17.2 Pressure Relief Valve (PRV) and Rupture Disk Sizing
PE Chemical Exam
Track your progress as you read
Finished sections get a check mark.
1 Introduction & Exam Overview
About the PE Chemical Exam How to Use This Guide and the NCEES Handbook
2 Chapter 1: Material Balances & Flowsheet Calculations
1.1 Degree-of-Freedom Analysis & Process Flowsheet Accounting 1.2 Steady-State Material Balances (Reactive & Non-Reactive Systems) 1.3 Recycle, Bypass, and Purge Operations
3 Chapter 2: Energy Balances & Thermochemistry
2.1 Enthalpy Accounting, Sensible Heat, and Phase Changes 2.2 Heats of Reaction, Formation, and Adiabatic Flame Temperatures 2.3 Unsteady-State Mass and Energy Balances
4 Chapter 3: Fluid Statics & Incompressible Pipe Flow
3.1 Fluid Statics, Pressure Measurement, and Manometry 3.2 Incompressible Flow, Friction Factors, and the Moody Diagram 3.3 Minor Losses, Equivalent Length, and Piping Networks 3.4 Pumps, Compressors, and NPSH Calculations
5 Chapter 4: Advanced Fluid Dynamics & Compressible Flow
4.1 Compressible Gas Flow, Sonic Velocity, and Choked Flow 4.2 Flow Measurement Devices (Orifices, Venturis, Rotameters) 4.3 Multiphase Flow and Fluidization Principles 4.4 Mixing, Agitation, and Agitator Scale-Up
6 Chapter 5: Thermodynamic Laws & Fundamental Relations
5.1 First and Second Laws, Heat Engines, and Carnot Efficiency 5.2 Entropy, Availability, and Exergy Analysis 5.3 Fundamental Property Relations and Maxwell Equations
7 Chapter 6: Real Gases & Equations of State
6.1 Volumetric Properties and Compressibility Factor Charts 6.2 Cubic Equations of State (vdW, RK, SRK, and Peng-Robinson) 6.3 Residual Properties and Enthalpy/Entropy Departure Functions
8 Chapter 7: Phase & Chemical Reaction Equilibria
7.1 Pure Component Vapor Pressure and Phase Equilibria 7.2 Vapor-Liquid Equilibrium (VLE), Raoult's Law, and Activity Coefficients 7.3 Chemical Reaction Equilibria and Equilibrium Constant Calculation
9 Chapter 8: Heat Transfer Mechanisms & Conduction
8.1 Steady-State Conduction in Planar, Cylindrical, and Spherical Geometries 8.2 Convective Heat Transfer and Dimensionless Correlations 8.3 Thermal Radiation, Emissivity, and Surface Radiation Exchange
10 Chapter 9: Heat Exchanger Design & Phase Change
9.1 Shell-and-Tube Exchanger Design, TEMA Standards, and LMTD 9.2 Effectiveness-NTU Method and Exchanger Rating 9.3 Boiling Regimes, Condensation Phenomena, and Fouling Resistances
11 Chapter 10: Mass Transfer Fundamentals & Diffusion
10.1 Molecular Diffusion, Fick's Laws, and Equimolar Counterdiffusion 10.2 Convective Mass Transfer and Film Theories 10.3 Mass Transfer Dimensionless Numbers (Sherwood, Schmidt, Peclet)
12 Chapter 11: Distillation Operations
11.1 Vapor-Liquid Equilibrium and Relative Volatility in Distillation 11.2 McCabe-Thiele Method for Binary Distillation 11.3 Packed vs Tray Columns, Flooding, and Tray Hydraulics 11.4 Multicomponent Distillation Fundamentals and Key Components
13 Chapter 12: Rate-Controlled & Equilibrium Separations
12.1 Gas Absorption, Stripping, and the Kremser Equation 12.2 Liquid-Liquid Extraction and Ternary Phase Equilibria 12.3 Adsorption, Membrane Separations, and Drying Operations 12.4 Filtration, Crystallization, and Solid-Fluid Separations
14 Chapter 13: Chemical Kinetics & Ideal Isothermal Reactors
13.1 Reaction Rates, Rate Laws, and Order of Reaction 13.2 Temperature Dependence and the Arrhenius Equation 13.3 Batch Reactors and Continuous Stirred-Tank Reactors (CSTR) 13.4 Plug Flow Reactors (PFR) and Reactor Combinations
