Study guide

Sprinkler layout, arcs, and zone flow accounting

Oregon Landscape Contractor License Study Guide 2026

Track your progress as you read

Finished sections get a check mark.

1 1. Licensing and business: 1

Exam structure, reference use, and license routes Oregon jurisdiction, license phases, and eligibility Bonds, insurance, and financial responsibility

2 2. Licensing and business: 2

Employee status, paid work, and payroll calculations Hiring, breaks, sick time, and workplace protections Contracts, cancellation, guarantees, and liens

3 3. Licensing and business: 3

LCP supervision and clear project communication Direct costs and overhead allocation Margin, markup, changes, and job costing

4 4. Site safety and utilities

Excavation safety and hazard controls Oregon 811 notices and utility protection

5 5. Soil science and site preparation: 1

Soil texture, structure, and pore space Density, regional profiles, and soil water Soil pH, diagnosis, and exchange capacity

6 6. Soil science and site preparation: 2

Amendments and fertilizer calculations Compaction, decompaction, and topsoil protection Topsoil placement, finish grades, and weeds

7 7. Plants, turf, and establishment: 1

Planting plans, stock sizes, and quantity takeoffs Botanical identification, plant types, and growth habits Mature size, landscape use, and exposure decisions

8 8. Plants, turf, and establishment: 2

Hardiness, microclimates, and plant names Native plant choices and invasive plants Nursery stock, root flares, and planting depth

9 9. Plants, turf, and establishment: 3

Backfill, staking, and mulch Turf species, mixtures, and site suitability Seed, sod, and establishment calculations

10 10. Plants, turf, and establishment: 4

Pruning and integrated pest management Pest diagnosis, weeds, and pesticide credentials

11 11. Paving and concrete: 1

Pavement foundations, drainage, and excavation Separation fabric, aggregate, and compaction Bedding, restraints, and square layout

12 12. Paving and concrete: 2

Paver laying, cuts, patterns, and joint fill Natural stone and rigid or flexible setting Concrete mixture, placement, and finishing

13 13. Paving and concrete: 3

Concrete joints and curing

14 14. Walls and exterior structures: 1

Segmental wall systems and foundations Wall drainage, backfill, and geogrid Earth pressure, stone walls, and footings

15 15. Walls and exterior structures: 2

Masonry reinforcement, wall permits, and failure Lumber dimensions, grades, fasteners, and finishing Treated lumber and outdoor exposure

16 16. Walls and exterior structures: 3

Wood durability, hardware, and post geometry Fences, decks, ledgers, and arbors Landscape steps, stairs, and safe transitions

17 17. Walls and exterior structures: 4

Low-voltage lighting design, wiring, and commissioning Water features, pumps, liners, and water quality

18 18. Design, grading, and drainage: 1

Landscape design, circulation, and coordinated details Surveying, benchmarks, and elevation checks Planting on roofs, decks, and other structures

19 19. Design, grading, and drainage: 2

Drawing sets, legends, and scale Contours, spot elevations, and benchmarks Slope ratios, pitch, and foundation fall

20 20. Design, grading, and drainage: 3

Earthwork, accessible routes, and swales Water sources and French drains Inlets, conveyance, cleanouts, and outlets

21 21. Design, grading, and drainage: 4

Bioretention sizing, media, and plants Swales and current DEQ erosion controls

22 22. Irrigation design and operation: 1

Irrigation site survey and available water Hydrozones and plant-based irrigation design Sprinkler layout, arcs, and zone flow accounting

23 23. Irrigation design and operation: 2

Irrigation symbols, plans, and material takeoffs Pressure, elevation, friction, and budgets Sprinkler types, pressure, and coverage

24 24. Irrigation design and operation: 3

Matched precipitation and runtime formulas Drip irrigation, filtration, and wetted root volume Pipe materials, bore, velocity, and valves

25 25. Irrigation design and operation: 4

Valve service, wiring, and smart controls Controller circuits and electrical troubleshooting Plant culture and root-zone watering decisions

26 26. Irrigation design and operation: 5

Evapotranspiration, soil depletion, and runtime Catch-can audits and irrigation repair diagnosis Installation, testing, winterization, and startup

27 27. Backflow and potable protection: 1

Cross-connections, hazards, and reverse flow Air gaps and physical potable-water separation Vacuum breakers, checks, and RP assemblies

28 28. Backflow and potable protection: 2

Potable, irrigation, and reclaimed-water piping Backflow assembly selection and hydraulic cases Backflow installation, winter care, and reports

Sprinkler layout, arcs, and zone flow accounting

Key Takeaways Explain This Topic AI

Establish coverage geometry before dividing heads among valves.

