6.4 Just-in-Time & Lean Production Planning: Pull Systems, Kanban Sizing, Heijunka & SMED

PE Industrial and Systems Exam

Track your progress as you read

Finished sections get a check mark.

1 Exam Overview, Strategy & Systems Foundations

1.1 PE Industrial Exam Format, Official Specification & Reference Handbook Strategy 1.2 System Analysis Tools, Process Definition, Requirements Engineering & QFD 1.3 Performance Measures: Output, Productivity, OEE, Cost & Environmental Sustainability 1.4 Process Types (Discrete, Continuous, Manufacturing, Service) & Value Analysis/Engineering

2 Optimization, Queueing, Simulation, Networks & Markov Chains

2.1 Linear Programming Formulation, Graphical Solutions & Sensitivity Analysis 2.2 Queueing Theory Models (M/M/1, M/M/s) & Little's Law Applications 2.3 Discrete-Event Simulation, Random Variates & Model Validation 2.4 Graph Theory & Network Models: Shortest Path, Minimal Spanning Tree & Maximum Flow 2.5 Markov Chains: Transition Matrices, Steady-State Probabilities & Absorbing States 2.6 Decision Trees, Expected Value & Bottleneck Analysis (Theory of Constraints)

3 Project Management & Planning

3.1 Project Scheduling with CPM and PERT: Critical Path, Float, Probability & Crashing 3.2 Project Planning & Control: Scope and WBS, Gantt Charts, Critical Chain (CCPM), Risk & Earned Value

4 Facility Layout, Space, Capacity & Material Handling

4.1 Systematic Layout Planning (SLP) & Activity Relationship (REL) Analysis 4.2 Workstation Design, Aisle Sizing & Space Requirements Planning 4.3 Capacity Analysis: Machine Requirements, Scrap Allowances & Personnel Requirements 4.4 Material Handling Equipment Selection, Unit Loads & Handling Principles

5 Site Location, Warehousing & Facility Economics

5.1 Facility Location Models: Center of Gravity & Minisum / Minimax Distance 5.2 Warehousing Systems, Storage Assignment & Order Picking Operations 5.3 Facility Life-Cycle Economics, Replacement Analysis & Rearrangement Costs

6 Demand Forecasting, Production Planning, MRP & JIT

6.1 Demand Forecasting Methods: Moving Averages, Exponential Smoothing & Error Metrics 6.2 Aggregate Planning Strategies & Master Production Scheduling (MPS) 6.3 Material Requirements Planning (MRP), Bill of Materials & Capacity Planning 6.4 Just-in-Time & Lean Production Planning: Pull Systems, Kanban Sizing, Heijunka & SMED

7 Inventory Systems, Scheduling, Logistics & Transportation Modes

7.1 Deterministic Inventory Control: Classical EOQ, EPQ & Quantity Discounts 7.2 Stochastic Inventory Management: Safety Stock, Continuous / Periodic Review & Newsvendor 7.3 Production Sequencing, Dispatching Rules & Johnson's Algorithm 7.4 Supply Chain Logistics, Transportation Simplex & Distribution Network Design 7.5 Transportation Modes, Freight Economics & the Transshipment Model

8 Engineering Economics, Break-Even Analysis & Costing Systems

8.1 Equivalence, Cash Flow Analysis & Discounted Cash Flow Metrics (PW, FW, EAC) 8.2 Rate of Return Analysis (IRR, Incremental IRR) & Benefit-Cost (B/C) Ratios 8.3 Asset Depreciation (MACRS, Straight-Line), Tax Effects & Replacement Decisions 8.4 Break-Even Analysis, Technical Capability Assessment & Costing Systems (Traditional, ABC & Standard Costs)

9 Methods Engineering, Work Measurement, Learning Curves, Line Balancing & Process Planning

9.1 Methods Analysis, Process Charting & Motion Study (Therbligs, 5S) 9.2 Worker–Machine (Man–Machine) Charts, Multiple Activity Analysis & Synchronous Servicing 9.3 Time Study Fundamentals, Performance Rating & Allowance Factors 9.4 Predetermined Motion Time Systems (PMTS, MTM, MOST) & Work Sampling 9.5 Learning Curves: Unit and Cumulative-Average Models, Learning Rates & Applications 9.6 Assembly Line Balancing, Precedence Constraints & Efficiency Heuristics 9.7 Manufacturing & Service Process Planning: Operation Selection, Sequencing, Route Sheets, Fixturing & Mistake Proofing

