7.1 Deterministic Inventory Control: Classical EOQ, EPQ & Quantity Discounts
PE Industrial and Systems Exam
Track your progress as you read
Finished sections get a check mark.
1 Exam Overview, Strategy & Systems Foundations
1.1 PE Industrial Exam Format, Official Specification & Reference Handbook Strategy 1.2 System Analysis Tools, Process Definition, Requirements Engineering & QFD 1.3 Performance Measures: Output, Productivity, OEE, Cost & Environmental Sustainability 1.4 Process Types (Discrete, Continuous, Manufacturing, Service) & Value Analysis/Engineering
2 Optimization, Queueing, Simulation, Networks & Markov Chains
2.1 Linear Programming Formulation, Graphical Solutions & Sensitivity Analysis 2.2 Queueing Theory Models (M/M/1, M/M/s) & Little's Law Applications 2.3 Discrete-Event Simulation, Random Variates & Model Validation 2.4 Graph Theory & Network Models: Shortest Path, Minimal Spanning Tree & Maximum Flow 2.5 Markov Chains: Transition Matrices, Steady-State Probabilities & Absorbing States 2.6 Decision Trees, Expected Value & Bottleneck Analysis (Theory of Constraints)
3 Project Management & Planning
3.1 Project Scheduling with CPM and PERT: Critical Path, Float, Probability & Crashing 3.2 Project Planning & Control: Scope and WBS, Gantt Charts, Critical Chain (CCPM), Risk & Earned Value
4 Facility Layout, Space, Capacity & Material Handling
4.1 Systematic Layout Planning (SLP) & Activity Relationship (REL) Analysis 4.2 Workstation Design, Aisle Sizing & Space Requirements Planning 4.3 Capacity Analysis: Machine Requirements, Scrap Allowances & Personnel Requirements 4.4 Material Handling Equipment Selection, Unit Loads & Handling Principles
5 Site Location, Warehousing & Facility Economics
5.1 Facility Location Models: Center of Gravity & Minisum / Minimax Distance 5.2 Warehousing Systems, Storage Assignment & Order Picking Operations 5.3 Facility Life-Cycle Economics, Replacement Analysis & Rearrangement Costs
6 Demand Forecasting, Production Planning, MRP & JIT
6.1 Demand Forecasting Methods: Moving Averages, Exponential Smoothing & Error Metrics 6.2 Aggregate Planning Strategies & Master Production Scheduling (MPS) 6.3 Material Requirements Planning (MRP), Bill of Materials & Capacity Planning 6.4 Just-in-Time & Lean Production Planning: Pull Systems, Kanban Sizing, Heijunka & SMED
7 Inventory Systems, Scheduling, Logistics & Transportation Modes
7.1 Deterministic Inventory Control: Classical EOQ, EPQ & Quantity Discounts 7.2 Stochastic Inventory Management: Safety Stock, Continuous / Periodic Review & Newsvendor 7.3 Production Sequencing, Dispatching Rules & Johnson's Algorithm 7.4 Supply Chain Logistics, Transportation Simplex & Distribution Network Design 7.5 Transportation Modes, Freight Economics & the Transshipment Model
8 Engineering Economics, Break-Even Analysis & Costing Systems
8.1 Equivalence, Cash Flow Analysis & Discounted Cash Flow Metrics (PW, FW, EAC) 8.2 Rate of Return Analysis (IRR, Incremental IRR) & Benefit-Cost (B/C) Ratios 8.3 Asset Depreciation (MACRS, Straight-Line), Tax Effects & Replacement Decisions 8.4 Break-Even Analysis, Technical Capability Assessment & Costing Systems (Traditional, ABC & Standard Costs)
9 Methods Engineering, Work Measurement, Learning Curves, Line Balancing & Process Planning
9.1 Methods Analysis, Process Charting & Motion Study (Therbligs, 5S) 9.2 Worker–Machine (Man–Machine) Charts, Multiple Activity Analysis & Synchronous Servicing 9.3 Time Study Fundamentals, Performance Rating & Allowance Factors 9.4 Predetermined Motion Time Systems (PMTS, MTM, MOST) & Work Sampling 9.5 Learning Curves: Unit and Cumulative-Average Models, Learning Rates & Applications 9.6 Assembly Line Balancing, Precedence Constraints & Efficiency Heuristics 9.7 Manufacturing & Service Process Planning: Operation Selection, Sequencing, Route Sheets, Fixturing & Mistake Proofing
10 Ergonomics, Human Capacity, Occupational Safety & DART Rates