Use actual arc-specific nozzle flows and compatible precipitation rates.

Verify zone flow and the controlling pressure path after every layout change.

Last updated: October 2026

Cover the area systematically

Start at corners and edges, placing nozzles whose arcs fit the boundary. Then fill the interior using the selected product's radius and spacing guidance. Head-to-head coverage is a common starting principle: neighboring heads reach each other's locations at the intended operating pressure. It does not mean a printed maximum radius guarantees uniformity in wind or behind an obstacle.

Measure the effective irrigated area and note trees, structures, paths, and narrow strips. Water should reach plants rather than walls and pavement. A large rotor is not automatically efficient in a small irregular bed because its radius can be reduced; excessive adjustment may distort its pattern and flow. Select strip or other appropriate patterns where their manufacturer-approved coverage fits.

Square spacing is useful for rectangular geometry. Triangular spacing staggers rows and uses a row distance about 0.866 times the between-head distance for equilateral triangles. Actual boundaries require tailored partial arcs and edge coverage. Do not stretch spacing to reduce head count without verifying distribution and the product's guidance.

Match arc and precipitation

A full-circle nozzle covers more area than a quarter-circle nozzle at the same radius. To maintain compatible application, flow generally scales with arc within a matched design. If a quarter-circle uses one gpm, a comparable half-circle uses two and full-circle four under the example's matched assumptions. Actual nozzle families and radius options must be checked rather than assume every product follows an identical flow table.

Rotors may need different nozzle sizes for different arcs. Spray families can provide matched precipitation sets, while adjustable nozzles still need selection and pressure review. Mixing low-rate rotary nozzles with much higher-rate sprays on one valve creates a runtime conflict. Identify both equipment type and actual precipitation instead of matching by visual size of the sprinkler body.

Count simultaneous flow

Suppose a zone includes four quarter-circle nozzles at one gpm each, two half-circle nozzles at two gpm each, and one full-circle at four gpm. Total simultaneous demand is four plus four plus four, or twelve gpm. If the verified allowable flow is fifteen gpm, the zone meets the flow constraint. It still must pass pipe velocity, friction, valve, assembly, and nozzle-pressure checks.

Adding two more half-circles raises demand to sixteen gpm, exceeding the stated limit. Options include redesigning zone boundaries, selecting a compatible lower-flow family, or changing the supply design where appropriate. Do not simply lower nozzle pressure until flow fits if that destroys the required radius and distribution.

When heads are divided among valves, each valve's layout must retain coverage and compatible scheduling. A boundary between zones should not create a dry seam. The controller must prevent unintended simultaneous demand or the supply calculation must include it. A master valve or pump-start circuit also has electrical and hydraulic requirements independent of the head count.

Trace the pressure path

Draw the route from source through meter or service components, backflow assembly, mainline, valve, lateral, fittings, and controlling head. Total the relevant losses at the flow in each segment. A lateral segment carries less water after branches discharge; use the actual downstream demand instead of applying total zone flow to every segment or assuming every segment carries one head's flow.

Evaluate higher and more distant heads, plus lower heads that may receive excessive pressure. Upsizing one pipe can reduce friction, but cannot compensate for all source or elevation problems. Pressure-regulated bodies or valves must be selected for the product and conditions. Record expected operating pressure at the important points for commissioning.

Revise and verify

A relocated tree, revised paving edge, or added planter can change head placement, coverage, elevation, and zone demand. Update the drawing and schedule together. Label valve numbers, nozzle types, arc, radius, pressure, and flow so the installer can reproduce the design rather than choose “a similar head.”

At commissioning, run one zone at a time, inspect arcs and obstructions, measure pressure where appropriate, and catch-can test distribution. Look for wind distortion, leaks, low pressure, and overly reduced radius. A wet sidewalk beside a dry corner is a design or adjustment signal, not proof that the lawn needs a longer overall runtime. Document corrections before final scheduling.

Field application

On a narrow rectangular strip, four corner quarter-arcs may fail to reach the middle if radius is reduced to avoid spraying a walkway. Measure the strip and select a product whose approved pattern fits it, or revise the application method. Do not declare the corners covered merely because every corner has a head. Check both lengthwise and cross-strip overlap at the actual pressure, then use the selected nozzle flows in the zone total.

Reference table

  • Example nozzles Quantity Each flow Subtotal
  • Quarter circle 4 1 gpm 4 gpm
  • Half circle 2 2 gpm 4 gpm
  • Full circle 1 4 gpm 4 gpm
  • Total simultaneous demand 7 — 12 gpm