Study guide
Matched precipitation and runtime formulas
Oregon Landscape Contractor License Study Guide 2026
Track your progress as you read
Finished sections get a check mark.
1 1. Licensing and business: 1
Exam structure, reference use, and license routes Oregon jurisdiction, license phases, and eligibility Bonds, insurance, and financial responsibility
2 2. Licensing and business: 2
Employee status, paid work, and payroll calculations Hiring, breaks, sick time, and workplace protections Contracts, cancellation, guarantees, and liens
3 3. Licensing and business: 3
LCP supervision and clear project communication Direct costs and overhead allocation Margin, markup, changes, and job costing
4 4. Site safety and utilities
Excavation safety and hazard controls Oregon 811 notices and utility protection
5 5. Soil science and site preparation: 1
Soil texture, structure, and pore space Density, regional profiles, and soil water Soil pH, diagnosis, and exchange capacity
6 6. Soil science and site preparation: 2
Amendments and fertilizer calculations Compaction, decompaction, and topsoil protection Topsoil placement, finish grades, and weeds
7 7. Plants, turf, and establishment: 1
Planting plans, stock sizes, and quantity takeoffs Botanical identification, plant types, and growth habits Mature size, landscape use, and exposure decisions
8 8. Plants, turf, and establishment: 2
Hardiness, microclimates, and plant names Native plant choices and invasive plants Nursery stock, root flares, and planting depth
9 9. Plants, turf, and establishment: 3
Backfill, staking, and mulch Turf species, mixtures, and site suitability Seed, sod, and establishment calculations
10 10. Plants, turf, and establishment: 4
Pruning and integrated pest management Pest diagnosis, weeds, and pesticide credentials
11 11. Paving and concrete: 1
Pavement foundations, drainage, and excavation Separation fabric, aggregate, and compaction Bedding, restraints, and square layout
12 12. Paving and concrete: 2
Paver laying, cuts, patterns, and joint fill Natural stone and rigid or flexible setting Concrete mixture, placement, and finishing
13 13. Paving and concrete: 3
Concrete joints and curing
14 14. Walls and exterior structures: 1
Segmental wall systems and foundations Wall drainage, backfill, and geogrid Earth pressure, stone walls, and footings
15 15. Walls and exterior structures: 2
Masonry reinforcement, wall permits, and failure Lumber dimensions, grades, fasteners, and finishing Treated lumber and outdoor exposure
16 16. Walls and exterior structures: 3
Wood durability, hardware, and post geometry Fences, decks, ledgers, and arbors Landscape steps, stairs, and safe transitions
17 17. Walls and exterior structures: 4
Low-voltage lighting design, wiring, and commissioning Water features, pumps, liners, and water quality
18 18. Design, grading, and drainage: 1
Landscape design, circulation, and coordinated details Surveying, benchmarks, and elevation checks Planting on roofs, decks, and other structures
19 19. Design, grading, and drainage: 2
Drawing sets, legends, and scale Contours, spot elevations, and benchmarks Slope ratios, pitch, and foundation fall
20 20. Design, grading, and drainage: 3
Earthwork, accessible routes, and swales Water sources and French drains Inlets, conveyance, cleanouts, and outlets
21 21. Design, grading, and drainage: 4
Bioretention sizing, media, and plants Swales and current DEQ erosion controls
22 22. Irrigation design and operation: 1
Irrigation site survey and available water Hydrozones and plant-based irrigation design Sprinkler layout, arcs, and zone flow accounting
23 23. Irrigation design and operation: 2
Irrigation symbols, plans, and material takeoffs Pressure, elevation, friction, and budgets Sprinkler types, pressure, and coverage
24 24. Irrigation design and operation: 3
Matched precipitation and runtime formulas Drip irrigation, filtration, and wetted root volume Pipe materials, bore, velocity, and valves
25 25. Irrigation design and operation: 4
Valve service, wiring, and smart controls Controller circuits and electrical troubleshooting Plant culture and root-zone watering decisions
26 26. Irrigation design and operation: 5
Evapotranspiration, soil depletion, and runtime Catch-can audits and irrigation repair diagnosis Installation, testing, winterization, and startup
27 27. Backflow and potable protection: 1
Cross-connections, hazards, and reverse flow Air gaps and physical potable-water separation Vacuum breakers, checks, and RP assemblies
28 28. Backflow and potable protection: 2
Potable, irrigation, and reclaimed-water piping Backflow assembly selection and hydraulic cases Backflow installation, winter care, and reports
Matched precipitation and runtime formulas
Key Takeaways Explain This Topic AI
Use compatible arc-specific flows for matched application.
Average rate in inches per hour equals 96.3 times gpm divided by square feet.
Triangular row spacing uses the 0.866 geometry factor.
Runtime equals required depth divided by rate, with time conversion.
Last updated: October 2026
Square Spacing vs. Equilateral Triangular Spacing
Sprinkler layouts use two geometric configurations:
Square Spacing: Sprinkler heads are laid out in a grid where spacing along the row ( S S S ) equals spacing between rows ( L L L ).
