Study guide

4.2 Groundwater Sources and Wells: Hydraulics, Construction and Protection

Oregon Water and Wastewater Operator Certification Exam

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: Oregon Operator Programs and DEQ Wastewater Certification

1.1 Dual-Agency Structure: DEQ Wastewater and OHA Drinking Water Programs 1.2 DEQ Wastewater System Classification and Supervision Rules 1.3 DEQ Certificates: Qualifications, OIT, Provisional Path, Exams and Fees

2 Chapter 2: OHA Drinking Water Certification and Certificate Renewal

2.1 OHA System Classification, Direct Responsible Charge and the Filtration Endorsement 2.2 OHA Certificates: Experience Tables, OIT, Exams, Fees and Small Water System Certification 2.3 Renewal, CEUs, Reinstatement, Reciprocity and Discipline for DEQ and OHA Certificates

3 Chapter 3: Federal Rules, Oregon Water Quality Standards and Cyanotoxins

3.1 Clean Water Act, Safe Drinking Water Act & NPDES Permitting 3.2 Willamette Basin TMDL and Oregon Water Quality Standards 3.3 Harmful Algal Blooms (HABs) & Oregon Cyanotoxin Rules (OAR 333-061-0510)

4 Chapter 4: Source Water, Intakes and Wells

4.1 Raw Water Sources, Intake Structures & Pretreatment 4.2 Groundwater Sources and Wells: Hydraulics, Construction and Protection

5 Chapter 5: Coagulation, Clarification and Filtration

5.1 Coagulation, Flocculation & Jar Testing Dynamics 5.2 Sedimentation, Clarification & Media Filtration Systems 5.3 Slow Sand, Diatomaceous Earth, Cartridge and Membrane Filtration

6 Chapter 6: Drinking Water Disinfection

6.1 Disinfection Chemistry, Chlorination Dynamics & CT Calculations 6.2 UV, Ozone, Chlorine Dioxide, Chloramines and Disinfection Byproduct Control

7 Chapter 7: Specialty Water Treatment and Residuals

7.1 Iron and Manganese Removal, Softening, and Taste and Odor Control 7.2 Corrosion Control, Lead and Copper, and Fluoridation 7.3 Water Treatment Residuals: Sludge, Backwash Water and Membrane Concentrate

8 Chapter 8: Distribution System Infrastructure

8.1 Distribution System Hydraulics, Piping Materials & Storage Facilities 8.2 Valves, Fire Hydrants & Water Main Installation / Disinfection 8.3 Service Connections, Meters, Water Loss Control and Utility Locating

9 Chapter 9: Distribution Operations, Cross-Connection Control and Water Quality

9.1 Storage Tank and Booster Pump Station Operation, Inspection and Disinfection 9.2 Cross-Connection Control & Backflow Prevention Assemblies (OAR 333-061-0070) 9.3 Water Quality in Distribution: Water Age, Nitrification & Flushing Programs

10 Chapter 10: Wastewater Preliminary and Primary Treatment and Lagoons

10.1 Preliminary Treatment: Screening, Grit Removal & Flow Measurement 10.2 Primary Clarification & Sedimentation Hydraulics 10.3 Stabilization Ponds and Aerated Lagoons

11 Chapter 11: Biological Wastewater Treatment

11.1 Secondary Treatment: Activated Sludge Process Control & Variations 11.2 Fixed-Film Treatment: Trickling Filters, RBCs, MBBR and IFAS 11.3 Biological Nutrient Removal: Nitrification, Denitrification & Phosphorus Removal

12 Chapter 12: Tertiary Treatment, Disinfection, Recycled Water and Small Systems

12.1 Tertiary Filtration, Membrane Bioreactors and Oregon Recycled Water Classes 12.2 Wastewater Disinfection and Dechlorination 12.3 Small Wastewater Systems, Septage Handling and Odor Control

13 Chapter 13: Solids Handling and Biosolids

13.1 Sludge Thickening, Conditioning & Dewatering Technologies 13.2 Anaerobic and Aerobic Digestion Operations & Control 13.3 Biosolids Quality, Land Application Rules & OAR 340-050 / 40 CFR 503

14 Chapter 14: Wastewater Collection Systems and Pumping

14.1 Gravity Sewer Design, Manholes & Inflow/Infiltration (I/I) Management 14.2 Lift Station Design, Wet Wells & Submersible / Centrifugal Pumps 14.3 Collection System Maintenance, Pipeline Inspection (CCTV) & Trench Safety

15 Chapter 15: Collection System Rehabilitation and Overflow Control

15.1 Sewer Rehabilitation, Trenchless Renewal and New-Pipe Acceptance Testing 15.2 Overflow Response, Bypass Pumping, CMOM Programs and Sewer Sulfide Control

