Surveying, benchmarks, and elevation checks

Oregon Landscape Contractor License Study Guide 2026

Track your progress as you read

Finished sections get a check mark.

1 1. Licensing and business: 1

Exam structure, reference use, and license routes Oregon jurisdiction, license phases, and eligibility Bonds, insurance, and financial responsibility

2 2. Licensing and business: 2

Employee status, paid work, and payroll calculations Hiring, breaks, sick time, and workplace protections Contracts, cancellation, guarantees, and liens

3 3. Licensing and business: 3

LCP supervision and clear project communication Direct costs and overhead allocation Margin, markup, changes, and job costing

4 4. Site safety and utilities

Excavation safety and hazard controls Oregon 811 notices and utility protection

5 5. Soil science and site preparation: 1

Soil texture, structure, and pore space Density, regional profiles, and soil water Soil pH, diagnosis, and exchange capacity

6 6. Soil science and site preparation: 2

Amendments and fertilizer calculations Compaction, decompaction, and topsoil protection Topsoil placement, finish grades, and weeds

7 7. Plants, turf, and establishment: 1

Planting plans, stock sizes, and quantity takeoffs Botanical identification, plant types, and growth habits Mature size, landscape use, and exposure decisions

8 8. Plants, turf, and establishment: 2

Hardiness, microclimates, and plant names Native plant choices and invasive plants Nursery stock, root flares, and planting depth

9 9. Plants, turf, and establishment: 3

Backfill, staking, and mulch Turf species, mixtures, and site suitability Seed, sod, and establishment calculations

10 10. Plants, turf, and establishment: 4

Pruning and integrated pest management Pest diagnosis, weeds, and pesticide credentials

11 11. Paving and concrete: 1

Pavement foundations, drainage, and excavation Separation fabric, aggregate, and compaction Bedding, restraints, and square layout

12 12. Paving and concrete: 2

Paver laying, cuts, patterns, and joint fill Natural stone and rigid or flexible setting Concrete mixture, placement, and finishing

13 13. Paving and concrete: 3

Concrete joints and curing

14 14. Walls and exterior structures: 1

Segmental wall systems and foundations Wall drainage, backfill, and geogrid Earth pressure, stone walls, and footings

15 15. Walls and exterior structures: 2

Masonry reinforcement, wall permits, and failure Lumber dimensions, grades, fasteners, and finishing Treated lumber and outdoor exposure

16 16. Walls and exterior structures: 3

Wood durability, hardware, and post geometry Fences, decks, ledgers, and arbors Landscape steps, stairs, and safe transitions

17 17. Walls and exterior structures: 4

Low-voltage lighting design, wiring, and commissioning Water features, pumps, liners, and water quality

18 18. Design, grading, and drainage: 1

Landscape design, circulation, and coordinated details Surveying, benchmarks, and elevation checks Planting on roofs, decks, and other structures

19 19. Design, grading, and drainage: 2

Drawing sets, legends, and scale Contours, spot elevations, and benchmarks Slope ratios, pitch, and foundation fall

20 20. Design, grading, and drainage: 3

Earthwork, accessible routes, and swales Water sources and French drains Inlets, conveyance, cleanouts, and outlets

21 21. Design, grading, and drainage: 4

Bioretention sizing, media, and plants Swales and current DEQ erosion controls

22 22. Irrigation design and operation: 1

Irrigation site survey and available water Hydrozones and plant-based irrigation design Sprinkler layout, arcs, and zone flow accounting

23 23. Irrigation design and operation: 2

Irrigation symbols, plans, and material takeoffs Pressure, elevation, friction, and budgets Sprinkler types, pressure, and coverage

24 24. Irrigation design and operation: 3

Matched precipitation and runtime formulas Drip irrigation, filtration, and wetted root volume Pipe materials, bore, velocity, and valves

25 25. Irrigation design and operation: 4

Valve service, wiring, and smart controls Controller circuits and electrical troubleshooting Plant culture and root-zone watering decisions

26 26. Irrigation design and operation: 5

Evapotranspiration, soil depletion, and runtime Catch-can audits and irrigation repair diagnosis Installation, testing, winterization, and startup

27 27. Backflow and potable protection: 1

Cross-connections, hazards, and reverse flow Air gaps and physical potable-water separation Vacuum breakers, checks, and RP assemblies

28 28. Backflow and potable protection: 2

Potable, irrigation, and reclaimed-water piping Backflow assembly selection and hydraulic cases Backflow installation, winter care, and reports

Surveying, benchmarks, and elevation checks

Key Takeaways Explain This Topic AI

Preserve a verified benchmark and use a consistent project datum.