10 Ergonomics, Human Capacity, Occupational Safety & DART Rates

10.1 Anthropometry, Percentile Design, Workstation Ergonomics & Link Analysis 10.2 Industrial Biomechanics, the NIOSH Lifting Equation & Lifting Aids 10.3 Limits of Human Capacity & Risk-Factor Tools: Work Physiology, Strength, Range of Motion, Vision, RULA & Slip Resistance 10.4 Environmental Ergonomics (Noise, Heat, Illumination), Human-Machine Systems & OSHA Safety 10.5 Safety Codes, Standards & Voluntary Guidelines (OSHA, ANSI, NIOSH, MIL-STD) and DART Rate Calculations

11 Statistical Process Control & Process Capability

11.1 Statistical Process Control for Variables (X-bar/R and X-bar/s Charts) 11.2 Statistical Process Control for Attributes (p, np, c, and u Charts) 11.3 Process Capability Indices (Cp, Cpk, Cpm, Pp, Ppk) & Sigma Levels

12 Design of Experiments, Acceptance Sampling & Quality Systems

12.1 Design of Experiments: 2^k Factorials, ANOVA & Taguchi Robust Design 12.2 Acceptance Sampling: OC Curves, AQL, LTPD, AOQL, Z1.4/MIL-STD-105E & Dodge-Romig 12.3 Quality Systems (Deming, TQM, ISO 9000, Benchmarking), Root Cause Analysis & DMAIC

13 Reliability Engineering & Maintenance Systems

13.1 Reliability Modeling, Failure Rates (lambda) & Life Distributions (Exponential, Weibull) 13.2 System Reliability Architecture: Series, Parallel, k-out-of-n & Redundancy 13.3 Equipment Maintenance Engineering, Availability (A), MTBF/MTTR & RCM

6.4 Just-in-Time & Lean Production Planning: Pull Systems, Kanban Sizing, Heijunka & SMED

Key Takeaways Explain This Topic AI

JIT pull systems release work only when downstream consumption signals a need, capping work-in-process, while push systems release work to a schedule or forecast.

The number of kanban containers is N = D × L × (1 + α) ÷ C, rounded up, where L is the replenishment lead time including waiting and α is a safety factor.

Heijunka levels the volume and mix of production, for example sequencing models A-B-A-C for a 2:1:1 demand ratio instead of running large batches.

SMED separates internal setup (machine stopped) from external setup (machine running), converts internal work to external, and streamlines the rest.

Because economic lot size grows with the square root of setup cost, cutting setup cost by 75% halves the economic lot size.

Last updated: October 2026

6.4 Just-in-Time and Lean Production Planning

The NCEES specification lists JIT among production planning methods alongside capacity planning, materials planning (MRP), lot sizing, workforce planning, and aggregate planning. MRP plans by pushing time-phased orders into the shop. Just-in-time (JIT) , developed as part of the Toyota Production System, controls the shop by pulling: nothing is produced until the next process needs it.

1. Push vs. Pull

  • Feature Push (MRP) Pull (JIT / kanban)
  • Trigger Schedule or forecast Actual consumption downstream
  • WIP control Indirect; WIP floats Capped by the number of kanbans or containers
  • Best fit Lumpy demand, long lead times, complex BOMs Stable, repetitive demand

Response to a disruption Work keeps arriving and queues grow Upstream stops when no signal arrives, so the problem surfaces fast

Many plants combine them: MRP plans long-lead materials and capacity, and kanban controls daily execution on the floor.

CONWIP (constant work-in-process) is a simple pull variant: a fixed number of cards circulate for an entire line, and a new job may start only when a finished job releases a card. Little's Law ( W I P = T H × C T WIP = TH \times CT W I P = T H × CT ) shows why capping WIP caps cycle time.

2. The Seven Wastes

Taiichi Ohno's seven wastes are what JIT tries to remove:

Transportation: unnecessary moves of material.

Inventory: stock beyond immediate need, which hides problems.

Motion: unnecessary movement of people.

Waiting: idle people or machines.