16 Chapter 16: Laboratory Procedures and Water Quality Testing

16.1 Drinking Water Microbiological Testing: Coliform, E. coli & RTCR 16.2 Wastewater Lab Analysis: BOD5, TSS, COD & Volatile Solids 16.3 Wastewater Lab: Nutrients, Alkalinity, Bacteria, Toxicity Testing and Lab Accreditation 16.4 Process Monitoring: pH, Turbidity, Dissolved Oxygen & Chlorine Residuals 16.5 Sampling Protocols, Quality Assurance / Chain of Custody & Reporting

17 Chapter 17: Equipment, Electrical Systems and Maintenance

17.1 Pumps, Blowers and Mechanical Maintenance Programs 17.2 Electrical Systems, Motors, Generators, Instrumentation and SCADA

18 Chapter 18: Applied Water and Wastewater Mathematics

18.1 Dimensional Analysis, Flow Conversions & Detention Time 18.2 Chemical Feed, Dosage Calculations & the Pounds Formula 18.3 Treatment Plant Hydraulics, Loading Rates (SOR, WOR) & Pumping Horsepower

19 Chapter 19: Utility Safety

19.1 OSHA Standards, Confined Space Entry & Hazardous Chemical Safety 19.2 Field Safety: Electrical Hazards, Fall Protection, Work Zones, PPE and Oregon OSHA Rules

20 Chapter 20: Emergency Preparedness, Security and Utility Management

20.1 Cascadia Subduction Zone (CSZ) Seismic Preparedness & Infrastructure Hardening 20.2 Wildfire Impacts on Watersheds, Post-Fire Water Quality & Emergency Operations 20.3 Security, Cybersecurity, Emergency Response Planning and Utility Management

4.2 Groundwater Sources and Wells: Hydraulics, Construction and Protection

Key Takeaways Explain This Topic AI

Drawdown equals pumping water level minus static water level, and specific capacity equals well yield divided by drawdown, in gpm per foot.

With an air line, depth to water equals the air line length minus the gauge reading times 2.31 feet per psi.

OHA requires the water supplier to own or hold a recorded easement over the area within 100 feet of a well; listed hazards are barred from that zone, and gravity sewers and septic tanks must be at least 50 feet away.

Oregon well heads need a casing at least 12 inches above a sloped concrete slab, a screened vent, a sample tap, pump-to-waste piping, flow measurement and a way to measure water levels.

A properly built well whose water meets microbiological standards may be used without disinfection, but a total coliform-positive routine sample triggers source sampling under the Ground Water Rule provisions.

Last updated: October 2026

Groundwater Basics

Groundwater fills the pore spaces and fractures of geologic formations called aquifers . Two aquifer types appear on every source-water exam:

Aquifer Description Operating implications

Unconfined (water table) No low-permeability layer above; the water table rises and falls with recharge More vulnerable to surface contamination; shallow alluvial wells along Oregon rivers may be evaluated as GWUDI

Confined (artesian) Overlain by clay or unfractured rock; water rises in the well above the top of the aquifer Better natural protection; the pressure surface is the piezometric surface, and a flowing artesian well rises above ground

OHA defines confined and unconfined wells this way in OAR 333-061-0050(1)(j) and requires both to be built to the Oregon Water Resources Department's well construction standards in OAR 690-200 through 690-220.

Groundwater under the direct influence of surface water (GWUDI) is groundwater with significant surface-water characteristics, such as rapid shifts in turbidity, temperature or conductivity, or the presence of insects, algae or large-diameter pathogens. OHA evaluates every new well or spring for possible direct influence (OAR 333-061-0032(7)). A GWUDI source is treated like surface water and must meet filtration and disinfection requirements.

Well Hydraulics

When a pump starts, water levels near the well fall and form a cone of depression . The extent of that cone is the zone of influence .

Term Meaning

Static water level (SWL) Distance from a reference point (top of casing) down to water when the pump has been off long enough to recover

  • Pumping water level (PWL) Distance to water while the pump runs at a steady rate
  • Drawdown PWL minus SWL, in feet
  • Specific capacity Yield (gpm) divided by drawdown (ft), in gpm per foot of drawdown
  • Recovery The return toward SWL after pumping stops

A falling specific capacity over time is a classic sign that the screen is plugging (encrustation or biofouling) or that the aquifer is being overdrawn.

Worked examples

Specific capacity. A well pumps 300 gpm. The SWL is 42 ft and the PWL is 92 ft.

