity takeoffs Botanical identification, plant types, and growth habits Mature size, landscape use, and exposure decisions
8 8. Plants, turf, and establishment: 2
Hardiness, microclimates, and plant names Native plant choices and invasive plants Nursery stock, root flares, and planting depth
9 9. Plants, turf, and establishment: 3
Backfill, staking, and mulch Turf species, mixtures, and site suitability Seed, sod, and establishment calculations
10 10. Plants, turf, and establishment: 4
Pruning and integrated pest management Pest diagnosis, weeds, and pesticide credentials
11 11. Paving and concrete: 1
Pavement foundations, drainage, and excavation Separation fabric, aggregate, and compaction Bedding, restraints, and square layout
12 12. Paving and concrete: 2
Paver laying, cuts, patterns, and joint fill Natural stone and rigid or flexible setting Concrete mixture, placement, and finishing
13 13. Paving and concrete: 3
Concrete joints and curing
14 14. Walls and exterior structures: 1
Segmental wall systems and foundations Wall drainage, backfill, and geogrid Earth pressure, stone walls, and footings
15 15. Walls and exterior structures: 2
Masonry reinforcement, wall permits, and failure Lumber dimensions, grades, fasteners, and finishing Treated lumber and outdoor exposure
16 16. Walls and exterior structures: 3
Wood durability, hardware, and post geometry Fences, decks, ledgers, and arbors Landscape steps, stairs, and safe transitions
17 17. Walls and exterior structures: 4
Low-voltage lighting design, wiring, and commissioning Water features, pumps, liners, and water quality
18 18. Design, grading, and drainage: 1
Landscape design, circulation, and coordinated details Surveying, benchmarks, and elevation checks Planting on roofs, decks, and other structures
19 19. Design, grading, and drainage: 2
Drawing sets, legends, and scale Contours, spot elevations, and benchmarks Slope ratios, pitch, and foundation fall
20 20. Design, grading, and drainage: 3
Earthwork, accessible routes, and swales Water sources and French drains Inlets, conveyance, cleanouts, and outlets
21 21. Design, grading, and drainage: 4
Bioretention sizing, media, and plants Swales and current DEQ erosion controls
22 22. Irrigation design and operation: 1
Irrigation site survey and available water Hydrozones and plant-based irrigation design Sprinkler layout, arcs, and zone flow accounting
23 23. Irrigation design and operation: 2
Irrigation symbols, plans, and material takeoffs Pressure, elevation, friction, and budgets Sprinkler types, pressure, and coverage
24 24. Irrigation design and operation: 3
Matched precipitation and runtime formulas Drip irrigation, filtration, and wetted root volume Pipe materials, bore, velocity, and valves
25 25. Irrigation design and operation: 4
Valve service, wiring, and smart controls Controller circuits and electrical troubleshooting Plant culture and root-zone watering decisions
26 26. Irrigation design and operation: 5
Evapotranspiration, soil depletion, and runtime Catch-can audits and irrigation repair diagnosis Installation, testing, winterization, and startup
27 27. Backflow and potable protection: 1
Cross-connections, hazards, and reverse flow Air gaps and physical potable-water separation Vacuum breakers, checks, and RP assemblies
28 28. Backflow and potable protection: 2
Potable, irrigation, and reclaimed-water piping Backflow assembly selection and hydraulic cases Backflow installation, winter care, and reports
Planting plans, stock sizes, and quantity takeoffs
Key Takeaways Explain This Topic AI
Use the plan legend and planting schedule together; symbols alone do not establish stock size.
Grid spacing and area calculations require consistent units and the stated layout.
Include preparation, handling, establishment, and replacements in a planting estimate.
Last updated: October 2026
Read the schedule before counting
A planting plan typically includes symbols, codes, botanical names, common names, quantities, stock sizes, spacing, and notes. A circle is a location symbol, not necessarily a scaled root ball or the final canopy diameter. Determine whether the drawing displays installation size, mature spread, or a graphic convention. Use the legend and schedule rather than infer meaning from a familiar symbol on another designer's plan.
