Study guide
15.1 Emergency Action Plans, Medical Services, First Aid & Sanitation (1926.35 / .50 / .51)
OSHA 30-Hour Construction Safety Exam
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: Safety Management, Regulatory Framework & Worker Rights
1.1 OSHA Regulatory Structure, OSH Act, General Duty Clause & Worker Rights 1.2 Safety Management Systems (SMS) & Safety Culture Leadership 1.3 Leading vs. Lagging Indicators, Safety Metrics & Recordkeeping (OSHA 300/300A/301) 1.4 Multi-Employer Worksite Citation Policy & Subcontractor Safety Oversight 1.5 Job Hazard Analysis (JHA/JSA), Hierarchy of Controls & Site-Specific Safety Plans (SSSP)
2 Chapter 2: Fall Protection Systems & Working at Heights
2.1 Fall Hazards, 6-Foot Rule & 29 CFR 1926 Subpart M Scope 2.2 Guardrail Systems, Safety Net Systems & Hole Covers 2.3 Personal Fall Arrest Systems (PFAS), Anchorages & Fall Clearance Calculations 2.4 Controlled Access Zones, Safety Monitoring Systems & Leading Edge Work 2.5 Stairways, Ladders & Access Systems (29 CFR 1926 Subpart X)
3 Chapter 3: Electrical Safety, Grounding & Energy Control
3.1 Electrical Hazards, Electrocution Dynamics & 29 CFR 1926 Subpart K 3.2 Ground Fault Circuit Interrupters (GFCI) & Assured Equipment Grounding Conductor Program (AEGCP) 3.3 Overhead Power Line Clearances & Encroachment Prevention 3.4 Lockout/Tagout (LOTO), De-energization & Hazardous Energy Control 3.5 Arc Flash Hazards, PPE Requirements & Qualified Worker Distinctions
4 Chapter 4: Scaffolding Systems & Aerial Lifts
4.1 Scaffold Classifications, Load Capacities & Subpart L General Requirements 4.2 Supported Scaffolds: Foundations, Planking, Bracing, Tie-ins & Erection 4.3 Suspended Scaffolds, Two-Point Swings & Rigging Counterweights 4.4 Aerial Lifts, Scissor Lifts & Mobile Elevated Work Platforms (MEWPs) 4.5 Competent Person Scaffold Inspection, Fall Protection & Access Rules
5 Chapter 5: Excavation, Trenching & Shoring Safety
5.1 Excavation Hazards, Soil Mechanics & Subpart P Scope 5.2 OSHA Soil Classification: Visual and Manual Field Testing (Types A, B, C) 5.3 Protective Systems: Sloping and Benching Ratios 5.4 Protective Systems: Hydraulic Shoring, Trench Boxes & Shields 5.5 Excavation Access/Egress, Hazardous Atmospheres & Competent Person Daily Inspections
6 Chapter 6: Cranes, Derricks, Hoists & Rigging
6.1 Subpart CC Scope, Operator Certification & Qualification Requirements 6.2 Crane Setup, Ground Conditions, Outriggers & Power Line Safety 6.3 Load Charts, Capacity Calculations & Lift Planning 6.4 Critical Lift Planning, Tandem Lifts & Personnel Hoisting 6.5 Rigging Hardware, Sling Angles, Hitches & Signal Person Qualifications
7 Chapter 7: Confined Spaces in Construction
7.1 29 CFR 1926 Subpart AA Scope & Confined Space vs. Permit-Required Confined Space (PRCS) 7.2 Atmospheric Testing: Sequential Order (O2, Flammability, Toxicity) & Calibration 7.3 PRCS Entry Permit Program, Isolation & Ventilation 7.4 Duties of Authorized Entrants, Attendants & Entry Supervisors 7.5 Non-Entry vs. Entry Rescue, Emergency Services & Retrieval Systems
8 Chapter 8: Incident Investigation, Root Cause Analysis & Prevention
8.1 Purpose of Incident Investigation & Blame-Free Reporting Culture 8.2 Immediate Response, Scene Security, Evidence Gathering & Witness Interviewing 8.3 Root Cause Analysis Methodologies: 5 Whys, Fishbone (Ishikawa), and Fault Tree 8.4 Human Factors, Swiss Cheese Model & Latent Organizational Failures 8.5 Corrective Action Plans, Hierarchy of Controls Application & Near-Miss Trending
9 Chapter 9: Occupational Health Hazards & Environmental Protection
9.1 Hazard Communication Standard (HazCom 2012 / GHS) & 16-Section Safety Data Sheets (SDSs) 9.2 Respirable Crystalline Silica (29 CFR 1926.1153) & Table 1 Control Methods 9.3 Lead & Asbestos Hazards in Construction Demolition and Renovation (29 CFR 1926.62 / 1926.1101) 9.4 Occupational Noise Exposure, Action Levels, PELs & Hearing Conservation Programs (Subpart D) 9.5 Thermal Stress (Heat Illness & Cold Injury Prevention) & Biological/Chemical Hazards
