Study guide
Earthwork, accessible routes, and swales
Oregon Landscape Contractor License Study Guide 2026
Track your progress as you read
Finished sections get a check mark.
1 1. Licensing and business: 1
Exam structure, reference use, and license routes Oregon jurisdiction, license phases, and eligibility Bonds, insurance, and financial responsibility
2 2. Licensing and business: 2
Employee status, paid work, and payroll calculations Hiring, breaks, sick time, and workplace protections Contracts, cancellation, guarantees, and liens
3 3. Licensing and business: 3
LCP supervision and clear project communication Direct costs and overhead allocation Margin, markup, changes, and job costing
4 4. Site safety and utilities
Excavation safety and hazard controls Oregon 811 notices and utility protection
5 5. Soil science and site preparation: 1
Soil texture, structure, and pore space Density, regional profiles, and soil water Soil pH, diagnosis, and exchange capacity
6 6. Soil science and site preparation: 2
Amendments and fertilizer calculations Compaction, decompaction, and topsoil protection Topsoil placement, finish grades, and weeds
7 7. Plants, turf, and establishment: 1
Planting plans, stock sizes, and quantity takeoffs Botanical identification, plant types, and growth habits Mature size, landscape use, and exposure decisions
8 8. Plants, turf, and establishment: 2
Hardiness, microclimates, and plant names Native plant choices and invasive plants Nursery stock, root flares, and planting depth
9 9. Plants, turf, and establishment: 3
Backfill, staking, and mulch Turf species, mixtures, and site suitability Seed, sod, and establishment calculations
10 10. Plants, turf, and establishment: 4
Pruning and integrated pest management Pest diagnosis, weeds, and pesticide credentials
11 11. Paving and concrete: 1
Pavement foundations, drainage, and excavation Separation fabric, aggregate, and compaction Bedding, restraints, and square layout
12 12. Paving and concrete: 2
Paver laying, cuts, patterns, and joint fill Natural stone and rigid or flexible setting Concrete mixture, placement, and finishing
13 13. Paving and concrete: 3
Concrete joints and curing
14 14. Walls and exterior structures: 1
Segmental wall systems and foundations Wall drainage, backfill, and geogrid Earth pressure, stone walls, and footings
15 15. Walls and exterior structures: 2
Masonry reinforcement, wall permits, and failure Lumber dimensions, grades, fasteners, and finishing Treated lumber and outdoor exposure
16 16. Walls and exterior structures: 3
Wood durability, hardware, and post geometry Fences, decks, ledgers, and arbors Landscape steps, stairs, and safe transitions
17 17. Walls and exterior structures: 4
Low-voltage lighting design, wiring, and commissioning Water features, pumps, liners, and water quality
18 18. Design, grading, and drainage: 1
Landscape design, circulation, and coordinated details Surveying, benchmarks, and elevation checks Planting on roofs, decks, and other structures
19 19. Design, grading, and drainage: 2
Drawing sets, legends, and scale Contours, spot elevations, and benchmarks Slope ratios, pitch, and foundation fall
20 20. Design, grading, and drainage: 3
Earthwork, accessible routes, and swales Water sources and French drains Inlets, conveyance, cleanouts, and outlets
21 21. Design, grading, and drainage: 4
Bioretention sizing, media, and plants Swales and current DEQ erosion controls
22 22. Irrigation design and operation: 1
Irrigation site survey and available water Hydrozones and plant-based irrigation design Sprinkler layout, arcs, and zone flow accounting
23 23. Irrigation design and operation: 2
Irrigation symbols, plans, and material takeoffs Pressure, elevation, friction, and budgets Sprinkler types, pressure, and coverage
24 24. Irrigation design and operation: 3
Matched precipitation and runtime formulas Drip irrigation, filtration, and wetted root volume Pipe materials, bore, velocity, and valves
25 25. Irrigation design and operation: 4
Valve service, wiring, and smart controls Controller circuits and electrical troubleshooting Plant culture and root-zone watering decisions
26 26. Irrigation design and operation: 5
Evapotranspiration, soil depletion, and runtime Catch-can audits and irrigation repair diagnosis Installation, testing, winterization, and startup
27 27. Backflow and potable protection: 1
Cross-connections, hazards, and reverse flow Air gaps and physical potable-water separation Vacuum breakers, checks, and RP assemblies
28 28. Backflow and potable protection: 2
Potable, irrigation, and reclaimed-water piping Backflow assembly selection and hydraulic cases Backflow installation, winter care, and reports
Earthwork, accessible routes, and swales
Key Takeaways Explain This Topic AI
A 3:1 slope is not automatically safe for a riding mower.
