4.3 Capacity Analysis: Machine Requirements, Scrap Allowances & Personnel Requirements
PE Industrial and Systems Exam
Track your progress as you read
Finished sections get a check mark.
1 Exam Overview, Strategy & Systems Foundations
1.1 PE Industrial Exam Format, Official Specification & Reference Handbook Strategy 1.2 System Analysis Tools, Process Definition, Requirements Engineering & QFD 1.3 Performance Measures: Output, Productivity, OEE, Cost & Environmental Sustainability 1.4 Process Types (Discrete, Continuous, Manufacturing, Service) & Value Analysis/Engineering
2 Optimization, Queueing, Simulation, Networks & Markov Chains
2.1 Linear Programming Formulation, Graphical Solutions & Sensitivity Analysis 2.2 Queueing Theory Models (M/M/1, M/M/s) & Little's Law Applications 2.3 Discrete-Event Simulation, Random Variates & Model Validation 2.4 Graph Theory & Network Models: Shortest Path, Minimal Spanning Tree & Maximum Flow 2.5 Markov Chains: Transition Matrices, Steady-State Probabilities & Absorbing States 2.6 Decision Trees, Expected Value & Bottleneck Analysis (Theory of Constraints)
3 Project Management & Planning
3.1 Project Scheduling with CPM and PERT: Critical Path, Float, Probability & Crashing 3.2 Project Planning & Control: Scope and WBS, Gantt Charts, Critical Chain (CCPM), Risk & Earned Value
4 Facility Layout, Space, Capacity & Material Handling
4.1 Systematic Layout Planning (SLP) & Activity Relationship (REL) Analysis 4.2 Workstation Design, Aisle Sizing & Space Requirements Planning 4.3 Capacity Analysis: Machine Requirements, Scrap Allowances & Personnel Requirements 4.4 Material Handling Equipment Selection, Unit Loads & Handling Principles
5 Site Location, Warehousing & Facility Economics
5.1 Facility Location Models: Center of Gravity & Minisum / Minimax Distance 5.2 Warehousing Systems, Storage Assignment & Order Picking Operations 5.3 Facility Life-Cycle Economics, Replacement Analysis & Rearrangement Costs
6 Demand Forecasting, Production Planning, MRP & JIT
6.1 Demand Forecasting Methods: Moving Averages, Exponential Smoothing & Error Metrics 6.2 Aggregate Planning Strategies & Master Production Scheduling (MPS) 6.3 Material Requirements Planning (MRP), Bill of Materials & Capacity Planning 6.4 Just-in-Time & Lean Production Planning: Pull Systems, Kanban Sizing, Heijunka & SMED
7 Inventory Systems, Scheduling, Logistics & Transportation Modes
7.1 Deterministic Inventory Control: Classical EOQ, EPQ & Quantity Discounts 7.2 Stochastic Inventory Management: Safety Stock, Continuous / Periodic Review & Newsvendor 7.3 Production Sequencing, Dispatching Rules & Johnson's Algorithm 7.4 Supply Chain Logistics, Transportation Simplex & Distribution Network Design 7.5 Transportation Modes, Freight Economics & the Transshipment Model
8 Engineering Economics, Break-Even Analysis & Costing Systems
8.1 Equivalence, Cash Flow Analysis & Discounted Cash Flow Metrics (PW, FW, EAC) 8.2 Rate of Return Analysis (IRR, Incremental IRR) & Benefit-Cost (B/C) Ratios 8.3 Asset Depreciation (MACRS, Straight-Line), Tax Effects & Replacement Decisions 8.4 Break-Even Analysis, Technical Capability Assessment & Costing Systems (Traditional, ABC & Standard Costs)
9 Methods Engineering, Work Measurement, Learning Curves, Line Balancing & Process Planning
9.1 Methods Analysis, Process Charting & Motion Study (Therbligs, 5S) 9.2 Worker–Machine (Man–Machine) Charts, Multiple Activity Analysis & Synchronous Servicing 9.3 Time Study Fundamentals, Performance Rating & Allowance Factors 9.4 Predetermined Motion Time Systems (PMTS, MTM, MOST) & Work Sampling 9.5 Learning Curves: Unit and Cumulative-Average Models, Learning Rates & Applications 9.6 Assembly Line Balancing, Precedence Constraints & Efficiency Heuristics 9.7 Manufacturing & Service Process Planning: Operation Selection, Sequencing, Route Sheets, Fixturing & Mistake Proofing
10 Ergonomics, Human Capacity, Occupational Safety & DART Rates
10.1 Anthropometry, Percentile Design, Workstation Ergonomics & Link Analysis 10.2 Industrial Biomechanics, the NIOSH Lifting Equation & Lifting Aids 10.3 Limits of Human Capacity & Risk-Factor Tools: Work Physiology, Strength, Range of Motion, Vision, RULA & Slip Resistance 10.4 Environmental Ergonomics (Noise, Heat, Illumination), Human-Machine Systems & OSHA Safety 10.5 Safety Codes, Standards & Voluntary Guidelines (OSHA, ANSI, NIOSH, MIL-STD) and DART Rate Calculations
11 Statistical Process Control & Process Capability
11.1 Statistical Process Control for Variables (X-bar/R and X-bar/s Charts) 11.2 Statistical Process Control for Attributes (p, np, c, and u Charts) 11.3 Process Capability Indices (Cp, Cpk, Cpm, Pp, Ppk) & Sigma Levels
