Study guide

10.6 Hazardous Materials (Subpart H): Compressed Gases, Spray Finishing & HAZWOPER (1910.101, 1910.107, 1910.120)

OSHA 511 Occupational Safety and Health Standards for General Industry Exam

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: OSH Act, Regulatory Framework & Inspection Procedures

1.1 OSH Act Purpose, Scope & General Duty Clause 1.2 OSHA Inspections, Priorities & Inspector Credentials 1.3 Citation Categories, Penalty Calculations & Contesting Procedures 1.4 Employer Rights, Employee Rights & Whistleblower Protections 1.5 Navigating 29 CFR: Standards Organization, Codification & Rulemaking 1.6 Safety & Health Programs, Cooperative Programs & Multi-Employer Worksites

2 Chapter 2: OSHA Recordkeeping & Reporting (29 CFR Part 1904)

2.1 Recording Criteria, Exclusions & First Aid vs. Medical Treatment 2.2 OSHA Recordkeeping Forms (Forms 300, 300A, 301) & Annual Summary Posting 2.3 Severe Injury Reporting Timelines, Privacy Cases & Electronic Submission

3 Chapter 3: Walking-Working Surfaces & Emergency Preparedness (Subparts D & E)

3.1 General Walking-Working Surface Requirements & Housekeeping (1910.22) 3.2 Ladders, Stairways, Scaffolds & Dockboards (1910.23-26) 3.3 Fall Protection Systems, Falling Object Protection & Training (1910.28-30) 3.4 Exit Routes, Emergency Action Plans (EAPs) & Fire Prevention Plans (1910.34-39) 3.5 Fire Protection (Subpart L): Extinguishers, Fixed Systems, Detection & Employee Alarms (1910.155-1910.165)

4 Chapter 4: Hazard Communication & GHS Standard (29 CFR 1910.1200)

4.1 Hazard Communication Standard Overview & Written HazCom Program 4.2 GHS Chemical Hazard Classification & Physical vs. Health Hazards 4.3 GHS Labels, Signal Words & 9 GHS Pictograms 4.4 Safety Data Sheets (16-Section SDS Format) & Employee Information/Training

5 Chapter 5: Personal Protective Equipment & Respiratory Protection (Subpart I)

5.1 Hierarchy of Controls & Hazard Assessment Certification (1910.132) 5.2 Eye, Face, Head, Foot & Hand Protection Standards (1910.133-138) 5.3 Respiratory Protection Program, Fit Testing & Medical Evaluations (1910.134) 5.4 Assigned Protection Factors (APFs), Maximum Use Concentrations & Respirator Selection

6 Chapter 6: Control of Hazardous Energy / Lockout/Tagout (29 CFR 1910.147)

6.1 Energy Control Program & Authorized vs. Affected Employee Roles 6.2 Lockout/Tagout Procedural Steps & Stored Energy Isolation 6.3 Special LOTO Situations: Group LOTO, Shift Changes & Outside Contractors 6.4 Periodic Annual Inspection, LOTO Hardware & Removal of Energy Controls

7 Chapter 7: Permit-Required Confined Spaces (29 CFR 1910.146)

7.1 Confined Space vs. Permit-Required Confined Space (PRCS) Identification 7.2 Atmospheric Testing Sequence, Testing Equipment & Acceptable Limits 7.3 PRCS Entry Roles: Entrant, Attendant, Entry Supervisor & Permit System 7.4 Non-Entry Rescue, Retrieval Systems & Emergency Response Services

8 Chapter 8: Electrical Safety & Safe Work Practices (Subpart S)

8.1 General Electrical Safety, NRTL Listing & Equipment Guarding (1910.303) 8.2 System Grounding, Ground-Fault Circuit Interrupters (GFCIs) & Wiring (1910.304-305) 8.3 Electrical Safe Work Practices, Qualified Persons & Approach Boundaries (1910.331-335) 8.4 Arc Flash Hazards, Personal Protective Equipment & Rubber Insulating Gloves

