Study guide
Bioretention sizing, media, and plants
Oregon Landscape Contractor License Study Guide 2026
Track your progress as you read
Finished sections get a check mark.
1 1. Licensing and business: 1
Exam structure, reference use, and license routes Oregon jurisdiction, license phases, and eligibility Bonds, insurance, and financial responsibility
2 2. Licensing and business: 2
Employee status, paid work, and payroll calculations Hiring, breaks, sick time, and workplace protections Contracts, cancellation, guarantees, and liens
3 3. Licensing and business: 3
LCP supervision and clear project communication Direct costs and overhead allocation Margin, markup, changes, and job costing
4 4. Site safety and utilities
Excavation safety and hazard controls Oregon 811 notices and utility protection
5 5. Soil science and site preparation: 1
Soil texture, structure, and pore space Density, regional profiles, and soil water Soil pH, diagnosis, and exchange capacity
6 6. Soil science and site preparation: 2
Amendments and fertilizer calculations Compaction, decompaction, and topsoil protection Topsoil placement, finish grades, and weeds
7 7. Plants, turf, and establishment: 1
Planting plans, stock sizes, and quantity takeoffs Botanical identification, plant types, and growth habits Mature size, landscape use, and exposure decisions
8 8. Plants, turf, and establishment: 2
Hardiness, microclimates, and plant names Native plant choices and invasive plants Nursery stock, root flares, and planting depth
9 9. Plants, turf, and establishment: 3
Backfill, staking, and mulch Turf species, mixtures, and site suitability Seed, sod, and establishment calculations
10 10. Plants, turf, and establishment: 4
Pruning and integrated pest management Pest diagnosis, weeds, and pesticide credentials
11 11. Paving and concrete: 1
Pavement foundations, drainage, and excavation Separation fabric, aggregate, and compaction Bedding, restraints, and square layout
12 12. Paving and concrete: 2
Paver laying, cuts, patterns, and joint fill Natural stone and rigid or flexible setting Concrete mixture, placement, and finishing
13 13. Paving and concrete: 3
Concrete joints and curing
14 14. Walls and exterior structures: 1
Segmental wall systems and foundations Wall drainage, backfill, and geogrid Earth pressure, stone walls, and footings
15 15. Walls and exterior structures: 2
Masonry reinforcement, wall permits, and failure Lumber dimensions, grades, fasteners, and finishing Treated lumber and outdoor exposure
16 16. Walls and exterior structures: 3
Wood durability, hardware, and post geometry Fences, decks, ledgers, and arbors Landscape steps, stairs, and safe transitions
17 17. Walls and exterior structures: 4
Low-voltage lighting design, wiring, and commissioning Water features, pumps, liners, and water quality
18 18. Design, grading, and drainage: 1
Landscape design, circulation, and coordinated details Surveying, benchmarks, and elevation checks Planting on roofs, decks, and other structures
19 19. Design, grading, and drainage: 2
Drawing sets, legends, and scale Contours, spot elevations, and benchmarks Slope ratios, pitch, and foundation fall
20 20. Design, grading, and drainage: 3
Earthwork, accessible routes, and swales Water sources and French drains Inlets, conveyance, cleanouts, and outlets
21 21. Design, grading, and drainage: 4
Bioretention sizing, media, and plants Swales and current DEQ erosion controls
22 22. Irrigation design and operation: 1
Irrigation site survey and available water Hydrozones and plant-based irrigation design Sprinkler layout, arcs, and zone flow accounting
23 23. Irrigation design and operation: 2
Irrigation symbols, plans, and material takeoffs Pressure, elevation, friction, and budgets Sprinkler types, pressure, and coverage
24 24. Irrigation design and operation: 3
Matched precipitation and runtime formulas Drip irrigation, filtration, and wetted root volume Pipe materials, bore, velocity, and valves
25 25. Irrigation design and operation: 4
Valve service, wiring, and smart controls Controller circuits and electrical troubleshooting Plant culture and root-zone watering decisions
26 26. Irrigation design and operation: 5
Evapotranspiration, soil depletion, and runtime Catch-can audits and irrigation repair diagnosis Installation, testing, winterization, and startup
27 27. Backflow and potable protection: 1
Cross-connections, hazards, and reverse flow Air gaps and physical potable-water separation Vacuum breakers, checks, and RP assemblies
28 28. Backflow and potable protection: 2
Potable, irrigation, and reclaimed-water piping Backflow assembly selection and hydraulic cases Backflow installation, winter care, and reports
Bioretention sizing, media, and plants
Key Takeaways Explain This Topic AI
Rain-garden size follows rainfall, storage, infiltration, and local criteria.
Approved media and underdrain details differ by design.
Match plants to ponding, transition, and upper-bank conditions.
Last updated: October 2026
Note
Bioretention uses plants, media, storage, and a controlled drainage route to manage runoff. Local requirements and site conditions establish dimensions and materials. Check infiltration feasibility, seasonal water, setbacks, overflow, and maintenance before construction.