Ideal for square or rectangular lawn boundaries and properties bordered by sidewalks and structures.
Spacing: S = L = Radius S = L = \text{Radius} S = L = Radius
Equilateral Triangular Spacing: Sprinkler heads are staggered across rows such that each head is equidistant from adjacent heads, forming equilateral triangles.
Provides superior distribution uniformity and greater resistance to wind distortion.
Row spacing is calculated as: L = S × 0.866 L = S \times 0.866 L = S × 0.866
Heads can be spaced slightly further apart across large irregular expanses while maintaining matched coverage.
Adjust for actual distribution and wind
Use the selected nozzle's performance chart at actual operating pressure and follow manufacturer spacing guidance. Wind, obstructions, slope, and pattern distortion can require closer spacing or a different device. There is no one ninety/eighty-percent spacing table applicable to every nozzle.
Lay out coverage first, then total the actual arc-specific nozzle flows and verify pressure. Adjust radius only within the product's permitted range. Catch-can testing provides evidence of the completed distribution. Changing one nozzle can change flow and precipitation, so record the resulting zone demand.
Matched Precipitation Rate (MPR): Principles and Arc Proportionality
Matched Precipitation Rate (MPR) is the foundational design principle ensuring that all sprinkler heads within a given zone apply water at a compatible rate per unit area, regardless of their individual arc patterns or geometry.
The Arc Proportionality Rule
A full-circle ( 360 ∘ 360^\circ 36 0 ∘ ) head covers four times the surface area of a quarter-circle ( 90 ∘ 90^\circ 9 0 ∘ ) head with the same radius. Therefore, if both nozzles discharged water at the same flow rate, the quarter-circle area would receive four times as much water as the full-circle area, drowning the corner lawn while starving the open turf.
To achieve matched precipitation, nozzle flow rates must be directly proportional to their arc of rotation: Flow Rate (GPM) ∝ Arc of Coverage \text{Flow Rate (GPM)} \propto \text{Arc of Coverage} Flow Rate (GPM) ∝ Arc of Coverage
Quarter-Circle ( 90 ∘ 90^\circ 9 0 ∘ Arc): Covers 1 / 4 1/4 1/4 area → \rightarrow → Requires 1.0 GPM 1.0\text{ GPM} 1.0 GPM
Half-Circle ( 180 ∘ 180^\circ 18 0 ∘ Arc): Covers 1 / 2 1/2 1/2 area → \rightarrow → Requires 2.0 GPM 2.0\text{ GPM} 2.0 GPM ( 2 × 2\times 2 × quarter)
Three-Quarter ( 270 ∘ 270^\circ 27 0 ∘ Arc): Covers 3 / 4 3/4 3/4 area → \rightarrow → Requires 3.0 GPM 3.0\text{ GPM} 3.0 GPM ( 3 × 3\times 3 × quarter)
Full-Circle ( 360 ∘ 360^\circ 36 0 ∘ Arc): Covers 1 1 1 full area → \rightarrow → Requires 4.0 GPM 4.0\text{ GPM} 4.0 GPM ( 4 × 4\times 4 × quarter)
Modern spray nozzle families are engineered with built-in MPR nozzle sets. However, when selecting nozzles for gear-driven rotors, the contractor must manually install proportional nozzle racks (e.g., placing a #2 nozzle in a quarter rotor, a #4 nozzle in a half rotor, and an #8 nozzle in a full rotor).
Warning
NEVER Combine Dissimilar Equipment on the Same Valve Zone: Because spray heads deliver 1.5 to 2.0 in/hr 1.5\text{ to }2.0\text{ in/hr} 1.5 to 2.0 in/hr while gear-driven rotors deliver 0.5 to 1.0 in/hr 0.5\text{ to }1.0\text{ in/hr} 0.5 to 1.0 in/hr , mixing spray heads and rotors on the same control valve zone is a poor design choice when the application rates differ. Running the zone long enough to satisfy the rotors (e.g., 45 minutes) will massively flood and erode the spray head areas. Conversely, running the zone for spray head runtimes (e.g., 15 minutes) will leave the rotor areas in severe drought.
Precipitation Rate Formulas & Mathematical Calculations
Precipitation rate ( P R PR PR ) is the depth of water applied to an irrigated area over a one-hour period, expressed in inches per hour ( in/hr \text{in/hr} in/hr ).
Derivation of the Universal Constant 96.3
Irrigation formulas utilize the conversion factor 96.3 to convert gallons per minute and square feet into inches per hour:
One gallon of water equals 231 cubic inches .
One square foot equals 144 square inches .
One gallon spread over one square foot creates a water depth of: 231 144 = 1.604 inches \frac{231}{144} = 1.604\text{ inches} 144 231 = 1.604 inches .