9 Chapter 9: Machine Guarding & Materials Handling (Subparts N & O)

9.1 General Machine Guarding Requirements & Safeguard Types (1910.212) 9.2 Mechanical Power Presses, Point of Operation & Power Transmission Guarding (1910.217, 1910.219) 9.3 Powered Industrial Trucks (Forklifts): Operator Training, Retraining & Safe Operation (1910.178) 9.4 Materials Handling, Storage, Slings & Overhead Cranes (1910.176, 1910.179, 1910.184) 9.5 Hand & Portable Powered Tools (Subpart P, 1910.241-1910.244)

10 Chapter 10: Occupational Health, Industrial Hygiene & Process Safety (Subparts G & Z)

10.1 Occupational Noise Exposure, Sound Levels & Hearing Conservation Program (1910.95) 10.2 Toxic & Hazardous Substances, Table Z-1 PELs & Industrial Hygiene Paradigm (1910.1000) 10.3 Specific Health Standards: Asbestos, Lead, Bloodborne Pathogens & Methylene Chloride 10.4 Process Safety Management (PSM) of Highly Hazardous Chemicals (1910.119 - 14 Elements) 10.5 Flammable Liquids (1910.106) & Welding, Cutting, and Brazing Safety (1910.252) 10.6 Hazardous Materials (Subpart H): Compressed Gases, Spray Finishing & HAZWOPER (1910.101, 1910.107, 1910.120) 10.7 General Environmental Controls & First Aid: Sanitation, Color Codes, Signs & Tags, Medical Services (Subparts J & K)

10.6 Hazardous Materials (Subpart H): Compressed Gases, Spray Finishing & HAZWOPER (1910.101, 1910.107, 1910.120)

Key Takeaways Explain This Topic AI

29 CFR 1910.101 works almost entirely through incorporation by reference: cylinder visual inspection follows CGA C-6, in-plant handling and storage follows CGA P-1, and safety relief devices follow CGA S-1.1, S-1.2, and S-1.3.

Spray booths require an independent exhaust duct with a minimum air velocity of 100 linear feet per minute for conventional spraying and 60 linear feet per minute for electrostatic operations (1910.107(b)(5)(i)), with ventilation running during and after spraying.

No open flame or spark-producing equipment may be located in a spraying area or within 20 feet of it unless separated by a partition; wiring inside the spray area must be explosion-proof for Class I Group D, and equipment within 20 feet must meet Class I Division 2 (1910.107(c)(2) and (c)(6)).

HAZWOPER covers three populations: uncontrolled hazardous waste site cleanup, RCRA corrective actions and TSD facilities, and emergency response to hazardous substance releases without regard to location - the third reaches ordinary general industry plants.

The five HAZWOPER emergency response levels are Awareness (competency-based), Operations (at least 8 hours, defensive), Hazardous Materials Technician (at least 24 hours, offensive), Hazardous Materials Specialist (at least 24 hours), and On Scene Incident Commander (at least 24 hours equal to the operations level).

Last updated: August 2026

  • 10.6 Hazardous Materials (Subpart H): Compressed Gases, Spray Finishing & HAZWOPER
  • What Is Left in Subpart H

29 CFR 1910 Subpart H - Hazardous Materials is the widest-ranging subpart in Part 1910. Two of its heaviest sections already have their own chapters in this guide: 1910.106 (Flammable Liquids) and 1910.119 (Process Safety Management) . This section covers the rest of the subpart that OSHA 511 names in its hazardous materials module:

  • Section Subject
  • 1910.101 Compressed gases (general requirements)
  • 1910.102 - 1910.105 Acetylene, hydrogen, oxygen, nitrous oxide
  • 1910.106 Flammable liquids (Section 10.5)
  • 1910.107 Spray finishing using flammable and combustible materials
  • 1910.109 Explosives and blasting agents
  • 1910.110 - 1910.111 Storage and handling of LP-Gas; anhydrous ammonia
  • 1910.119 Process Safety Management (Section 10.4)
  • 1910.120 Hazardous waste operations and emergency response (HAZWOPER)

Note the boundary that trips people up: Subpart H, 1910.101 covers the compressed gas in the cylinder; Subpart M (1910.166-1910.169) covers compressed air receivers and compressed air equipment. Two different subparts, two different tabs.