Height of instrument equals benchmark elevation plus backsight.

Point elevation equals height of instrument minus foresight; close the loop to check error.

Last updated: October 2026

Establish control

Surveying for landscape construction locates points and transfers elevations from reliable control. A benchmark has a stated elevation in the project's datum. That datum may be a recognized elevation system or an arbitrary reference, such as assigning a stable point elevation 100.00 feet. Never combine those numbers without a documented relationship. Mark and protect control outside the excavation and equipment path.

Verify the benchmark description and location against the drawing. A nail in a fence may move when the fence is replaced; a temporary mark in a tree can be lost or change. Use an appropriate stable point and maintain backup control. If control is disturbed, reestablish it from verified information rather than estimate its former height from memory.

Construction layout does not establish legal boundaries. When a wall, fence, or structure is near a property line, use the required survey and legal information. A neighbor's fence, an old stake, or an online map can be misleading. Resolve boundary uncertainty before permanent work rather than explain an encroachment afterward.

Read an optical or digital level

Level the instrument, check calibration and setup, and hold the rod plumb. A backsight is a reading to a point of known elevation. Height of instrument, or HI, equals the known elevation plus that reading. A foresight or intermediate sight to an unknown point is subtracted from HI to find the point's elevation.

With benchmark elevation 100.00 feet and backsight 4.25 feet, HI is 104.25 feet. A reading of 5.10 feet on a patio corner gives elevation 99.15 feet. A reading of 3.65 feet on another corner gives 100.60 feet. The larger rod reading corresponds to the lower point because more vertical distance separates the ground from the same horizontal line of sight.

To set a target grade of 99.50 feet under the same HI, the required rod reading is 104.25 minus 99.50, or 4.75 feet. If the existing reading is 5.10, the ground is 0.35 foot too low and needs fill to the target, subject to the designed material layers. Do not reverse the cut/fill sign merely because the rod number is larger.

Move the instrument with a turning point

When the next area is outside the instrument's useful range, use a stable turning point. Read a foresight on it before moving, calculate its elevation, then take a backsight on the same point from the new setup. That transfers the datum without assuming the new instrument stands at the old height.

Suppose HI is 104.25 and the turning-point foresight is 6.20. Its elevation is 98.05. After moving, a backsight of 3.40 gives new HI 101.45. A foresight of 2.15 at a drain gives elevation 99.30. The two setups use different HIs but the same datum. Record every backsight, foresight, point name, and calculated elevation in sequence.

Close the level run on known control. The sum of backsights minus the sum of foresights should equal the difference between ending and starting elevations. A discrepancy is closure error. Compare it with the project's tolerance and investigate rod, arithmetic, setup, or point-identification errors before using questionable elevations. Do not distribute a large mistake across all points and call the survey acceptable.

Lasers, contours, and grade checks

A rotating laser and receiver transfer a horizontal or specified sloping plane. Check instrument setup, calibration, receiver offset, rod units, and accidental disturbance. A laser receiver tone alone does not tell whether the point meets finish grade unless the target offset has been established. Observe manufacturer distance and accuracy limits and periodically verify control.

Contour lines connect equal elevations. Closely spaced contours show a steeper slope; widely spaced lines show a gentler one. Spot elevations provide specific values at critical locations such as drain inverts and thresholds. A contour plan is not a substitute for a required detailed corner elevation, especially on a nearly flat patio.

For a twenty-foot run requiring two percent fall, the elevation difference is 0.40 foot, or 4.8 inches. Set upstream and downstream targets and check intermediate points for local humps. Record whether the targets are subgrade, base, or finished surface. A correct subgrade elevation plus the wrong material thickness can still produce an incorrect final level. Recheck after compaction and before concealment so correction is practical.

Field application

Check rod units before subtraction. A decimal-foot rod reading of 4.50 feet means four feet six inches; it does not mean four feet five inches. A six-inch error at a drain can defeat the entire outlet relationship. Record the units beside readings and use the same rod convention throughout the run. When another crew uses inch-based grade stakes, explicitly convert the decimal-foot elevations rather than transfer the digits unchanged.

Reference table

  • Level example Calculation Elevation or HI, feet
  • Initial HI 100.00 + 4.25 104.25
  • First point 104.25 - 5.10 99.15
  • Turning point 104.25 - 6.20 98.05
  • New HI 98.05 + 3.40 101.45
  • Drain 101.45 - 2.15 99.30