10.1 Anthropometry, Percentile Design, Workstation Ergonomics & Link Analysis 10.2 Industrial Biomechanics, the NIOSH Lifting Equation & Lifting Aids 10.3 Limits of Human Capacity & Risk-Factor Tools: Work Physiology, Strength, Range of Motion, Vision, RULA & Slip Resistance 10.4 Environmental Ergonomics (Noise, Heat, Illumination), Human-Machine Systems & OSHA Safety 10.5 Safety Codes, Standards & Voluntary Guidelines (OSHA, ANSI, NIOSH, MIL-STD) and DART Rate Calculations
11 Statistical Process Control & Process Capability
11.1 Statistical Process Control for Variables (X-bar/R and X-bar/s Charts) 11.2 Statistical Process Control for Attributes (p, np, c, and u Charts) 11.3 Process Capability Indices (Cp, Cpk, Cpm, Pp, Ppk) & Sigma Levels
12 Design of Experiments, Acceptance Sampling & Quality Systems
12.1 Design of Experiments: 2^k Factorials, ANOVA & Taguchi Robust Design 12.2 Acceptance Sampling: OC Curves, AQL, LTPD, AOQL, Z1.4/MIL-STD-105E & Dodge-Romig 12.3 Quality Systems (Deming, TQM, ISO 9000, Benchmarking), Root Cause Analysis & DMAIC
13 Reliability Engineering & Maintenance Systems
13.1 Reliability Modeling, Failure Rates (lambda) & Life Distributions (Exponential, Weibull) 13.2 System Reliability Architecture: Series, Parallel, k-out-of-n & Redundancy 13.3 Equipment Maintenance Engineering, Availability (A), MTBF/MTTR & RCM
7.1 Deterministic Inventory Control: Classical EOQ, EPQ & Quantity Discounts
Key Takeaways Explain This Topic AI
The classical Economic Order Quantity (EOQ) balances annual setup costs ( D Q S \frac{D}{Q}S Q D S ) and annual holding costs ( Q 2 H \frac{Q}{2}H 2 Q H ), reaching the global minimum total relevant cost at EOQ = 2 D S H \text{EOQ} = \sqrt{\frac{2DS}{H}} EOQ = H 2 D S where holding and ordering costs are strictly equal.
The total cost curve near the EOQ is flat: ordering 25% more than Q ∗ Q^* Q ∗ raises holding plus ordering cost by only 2.5%, while ordering 25% less raises it by 4.2%.
The Economic Production Quantity (EPQ / POQ) accounts for finite production replenishment at rate p > d p > d p > d , reducing maximum on-hand inventory to I max = Q ( 1 − d / p ) I_{\max} = Q(1 - d/p) I m a x = Q ( 1 − d / p ) and scaling lot size to EPQ = 2 D S H ( 1 − d / p ) \text{EPQ} = \sqrt{\frac{2DS}{H(1 - d/p)}} EPQ = H ( 1 − d / p ) 2 D S .
Evaluating all-units quantity discounts requires a structured 4-step algorithm: calculate unconstrained EOQs for each price tier, adjust infeasible EOQs upward to price breakpoints, and compare total acquisition plus inventory carrying costs.
Planned backorder models permit customer shortages at penalty cost C b C_b C b , reducing average physical holding inventory and expanding the optimal order quantity by the factor H + C b C b \sqrt{\frac{H + C_b}{C_b}} C b H + C b .
Last updated: October 2026
Deterministic Inventory Control: Classical EOQ, EPQ & Quantity Discounts
Inventory management is a fundamental discipline in industrial and systems engineering, balancing working capital investment against production continuity and customer satisfaction. Inventory represents a major asset on an organization's balance sheet, often comprising 20% to 50% of total capital. Operating without sufficient inventory risks catastrophic line shutdowns and lost customer goodwill, whereas holding excessive stock ties up valuable working capital and incurs warehousing, taxation, insurance, and obsolescence costs.
Deterministic inventory control models evaluate scenarios where demand rates, production rates, ordering lead times, and unit purchase costs are known with certainty. These foundational formulations provide the theoretical and mathematical baseline for modern aggregate planning, Material Requirements Planning (MRP), and advanced Enterprise Resource Planning (ERP) systems.
- 1. Inventory Taxonomy and Cost Structures
- Functional Classifications of Industrial Inventory
Industrial inventory is categorized according to its position across the transformation value stream:
Raw Materials: Unprocessed purchased materials, raw commodities, and standard hardware awaiting introduction into manufacturing operations.