Compressed Gases (1910.101 and 1910.102-1910.105)

29 CFR 1910.101 is unusually short because it does its work almost entirely through incorporation by reference under 1910.6. Three duties:

Cylinder inspection (1910.101(a)): the employer must determine that compressed gas cylinders under its control are in a safe condition to the extent that this can be determined by visual inspection, performed in accordance with Compressed Gas Association (CGA) Pamphlet C-6 . Visual inspection means checking for corrosion, gouges, dents, arc burns, fire damage, bulges, defective valves, and illegible or missing markings.

Handling, storage, and utilization (1910.101(b)): must comply with CGA Pamphlet P-1 , which is where the practical rules live - cylinders secured upright, valve protection caps in place when the cylinder is not in use or being moved, cylinders never used as rollers or supports, and cylinders kept away from ignition sources and electrical circuits.

Safety relief devices (1910.101(c)): compressed gas cylinders, portable tanks, and cargo tanks must have pressure relief devices installed and maintained in accordance with CGA Pamphlets S-1.1, S-1.2, and S-1.3 .

The sections that follow are gas-specific: 1910.102 acetylene (adopting CGA G-1), 1910.103 hydrogen, 1910.104 oxygen, and 1910.105 nitrous oxide. The bulk oxygen and welding-gas separation rules that OSHA 511 tests are in 1910.253 and are covered in Section 10.5 of this guide - oxygen separated from fuel-gas cylinders and combustibles by 20 feet or by a 5-foot noncombustible barrier with at least a half-hour fire rating .

Spray Finishing with Flammable and Combustible Materials (1910.107)

A spray booth is a small, deliberately ventilated flammable vapor space with an ignition source pointed into it, which is why 1910.107 is prescriptive.

Booth Construction (1910.107(b))

Spray booths must be substantially constructed of steel, securely and rigidly supported, or of concrete or masonry (1910.107(b)(1)).

Interior surfaces must be smooth and continuous without edges , and designed to prevent pockets that collect residues and to permit easy cleaning and washing without injury (1910.107(b)(2)).

Floors and baffles must be noncombustible; where the floor is combustible it must be covered with noncombustible material.

Ventilation (1910.107(b)(5) and (d))

Each spray booth must have an independent exhaust duct discharging to the exterior .

Air velocity through the booth must be maintained at the rates in the standard: a minimum of 100 linear feet per minute for conventional air-atomizing spraying, reduced to a minimum of 60 linear feet per minute for electrostatic operations (1910.107(b)(5)(i)).

The ventilating system must be kept in operation while spraying and for a sufficient time afterward to exhaust vapors from drying coated articles and finishing material residue (1910.107(d)(2)). The interlock rule follows from this: spray apparatus must not operate unless the exhaust fan is running.

Ignition Control (1910.107(c))

No open flame or spark-producing equipment may be located in any spraying area nor within 20 feet of it, unless separated by a partition (1910.107(c)(2)).

Electrical wiring and equipment inside any spray area where deposits of combustible residues may accumulate must be explosion-proof and approved for Class I, Group D locations ; equipment within 20 feet of the spray area, but outside it, must not produce sparks under normal operating conditions and must meet Class I, Division 2 requirements (1910.107(c)(6)).

Space heating appliances, steam pipes, or hot surfaces must not be located where deposits of combustible residues could ignite.

Housekeeping and Quantities (1910.107(e) and (g))

The quantity of flammable or combustible liquid kept in the vicinity of spraying operations should ordinarily not exceed a supply for one day or one shift (1910.107(e)(2)).

Original closed containers, approved portable tanks, approved safety cans, or a properly arranged system of piping must be used for bringing flammable liquid into spray finishing rooms.