15 Chapter 14: Non-Ideal Flow, Non-Isothermal Reactors & Catalysis
14.1 Yield, Selectivity, and Multiple Reactions (Series and Parallel) 14.2 Non-Isothermal Reactor Design and Thermal Runaway 14.3 Heterogeneous Catalysis, Thiele Modulus, and RTD Models
16 Chapter 15: Physical & Transport Properties of Fluids
15.1 Fluid Density, Specific Gravity, and Viscosity Correlations 15.2 Thermal Conductivity and Specific Heat Capacities 15.3 Estimation Methods and Corresponding States Principles
17 Chapter 16: Materials of Construction & Corrosion
16.1 Mechanical Properties and Materials Selection in Chemical Plants 16.2 Corrosion Mechanisms, Materials Degradation, and Prevention
18 Chapter 17: Process Safety & Pressure Relief Systems
17.1 Hazard Identification Methodologies (HAZOP, FMEA, What-If) 17.2 Pressure Relief Valve (PRV) and Rupture Disk Sizing 17.3 Flammability, Explosions, and Toxic Dispersion Limits 17.4 Inerting, Purging, Discharge Location, and Containment
19 Chapter 18: Process Control & Engineering Economics
18.1 Process Dynamics and Feedback Control Loops 18.2 PID Controller Tuning and Loop Stability 18.3 Chemical Plant Capital Cost Estimation and Profitability Analysis 18.4 Field Instrumentation, Control Valves, Alarms, and Safety Instrumented Systems
20 Chapter 19: Process Design, Equipment Selection & Environmental Compliance
19.1 Process Flow Diagrams, P&IDs, Scale-Up, and Plant Siting 19.2 Process Equipment Selection, Sizing, and Optimization 19.3 Emissions Evaluation, Mitigation, and Remediation
21 Chapter 20: Plant Operation, Reliability & Continuous Improvement
20.1 Operating Procedures, Startup, and Shutdown 20.2 Mechanical Integrity, Reliability, and Failure Mechanisms 20.3 Debottlenecking, Optimization, and Troubleshooting
17.2 Pressure Relief Valve (PRV) and Rupture Disk Sizing
Key Takeaways Explain This Topic AI
ASME Boiler and Pressure Vessel Code Section VIII Div. 1 dictates maximum overpressure allowances above MAWP: 10% for a single non-fire relief valve, 16% for multiple non-fire valves, and 21% for external fire engulfment scenarios.
API 521 evaluates fire relief heat absorption via Q = 21,000 F A_w^0.82 (Btu/hr) or Q = 43,200 F A_w^0.82 (W), where wetted surface area A_w is strictly limited to an elevation cutoff of 25 ft (7.6 m) above the flame source.
Conventional PRVs tolerate backpressure only up to 10% of set pressure; balanced bellows PRVs isolate the bonnet to handle variable backpressure up to 30% to 50% of set pressure; pilot-operated valves handle backpressures exceeding 70% while maintaining tight shut-off near set pressure.
Standard API 526 orifice designations range from D (0.110 in²) to T (26.00 in²); critical gas flow is sized via A = W / (C K_d P_1 K_b K_c) * sqrt(T Z / M), while liquid flow uses A = Q / (38 K_d K_w K_c K_v) * sqrt(SG / ΔP).
When a rupture disk is installed upstream of a PRV without certified combination laboratory capacity testing, ASME and API mandate an automatic combination capacity derating factor of K_c = 0.90.
Last updated: September 2026
17.2 Pressure Relief Valve (PRV) and Rupture Disk Sizing
Pressure relief systems represent the definitive line of defense protecting pressurized chemical equipment against catastrophic mechanical failure. The NCEES PE Chemical Exam tests the application of ASME Boiler and Pressure Vessel Code (BPVC) Section VIII and American Petroleum Institute (API) Standards 520, 521, and 526 to size relief valves, calculate fire heat absorption, evaluate backpressure limitations, and select standard orifice areas.
