Study guide

Slope ratios, pitch, and foundation fall

Oregon Landscape Contractor License Study Guide 2026

Track your progress as you read

Finished sections get a check mark.

1 1. Licensing and business: 1

Exam structure, reference use, and license routes Oregon jurisdiction, license phases, and eligibility Bonds, insurance, and financial responsibility

2 2. Licensing and business: 2

Employee status, paid work, and payroll calculations Hiring, breaks, sick time, and workplace protections Contracts, cancellation, guarantees, and liens

3 3. Licensing and business: 3

LCP supervision and clear project communication Direct costs and overhead allocation Margin, markup, changes, and job costing

4 4. Site safety and utilities

Excavation safety and hazard controls Oregon 811 notices and utility protection

5 5. Soil science and site preparation: 1

Soil texture, structure, and pore space Density, regional profiles, and soil water Soil pH, diagnosis, and exchange capacity

6 6. Soil science and site preparation: 2

Amendments and fertilizer calculations Compaction, decompaction, and topsoil protection Topsoil placement, finish grades, and weeds

7 7. Plants, turf, and establishment: 1

Planting plans, stock sizes, and quantity takeoffs Botanical identification, plant types, and growth habits Mature size, landscape use, and exposure decisions

8 8. Plants, turf, and establishment: 2

Hardiness, microclimates, and plant names Native plant choices and invasive plants Nursery stock, root flares, and planting depth

9 9. Plants, turf, and establishment: 3

Backfill, staking, and mulch Turf species, mixtures, and site suitability Seed, sod, and establishment calculations

10 10. Plants, turf, and establishment: 4

Pruning and integrated pest management Pest diagnosis, weeds, and pesticide credentials

11 11. Paving and concrete: 1

Pavement foundations, drainage, and excavation Separation fabric, aggregate, and compaction Bedding, restraints, and square layout

12 12. Paving and concrete: 2

Paver laying, cuts, patterns, and joint fill Natural stone and rigid or flexible setting Concrete mixture, placement, and finishing

13 13. Paving and concrete: 3

Concrete joints and curing

14 14. Walls and exterior structures: 1

Segmental wall systems and foundations Wall drainage, backfill, and geogrid Earth pressure, stone walls, and footings

15 15. Walls and exterior structures: 2

Masonry reinforcement, wall permits, and failure Lumber dimensions, grades, fasteners, and finishing Treated lumber and outdoor exposure

16 16. Walls and exterior structures: 3

Wood durability, hardware, and post geometry Fences, decks, ledgers, and arbors Landscape steps, stairs, and safe transitions

17 17. Walls and exterior structures: 4

Low-voltage lighting design, wiring, and commissioning Water features, pumps, liners, and water quality

18 18. Design, grading, and drainage: 1

Landscape design, circulation, and coordinated details Surveying, benchmarks, and elevation checks Planting on roofs, decks, and other structures

19 19. Design, grading, and drainage: 2

Drawing sets, legends, and scale Contours, spot elevations, and benchmarks Slope ratios, pitch, and foundation fall

20 20. Design, grading, and drainage: 3

Earthwork, accessible routes, and swales Water sources and French drains Inlets, conveyance, cleanouts, and outlets

21 21. Design, grading, and drainage: 4

Bioretention sizing, media, and plants Swales and current DEQ erosion controls

22 22. Irrigation design and operation: 1

Irrigation site survey and available water Hydrozones and plant-based irrigation design Sprinkler layout, arcs, and zone flow accounting

23 23. Irrigation design and operation: 2

Irrigation symbols, plans, and material takeoffs Pressure, elevation, friction, and budgets Sprinkler types, pressure, and coverage

24 24. Irrigation design and operation: 3

Matched precipitation and runtime formulas Drip irrigation, filtration, and wetted root volume Pipe materials, bore, velocity, and valves

25 25. Irrigation design and operation: 4

Valve service, wiring, and smart controls Controller circuits and electrical troubleshooting Plant culture and root-zone watering decisions

26 26. Irrigation design and operation: 5

Evapotranspiration, soil depletion, and runtime Catch-can audits and irrigation repair diagnosis Installation, testing, winterization, and startup

27 27. Backflow and potable protection: 1

Cross-connections, hazards, and reverse flow Air gaps and physical potable-water separation Vacuum breakers, checks, and RP assemblies

28 28. Backflow and potable protection: 2

Potable, irrigation, and reclaimed-water piping Backflow assembly selection and hydraulic cases Backflow installation, winter care, and reports

Slope ratios, pitch, and foundation fall

Key Takeaways Explain This Topic AI

Percent slope equals rise divided by horizontal run times one hundred.