12 Design of Experiments, Acceptance Sampling & Quality Systems
12.1 Design of Experiments: 2^k Factorials, ANOVA & Taguchi Robust Design 12.2 Acceptance Sampling: OC Curves, AQL, LTPD, AOQL, Z1.4/MIL-STD-105E & Dodge-Romig 12.3 Quality Systems (Deming, TQM, ISO 9000, Benchmarking), Root Cause Analysis & DMAIC
13 Reliability Engineering & Maintenance Systems
13.1 Reliability Modeling, Failure Rates (lambda) & Life Distributions (Exponential, Weibull) 13.2 System Reliability Architecture: Series, Parallel, k-out-of-n & Redundancy 13.3 Equipment Maintenance Engineering, Availability (A), MTBF/MTTR & RCM
4.3 Capacity Analysis: Machine Requirements, Scrap Allowances & Personnel Requirements
Key Takeaways Explain This Topic AI
Required input to an operation is its required good output divided by (1 − scrap fraction), applied backward from the last operation to the first.
The number of machines needed is F = S × Q ÷ (E × H × R), where S is standard hours per unit, Q is units processed per period, E is efficiency, H is available hours per machine, and R is reliability or availability.
Fractional machine results are rounded up unless overtime, subcontracting, or a shared machine can cover the fraction; the rounding decision is part of the capacity plan.
Operators required equal total standard labor hours divided by (available hours per worker × efficiency), then increased for absenteeism.
Setup time consumes capacity: machine hours per period = setups × setup time + units × run time, so smaller lots raise machine requirements unless setups are reduced.
Last updated: October 2026
4.3 Capacity Analysis: Machine and Personnel Requirements
Facilities planning starts with a capacity question: how many machines and people does the production plan require? The answer sets the floor space in the space-requirement models, the number of material handling moves, and the budget. The NCEES specification lists "calculation of personnel requirements" and "calculation of machine requirements" under capacity analysis.
1. Step One: Work Backward Through Scrap
Every operation loses some units to scrap. To deliver O k O_k O k good units from operation k k k with scrap fraction d k d_k d k , the operation must start with:
I k = O k 1 − d k I_k = \frac{O_k}{1 - d_k} I k = 1 − d k O k
The input to operation k k k is the required output of operation k − 1 k - 1 k − 1 , so the calculation runs backward from the final operation .
Example: A plant must ship 1,000 good shafts per day. The routing has three operations:
- Operation Scrap rate Required good output Required input
- 30 Grind 5% 1,000 1,000 ÷ 0.95 = 1,052.6
- 20 Mill 2% 1,052.6 1,052.6 ÷ 0.98 = 1,074.1
- 10 Turn 4% 1,074.1 1,074.1 ÷ 0.96 = 1,118.9
The plant must start about 1,119 blanks per day . The overall yield is 0.96 × 0.98 × 0.95 = 0.894 0.96 \times 0.98 \times 0.95 = 0.894 0.96 × 0.98 × 0.95 = 0.894 , and 1,000 / 0.894 = 1,119 1{,}000 / 0.894 = 1{,}119 1 , 000/0.894 = 1 , 119 gives the same answer. Note that you divide by ( 1 − d ) (1 - d) ( 1 − d ) ; multiplying 1,000 by 1.05 understates the need, because 5% of the larger input is also lost.
2. Step Two: Machine Requirements
A common facilities-planning form of the machine requirement is:
F = S ⋅ Q E ⋅ H ⋅ R F = \frac{S \cdot Q}{E \cdot H \cdot R} F = E ⋅ H ⋅ R S ⋅ Q
- Symbol Meaning
- F F F Number of machines required (before rounding)
- S S S Standard time per unit (hours)
- Q Q Q Units the operation must process per period (its input, from Step 1)
- E E E Efficiency: actual performance relative to standard
- H H H Hours available per machine per period (shifts × hours per shift)
- R R R Reliability: the fraction of available time the machine is not down for failures
Example (Operation 20, milling): S = 0.12 S = 0.12 S = 0.12 hr per unit, Q = 1,074.1 Q = 1{,}074.1 Q = 1 , 074.1 units per day, E = 0.90 E = 0.90 E = 0.90 , two 8-hour shifts so H = 16 H = 16 H = 16 hr, and R = 0.95 R = 0.95 R = 0.95 :
F = 0.12 × 1,074.1 0.90 × 16 × 0.95 = 128.9 13.68 = 9.42 machines F = \frac{0.12 \times 1{,}074.1}{0.90 \times 16 \times 0.95} = \frac{128.9}{13.68} = 9.42 \text{ machines} F = 0.90 × 16 × 0.95 0.12 × 1 , 074.1 = 13.68 128.9 = 9.42 machines
Rounding. Ten machines cover the load with about 6% spare capacity. Nine machines would need roughly 6% overtime or a third shift on some machines. On an exam, round up unless the problem allows overtime or subcontracting. In design work, compare the cost of a tenth machine against overtime premiums.