Work-in-Process (WIP): Semi-finished parts, subassemblies, and batches physically situated between intermediate machining, fabrication, or assembly operations.
Finished Goods: Completely fabricated and inspected products packaged at the factory or warehouse awaiting customer distribution.
Maintenance, Repair, and Operating (MRO) Supplies: Consumables, cutting tooling, machine lubricants, spare parts, and personal protective equipment required to support operations without becoming part of the end product.
Pipeline / Transit Inventory: Goods in transit between supply chain nodes (e.g., loaded on trucks, railcars, or container ships).
Decoupling Inventory: Buffers positioned between adjacent manufacturing stages having unequal cycle times, preventing upstream disruptions from idling downstream workstations.
Economic Cost Components
Every lot-sizing decision balances three antagonistic financial cost vectors:
Unit Purchasing Cost ( C C C ): The acquisition price paid to a supplier or the variable direct manufacturing cost per unit ($/unit).
Ordering / Setup Cost ( S S S ): The fixed cost incurred each time a replenishment order is placed or a production line is changed over ($/order or $/setup). For external purchases, S S S captures requisition processing, purchase order generation, freight administrative fees, receiving dock handling, and incoming QA inspections. In manufacturing, S S S captures teardown, die replacement, machine recalibration, purging, scrap from test runs, and lost line capacity.
Holding / Carrying Cost ( H H H ): The annual cost to carry one unit of inventory for one full year ($/unit-year). It is universally formulated as a percentage i i i of the unit acquisition cost: H = i × C H = i \times C H = i × C Where the carrying charge rate i i i (typically 15% to 35% annually) aggregates:
Cost of Capital / WACC (10%–20%): Opportunity cost of working capital tied up in stock.
Storage & Warehousing (2%–5%): Building depreciation, lease expenses, utility power, climate control, and material handling equipment leases.
Risk & Obsolescence (3%–10%): Product expiration, engineering design revisions rendering stock scrap, and inventory write-downs.
Taxes & Insurance (1%–3%): Property taxes on stored assets and comprehensive casualty/theft insurance premiums.
Shortage / Stockout Cost ( C s C_s C s or p s p_s p s ): The penalty incurred when customer demand exceeds available on-hand stock ($/unit short per unit time), incorporating administrative expediting, overtime premiums, special air freight charges, lost gross margin, and contractual late delivery penalties.
2. The Classical Economic Order Quantity (EOQ) Model
Originally derived by Ford Whitman Harris in 1913, the classical Economic Order Quantity (EOQ) model determines the replenishment lot size Q Q Q that minimizes the total annual cost of ordering and holding inventory.
Foundational Assumptions
Demand rate D D D is constant, continuous, and deterministic (units/year).
Replenishment is instantaneous; the entire order quantity Q Q Q arrives simultaneously in a single batch (infinite replenishment rate, p → ∞ p \to \infty p → ∞ ).
Replenishment lead time L L L is fixed, constant, and known with certainty.
Unit purchasing cost C C C is strictly constant, independent of order quantity (no volume discounts).
No stockouts or shortages are permitted ( C s → ∞ C_s \to \infty C s → ∞ ).
The planning horizon is infinite, and inventory involves a single independent product.
Mathematical Derivation of EOQ
Under instantaneous batch replenishment and steady demand rate D D D , the on-hand inventory traces a repeating sawtooth profile fluctuating between a maximum of Q Q Q and a minimum of 0 0 0 . The average inventory level held across the operational cycle is:
I ˉ = Q + 0 2 = Q 2 \bar{I} = \frac{Q + 0}{2} = \frac{Q}{2} I ˉ = 2 Q + 0 = 2 Q
The number of replenishment cycles initiated per year is:
N = D Q N = \frac{D}{Q} N = Q D
The Total Annual Cost function T C ( Q ) TC(Q) TC ( Q ) comprises annual material acquisition cost, annual ordering cost, and annual inventory holding cost:
T C ( Q ) = D ⋅ C + D Q S + Q 2 H TC(Q) = D \cdot C + \frac{D}{Q}S + \frac{Q}{2}H TC ( Q ) = D ⋅ C + Q D S + 2 Q H
Because annual acquisition cost D ⋅ C D \cdot C D ⋅ C is constant with respect to lot size Q Q Q , the lot-sizing optimization focuses strictly on the Total Relevant Cost ( T R C TRC TRC ) :
T R C ( Q ) = D Q S + Q 2 H TRC(Q) = \frac{D}{Q}S + \frac{Q}{2}H TRC ( Q ) = Q D S + 2 Q H
To find the minimizing lot size, compute the first derivative of T R C ( Q ) TRC(Q) TRC ( Q ) with respect to Q Q Q and set it to zero:
d ( T R C ) d Q = − D Q 2 S + H 2 = 0 \frac{d(TRC)}{dQ} = -\frac{D}{Q^2}S + \frac{H}{2} = 0 d Q d ( TRC ) = − Q 2 D S + 2 H = 0
Equating annual ordering cost to annual holding cost:
D Q S = Q 2 H \frac{D}{Q}S = \frac{Q}{2}H Q D S = 2 Q H
Solving for Q Q Q yields the celebrated classical EOQ formula:
Q ∗ = E O Q = 2 D S H = 2 D S i C Q^* = EOQ = \sqrt{\frac{2DS}{H}} = \sqrt{\frac{2DS}{iC}} Q ∗ = EOQ = H 2 D S = i C 2 D S
To verify that Q ∗ Q^* Q ∗ is a global minimum, examine the second derivative:
d 2 ( T R C ) d Q 2 = 2 D S Q 3 > 0 ∀ Q > 0 \frac{d^2(TRC)}{dQ^2} = \frac{2DS}{Q^3} > 0 \quad \forall Q > 0 d Q 2 d 2 ( TRC ) = Q 3 2 D S > 0 ∀ Q > 0
Because the second derivative is strictly positive for all physical quantities Q > 0 Q > 0 Q > 0 , the total relevant cost curve is strictly convex, confirming that Q ∗ Q^* Q ∗ uniquely minimizes total annual inventory cost. Cost (\$/Year)
- ^
- | / Total Relevant Cost TRC(Q)
| / .__-—--_.
- | / / \
- | / / \ Holding Cost (Q/2 * H)
- | / / \ /
- | / / \ /
- | | / EOQ X
- | | / | / \
- | | / | / \
- | |/ v / \ Ordering Cost (D/Q * S)
- +-------------------------------------------------------> Order Quantity (Q)
- Q*
- Operational Metrics at EOQ
When operating at the optimal order quantity Q ∗ = 2 D S / H Q^* = \sqrt{2DS/H} Q ∗ = 2 D S / H :
Equivalence of Costs: Annual ordering cost equals annual holding cost exactly: Annual Ordering Cost = D Q ∗ S = D S H 2 \text{Annual Ordering Cost} = \frac{D}{Q^*}S = \sqrt{\frac{DSH}{2}} Annual Ordering Cost = Q ∗ D S = 2 D S H Annual Holding Cost = Q ∗ 2 H = D S H 2 \text{Annual Holding Cost} = \frac{Q^*}{2}H = \sqrt{\frac{DSH}{2}} Annual Holding Cost = 2 Q ∗ H = 2 D S H
Minimum Total Relevant Cost: T R C ( Q ∗ ) = D Q ∗ S + Q ∗ 2 H = 2 D S H 2 = 2 D S H TRC(Q^*) = \frac{D}{Q^*}S + \frac{Q^*}{2}H = 2 \sqrt{\frac{DSH}{2}} = \sqrt{2DSH} TRC ( Q ∗ ) = Q ∗ D S + 2 Q ∗ H = 2 2 D S H = 2 D S H
Optimal Order Frequency: The number of orders placed per year is: N ∗ = D Q ∗ = D H 2 S N^* = \frac{D}{Q^*} = \sqrt{\frac{DH}{2S}} N ∗ = Q ∗ D = 2 S DH
Optimal Cycle Time ( T ∗ T^* T ∗ ): The duration between successive replenishment orders: T ∗ = Q ∗ D = 2 S D H (years) T^* = \frac{Q^*}{D} = \sqrt{\frac{2S}{DH}} \text{ (years)} T ∗ = D Q ∗ = DH 2 S (years) T ∗ = Q ∗ D × N d a y s (operating working days) T^* = \frac{Q^*}{D} \times N_{days} \text{ (operating working days)} T ∗ = D Q ∗ × N d a ys (operating working days)
Reorder Point ( R O P ROP ROP ): Under deterministic lead time L L L (expressed in years): R O P = d × L = ( D Operating Days/Year ) × L days ROP = d \times L = \left( \frac{D}{\text{Operating Days/Year}} \right) \times L_{\text{days}} ROP = d × L = ( Operating Days/Year D ) × L days Note: If lead time L L L exceeds the cycle time T ∗ T^* T ∗ , use effective lead time L e = L − m T ∗ L_e = L - m T^* L e = L − m T ∗ , where m = ⌊ L / T ∗ ⌋ m = \lfloor L / T^* \rfloor m = ⌊ L / T ∗ ⌋ .