A 5% grade is 0.6 inch per foot.

Keep horizontal-to-vertical ratios and all units explicit.

Last updated: October 2026

Note

Calculate slope as rise divided by horizontal run. A 3H:1V slope is 33.3%; one-quarter inch per foot is about 2.08%. Foundation drainage, accessibility, erosion protection, equipment safety, and earthwork each require separate design checks.

Fundamental Slope Formulas and Mathematical Conversions

All surface grading calculations rely on the direct mathematical relationship between vertical elevation change ( Rise ) and horizontal distance ( Run ). Before performing any slope calculation, contractors must ensure that both Rise and Run are expressed in the exact same unit of measurement (either decimal feet or inches).

The Three Core Slope Formulas

Calculating Slope Percentage ( S % S\% S % ): Slope % = ( Rise Run ) × 100 \text{Slope } \% = \left( \frac{\text{Rise}}{\text{Run}} \right) \times 100 Slope % = ( Run Rise ​ ) × 100

Calculating Vertical Rise (Elevation Drop or Gain): Rise = Run × ( Slope % 100 ) \text{Rise} = \text{Run} \times \left( \frac{\text{Slope } \%}{100} \right) Rise = Run × ( 100 Slope % ​ )

Calculating Horizontal Run (Distance Required): Run = Rise ( Slope % 100 ) = ( Rise Slope % ) × 100 \text{Run} = \frac{\text{Rise}}{\left( \frac{\text{Slope } \%}{100} \right)} = \left( \frac{\text{Rise}}{\text{Slope } \%} \right) \times 100 Run = ( 100 Slope % ​ ) Rise ​ = ( Slope % Rise ​ ) × 100

Slope Expressions: Percentage, Ratio ( H : V H:V H : V ), and Pitch (Inches per Foot)

Landscape plans and civil engineering specifications express slope in three distinct formats:

Percentage of Slope ( S % S\% S % ): The vertical rise in feet per 100 feet of horizontal run. A grade dropping 2.0 feet over a 100-foot run has a 2.0 % 2.0\% 2.0% slope.

Horizontal-to-Vertical Ratio ( H : V H:V H : V ): Expresses the horizontal run ( H H H ) required for every single unit of vertical rise ( V V V ). For example, a 3 : 1 3:1 3 : 1 slope indicates a 3-foot horizontal distance for every 1-foot vertical drop: S % = ( 1 / 3 ) × 100 = 33.33 % S\% = (1 / 3) \times 100 = 33.33\% S % = ( 1/3 ) × 100 = 33.33% . A 2 : 1 2:1 2 : 1 slope indicates 2 feet of run per 1 foot of rise: S % = ( 1 / 2 ) × 100 = 50.0 % S\% = (1 / 2) \times 100 = 50.0\% S % = ( 1/2 ) × 100 = 50.0% .

Pitch in Inches per Foot: Commonly used for flatwork, patios, and drainage pipe runs.