1. ASME BPVC Section VIII Overpressure Allowances
The fundamental design reference for any unfired pressure vessel is its Maximum Allowable Working Pressure (MAWP) —the maximum gauge pressure permitted at the top of the vessel in its operating position at the designated design temperature. Overpressure allowances are defined as percentage increases above MAWP: Pressure Scale: ASME Section VIII Overpressure Allowances
- =========================================================================
- 121% MAWP +-----------------------------+ Max Relieving Pressure (Fire Case)
- | Allowed Accumulation: +21% |
- 116% MAWP +-----------------------------+ Max Relieving Pressure (Multiple Non-Fire PRVs)
- | Allowed Accumulation: +16% |
- 110% MAWP +-----------------------------+ Max Relieving Pressure (Single Non-Fire PRV)
- | Allowed Accumulation: +10% |
- 100% MAWP +=============================+ MAWP = Typical Single PRV Set Pressure
- | Normal Operating Margin |
- 90% MAWP +-----------------------------+ Typical Maximum Operating Pressure
- | |
- 0 psig +-----------------------------+ Atmospheric Pressure Reference
Relief Sizing Contingency / Scenario Maximum Allowable PRV Set Pressure Maximum Relieving Pressure (% of MAWP) Maximum Permitted Accumulation Overpressure
Single Valve (Non-Fire Process Case) 100 % 100\% 100% of MAWP 110 % 110\% 110% of MAWP 10 % 10\% 10% Overpressure (or 3 psi 3\text{ psi} 3 psi , whichever is greater)
Multiple Valves (Non-Fire Process Case) 1st valve ≤ 100 % \le 100\% ≤ 100% MAWP; Additional valves ≤ 105 % \le 105\% ≤ 105% MAWP 116 % 116\% 116% of MAWP 16 % 16\% 16% Overpressure (or 4 psi 4\text{ psi} 4 psi , whichever is greater)
External Fire Engulfment Case Supplemental valve ≤ 105 % \le 105\% ≤ 105% MAWP 121 % 121\% 121% of MAWP 21 % 21\% 21% Overpressure above MAWP
Thermal Liquid Expansion Only 100 % 100\% 100% of MAWP (or up to 105 % 105\% 105% if supplemental) 110 % 110\% 110% of MAWP (or 121 % 121\% 121% if fire-induced) 10 % 10\% 10% to 21 % 21\% 21% Overpressure
Note
Overpressure vs. Accumulation: Accumulation is the pressure rise above MAWP during discharge, expressed as a percentage of MAWP. Overpressure is the pressure rise above the valve set pressure. When a PRV is set exactly at the vessel's MAWP, accumulation and overpressure are numerically identical.
2. Relief Scenario Analysis & API 521 Fire Heat Absorption
Before sizing a relief device, chemical engineers perform an Overpressure Contingency Analysis to establish the credible relief scenarios, including:
Blocked Liquid/Vapor Discharge: Control valve or manual isolation valve closed while feed continues.
Utility Failure: Complete loss of cooling water to condensers, power outage to air-fin coolers, or loss of instrument air.
Heat Exchanger Tube Rupture: High-pressure fluid back-pressuring the low-pressure exchanger shell. The Two-Thirds Rule (or 10/13 Rule in modern ASME) states that tube rupture need not be considered a relief scenario if the low-pressure side design pressure is at least 10 / 13 10/13 10/13 ( 76.9 % 76.9\% 76.9% ) of the high-pressure side design pressure.
Thermal Liquid Expansion: Solar radiation or tracing heat expanding blocked liquid in piping or heat exchanger tubes.
External Pool Fire Engulfment: Heat transfer from surrounding burning liquid pools.
API 521 Wetted Surface Fire Heat Absorption Equation
When a liquid-containing vessel is engulfed in an external hydrocarbons pool fire, heat absorbed by the wetted interior generates boil-off vapor. API Standard 521 defines the total heat absorption ( Q Q Q ): U S C u s t o m a r y : Q = 21,000 F A w 0.82 ( Q in Btu/hr, A w in ft 2 ) \mathbf{US\;Customary:}\quad Q = 21{,}000\, F\, A_w^{0.82} \quad (Q\text{ in Btu/hr, } A_w\text{ in }\text{ft}^2) US Customary : Q = 21 , 000 F A w 0.82 ( Q in Btu/hr, A w in ft 2 ) S I M e t r i c : Q = 43,200 F A w 0.82 ( Q in Watts, A w in m 2 ) \mathbf{SI\;Metric:}\quad Q = 43{,}200\, F\, A_w^{0.82} \quad (Q\text{ in Watts, } A_w\text{ in }\text{m}^2) SI Metric : Q = 43 , 200 F A w 0.82 ( Q in Watts, A w in m 2 )
Where:
Q Q Q = total heat absorption rate into the wetted liquid inventory.
F F F = Environment Factor accounting for thermal insulation and installation type:
Bare vessel on grade: F = 1.0 F = 1.0 F = 1.0 .
Insulated vessel with fire-resistant jacketing: F = 0.075 to 0.30 F = 0.075 \text{ to } 0.30 F = 0.075 to 0.30 (calculated from insulation thermal conductivity k k k and thickness t t t per API 521 formula F = k ( 1660 − T relief ) 21,000 t F = \frac{k (1660 - T_{\text{relief}})}{21{,}000 t} F = 21 , 000 t k ( 1660 − T relief ) ).
Water spray deluge: API 521 does not permit credit ( F = 1.0 F=1.0 F = 1.0 ) unless the drainage system, water supply reliability, and spray pattern are proven under extreme fire conditions.
Earth-covered / mounded storage: F = 0.03 F = 0.03 F = 0.03 .
A w A_w A w = Wetted Surface Area exposed to fire.