Converting minutes to hours ( 60 min/hr 60\text{ min/hr} 60 min/hr ): 1.604 × 60 = 96.25 ≈ 96.3 1.604 \times 60 = 96.25 \approx \mathbf{96.3} 1.604 × 60 = 96.25 ≈ 96.3 .
Formula 1: Full-Zone Area Method
Used to calculate the average precipitation rate for an entire irregularly shaped landscape bed or established zone: P R ( in/hr ) = 96.3 × Total Zone GPM Total Irrigated Area (sq ft) PR (\text{in/hr}) = \frac{96.3 \times \text{Total Zone GPM}}{\text{Total Irrigated Area (sq ft)}} PR ( in/hr ) = Total Irrigated Area (sq ft) 96.3 × Total Zone GPM
Example: An irrigation zone supplies 8 spray heads totaling 14.0 GPM 14.0\text{ GPM} 14.0 GPM across a residential lawn measuring 800 sq ft 800\text{ sq ft} 800 sq ft : P R = 96.3 × 14.0 800 = 1348.2 800 = 1.69 in/hr PR = \frac{96.3 \times 14.0}{800} = \frac{1348.2}{800} = \mathbf{1.69\text{ in/hr}} PR = 800 96.3 × 14.0 = 800 1348.2 = 1.69 in/hr
Formula 2: Spacing Method (Square Spacing)
Used during design to determine precipitation rate based on head spacing ( S S S ) and row spacing ( L L L ): P R ( in/hr ) = 96.3 × GPM per Full-Head Equivalent S × L PR (\text{in/hr}) = \frac{96.3 \times \text{GPM per Full-Head Equivalent}}{S \times L} PR ( in/hr ) = S × L 96.3 × GPM per Full-Head Equivalent
For square spacing where head spacing along the row ( S S S ) equals row spacing ( L L L ): P R = 96.3 × GPM S 2 PR = \frac{96.3 \times \text{GPM}}{S^2} PR = S 2 96.3 × GPM
Example: Spray heads with 15-foot radius are spaced 15 feet apart in a square pattern ( 15 ′ × 15 ′ 15' \times 15' 1 5 ′ × 1 5 ′ ). Each full-circle head emits 3.6 GPM 3.6\text{ GPM} 3.6 GPM : P R = 96.3 × 3.6 15 × 15 = 346.68 225 = 1.54 in/hr PR = \frac{96.3 \times 3.6}{15 \times 15} = \frac{346.68}{225} = \mathbf{1.54\text{ in/hr}} PR = 15 × 15 96.3 × 3.6 = 225 346.68 = 1.54 in/hr
Formula 3: Spacing Method (Equilateral Triangular Spacing)
For equilateral triangular spacing, the distance between rows is L = S × 0.866 L = S \times 0.866 L = S × 0.866 : P R ( in/hr ) = 96.3 × GPM S × ( S × 0.866 ) = 96.3 × GPM 0.866 × S 2 PR (\text{in/hr}) = \frac{96.3 \times \text{GPM}}{S \times (S \times 0.866)} = \frac{96.3 \times \text{GPM}}{0.866 \times S^2} PR ( in/hr ) = S × ( S × 0.866 ) 96.3 × GPM = 0.866 × S 2 96.3 × GPM
Example: Rotors spaced at 40 feet in an equilateral triangular pattern ( S = 40 ′ S=40' S = 4 0 ′ , L = 40 × 0.866 = 34.64 ′ L = 40 \times 0.866 = 34.64' L = 40 × 0.866 = 34.6 4 ′ ). Each full head discharges 6.0 GPM 6.0\text{ GPM} 6.0 GPM : P R = 96.3 × 6.0 40 × 34.64 = 577.8 1385.6 = 0.42 in/hr PR = \frac{96.3 \times 6.0}{40 \times 34.64} = \frac{577.8}{1385.6} = \mathbf{0.42\text{ in/hr}} PR = 40 × 34.64 96.3 × 6.0 = 1385.6 577.8 = 0.42 in/hr
Calculating Runtime to Apply Target Water Depth
Once precipitation rate is known, runtime required to satisfy weekly or daily evapotranspiration (ET) demand is calculated as: Runtime (minutes) = ( Target Water Depth (inches) P R ( in/hr ) ) × 60 \text{Runtime (minutes)} = \left( \frac{\text{Target Water Depth (inches)}}{PR (\text{in/hr})} \right) \times 60 Runtime (minutes) = ( PR ( in/hr ) Target Water Depth (inches) ) × 60
If a turf zone with a precipitation rate of 1.50 in/hr 1.50\text{ in/hr} 1.50 in/hr must receive 0.50 inches 0.50\text{ inches} 0.50 inches of water during a peak summer irrigation cycle: Runtime = ( 0.50 1.50 ) × 60 = 0.333 × 60 = 20 minutes \text{Runtime} = \left( \frac{0.50}{1.50} \right) \times 60 = 0.333 \times 60 = \mathbf{20\text{ minutes}} Runtime = ( 1.50 0.50 ) × 60 = 0.333 × 60 = 20 minutes