Overproduction: making more or earlier than needed. Ohno considered this the worst, because it creates the others.

Overprocessing: work beyond what the customer values.

Defects: scrap, rework, and inspection.

  • (Many lean texts add an eighth waste, unused employee skill.)
  • 3. Kanban Systems

A kanban ("signboard") is a signal, usually a card or an empty container, that authorizes production or withdrawal.

Withdrawal (conveyance) kanban: authorizes moving a container from the supplying process to the using process.

Production kanban: authorizes the supplying process to make one container to replace what was withdrawn.

Kanban rules (Toyota):

The downstream process withdraws only what it needs.

The upstream process produces only what was withdrawn.

No defective parts are passed on.

The number of kanbans is reduced over time to expose problems.

  • Number of Kanbans
  • N = D ⋅ L ⋅ ( 1 + α ) C N = \frac{D \cdot L \cdot (1 + \alpha)}{C} N = C D ⋅ L ⋅ ( 1 + α ) ​

where D D D is the demand rate, L L L is the replenishment lead time (waiting, processing, and transport for one container), α \alpha α is a safety factor (often 0.10 or less in a mature system), and C C C is the container size. Round up.

Example: A cell uses 600 brackets per day. A container holds 20 brackets. The time to replenish a container (wait, make, move) is 0.25 day, and the safety factor is 10%.

N = 600 × 0.25 × 1.10 20 = 165 20 = 8.25 ⇒ 9 containers N = \frac{600 \times 0.25 \times 1.10}{20} = \frac{165}{20} = 8.25 \Rightarrow 9 \text{ containers} N = 20 600 × 0.25 × 1.10 ​ = 20 165 ​ = 8.25 ⇒ 9 containers

The most brackets that can be in the loop is 9 × 20 = 180 9 \times 20 = 180 9 × 20 = 180 , which caps the WIP between the two processes. Cutting replenishment lead time to 0.15 day reduces the count to ⌈ 4.95 ⌉ = 5 \lceil 4.95 \rceil = 5 ⌈ 4.95 ⌉ = 5 containers.

4. Level Scheduling (Heijunka) and Mixed-Model Sequencing

Large batches of one model create surges in upstream demand. Heijunka levels both volume and mix .

Example: Daily demand is 400 of model A, 200 of model B, and 200 of model C, a ratio of 2:1:1. Instead of running all A, then all B, then all C, the line repeats the 4-unit sequence A–B–A–C 200 times per day. Every upstream process then sees steady demand for every component, and fewer kanbans are needed.

Leveling depends on short changeovers, which leads to SMED.

5. Setup Reduction: SMED

Shigeo Shingo's Single-Minute Exchange of Die (SMED) aims for changeovers under 10 minutes ("single-digit minutes"):

Observe and record every step of the current changeover.

Separate internal from external setup. Internal steps can only be done with the machine stopped; external steps can be done while it runs, such as staging the next die and tools.

Convert internal to external, for example by pre-heating dies or using standard die heights and fixture plates.

Streamline everything: quick-release clamps instead of bolts, eliminating adjustments, and parallel work by two people.

Example: A 60-minute changeover includes 25 minutes of work that could be done while the press runs. Moving that work to external setup cuts downtime to 35 minutes before any streamlining.

Why Setup Reduction Matters for Lot Sizing

The economic lot size is Q ∗ = 2 D S / H Q^* = \sqrt{2DS/H} Q ∗ = 2 D S / H ​ , so Q ∗ Q^* Q ∗ is proportional to S \sqrt{S} S ​ . Cutting setup cost by 75% (to one quarter) reduces the economic lot size to 0.25 = 0.5 \sqrt{0.25} = 0.5 0.25 ​ = 0.5 of its former value. Smaller lots mean less inventory, shorter lead times, and easier leveling without higher total cost. JIT does not ignore the EOQ tradeoff; it lowers the setup cost that drives it.

6. Supporting Practices

Takt-paced one-piece flow in cells sized to customer demand.

Total productive maintenance , because pull systems have little buffer stock to cover breakdowns.

Supplier partnerships with frequent, small, quality-certified deliveries.

Jidoka (automation with a human touch): stop the line when a defect is detected so the problem is fixed at its source.

Andon signals and visual management to make abnormalities obvious.