10 Chapter 10: Ergonomics, Material Handling & Tool Safety
10.1 Ergonomic Risk Factors in Construction & Musculoskeletal Disorders (MSDs) 10.2 Manual Material Handling, Safe Lifting Principles & Ergonomic Engineering Solutions 10.3 Hand-Arm Vibration Syndrome (HAVS), Whole-Body Vibration & Power Tool Safety (Subpart I) 10.4 Material Storage, Rigging Safety, Housekeeping & Disposal (29 CFR 1926 Subpart H) 10.5 Motor Vehicles, Heavy Equipment, Highway Work Zone Safety & Struck-By Prevention (Subpart O/G)
11 Chapter 11: Personal Protective and Life-Saving Equipment (29 CFR 1926 Subpart E)
11.1 PPE Programs, Hazard Assessment, the Proper-Fit Rule & Employer Payment 11.2 Head, Eye, and Face Protection (1926.100 / 1926.102) 11.3 Hearing, Hand, Foot, and Body Protection (1926.101 / 1926.95 / 1926.96) 11.4 Respiratory Protection: Program, Selection, Medical Evaluation & Fit Testing (1926.103)
12 Chapter 12: Struck-By and Caught-In/Between Focus Four Hazards
12.1 Struck-By Hazards: Flying, Falling, Swinging & Rolling Objects 12.2 Caught-In/Between Hazards, Machine Guarding & Rollover Protection 12.3 Powered Industrial Trucks, Telehandlers & Rough-Terrain Forklifts (1926.602)
13 Chapter 13: Concrete, Masonry & Steel Erection (Subparts Q and R)
13.1 Cast-in-Place Concrete, Formwork, Shoring & Rebar Impalement (Subpart Q) 13.2 Masonry Construction, Limited Access Zones & Precast/Tilt-Up Panels (Subpart Q) 13.3 Steel Erection: Column Anchorage, Connectors, Decking & the CDZ (Subpart R)
14 Chapter 14: Fire Prevention, Welding & Cutting, and Demolition (Subparts F, J, T)
14.1 Fire Protection and Prevention (29 CFR 1926 Subpart F) 14.2 Welding, Cutting & Hot Work (29 CFR 1926 Subpart J) 14.3 Demolition: Engineering Surveys & Sequenced Removal (29 CFR 1926 Subpart T)
15 Chapter 15: Emergency Preparedness, Site Welfare & Safety Leadership
15.1 Emergency Action Plans, Medical Services, First Aid & Sanitation (1926.35 / .50 / .51) 15.2 Foundations for Safety Leadership & the OSHA Outreach Card
15.1 Emergency Action Plans, Medical Services, First Aid & Sanitation (1926.35 / .50 / .51)
Key Takeaways Explain This Topic AI
Under 29 CFR 1926.35(e)(3), the emergency action plan must be written and kept at the workplace, except that employers with 10 or fewer employees may communicate the plan orally.
29 CFR 1926.50(c) requires a person holding a valid first-aid certificate to be available at the worksite whenever no infirmary, clinic, hospital, or physician is reasonably accessible in terms of time and distance.
First aid supplies must be in a weatherproof container with individual sealed packages for each item, checked by the employer before being sent out on each job and at least weekly on each job (29 CFR 1926.50(d)(2)).
Where eyes or body may be exposed to injurious corrosive materials, suitable facilities for quick drenching or flushing must be provided within the work area for immediate emergency use (29 CFR 1926.50(g)).
The toilet ratio in 29 CFR 1926.51(c)(1) is one facility for 20 or fewer employees, then one toilet seat and one urinal per 40 workers, and one toilet seat and one urinal per 50 workers at 200 or more.
Last updated: November 2026
15.1 Emergency Action Plans, Medical Services, First Aid & Sanitation
The 30-hour Construction Outreach curriculum reserves 4 optional hours for "other construction industry hazards or policies," and emergency preparedness plus site welfare is one of the most common uses of that time. These provisions are also cited constantly, because compliance is visible from the gate: is there a plan, is there a trained first-aider, is there potable water, are there enough toilets.