Match each code to a complete specification. “ACPA” might mean a maple on one plan and something else on another. Botanical names resolve ambiguity, while cultivar names can distinguish dramatically different size, color, and growth habit. Container volume, tree caliper, height, branching, and root-stock type describe different attributes. A five-gallon shrub and a two-inch-caliper tree cannot be priced from the same size column without reading its heading.
Review drawing notes and details with the schedule. They can establish nursery quality, prohibited substitutions, planting depth, staking, mulch, watering, and guarantee requirements. The contract may also establish who removes unsuitable soil or maintains plants until acceptance. Count from the latest revision, and identify whether a schedule quantity or drawn count governs when they disagree. Resolve a discrepancy rather than silently choose the smaller order.
Quantities and spacing
Count individual trees and shrubs directly when each location is shown. For a massed groundcover bed, use the stated spacing geometry and the effective planted area. Square spacing allocates roughly spacing squared to each plant; equilateral triangular spacing allocates about 0.866 times spacing squared. The latter supports more plants per unit area at the same center-to-center distance.
For a 600-square-foot bed at two-foot square spacing, the simple estimate is 600 divided by four, or 150 plants. At two-foot triangular spacing, the estimate is 600 divided by 3.464, about 173.2, requiring a whole-number ordering decision. These are interior-area approximations. Actual edge offsets, irregular geometry, access openings, and obstacles affect the layout, so do not claim the formula gives an exact field count for every bed.
Convert inches to feet first. Eighteen inches is 1.5 feet, so square spacing uses 2.25 square feet per plant. Dividing area by eighteen squared would mix units and produce a wildly incorrect quantity. Add a documented allowance for the particular handling and replacement risks rather than automatically add ten percent to all plants. A specified contract quantity and a purchasing allowance should remain separately visible.
Stock, access, and planting labor
Labor depends on stock type and handling. Container stock may need circling-root correction; balled-and-burlapped trees need equipment and careful package removal; bare-root stock needs protection from desiccation. Estimate unloading, movement to the bed, excavation, unsuitable-soil handling, backfill, watering, staking when needed, and cleanup. A tree's purchase price alone does not represent its installed cost.
Check gate width, overhead lines, slopes, pavement load limits, and protected roots before selecting machinery. If a root ball cannot pass through the available gate, the contractor needs a different access plan, stock choice, or handling method before delivery. Lifting by the trunk can damage the tree even when the crown looks intact. Include protection for lawns and paving used as access routes.
Verify plants on delivery: identity, quantity, size, root-ball condition, pests, damage, moisture, and agreement with the accepted specification. Record rejected stock and approved substitutions. Do not count a dead plant in the delivered quantity as if it satisfied the contract. Protect staged plants from wind, heat, freezing, and inadequate watering while other trades finish.
Coordinate the installation
Planting locations must fit grading, drainage, underground utilities, paving, lighting, and irrigation. A tree placed over a drain cleanout can block maintenance; a mature canopy can obstruct a light; a planting pit can damage a recently installed lateral. Locate and stake major plants after the required site investigations and before excavation. Confirm sightlines, setbacks, and owner-approved adjustments.
Finish with a reconciled record of specified, delivered, installed, substituted, and remaining quantities. A measured takeoff supports procurement, but field verification and closeout establish what actually exists. Update the irrigation and maintenance instructions when the accepted planting changes: replacing a drought-adapted shrub with a moisture-loving one can alter zone needs. This links estimating and plan reading to plant culture rather than treating them as separate paperwork tasks.
Field application
A triangular-spaced bed with an access hatch needs its unobstructed planting area reduced before estimating stock. If a 600-square-foot outline contains a 36-square-foot access opening, use 564 square feet for the interior approximation, then resolve edge rows in the field layout. Ordering from the gross outline would place plants over required access or leave unexplained excess material. Mark the opening on both planting and irrigation plans so the crew does not restore the apparent gap during installation.
Reference table
- Interior spacing example Area per plant Approximate count in 600 sq ft
- Two-foot square 4 sq ft 150
- Two-foot triangular 3.464 sq ft 173.2 before whole-number and edge decisions
- Eighteen-inch square 2.25 sq ft 266.7 before layout decisions