Study guide

10.5 Signs, Signals, Barricades & Demolition (Subparts G and T)

OSHA 500 Trainer Course in Occupational Safety and Health Standards for the Construction Industry Exam

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: OSHA Outreach Training Program Policies & Trainer Authorization

1.1 Outreach Trainer Qualifications, Authorization & Renewal 1.2 Class Administration, Attendance & Delivery Limits 1.3 10-Hour and 30-Hour Construction Curricula & Hour Requirements 1.4 Documentation, Records Retention & Card Processing 1.5 Required Outreach Curriculum, Focus Four Objectives & Student Materials 1.6 Trainer Roles, Training Language, Geographic Jurisdiction & Alternative Delivery

2 Chapter 2: OSH Act, Inspections & Multi-Employer Worksites

2.1 The OSH Act & The General Duty Clause 2.2 OSHA Inspection Process, Citations & Penalties 2.3 Injury/Illness Recordkeeping & Fatality Reporting 2.4 Multi-Employer Worksite Policy & Safety Roles 2.5 Managing Safety and Health: Programs, JHAs, Investigations & Safety Leadership

3 Chapter 3: Fall Protection Standards (29 CFR 1926 Subpart M)

3.1 Fall Protection Triggers, Scope & Duty to Have Fall Protection 3.2 Guardrail Systems, Safety Nets & Falling Object Protection 3.3 Personal Fall Arrest Systems (PFAS), Positioning & Restraint 3.4 Warning Lines, Safety Monitoring & Fall Protection Plans

4 Chapter 4: Scaffolds, Stairways, and Ladders (Subparts L & X)

4.1 Supported Scaffolds: Capacity, Planking & Erection 4.2 Suspended Scaffolds, Special Types & Fall Protection 4.3 Stairways and Stair Rails 4.4 Portable and Fixed Ladders: Setup, Inspection & Use

5 Chapter 5: Excavations, Trenching & Soil Mechanics (Subpart P)

5.1 Excavation Hazards, Access & Protective System Triggers 5.2 Soil Classification & Field Testing Procedures 5.3 Sloping, Benching, Shoring & Shield Systems 5.4 Trench Atmospheres, Utilities & Daily Competent Person Inspections

6 Chapter 6: Cranes, Rigging & Heavy Equipment Safety

6.1 Crane Standards (Subpart CC): Setup, Ground Conditions & Power Lines 6.2 Crane Operation, Signal Persons & Operator Qualifications 6.3 Rigging Equipment & Slings (Subpart H) 6.4 Motor Vehicles, Mechanized Equipment & Struck-By Prevention

7 Chapter 7: Electrical Safety, Confined Spaces & Physical Hazards

7.1 Ground-Fault Protection (GFCI) & Assured Grounding Programs 7.2 Electrical Wiring, Overcurrent Protection & Lockout/Tagout 7.3 Confined Spaces in Construction (Subpart AA) 7.4 Fire Protection, Welding & Hot Work Safety (Subparts F & J)

8 Chapter 8: Health Hazards, Silica, Noise & Personal Protective Equipment

8.1 Respirable Crystalline Silica (1926.1153) & Dust Controls 8.2 Occupational Noise, Lead & Chemical Hazards 8.3 Hazard Communication & Safety Data Sheets 8.4 Personal Protective Equipment & Respiratory Protection

9 Chapter 9: Adult Learning Principles & Instructional Delivery

9.1 Principles of Adult Learning (Andragogy) & Learner Engagement 9.2 Writing Performance-Based Learning Objectives & Bloom's Taxonomy 9.3 Instructional Methods, Questioning & Classroom Management 9.4 Training Evaluation & OSHA 500 Presentation Test Preparation

10 Chapter 10: Additional 29 CFR 1926 Subparts & Outreach Elective Topics

10.1 Steel Erection (Subpart R) 10.2 Concrete and Masonry Construction (Subpart Q) 10.3 Hand and Power Tools (Subpart I) 10.4 Materials Handling, Storage, Use & Disposal and Powered Industrial Vehicles 10.5 Signs, Signals, Barricades & Demolition (Subparts G and T) 10.6 Subparts C & D: Employer Duties, Sanitation, Illumination, Heat and Cold Stress & Ergonomics

10.5 Signs, Signals, Barricades & Demolition (Subparts G and T)

Key Takeaways Explain This Topic AI

Danger signs use red as the predominating color on the upper panel and are used only where an immediate hazard exists; caution signs are predominantly yellow and warn against potential hazards or unsafe practices.

Accident prevention tags are a temporary means of warning employees of an existing hazard and may never substitute for an accident prevention sign.