Important
The 25-Foot Elevation Cutoff Rule: API 521 specifies that pool fire flames engulf equipment only up to an elevation of 25 ft 25\text{ ft} 25 ft ( 7.6 m 7.6\text{ m} 7.6 m ) above the source of flame (grade or intermediate solid decking). Any vessel surface located higher than 25 ft 25\text{ ft} 25 ft above grade is excluded from the wetted area calculation ( A w A_w A w ). For spherical vessels, the cutoff is the elevation of the horizontal equator or 30 ft 30\text{ ft} 30 ft ( 9.1 m 9.1\text{ m} 9.1 m ), whichever is greater.
The required mass relieving rate of vapor ( W W W ) is calculated by dividing the total heat absorption by the latent heat of vaporization ( Δ H vap \Delta H_{\text{vap}} Δ H vap ) evaluated at relieving conditions: W = Q Δ H vap W = \frac{Q}{\Delta H_{\text{vap}}} W = Δ H vap Q
- 3. Pressure Relief Device Mechanical Classifications Conventional PRV Balanced Bellows PRV Pilot-Operated PRV
- +--------------------+ +--------------------+ +---------------------+
- | Bonnet Open to | | Sealed Bellows | | Process Sensed to |
- | Downstream Flange | | Isolates Bonnet; | | Dome Chamber; |
- | (Backpressure adds | | Vented to Atm. | | Tight Seal up to |
- | directly to spring)| | (Handles Backpress)| | Set Point |
- +--------------------+ +--------------------+ +---------------------+
- 1. Conventional Spring-Loaded PRV
Mechanics: The process pressure exerts an upward force on the disk ( F = P × A seat F = P \times A_{\text{seat}} F = P × A seat ). A calibrated mechanical spring exerts a downward closing force. The bonnet is vented directly to the valve discharge nozzle.
Backpressure Behavior: Superimposed backpressure (pressure in the discharge manifold before the valve lifts) and built-up backpressure (pressure generated in the outlet piping by turbulent flow during relief) act directly on top of the disk.
Limitation: Maximum allowable total backpressure is ≤ 10 % \le 10\% ≤ 10% of set pressure (gauge) . If backpressure exceeds 10 % 10\% 10% , the effective opening pressure increases, seat chattering occurs, and discharge flow capacity drops precipitously.
2. Balanced Bellows PRV
Mechanics: A metallic bellows (typically Inconel or stainless steel) seals the disk guide and isolates the upper disk surface and bonnet cavity from discharge backpressure. The bonnet is vented to the atmosphere (or a safe non-hazardous vent).
Backpressure Behavior: Backpressure acts equally on opposing equal areas of the bellows and disk, neutralizing backpressure effects on set point.
Limitation: Handles variable superimposed and built-up backpressure from 30 % 30\% 30% up to 50 % 50\% 50% of set pressure . When backpressure exceeds critical flow velocity, capacity must be derated by the backpressure correction factor ( K b < 1.0 K_b < 1.0 K b < 1.0 ).
3. Pilot-Operated PRV
Mechanics: Process fluid is piped to a control pilot and into a dome chamber above a main piston/diaphragm. Because the dome area exceeds the seat nozzle area, higher process pressure drives the seat tighter as set point is approached. At set pressure, the pilot rapidly vents the dome, popping the main valve fully open.
Advantages: Completely insensitive to backpressure (up to > 70 % > 70\% > 70% ); tight shut-off up to 95 − 98 % 95-98\% 95 − 98% of set pressure.
Limitations: Not suitable for polymerizing, highly viscous, fouling, or cryogenic services that plug the small pilot sensing tubes.
4. Rupture Disks (Non-Reclosing)
Thin calibrated diaphragms (forward-acting tension loaded, or reverse-buckling compression loaded) designed to burst at a precise differential pressure.
Combination with PRVs: When corrosive, fouling, or toxic chemicals threaten PRV seat leakage, a rupture disk is installed upstream of the PRV. ASME Section VIII mandates that the intermediate cavity between the disk and PRV must have a "tell-tale" assembly (pressure gauge, excess flow valve, or pressure switch) to detect disk pinhole pin leaks, because backpressure accumulation in the cavity would raise the effective burst pressure of the disk!
Combination Capacity Derating: If an ASME-certified combination test flow factor has not been established, the engineer must apply a combination correction factor of K c = 0.90 K_c = 0.90 K c = 0.90 ( 10 % 10\% 10% capacity reduction).