Low Impact Development (LID) and Watershed Hydrology
Conventional civil engineering historically treated stormwater as a waste product to be collected in pipes and rapidly evacuated off site into municipal storm sewers and regional rivers. In urbanized landscapes, replacing natural forest cover with impervious rooftops, asphalt roads, and concrete flatwork causes severe watershed degradation:
Runoff Volume Surge: Peak runoff and volume can increase substantially, causing extreme stream channel erosion, scouring out salmonid spawning gravels, and overwhelming combined municipal sewer networks.
Loss of Baseflow: Preventing natural groundwater infiltration lowers regional water tables, causing Pacific Northwest streams to run dry or overheat during summer months.
Nonpoint Source Pollution: Urban runoff carries concentrated environmental toxins—including heavy metals (copper from vehicle brake pads, zinc from tire wear), petroleum hydrocarbons (motor oils, fuels), excess nitrogen and phosphorus fertilizers, and suspended soil sediment.
Low Impact Development (LID) is an ecologically engineered approach that manages rainfall at the source. By incorporating decentralized, naturalized landscape features—such as bioretention cells, rain gardens, vegetated bioswales, and permeable interlocking concrete pavements—LID mimics pre-development hydrology through on-site infiltration, evapotranspiration, and biological pollutant filtration.
Rain Gardens and Bioretention Engineering
A rain garden (or bioretention cell) is an engineered, landscaped shallow depression designed to capture, detain, filter, and infiltrate stormwater runoff from designated impervious surfaces (roofs, driveways, parking lots).
Site investigation and sizing
Identify the contributing roof, paving, and landscape areas, local design storm, infiltration conditions, groundwater, utilities, and approved overflow route. Confirm infiltration feasibility with the applicable local test method. A small rain garden is not automatically sized at five to ten percent of roof area; required footprint depends on storage, soil conductivity, rainfall, and the design standard.
For an illustrative design prescribing a ten-percent surface-area ratio, a 2,400-square-foot roof implies 240 square feet. This arithmetic does not establish that ten percent is correct for another site. Calculate storage using effective ponding area and depth, and account for sloped sides rather than multiply the largest top footprint by full depth.
Setbacks from foundations, property lines, wells, septic systems, slopes, and groundwater come from applicable local criteria and site review. Do not present one statewide set of distances as universally mandatory. Infiltration on a slope or near a foundation can create geotechnical or moisture problems even when the planting looks attractive.
Media, drainage, and overflow
Use the jurisdiction's approved bioretention media and construction detail. Sand, organic matter, mineral soil, gradation, conductivity, and nutrient content are specified together. Arbitrarily combining three percentage ranges can produce an inconsistent mix. Ordinary rich planting compost is not automatically approved stormwater treatment media.
Protect the excavated basin from compaction and construction sediment. Provide the specified ponding depth, drawdown performance, underdrain where required by the design, and a safe overflow. An underdrain is not universally required merely because a soil is clay; some facilities infiltrate and others primarily filter and drain. Its invert controls storage and drawdown.
Use transition materials that prevent media migration into the drain layer. Keep cleanouts accessible. The overflow must discharge to an approved route without flooding a building or neighboring property. Local criteria establish the design and overflow storms, not a universal ten- or twenty-five-year number. Inspect the facility after storms and maintain inlets, sediment pretreatment, mulch, and plants.
Three-Tiered Bioretention Planting Zones
Match plants to the facility's actual inundation, drawdown, sun, and summer moisture. Wet-tolerant plants can occupy the bottom while better-drained species occupy higher positions, but a basin designed for temporary ponding is not automatically a permanently anaerobic wetland. Use the applicable local plant list and verify each species' tolerances.
Position Moisture condition to verify Illustrative plant selection question
Basin bottom Temporary ponding and drawdown; possible summer drying Would slough sedge or an appropriate rush tolerate the measured regime and sun?
Side slope Intermittent wetting; varying shade and drainage Does the chosen shrub tolerate both occasional inundation and summer conditions?
Upper edge Better drainage; generally less inundation Could Oregon iris or another upland species fit the exposure and moisture?
Oregon iris ( Iris tenax ) should not be listed as a default plant for a deeply flooded basin bottom. Species selection also considers mature size and maintenance access; a large shrub must not block the overflow or inspection point.
Construction sequence and acceptance
Keep sediment-laden construction runoff out of the facility until the contributing site is stabilized. Otherwise the new soil surface may seal before the plants establish. Inspect subgrade conditions before placing media; a field discrepancy such as buried fill or unexpectedly high water needs design review. Confirm the finished media elevation and overflow level after settlement. An overflow set lower than intended reduces storage; one set too high can flood adjacent improvements.
For an illustrative basin with a constant two-hundred-square-foot horizontal storage area and six inches of ponding, simple rectangular storage is one hundred cubic feet. Real sloping sides change the area with depth, so use the actual geometry. Storage alone does not establish treatment performance: the rate of infiltration or underdrain discharge determines how soon capacity becomes available again. Record the acceptance checks, plant replacement responsibilities, and who will remove incoming sediment. Repeated ponding beyond the approved drawdown time is a diagnostic signal, not evidence that adding more wetland plants will correct the hydraulic problem.