Before demolition begins, a competent person must perform an engineering survey of the structure and adjacent structures, and the employer must have written evidence that the survey was performed.

All electric, gas, water, steam, sewer, and other service lines must be shut off, capped, or otherwise controlled outside the building line before demolition work starts, with the utility notified in advance.

Material dropped more than 20 feet outside the exterior walls requires an enclosed chute; wall openings that expose a fall hazard must be protected to a height of approximately 42 inches.

Last updated: September 2026

10.5 Signs, Signals, Barricades & Demolition (Subparts G and T)

Core Principle: Subpart G (1926.200–203) is how a jobsite tells people what it is about to do to them. Subpart T (1926.850–860) governs demolition, the one phase of construction in which the structure's real condition is unknown, its as-built drawings are often wrong, and the sequence of removal determines whether the building comes down where it was planned to. Signs, signals, and barricades is part of the named outreach elective "Motor Vehicles; Mechanized Equipment and Marine Operations; Rollover Protective Structures and Overhead Protection; and Signs, Signals, and Barricades."

  • 1. Accident Prevention Signs and Tags (1926.200)
  • The General Rule

Signs and symbols required by Subpart G shall be visible at all times when work is being performed , and shall be removed or covered promptly when the hazards no longer exist . That second half matters: a site papered with stale danger signs teaches workers to ignore them.

Sign Types, Uses, and Colors

Sign Type When It Is Used Color Scheme

Danger (1926.200(b)) Only where an immediate hazard exists Red as the predominating color for the upper panel; black outline on the borders; a white lower panel for additional wording

Caution (1926.200(c)) Only to warn against potential hazards or to caution against unsafe practices Yellow as the predominating color; black upper panel and borders; yellow lettering of "caution" on the black panel; lower yellow panel for additional wording in black letters

Exit (1926.200(d)) Marking exits where required Legible red letters not less than 6 inches high on a white field , principal stroke of the letters at least three-fourths inch wide

Safety instruction (1926.200(e)) General instructions and suggestions relative to safety measures White with a green upper panel with white letters for the principal message; additional wording in black on the white background

Directional (1926.200(f)) Directing traffic other than automotive traffic White with a black panel and a white directional symbol ; additional wording in black on white

Traffic control (1926.200(g)) Points of hazard in construction areas Design and use of all traffic control devices, including signs, signals, markings, barricades and other devices for protection of construction workers, shall conform to Part 6 of the MUTCD

Danger and caution signs follow the specifications illustrated in ANSI Z35.1-1968 or ANSI Z535.2-2011 , incorporated by reference in 1926.6 — either edition is acceptable, which is why both the older red-oval and the modern Z535 formats are seen in the field.

Accident Prevention Tags (1926.200(h))

Tags are a temporary means of warning employees of an existing hazard , such as defective tools or equipment. The key sentence is the limitation: they shall not be used in place of, or as a substitute for, accident prevention signs. A "Danger — Do Not Operate" tag on a broken saw is correct use; a tag hung where a permanent danger sign is required is not.

Signaling and Barricades (1926.201 and 1926.202)

1926.201(a) Flagging: signaling by flaggers and the use of flaggers, including the warning garments worn by flaggers, shall conform to Part 6 of the MUTCD.

1926.201(b) Crane and hoist signals: where employees are exposed, signals shall be posted at the operator's station.

1926.202 Barricades: barricades for protection of employees shall conform to Part 6 of the MUTCD.

2. Demolition: Preparatory Operations (1926.850)

Subpart T front-loads its safety into work that happens before a single wall comes down.

The Engineering Survey — 1926.850(a)

Prior to permitting employees to start demolition operations, an engineering survey shall be made, by a competent person, of the structure to determine the condition of the framing, floors, and walls, and possibility of unplanned collapse of any portion of the structure. Any adjacent structure where employees may be exposed shall also be similarly checked. The employer shall have in writing evidence that such a survey has been performed.

Three examinable points hide in that sentence: the survey is performed by a competent person (not necessarily an engineer despite the name); it must cover adjacent structures where employees may be exposed; and the employer must hold written evidence that it was done.

Fire, Flood, and Explosion Damage — 1926.850(b)

Where employees must work within a structure damaged by fire, flood, explosion, or other cause , the walls or floor shall be shored or braced .

Utilities — 1926.850(c) and (d)

All electric, gas, water, steam, sewer, and other service lines shall be shut off, capped, or otherwise controlled, outside the building line before demolition work is started. In each case, any utility company which is involved shall be notified in advance. If a utility must be maintained during demolition, it shall be temporarily relocated as necessary and protected .