- 4. Orifice Sizing Equations (API 520 Part I)
- Standard API 526 Orifice Letter Designations
API Standard 526 standardizes 14 flanged relief valve orifice sizes:
Letter Area ( in 2 \text{in}^2 in 2 ) Area ( cm 2 \text{cm}^2 cm 2 ) Letter Area ( in 2 \text{in}^2 in 2 ) Area ( cm 2 \text{cm}^2 cm 2 ) Letter Area ( in 2 \text{in}^2 in 2 ) Area ( cm 2 \text{cm}^2 cm 2 )
D 0.110 0.110 0.110 0.710 0.710 0.710 H 0.785 0.785 0.785 5.065 5.065 5.065 N 4.340 4.340 4.340 28.00 28.00 28.00
E 0.196 0.196 0.196 1.265 1.265 1.265 J 1.287 1.287 1.287 8.303 8.303 8.303 P 6.380 6.380 6.380 41.16 41.16 41.16
F 0.307 0.307 0.307 1.981 1.981 1.981 K 1.838 1.838 1.838 11.858 11.858 11.858 Q 11.050 11.050 11.050 71.29 71.29 71.29
G 0.503 0.503 0.503 3.245 3.245 3.245 L 2.853 2.853 2.853 18.406 18.406 18.406 R 16.000 16.000 16.000 103.23 103.23 103.23
- — — — M 3.600 3.600 3.600 23.226 23.226 23.226 T 26.000 26.000 26.000 167.74 167.74 167.74
- Gas and Vapor Sizing (Critical Sonic Flow)
Critical (choked) flow occurs across the PRV nozzle when the downstream backpressure is less than or equal to the critical flow pressure ( P c f P_{cf} P c f ): P c f P 1 = ( 2 k + 1 ) k k − 1 \frac{P_{cf}}{P_1} = \left( \frac{2}{k+1} \right)^{\frac{k}{k-1}} P 1 P c f = ( k + 1 2 ) k − 1 k
Where k = c p / c v k = c_p/c_v k = c p / c v is the ideal gas specific heat ratio. (For k = 1.4 k=1.4 k = 1.4 , P c f / P 1 = 0.528 P_{cf}/P_1 = 0.528 P c f / P 1 = 0.528 ; for k = 1.13 k=1.13 k = 1.13 , P c f / P 1 = 0.579 P_{cf}/P_1 = 0.579 P c f / P 1 = 0.579 ).
Under critical flow conditions, API 520 specifies the required effective discharge area ( A A A ): A = W C K d P 1 K b K c T Z M A = \frac{W}{C\, K_d\, P_1\, K_b\, K_c} \sqrt{\frac{T\, Z}{M}} A = C K d P 1 K b K c W M T Z
Where:
A A A = effective discharge area ( in 2 \text{in}^2 in 2 ).
W W W = required relieving mass flow rate ( lbm/hr \text{lbm/hr} lbm/hr ).
C C C = gas expansion coefficient, defined as: C = 520 k ( 2 k + 1 ) k + 1 k − 1 C = 520 \sqrt{k \left( \frac{2}{k+1} \right)^{\frac{k+1}{k-1}}} C = 520 k ( k + 1 2 ) k − 1 k + 1 (Representative values: for k = 1.40 k=1.40 k = 1.40 , C = 356.1 C = 356.1 C = 356.1 ; for k = 1.30 k=1.30 k = 1.30 , C = 346.0 C = 346.0 C = 346.0 ; for k = 1.13 k=1.13 k = 1.13 , C = 329.0 C = 329.0 C = 329.0 ).
K d K_d K d = effective discharge coefficient ( K d = 0.975 K_d = 0.975 K d = 0.975 for gas/vapor PRVs with or without rupture disks per API 520).
P 1 P_1 P 1 = absolute upstream relieving pressure ( psia \text{psia} psia ) = Set Pressure + Overpressure + 14.7 psi 14.7\text{ psi} 14.7 psi .
K b K_b K b = backpressure capacity correction factor ( K b = 1.0 K_b = 1.0 K b = 1.0 for conventional PRVs under critical flow; for balanced bellows, K b K_b K b is read from manufacturer curves when backpressure exceeds 30 % 30\% 30% ).
K c K_c K c = combination correction factor ( K c = 1.0 K_c = 1.0 K c = 1.0 standalone; K c = 0.90 K_c = 0.90 K c = 0.90 with upstream rupture disk).
T T T = relieving temperature ( ∘ R = ∘ F + 459.67 ^\circ\text{R} = ^\circ\text{F} + 459.67 ∘ R = ∘ F + 459.67 ).
Z Z Z = gas compressibility factor at relieving conditions.
M M M = gas molecular weight ( lbm/lbmol \text{lbm/lbmol} lbm/lbmol ).
Liquid Sizing (API 520)
For non-viscous liquids, the orifice area is governed by Bernoulli's orifice relation: A = Q 38 K d K w K c K v S G Δ P A = \frac{Q}{38\, K_d\, K_w\, K_c\, K_v} \sqrt{\frac{SG}{\Delta P}} A = 38 K d K w K c K v Q Δ P SG
Where:
Q Q Q = liquid flow rate ( gpm \text{gpm} gpm ).
Δ P = P 1 − P b \Delta P = P_1 - P_b Δ P = P 1 − P b = differential pressure across the valve ( psi \text{psi} psi ), where P 1 P_1 P 1 is gauge relieving pressure and P b P_b P b is gauge total backpressure.