Applicable accessible walking surfaces generally use 1:20 running and 1:48 cross-slope limits.
Distinguish bank, loose, and compacted earthwork volumes.
Swale geometry and lining must fit design flow and outlet.
Last updated: October 2026
Lawn slopes and equipment safety
Flatter slopes are generally easier to establish, irrigate, mow, and use. A 3:1 slope is a 33.3% grade and about 18.4 degrees; it is not automatically safe for a riding mower. Follow the equipment's permitted slope, travel direction, surface, and rollover guidance. Wet grass, holes, and abrupt edges can make a shallower slope hazardous.
Choose planting and maintenance methods that fit the actual terrain. If a slope exceeds safe access, redesign the area, use appropriate specialist equipment, or select vegetation that does not require routine mowing. Turf selection cannot compensate for an unsafe maintenance layout.
Embankments and soil stability
Vegetation reduces surface erosion but does not prove deep slope stability. Soil strength, groundwater, fill compaction, stratification, and toe support determine stability. The angle of repose describes loose granular material under specific conditions; it is not a universal design slope for every soil or planted embankment.
Specify erosion protection and seek geotechnical design where slope movement could affect buildings, public access, or neighboring property. Avoid treating 2:1 as automatically stable because plants are present. Concentrated runoff and seepage can destabilize an otherwise acceptable-looking slope.
Accessible routes and ordinary paths
Where accessibility standards apply, a walking surface generally has running slope no steeper than 1:20 and cross slope no steeper than 1:48. A steeper accessible route is a ramp and must satisfy ramp provisions, commonly including a 1:12 maximum slope, landings, edge protection, and handrails when triggered. A handrail is generally triggered by ramp rise over six inches, not automatically by every sloping walkway.
Determine which accessibility and building provisions apply to the project rather than impose ADA geometry on every private garden path. Check finished elevations and transitions; a correct average slope can still contain a short excessive slope or lip. Provide positive drainage without exceeding required cross-slope limits.
Earthwork Volume Estimation: Average End Area Method and Soil Factors
Earthwork estimation involves computing the volumetric quantities of soil excavated ( Cut ) and soil placed ( Fill ). Accurate calculations prevent underbidding hauling costs, equipment mobilization, and aggregate purchases.
The Average End Area Formula
The Average End Area method is the standard civil engineering standard for linear earthwork projects, such as drainage swales, berms, terraces, and road cuts: Volume (Cubic Feet) = ( A 1 + A 2 2 ) × L \text{Volume (Cubic Feet)} = \left( \frac{A_1 + A_2}{2} \right) \times L Volume (Cubic Feet) = ( 2 A 1 + A 2 ) × L Volume (Cubic Yards) = ( A 1 + A 2 2 ) × L 27 \text{Volume (Cubic Yards)} = \frac{\left( \frac{A_1 + A_2}{2} \right) \times L}{27} Volume (Cubic Yards) = 27 ( 2 A 1 + A 2 ) × L
Where A 1 A_1 A 1 and A 2 A_2 A 2 are the cross-sectional areas of cut or fill in square feet at two successive survey stations, and L L L is the horizontal distance in feet between the stations.
Dividing by 27 converts cubic feet to Cubic Yards (CY) ( 1 CY = 27 cu ft 1\text{ CY} = 27\text{ cu ft} 1 CY = 27 cu ft ).