1 / 4 " per foot = 0.25 " / 12 " = 0.02083 = 2.08 % 1/4" \text{ per foot} = 0.25" / 12" = 0.02083 = 2.08\% 1/4" per foot = 0.25"/12" = 0.02083 = 2.08%

1 / 8 " per foot = 0.125 " / 12 " = 0.01042 = 1.04 % 1/8" \text{ per foot} = 0.125" / 12" = 0.01042 = 1.04\% 1/8" per foot = 0.125"/12" = 0.01042 = 1.04%

1 / 2 " per foot = 0.500 " / 12 " = 0.04167 = 4.17 % 1/2" \text{ per foot} = 0.500" / 12" = 0.04167 = 4.17\% 1/2" per foot = 0.500"/12" = 0.04167 = 4.17%

  • Ratio, horizontal:vertical Slope Exact pitch, inches per foot Fall over ten feet
  • 100:1 1% 0.12 1.2 inches
  • 50:1 2% 0.24 2.4 inches
  • 20:1 5% 0.60 6 inches
  • 12:1 8.33% approximately 1.00 10 inches
  • 4:1 25% 3.00 30 inches
  • 3:1 33.33% approximately 4.00 40 inches
  • 2:1 50% 6.00 60 inches
  • 1:1 100% 12.00 120 inches

These are mathematical conversions, not safe-mowing limits or approval of a planted slope. One-eighth and one-quarter inch per foot are commonly rounded construction pitches; they do not exactly equal one and two percent.

Step-by-Step Slope Calculation Examples

Example 1 (Finding Required Vertical Drop for a Patio): A concrete paver patio extends out 28.0 feet 28.0\text{ feet} 28.0 feet horizontally from a home foundation. The project specifications call for a positive drainage pitch of 1 / 4 " per foot 1/4" \text{ per foot} 1/4" per foot ( 2.08 % 2.08\% 2.08% ). What is the total vertical drop required across the patio? Rise = Run × Pitch = 28.0 ft × 0.25 " / ft = 7.0 inches ( 0.583 ft ) \text{Rise} = \text{Run} \times \text{Pitch} = 28.0\text{ ft} \times 0.25"/\text{ft} = 7.0\text{ inches} \quad (0.583\text{ ft}) Rise = Run × Pitch = 28.0 ft × 0.25"/ ft = 7.0 inches ( 0.583 ft )

The outer patio edge must be set exactly 7 inches lower than the foundation line.

Example 2 (Finding Percentage Slope from Field Elevation Shots): A laser level survey reads an elevation of 142.50 ft 142.50\text{ ft} 142.50 ft at the upper end of a lawn and 139.80 ft 139.80\text{ ft} 139.80 ft at the lower property line. The horizontal distance between the two survey pins is 45.0 feet 45.0\text{ feet} 45.0 feet . What is the slope percentage? Rise = 142.50 ft − 139.80 ft = 2.70 ft \text{Rise} = 142.50\text{ ft} - 139.80\text{ ft} = 2.70\text{ ft} Rise = 142.50 ft − 139.80 ft = 2.70 ft Slope % = ( 2.70 ft 45.0 ft ) × 100 = 0.060 × 100 = 6.0 % \text{Slope } \% = \left( \frac{2.70\text{ ft}}{45.0\text{ ft}} \right) \times 100 = 0.060 \times 100 = 6.0\% Slope % = ( 45.0 ft 2.70 ft ​ ) × 100 = 0.060 × 100 = 6.0%

Standard Regulatory and Functional Slopes in Landscape Construction

Operating in compliance with the Oregon Residential Specialty Code (ORSC) and standard landscape architectural practices requires adhering to strict slope boundaries:

Positive Drainage Away from Building Foundations

Water pooling against foundation walls causes basement flooding, crawlspace rot, mold growth, and structural settlement. Under standard building codes (ORSC R401.3):

Standard Code Mandate: The ground surface immediately adjacent to foundation walls must slope positively away from the building at a minimum of 5% slope for the first 10 feet of horizontal distance.

Physical Measurement: A 5% slope over 10 feet equates to a minimum vertical fall of 6 inches ( 10 ft × 0.05 = 0.50 ft = 6 inches 10\text{ ft} \times 0.05 = 0.50\text{ ft} = 6\text{ inches} 10 ft × 0.05 = 0.50 ft = 6 inches ).

Restricted Space: Where lot lines, walls, slopes, or other physical barriers prevent the prescribed fall, provide drains or swales as required by the applicable provision to carry water away. Check the approved alternate and impervious-surface requirements rather than assuming every alternate must retain five-percent grade.