K d K_d K d = certified liquid discharge coefficient (standard default K d = 0.65 K_d = 0.65 K d = 0.65 per API 520).
K w K_w K w = backpressure correction factor for balanced bellows in liquid service ( K w = 1.0 K_w = 1.0 K w = 1.0 for conventional valves).
K v K_v K v = viscosity correction factor (evaluated via Reynolds number Re = Q ( 2800 ⋅ S G ) μ A \text{Re} = \frac{Q (2800 \cdot SG)}{\mu \sqrt{A}} Re = μ A Q ( 2800 ⋅ SG ) ; K v = 1.0 K_v = 1.0 K v = 1.0 for water and light hydrocarbons where μ < 20 cP \mu < 20\text{ cP} μ < 20 cP ).
S G SG SG = liquid specific gravity at relieving temperature relative to water at 60 ∘ F 60^\circ\text{F} 6 0 ∘ F .
Two-Phase Flashing Relief: DIERS Methodology
When runaway reactions, boiling liquid foaming, or flashing liquids relieve through a PRV, two-phase vapor-liquid flow occurs. The Design Institute for Emergency Relief Systems (DIERS) developed the Homogeneous Equilibrium Model (HEM) and coupling models. Because entrained dense liquid drastically slows sonic velocity across the nozzle, two-phase mass flux ( G G G ) is typically 2 2 2 to 10 10 10 times lower than single-phase vapor flux, requiring substantially larger relief areas (often 2 2 2 to 3 3 3 standard orifice sizes larger).
- 5. Comprehensive Worked Numerical Example
- Problem Statement
A horizontal cylindrical bullet tank contains saturated liquid propane ( M = 44.10 lbm/lbmol M = 44.10\text{ lbm/lbmol} M = 44.10 lbm/lbmol , k = 1.13 k = 1.13 k = 1.13 ). Solve the complete relief system sizing evaluation:
Vessel Geometry & Wetted Area: The tank has an inside diameter of D = 8.0 ft D = 8.0\text{ ft} D = 8.0 ft and tangent-to-tangent length of L = 30.0 ft L = 30.0\text{ ft} L = 30.0 ft , with two 2:1 semi-elliptical heads. The bottom of the vessel is elevated 3.0 ft 3.0\text{ ft} 3.0 ft above grade. Operating procedures specify maximum fill at 80 % 80\% 80% volume, yielding a calculated wetted surface area of A w = 720.0 ft 2 A_w = 720.0\text{ ft}^2 A w = 720.0 ft 2 . Verify whether the 25 ft 25\text{ ft} 25 ft elevation cutoff applies.
Fire Case Heat Absorption: The vessel is uninsulated bare steel ( F = 1.0 F = 1.0 F = 1.0 ) on grade with no certified water deluge. Calculate the total fire heat input Q Q Q in Btu/hr \text{Btu/hr} Btu/hr per API 521.
Relieving Rate & Orifice Sizing: The vessel MAWP is 250.0 psig 250.0\text{ psig} 250.0 psig , and the PRV is set at 250.0 psig 250.0\text{ psig} 250.0 psig . At the permitted fire overpressure, saturated propane relieves at T = 136.5 ∘ F T = 136.5^\circ\text{F} T = 136. 5 ∘ F ( 596.17 ∘ R 596.17^\circ\text{R} 596.1 7 ∘ R ) with latent heat Δ H vap = 125.0 Btu/lbm \Delta H_{\text{vap}} = 125.0\text{ Btu/lbm} Δ H vap = 125.0 Btu/lbm and compressibility Z = 0.82 Z = 0.82 Z = 0.82 . The PRV discharges to atmosphere ( P b = 0 psig = 14.7 psia P_b = 0\text{ psig} = 14.7\text{ psia} P b = 0 psig = 14.7 psia ). Determine the relieving pressure P 1 P_1 P 1 , mass relieving rate W W W , gas expansion factor C C C , required effective orifice area A A A in in 2 \text{in}^2 in 2 , and select the appropriate API 526 orifice letter designation.
Step 1: Vessel Elevation Cutoff Check
Vessel bottom elevation = 3.0 ft 3.0\text{ ft} 3.0 ft above grade.
Vessel top elevation = 3.0 ft + D = 3.0 + 8.0 = 11.0 ft 3.0\text{ ft} + D = 3.0 + 8.0 = 11.0\text{ ft} 3.0 ft + D = 3.0 + 8.0 = 11.0 ft above grade.
Since the entire vessel resides well below the 25.0 ft 25.0\text{ ft} 25.0 ft elevation threshold ( 11.0 ft < 25.0 ft 11.0\text{ ft} < 25.0\text{ ft} 11.0 ft < 25.0 ft ), all wetted surface area is subject to pool fire engulfment .