Hazardous Substances — 1926.850(e)

It must be determined whether any hazardous chemicals, gases, explosives, flammable materials, or similarly dangerous substances have been used in any pipes, tanks, or other equipment on the property. Where their presence is apparent or suspected, testing and purging shall be performed and the hazard eliminated before demolition is started.

Physical Preparations — 1926.850(f) through (j)

  • Paragraph Requirement
  • (f) Where a hazard exists from fragmentation of glass , such hazards shall be removed

(g) Where a hazard exists to employees falling through wall openings , the opening shall be protected to a height of approximately 42 inches

(h) When debris is dropped through holes in the floor without chutes , the landing area shall be completely enclosed with barricades not less than 42 inches high and not less than 6 feet back from the projected edge of the opening above; signs warning of falling materials at each level ; no removal below until debris handling ceases above

(i) All floor openings not used as material drops shall be covered with material substantial enough to support the imposed load, properly secured against accidental movement

(j) Except for the cutting of holes for chutes, holes for equipment, and similar necessary openings, floor openings within 10 feet of any wall being demolished shall be planked solid

Stairs, Passageways, and Ladders — 1926.851

Only stairways, passageways, and ladders designated as means of access to the structure of a building shall be used, and other access ways shall be entirely closed at all times . All stairs, passageways, ladders, and incidental equipment covered by the section shall be periodically inspected and maintained in a clean, safe condition . In a multistory building where a stairwell is being used, it shall be properly illuminated by either natural or artificial means and completely and substantially covered over at a point not less than two floors below the floor on which work is being performed , with access to the floor where work is in progress through a properly lighted, protected, and separate passageway .

Chutes — 1926.852

(a) No material shall be dropped to any point lying outside the exterior walls of the structure unless the area is effectively protected .

(b) All material chutes, or sections thereof, at an angle of more than 45° from the horizontal, shall be entirely enclosed , except for openings equipped with closures at or about floor level for the insertion of materials. Those openings shall not exceed 48 inches in height measured along the wall of the chute, and at all stories below the top floor such openings shall be kept closed when not in use .

(c) A substantial gate shall be installed in each chute at or near the discharge end , with a competent employee assigned to control its operation and the backing and loading of trucks.

(f) Where the material is dumped from mechanical equipment or wheelbarrows, a securely attached toeboard or bumper, not less than 4 inches thick and 6 inches high , shall be provided at each chute opening. Any space between the chute and the edge of the floor openings through which it passes shall be solidly covered over .

(g) Chutes shall be designed and constructed of such strength as to eliminate failure due to impact of materials or debris loaded therein .

3. Sequence and Mechanical Demolition

1926.854 Walls, masonry sections, and chimneys: masonry walls or sections of masonry shall not be permitted to fall upon the floors of the building in such masses as to exceed the safe carrying capacities of the floors . No wall section more than one story in height shall be permitted to stand alone without lateral bracing, unless the wall was originally designed to stand without such support and is in a safe condition. Employees shall not be permitted to work on the top of a wall when weather conditions constitute a hazard.

1926.856 Removal of walls, floors, and material with equipment: floor openings shall have curbs or stop-logs to prevent equipment from running over the edge, and mechanical equipment shall not be used on floors or working surfaces unless those surfaces are of sufficient strength to support the imposed load.

1926.859 Mechanical demolition: no employee shall be permitted in any area that can be adversely affected by demolition when balling or clamming is being performed; the weight of the demolition ball shall not exceed 50 percent of the crane's rated load, based on the length of the boom and the maximum angle of operation at which the ball will be used , or 25 percent of the nominal breaking strength of the line by which it is suspended, whichever results in a lesser value . The crane boom and load line shall be as short as possible, and the ball shall be attached to the load line with a swivel-type connection to prevent twisting, and attached by a positive means so it cannot become accidentally disconnected.

4. Demolition and the Rest of 1926

Demolition never stands alone. On a live demolition project a trainer should expect all of the following to apply simultaneously:

  • Hazard Governing standard
  • Falls at 6 ft or more, holes, and wall openings Subpart M, plus 1926.850(g)-(j)

Asbestos in thermal system insulation, flooring, and surfacing 1926.1101, including the Class I through IV work classifications

Lead in paint on structural steel and plaster 1926.62 trigger tasks, including manual demolition of lead-containing structures

  • Silica from concrete cutting, crushing, and jackhammering 1926.1153 Table 1
  • Cranes and the demolition ball Subpart CC and 1926.859
  • Struck-by from equipment and falling material Subpart O, 1926.252, 1926.850(h)
  • Confined spaces in tanks, vaults, and pits Subpart AA