All spraying areas must be kept as free from the accumulation of deposits of combustible residues as practical, with cleaning done only with nonsparking tools (1910.107(g)).

"No Smoking" signs in large letters on a contrasting color background must be conspicuously posted at all spraying areas and paint storage rooms.

  • HAZWOPER: Hazardous Waste Operations and Emergency Response (1910.120)
  • The Three Covered Populations

29 CFR 1910.120(a)(1) reaches three distinct groups. Which one applies determines everything about training and program requirements:

Uncontrolled hazardous waste site cleanup required by a governmental body - federal, state, local, or other - whether the site is on the National Priorities List or not, including initial investigations before the presence or absence of hazardous substances has been ascertained.

RCRA corrective actions - cleanup operations at sites covered by the Resource Conservation and Recovery Act, and routine operations at treatment, storage, and disposal (TSD) facilities licensed under RCRA.

Emergency response operations for releases of, or substantial threats of releases of, hazardous substances without regard to the location of the hazard . This third population is the one that reaches ordinary general industry plants, because a chemical release in a manufacturing facility is an emergency response even though the plant is not a waste site.

Site Worker Training (1910.120(e))

Worker category Minimum initial training

General site workers (equipment operators, general laborers, supervisory personnel engaged in hazardous substance removal or other activities exposing them to hazardous substances and health hazards) 40 hours of instruction off the site, plus a minimum of 3 days actual field experience under the direct supervision of a trained, experienced supervisor

Workers on site only occasionally for a specific limited task (such as groundwater monitoring, land surveying, or geophysical surveying) and unlikely to be exposed over permissible exposure limits 24 hours of instruction off the site, plus a minimum of 1 day actual field experience

Workers regularly on site who work in areas monitored and fully characterized as having exposures under permissible exposure limits and published exposure levels, where respirators are not necessary 24 hours of instruction off the site, plus a minimum of 1 day actual field experience

On-site management and supervisors directly responsible for or supervising employees engaged in hazardous waste operations Same training as the workers they supervise, plus at least 8 additional hours of specialized training

Employees covered by 1910.120(e)(1) must receive 8 hours of refresher training annually (1910.120(e)(8)).

The Five Emergency Response Training Levels (1910.120(q)(6))

Training is based on the duties and functions each responder will perform, and each higher level builds on the one below:

Level Role Minimum training

First Responder Awareness Likely to witness or discover a release and trained only to initiate the emergency response sequence by notifying the proper authorities - they take no further action Sufficient training, or sufficient experience, to objectively demonstrate competency in the listed areas (no fixed hour requirement)

First Responder Operations Respond defensively to contain the release from a safe distance, keep it from spreading, and prevent exposures - without trying to stop the release At least 8 hours of training, or sufficient experience to objectively demonstrate competency, in addition to the awareness-level competencies

Hazardous Materials Technician Respond aggressively and approach the point of release to plug, patch, or otherwise stop it At least 24 hours of training equal to the first responder operations level, plus certified competency in the listed areas

Hazardous Materials Specialist Provide direct support to the technician with more specific knowledge of the substances, and act as the site liaison with federal, state, local, and other government authorities At least 24 hours of training equal to the technician level, plus certified competency in the listed areas

On Scene Incident Commander Assume control of the incident scene beyond the awareness level At least 24 hours of training equal to the first responder operations level, plus certified competency in the Incident Command System, the employer's emergency response plan, hazard and risk assessment, PPE selection, and decontamination

EXAM FRAMING : OSHA 511 will not ask you to design a HAZWOPER program. It will ask you to place a plant employee at the right level. The forklift driver told to call the control room and evacuate when a drum ruptures is Awareness . The plant spill team that closes a valve, dikes the spill, and re-enters to plug the leak is at least Operations , and plugging or patching moves it to Technician .

Loading diagram... HAZWOPER 1910.120(q)(6): The Five Emergency Response Training Levels