Wetted area for sizing: A w = 720.0 ft 2 A_w = 720.0\text{ ft}^2 A w = 720.0 ft 2 .
Step 2: Total Fire Heat Input (API 521)
Calculate Q Q Q using the US Customary API 521 formulation with F = 1.0 F = 1.0 F = 1.0 : Q = 21,000 F A w 0.82 = 21,000 × 1.0 × ( 720.0 ) 0.82 Q = 21{,}000\, F\, A_w^{0.82} = 21{,}000 \times 1.0 \times (720.0)^{0.82} Q = 21 , 000 F A w 0.82 = 21 , 000 × 1.0 × ( 720.0 ) 0.82
Evaluate the exponential term: ln ( 720.0 ) = 6.57925 \ln(720.0) = 6.57925 ln ( 720.0 ) = 6.57925 0.82 × 6.57925 = 5.394986 0.82 \times 6.57925 = 5.394986 0.82 × 6.57925 = 5.394986 ( 720.0 ) 0.82 = exp ( 5.394986 ) = 220.297 ft 1.64 (720.0)^{0.82} = \exp(5.394986) = 220.297\text{ ft}^{1.64} ( 720.0 ) 0.82 = exp ( 5.394986 ) = 220.297 ft 1.64 Q = 21,000 × 220.297 = 4,626,237 Btu/hr ≈ 4.626 × 10 6 Btu/hr Q = 21{,}000 \times 220.297 = \mathbf{4{,}626{,}237\text{ Btu/hr}} \approx 4.626 \times 10^6\text{ Btu/hr} Q = 21 , 000 × 220.297 = 4 , 626 , 237 Btu/hr ≈ 4.626 × 1 0 6 Btu/hr
Step 3: Required Relieving Rate and Orifice Sizing
Compute mass relieving rate from latent heat: W = Q Δ H vap = 4,626,237 Btu/hr 125.0 Btu/lbm = 37,010 lbm/hr W = \frac{Q}{\Delta H_{\text{vap}}} = \frac{4{,}626{,}237\text{ Btu/hr}}{125.0\text{ Btu/lbm}} = \mathbf{37{,}010\text{ lbm/hr}} W = Δ H vap Q = 125.0 Btu/lbm 4 , 626 , 237 Btu/hr = 37 , 010 lbm/hr
Determine upstream relieving pressure ( P 1 P_1 P 1 ) for external fire:
ASME Section VIII allows 21 % 21\% 21% overpressure above MAWP for fire contingencies: P rel,gauge = 1.21 × MAWP = 1.21 × 250.0 psig = 302.5 psig P_{\text{rel,gauge}} = 1.21 \times \text{MAWP} = 1.21 \times 250.0\text{ psig} = 302.5\text{ psig} P rel,gauge = 1.21 × MAWP = 1.21 × 250.0 psig = 302.5 psig
Convert to absolute pressure: P 1 = P rel,gauge + P atm = 302.5 + 14.7 = 317.2 psia P_1 = P_{\text{rel,gauge}} + P_{\text{atm}} = 302.5 + 14.7 = \mathbf{317.2\text{ psia}} P 1 = P rel,gauge + P atm = 302.5 + 14.7 = 317.2 psia
Verify critical choked flow across nozzle: P c f P 1 = ( 2 k + 1 ) k k − 1 = ( 2 2.13 ) 1.13 0.13 = ( 0.938967 ) 8.6923 = 0.579 \frac{P_{cf}}{P_1} = \left( \frac{2}{k+1} \right)^{\frac{k}{k-1}} = \left( \frac{2}{2.13} \right)^{\frac{1.13}{0.13}} = (0.938967)^{8.6923} = 0.579 P 1 P c f = ( k + 1 2 ) k − 1 k = ( 2.13 2 ) 0.13 1.13 = ( 0.938967 ) 8.6923 = 0.579 P c f = 0.579 × 317.2 psia = 183.7 psia P_{cf} = 0.579 \times 317.2\text{ psia} = 183.7\text{ psia} P c f = 0.579 × 317.2 psia = 183.7 psia Actual backpressure P b = 14.7 psia ≪ 183.7 psia ⟹ C r i t i c a l F l o w A p p l i e s ( K b = 1.0 ) \text{Actual backpressure } P_b = 14.7\text{ psia} \ll 183.7\text{ psia} \implies \mathbf{Critical\;Flow\;Applies} \;(K_b = 1.0) Actual backpressure P b = 14.7 psia ≪ 183.7 psia ⟹ Critical Flow Applies ( K b = 1.0 )
Calculate gas expansion factor C C C for k = 1.13 k = 1.13 k = 1.13 : C = 520 k ( 2 k + 1 ) k + 1 k − 1 = 520 1.13 × ( 0.938967 ) 2.13 0.13 = 520 1.13 × 0.35416 = 520 0.4002 = 329.0 C = 520 \sqrt{k \left( \frac{2}{k+1} \right)^{\frac{k+1}{k-1}}} = 520 \sqrt{1.13 \times (0.938967)^{\frac{2.13}{0.13}}} = 520 \sqrt{1.13 \times 0.35416} = 520 \sqrt{0.4002} = \mathbf{329.0} C = 520 k ( k + 1 2 ) k − 1 k + 1 = 520 1.13 × ( 0.938967 ) 0.13 2.13 = 520 1.13 × 0.35416 = 520 0.4002 = 329.0