  • Drawdown = 92 − 42 = 50 ft
  • Specific capacity = 300 ÷ 50 = 6 gpm per ft

Air line. Many wells measure water level with an air line , a small tube of known length running down beside the pump. Air is pumped in until the gauge pressure stops rising; that pressure equals the water column above the tube bottom. Depth to water (ft) = Air line length (ft) − ( Gauge reading (psi) × 2.31 ) \text{Depth to water (ft)} = \text{Air line length (ft)} - \left(\text{Gauge reading (psi)} \times 2.31\right) Depth to water (ft) = Air line length (ft) − ( Gauge reading (psi) × 2.31 )

With a 200 ft air line reading 45 psi: 45 × 2.31 = 104 ft submerged, so the depth to water is 200 − 104 = 96 ft .

Oregon Well Construction and Protection Rules (OAR 333-061-0050(2))

Requirement Oregon standard

Control of the well site The supplier owns, or holds a perpetual restrictive easement recorded with the county over, all land within 100 feet of the well (public land may use a permit instead)

Prohibited within 100 ft Privies, drainfields, cesspools, solid waste sites, pressure sewer lines, buried fuel tanks, animal yards, chemical storage or application, fuel transfer, vehicle maintenance, cemeteries, unapproved or improperly abandoned wells, and similar hazards, unless OHA waives the restriction

Within 50 ft No gravity sewer line or septic tank

Flooding Avoid flood-prone sites; otherwise mound the area and extend the casing at least 2 ft above the 100-year flood level

Casing and slab Reinforced concrete slab sloped away from the casing; casing top at least 12 in above the slab

Pump and wellhead Turbine pumps sealed to the casing (water-lubricated or food-grade-lubricated bearings); submersibles with a watertight sanitary seal; screened, downward-facing casing vent (not required with pitless units)

Appurtenances Water-level measurement provision; raw sample tap on the discharge; piping to pump the whole flow to waste; a way to measure each well's output

Before use Lab analyses under OAR 333-061-0036, pump test reports for unconfined wells, pump performance data, any disinfection proposal, and the GWUDI determination

Missing or failing items here are sanitary survey significant deficiencies : a casing or sanitary seal that is not watertight, or an unscreened vent.

Disinfection Decisions and Triggered Monitoring

Oregon does not require every well to be disinfected. Water from wells built to these standards that consistently meets microbiological standards may be served without treatment (OAR 333-061-0050(5)). When disinfection is required for groundwater, the design must provide 4-log virus inactivation or removal. Alternatively, it must achieve either 0.2 mg/L free chlorine after 30 minutes of contact, or 2.0 mg/L combined chlorine after 3 hours , before the first user under all flow conditions.

Ground Water Rule provisions add triggered source monitoring . After a routine distribution sample is total coliform-positive, the supplier collects raw-water samples from each well in use. A confirmed E. coli -positive source sample leads to corrective action: fixing the defect, providing an alternate source, eliminating the source, or installing treatment that reliably achieves 4-log virus inactivation.

Well Problems Operators Must Recognize

Encrustation. Iron and manganese oxides, carbonate scale or iron-bacteria slime plug the screen and gravel pack. Specific capacity drops, and the pump may run near its shutoff head. Rehabilitation uses mechanical surging and brushing plus acids, chlorine or specialized cleaners.

Sand pumping. Usually a sign of a damaged screen or poor development. It abrades pump bowls and fills distribution lines with sediment.

Cascading water. Water entering above the pumping level tumbles down the casing, entraining air and promoting corrosion and biofouling.

Pumping water level near the pump intake. Leads to cavitation or air entrainment; check whether drawdown has grown or the well is being over-pumped.

Contamination after work. Wells are disinfected after construction, repair or pump pulls, following AWWA C654 methods, then flushed to waste and sampled for coliform before returning to service.

Many Oregon systems also run a wellhead protection program. OHA can certify a program that meets OAR 333-061-0057 and DEQ's groundwater rules in OAR 340-040. The program delineates the protection area and inventories potential contaminant sources, and it adds management and contingency plans coordinated with county emergency plans.

The Annular Seal

The most important protection for a well is a watertight seal between the casing and the borehole. Without it, surface water can run down the outside of the casing straight into the aquifer.

Oregon Water Resources Department well construction standards (OAR 690-210) require water supply wells to have watertight, unperforated casing and an upper oversize drillhole four inches larger than the casing , both extending at least 18 feet below land surface. The annular space is filled with cement or bentonite grout. Deeper seals are required in some geologic settings, such as clay beds or consolidated rock.

On inspection, look for a casing that ends at or below grade, a cracked or missing well cap or vent screen, a pump base that is not watertight, and ponding or slopes draining toward the wellhead. Any of these is a pathway for contamination and can become a sanitary survey deficiency.