Including Setup Time
When an operation runs several products or lots, setups consume machine time:
Machine hours required = ∑ j ( n j ⋅ t setup , j + Q j ⋅ t run , j ) \text{Machine hours required} = \sum_j \left( n_j \cdot t_{\text{setup},j} + Q_j \cdot t_{\text{run},j} \right) Machine hours required = ∑ j ( n j ⋅ t setup , j + Q j ⋅ t run , j )
where n j n_j n j is the number of setups for product j j j in the period. Divide by E ⋅ H ⋅ R E \cdot H \cdot R E ⋅ H ⋅ R to get machines. Cutting lot sizes in half doubles the number of setups. Without setup reduction, smaller lots increase the machines required, which is the capacity side of the JIT tradeoff.
Example: A press runs two parts per week. Part X needs 4 setups of 1.5 hr and 6,000 pieces at 0.01 hr each. Part Y needs 6 setups of 2 hr and 3,000 pieces at 0.02 hr each. Machine hours = 4 ( 1.5 ) + 60 + 6 ( 2 ) + 60 = 138 = 4(1.5) + 60 + 6(2) + 60 = 138 = 4 ( 1.5 ) + 60 + 6 ( 2 ) + 60 = 138 hours. With H = 80 H = 80 H = 80 hr per week, E = 0.95 E = 0.95 E = 0.95 , and R = 0.92 R = 0.92 R = 0.92 , F = 138 / 69.9 = 1.97 F = 138 / 69.9 = 1.97 F = 138/69.9 = 1.97 , so two presses are needed.
- 3. Step Three: Personnel Requirements
- Direct Labor for Manual Operations
Operators = ∑ ( units × standard hours per unit ) productive hours per worker × efficiency × 1 1 − absenteeism \text{Operators} = \frac{\sum (\text{units} \times \text{standard hours per unit})}{\text{productive hours per worker} \times \text{efficiency}} \times \frac{1}{1 - \text{absenteeism}} Operators = productive hours per worker × efficiency ∑ ( units × standard hours per unit ) × 1 − absenteeism 1
Example: A manual assembly area must build 1,200 units per day at a standard of 0.40 hr per unit (allowances already included). Each worker has 7.5 productive hours per shift and works at 95% efficiency, and absenteeism averages 5%.
1,200 × 0.40 7.5 × 0.95 = 480 7.125 = 67.4 workers present , 67.4 0.95 = 70.9 ⇒ 71 on the roster \frac{1{,}200 \times 0.40}{7.5 \times 0.95} = \frac{480}{7.125} = 67.4 \text{ workers present}, \qquad \frac{67.4}{0.95} = 70.9 \Rightarrow 71 \text{ on the roster} 7.5 × 0.95 1 , 200 × 0.40 = 7.125 480 = 67.4 workers present , 0.95 67.4 = 70.9 ⇒ 71 on the roster
Machine Operators
For automated equipment, staffing depends on how many machines one person can tend. That comes from worker–machine (man–machine) analysis, covered in the methods engineering chapter. If each operator can tend three machines, ten mills need four operators per shift (10 ÷ 3 rounded up), not ten.
Indirect and Support Staff
Material handlers, setup technicians, inspectors, and maintenance staff are sized from their own workloads: moves per shift times minutes per move, setups per week times setup hours, and so on. Support staffing is often checked against ratios from comparable plants.
4. Capacity Concepts That Tie It Together
Design capacity is the maximum output under ideal conditions. Effective capacity allows for setups, maintenance, and product mix. Actual output is what is achieved.
A capacity cushion (planned spare capacity) protects against demand variability and breakdowns. Queueing theory shows that waiting time rises sharply as utilization nears 100%, so do not plan machines at 100% load.
The machine count for each operation reveals the bottleneck : the operation with the highest load relative to its capacity sets plant throughput.
- Mistake Correct approach
- Using shipped quantity at every operation Use the input each operation must process, after downstream scrap
- Multiplying by ( 1 + d ) (1 + d) ( 1 + d ) for scrap Divide by ( 1 − d ) (1 - d) ( 1 − d )
- Ignoring setup hours Add setups × setup time to run time
- Rounding 9.42 machines down to 9 Round up unless overtime or outsourcing is allowed
Forgetting absenteeism Divide workers present by ( 1 − absenteeism rate ) (1 - \text{absenteeism rate}) ( 1 − absenteeism rate )