- 1. Emergency Action Plans — 29 CFR 1926.35
- The six required elements — 1926.35(b)
At a minimum, the plan must include:
- Emergency escape procedures and emergency escape route assignments
- Procedures to be followed by employees who remain to operate critical plant operations before they evacuate
- Procedures to account for all employees after emergency evacuation has been completed
- Rescue and medical duties for those employees who are to perform them
- The preferred means of reporting fires and other emergencies
Names or regular job titles of persons or departments who can be contacted for further information or explanation of duties under the plan
Note
Element 3 is the one that fails in the field. Head counts at the muster point are the only mechanism that tells an incident commander whether anyone is still in the building. On a site with a dozen subcontractors and a floating workforce, this requires a defined muster location per phase, a defined accounting method, and a defined person responsible.
Alarm system — 1926.35(c)
The employer must establish an employee alarm system . 1926.35(c) still names § 1926.159, but OSHA removed that section from Part 1926 in 1996; 1926.150(e)(1) requires an alarm that can alert employees on the site and the local fire department. If the alarm is used for alerting fire brigade members or for other purposes, a distinctive signal for each purpose must be used. The general-industry alarm rule, 1910.165 , adds that the alarm must be perceived above ambient noise or light levels .
Evacuation types and exit route assignments — 1926.35(d)
The employer must establish in the plan the types of evacuation to be used in emergency circumstances — full evacuation, partial evacuation, or shelter in place.
Training — 1926.35(e)
Requirement Provision
The employer must designate and train a sufficient number of persons to assist in the safe and orderly emergency evacuation of employees 1926.35(e)(1)
The employer must review the plan with each covered employee : initially when the plan is developed, whenever the employee's responsibilities or designated actions change , and whenever the plan is changed 1926.35(e)(2)
The written plan must be kept at the workplace and made available for employee review. Employers with 10 or fewer employees may communicate the plan orally and need not maintain a written plan 1926.35(e)(3)
Caution
The 10-employee threshold works in a specific direction. With more than 10 employees , the plan must be written and kept at the workplace. With 10 or fewer , it may be communicated orally . The obligation to have a plan does not disappear at 10 employees — only the writing requirement does.
Construction-specific emergency scenarios worth planning
- Scenario Plan elements
- Trench collapse Non-entry rescue only; call 911 immediately; never send workers in (Chapter 5)
Confined space emergency Pre-arranged rescue service evaluated in advance; non-entry retrieval; attendant stays outside until relieved (Section 7.5)
Fall arrest / suspension trauma Post-fall rescue plan with a defined method and time target; suspension intolerance can develop rapidly (Chapter 2)
Crane contact with power lines Operator stays in the cab unless fire forces evacuation; then jump clear, feet together, shuffle away (Section 3.3)
Severe weather / high wind Wind-speed thresholds for crane, scaffold, masonry, and tilt-up operations; defined shelter locations; lightning evacuation
- Structural collapse Immediate exclusion zone; no re-entry without engineering assessment
- 2. Medical Services and First Aid — 29 CFR 1926.50
Provision Requirement
(a) The employer must ensure the availability of medical personnel for advice and consultation on matters of occupational health
(b) Provisions must be made prior to commencement of the project for prompt medical attention in case of serious injury
(c) In the absence of an infirmary, clinic, hospital, or physician that is reasonably accessible in terms of time and distance to the worksite, a person who has a valid certificate in first-aid training from the U.S. Bureau of Mines, the American Red Cross, or equivalent training verifiable by documentary evidence, must be available at the worksite to render first aid
(d)(1) First aid supplies must be easily accessible when required
(d)(2) Contents of the first aid kit must be placed in a weatherproof container with individual sealed packages for each type of item, and must be checked by the employer before being sent out on each job and at least weekly on each job to replace expended items
(e) Proper equipment for prompt transportation of the injured person to a physician or hospital, or a communication system for contacting necessary ambulance service, must be provided
(f) In areas where 911 is not available, telephone numbers of physicians, hospitals, or ambulances must be conspicuously posted
(g) Where the eyes or body of any person may be exposed to injurious corrosive materials , suitable facilities for quick drenching or flushing of the eyes and body must be provided within the work area for immediate emergency use
"Reasonably accessible in terms of time and distance"
The standard does not state a number, but OSHA has interpreted the requirement consistently in guidance and letters of interpretation:
For injuries where life is threatened — cardiac arrest, airway obstruction, or severe bleeding — the response time should be 3 to 4 minutes , because irreversible brain damage from oxygen deprivation begins in roughly that window.
For less serious injuries , a response time of no more than 15 minutes is generally acceptable.