Calculate required orifice area ( K d = 0.975 , K b = 1.0 , K c = 1.0 K_d = 0.975, K_b = 1.0, K_c = 1.0 K d = 0.975 , K b = 1.0 , K c = 1.0 ): T Z M = ( 596.17 ) × ( 0.82 ) 44.10 = 488.86 44.10 = 11.0853 = 3.32946 \sqrt{\frac{T Z}{M}} = \sqrt{\frac{(596.17) \times (0.82)}{44.10}} = \sqrt{\frac{488.86}{44.10}} = \sqrt{11.0853} = 3.32946 M TZ = 44.10 ( 596.17 ) × ( 0.82 ) = 44.10 488.86 = 11.0853 = 3.32946 A = W C K d P 1 K b K c T Z M = 37,010 ( 329.0 ) × ( 0.975 ) × ( 317.2 ) × 1.0 × 1.0 × 3.32946 A = \frac{W}{C K_d P_1 K_b K_c} \sqrt{\frac{T Z}{M}} = \frac{37{,}010}{(329.0) \times (0.975) \times (317.2) \times 1.0 \times 1.0} \times 3.32946 A = C K d P 1 K b K c W M TZ = ( 329.0 ) × ( 0.975 ) × ( 317.2 ) × 1.0 × 1.0 37 , 010 × 3.32946 Denominator = 329.0 × 0.975 × 317.2 = 101,752.5 \text{Denominator} = 329.0 \times 0.975 \times 317.2 = 101{,}752.5 Denominator = 329.0 × 0.975 × 317.2 = 101 , 752.5 A = 37,010 × 3.32946 101,752.5 = 123,223.3 101,752.5 = 1.211 in 2 A = \frac{37{,}010 \times 3.32946}{101{,}752.5} = \frac{123{,}223.3}{101{,}752.5} = \mathbf{1.211\text{ in}^2} A = 101 , 752.5 37 , 010 × 3.32946 = 101 , 752.5 123 , 223.3 = 1.211 in 2
Select standard API 526 orifice:
Orifice H ( A = 0.785 in 2 A = 0.785\text{ in}^2 A = 0.785 in 2 ) is undersized ( 0.785 < 1.211 0.785 < 1.211 0.785 < 1.211 ).
Orifice J ( A = 1.287 in 2 A = 1.287\text{ in}^2 A = 1.287 in 2 ) is the next standard size and provides sufficient relieving capacity ( 1.287 > 1.211 1.287 > 1.211 1.287 > 1.211 ).
6. Critical PE Exam Traps & Pitfalls
- Warning
- Trap 1: Applying Fire Overpressure (21%) to Non-Fire Scenarios
ASME Section VIII permits 21 % 21\% 21% overpressure only for fire contingencies. Using 21 % 21\% 21% overpressure for a blocked discharge or utility failure case is a major error; standard non-fire process contingencies strictly limit overpressure to 10 % 10\% 10% for a single valve or 16 % 16\% 16% for multiple valves.
- Warning
- Trap 2: Gauge vs. Absolute Pressure in Gas Sizing
The upstream relieving pressure P 1 P_1 P 1 in the API 520 gas sizing formula MUST be in absolute pressure ( psia \text{psia} psia ). Forgetting to add atmospheric pressure ( 14.7 psi 14.7\text{ psi} 14.7 psi ) to the gauge relieving pressure is one of the most frequent mathematical errors on the exam.
- Warning
- Trap 3: Conventional PRVs with Excessive Backpressure
Specifying a conventional spring-loaded PRV when backpressure exceeds 10 % 10\% 10% of set pressure will lose points. When total backpressure fluctuates between 10 % 10\% 10% and 50 % 50\% 50% , a balanced bellows PRV is required. If backpressure exceeds 50 % 50\% 50% , a pilot-operated PRV must be selected.
- Warning
- Trap 4: Omitting Rupture Disk Combination Factor ( K c = 0.90 K_c = 0.90 K c = 0.90 )
When a rupture disk is piped upstream of a PRV without certified ASME flow testing data, the relief area calculation must include K c = 0.90 K_c = 0.90 K c = 0.90 in the denominator, effectively requiring an 11.1 % 11.1\% 11.1% larger flow area.