Worked Earthwork Calculation
Problem: A contractor is excavating a 90-foot-long drainage swale. At Station 0 + 00 0+00 0 + 00 , the cut cross-section ( A 1 A_1 A 1 ) is 14.0 sq ft 14.0\text{ sq ft} 14.0 sq ft . At Station 0 + 90 0+90 0 + 90 ( L = 90 ft L = 90\text{ ft} L = 90 ft ), the cut cross-section ( A 2 A_2 A 2 ) is 22.0 sq ft 22.0\text{ sq ft} 22.0 sq ft . How many cubic yards of soil must be excavated? Average Area = 14.0 sq ft + 22.0 sq ft 2 = 36.0 2 = 18.0 sq ft \text{Average Area} = \frac{14.0\text{ sq ft} + 22.0\text{ sq ft}}{2} = \frac{36.0}{2} = 18.0\text{ sq ft} Average Area = 2 14.0 sq ft + 22.0 sq ft = 2 36.0 = 18.0 sq ft Volume (Cubic Feet) = 18.0 sq ft × 90.0 ft = 1 , 620 cu ft \text{Volume (Cubic Feet)} = 18.0\text{ sq ft} \times 90.0\text{ ft} = 1,620\text{ cu ft} Volume (Cubic Feet) = 18.0 sq ft × 90.0 ft = 1 , 620 cu ft Volume (Cubic Yards) = 1 , 620 cu ft 27 cu ft/CY = 60.0 CY \text{Volume (Cubic Yards)} = \frac{1,620\text{ cu ft}}{27\text{ cu ft/CY}} = 60.0\text{ CY} Volume (Cubic Yards) = 27 cu ft/CY 1 , 620 cu ft = 60.0 CY
Bank, loose, and compacted volumes
Bank volume describes undisturbed soil. Excavation creates a loose volume that can be larger because pore arrangement changes; placement and compaction create a third volume. Use the project's tested or specified conversion factors, not one universal ten-percent allowance.
If 100 bank cubic yards have an assumed swell factor of 1.20, hauling volume is 120 loose cubic yards. If the specified compacted yield is 0.90 compacted cubic yard per bank cubic yard, the same excavation produces 90 compacted cubic yards. Do not apply the swell percentage a second time to calculate compacted fill. Record the unit basis on every estimate and truck order.
Surface Drainage Swales: Hydraulic Design and Construction
A drainage swale is an engineered, gently sloped, open vegetated channel designed to collect overland sheet runoff and convey it safely to an approved discharge point without causing surface erosion.
Cross-Sectional Geometry: Parabolic vs. Trapezoidal
Parabolic (Curvilinear) Swales: Feature a smooth, dish-shaped or saucer-shaped cross-section. They are the preferred design for residential lawns and parklands because they blend naturally into the surrounding turf, possess no sharp transitions, and can be mowed effortlessly with standard lawn mowers without scalping.
Trapezoidal Swales: Feature a wide, flat bottom with angled side slopes (typically graded at 3 : 1 3:1 3 : 1 or 4 : 1 4:1 4 : 1 ). Their capacity depends on the specified area, hydraulic radius, slope, and roughness; they are commonly used and are selected for commercial perimeter buffers, agricultural diversions, and large roadside channels.
Warning
A narrow pointed channel can concentrate flow and be difficult to mow. Choose cross-section and lining for design discharge, erosion resistance, and maintenance equipment. A triangular channel is not categorically forbidden; it needs an appropriate hydraulic and maintenance design.
Swale slope and lining
Determine the swale's longitudinal slope from upstream and downstream invert elevations and length. Choose section, lining, and grade to convey the design flow without excessive erosion or prolonged ponding. A vegetated treatment swale can have a different grade and hydraulic criterion from a simple conveyance swale.
There is no universal two-percent minimum or six-inch freeboard for every landscape swale. Use the approved drainage design and local stormwater criteria. Check the outlet elevation, downstream capacity, overflow route, and transitions. A steep swale may need erosion-resistant lining or energy dissipation even though it drains quickly.
Swale Freeboard
Freeboard is the vertical distance from the design water surface to the containing bank or structure. The required allowance comes from the approved design and local criteria, not one universal three-to-six-inch minimum. Verify it after construction and preserve overflow capacity. Settlement, excess mulch, or a raised outlet can reduce the effective allowance and cause water to leave the intended route.