Caution
Exam framing: a scenario placing a jobsite 25 or 30 minutes from the nearest emergency department is describing a site where medical care is not reasonably accessible , which triggers the 1926.50(c) requirement for a certified first-aider on site. Note that the standard says "first-aid training"; most employers meet it with combined first aid, CPR, and AED certification, and 1926.50 does not itself require CPR certification by name .
Eyewash — 1926.50(g)
The construction standard is performance-based: suitable facilities for quick drenching or flushing , within the work area , for immediate emergency use . Where the exposure is to a strong corrosive — masonry cleaning acid, concrete admixtures, battery electrolyte — the widely adopted consensus benchmark is ANSI/ISEA Z358.1 , which specifies a 10-second travel time (roughly 55 feet on an unobstructed path) and a 15-minute flush duration . A personal squeeze bottle is a supplement to a plumbed or gravity-fed unit, never a substitute for one.
3. Sanitation — 29 CFR 1926.51
Sanitation is not a comfort provision. Dehydration is a direct contributor to heat illness (Section 9.5), and inadequate handwashing drives lead and silica take-home exposure to workers' families (Section 9.3).
Potable water — 1926.51(a)
- Requirement Provision
- An adequate supply of potable water must be provided in all places of employment 1926.51(a)(1)
Portable containers must be capable of being tightly closed and equipped with a tap ; water must not be dipped from the container 1926.51(a)(2)
Any container used to distribute drinking water must be clearly marked as to its contents and must not be used for any other purpose 1926.51(a)(3)
The common drinking cup is prohibited 1926.51(a)(4)
Where single-service cups are supplied, both a sanitary container for unused cups and a receptacle for used cups must be provided 1926.51(a)(5)
1926.51(b): outlets for nonpotable water — such as water for industrial or firefighting purposes — must be identified by signs meeting 1926.200 to indicate clearly that the water is unsafe and is not to be used for drinking, washing, or cooking. There must be no cross-connection , open or potential, between a potable and a nonpotable system.
Toilets — 1926.51(c)
- Number of Employees Minimum Number of Facilities
- 20 or fewer 1
- 20 or more 1 toilet seat and 1 urinal per 40 workers
- 200 or more 1 toilet seat and 1 urinal per 50 workers
1926.51(c)(2): Under temporary field conditions , provision must be made to assure not less than one toilet facility is available .
1926.51(c)(3): This section does not apply to mobile crews having transportation readily available to nearby toilet facilities .
1926.51(c)(4): Job sites not provided with a sanitary sewer must be provided with chemical toilets, recirculating toilets, combustion toilets, or flush toilets.
Washing facilities — 1926.51(f)
The employer must provide adequate washing facilities for employees engaged in the application of paints, coatings, herbicides, or insecticides , or in other operations where contaminants may be harmful . The facilities must be in near proximity to the worksite and must be so equipped as to enable employees to remove such substances .
Note
Washing facilities are a lead and silica control. 1926.62(i) requires clean change areas, showers where feasible, and handwashing facilities for lead work; 1926.1153(i) drives the same logic for silica. A worker who eats lunch with lead dust on their hands ingests lead, and a worker who drives home in contaminated clothes brings it to their family.
Eating and drinking areas — 1926.51(g) and food handling — 1926.51(d)
No employee shall be allowed to consume food or beverages in a toilet room or in any area exposed to a toxic material . All food service facilities and operations must meet applicable state and local laws , and all employee food service facilities must be sanitary .
4. Signs, Signals, and Barricades — 29 CFR 1926 Subpart G
Subpart G supports every emergency and welfare provision above by making hazards and instructions visible.
- Sign Type Colors Use Citation
- Danger Red, black, and white Immediate hazard; special precautions necessary 1926.200(b)
Caution Yellow background, black panel with yellow letters Warn against potential hazards or caution against unsafe practices 1926.200(c)
Exit Legible, per the standard Marking exits 1926.200(d)
Safety instruction White background, green panel with white letters General instructions relating to safety measures 1926.200(e)
Directional White with black panel and white directional symbol Directions to first aid, medical, and similar facilities 1926.200(f)
Traffic Per MUTCD Construction areas where traffic hazards exist 1926.200(g)
Accident prevention tags Per 1926.200(h) Temporary hazards — "Do Not Start," "Do Not Operate," "Out of Order," defective equipment 1926.200(h)
Flaggers (1926.201(a)) must use STOP/SLOW paddles, hand-signaling devices, or red flags conforming to the MUTCD, and must wear high-visibility apparel as covered in Section 11.3.