3. Parametric Sensitivity and the Flat Cost Curve
A critical insight for practicing industrial engineers is the mathematical robustness of the EOQ formula. In real-world factory operations, parameter inputs ( D , S , H D, S, H D , S , H ) are estimates subject to forecasting error or accounting variability. Furthermore, logistics realities (such as master carton counts, skid/pallet quantities, or truckload capacities) often force engineers to round the computed lot size Q ∗ Q^* Q ∗ to a convenient packaging multiple.
Sensitivity Formulation
Let Q Q Q represent an arbitrary, non-optimal order quantity, and let Q ∗ Q^* Q ∗ represent the true theoretical EOQ. The ratio of total relevant cost at Q Q Q relative to the optimal cost T R C ( Q ∗ ) TRC(Q^*) TRC ( Q ∗ ) is derived algebraically:
T R C ( Q ) T R C ( Q ∗ ) = D Q S + Q 2 H 2 D S H \frac{TRC(Q)}{TRC(Q^*)} = \frac{\frac{D}{Q}S + \frac{Q}{2}H}{\sqrt{2DSH}} TRC ( Q ∗ ) TRC ( Q ) = 2 D S H Q D S + 2 Q H
Substituting S = ( Q ∗ ) 2 H 2 D S = \frac{(Q^*)^2 H}{2D} S = 2 D ( Q ∗ ) 2 H into the numerator:
T R C ( Q ) T R C ( Q ∗ ) = D Q [ ( Q ∗ ) 2 H 2 D ] + Q 2 H 2 D [ ( Q ∗ ) 2 H 2 D ] H = ( Q ∗ ) 2 H 2 Q + Q H 2 Q ∗ H = 1 2 ( Q ∗ Q + Q Q ∗ ) \frac{TRC(Q)}{TRC(Q^*)} = \frac{\frac{D}{Q} \left[ \frac{(Q^*)^2 H}{2D} \right] + \frac{Q}{2}H}{\sqrt{2D \left[ \frac{(Q^*)^2 H}{2D} \right] H}} = \frac{\frac{(Q^*)^2 H}{2Q} + \frac{QH}{2}}{Q^* H} = \frac{1}{2} \left( \frac{Q^*}{Q} + \frac{Q}{Q^*} \right) TRC ( Q ∗ ) TRC ( Q ) = 2 D [ 2 D ( Q ∗ ) 2 H ] H Q D [ 2 D ( Q ∗ ) 2 H ] + 2 Q H = Q ∗ H 2 Q ( Q ∗ ) 2 H + 2 Q H = 2 1 ( Q Q ∗ + Q ∗ Q )
This simple, elegant equation reveals the fundamental cost ratio relationship :
T R C ( Q ) T R C ( Q ∗ ) = 1 2 ( Q Q ∗ + Q ∗ Q ) \frac{TRC(Q)}{TRC(Q^*)} = \frac{1}{2} \left( \frac{Q}{Q^*} + \frac{Q^*}{Q} \right) TRC ( Q ∗ ) TRC ( Q ) = 2 1 ( Q ∗ Q + Q Q ∗ )
Quantitative Impact of Lot-Sizing Deviations
Operational Ratio ( Q / Q ∗ Q / Q^* Q / Q ∗ ) Percentage Error in Lot Size Cost Ratio ( T R C / T R C ∗ TRC / TRC^* TRC / TR C ∗ ) Total Cost Penalty Above Optimal
0.50 − 50 % -50\% − 50% (Under-ordering) 1 2 ( 0.50 + 2.00 ) = 1.250 \frac{1}{2}(0.50 + 2.00) = 1.250 2 1 ( 0.50 + 2.00 ) = 1.250 + 25.0 % +25.0\% + 25.0%
0.75 − 25 % -25\% − 25% 1 2 ( 0.75 + 1.333 ) = 1.042 \frac{1}{2}(0.75 + 1.333) = 1.042 2 1 ( 0.75 + 1.333 ) = 1.042 + 4.2 % +4.2\% + 4.2%
0.80 − 20 % -20\% − 20% 1 2 ( 0.80 + 1.250 ) = 1.025 \frac{1}{2}(0.80 + 1.250) = 1.025 2 1 ( 0.80 + 1.250 ) = 1.025 + 2.5 % +2.5\% + 2.5%
0.90 − 10 % -10\% − 10% 1 2 ( 0.90 + 1.111 ) = 1.006 \frac{1}{2}(0.90 + 1.111) = 1.006 2 1 ( 0.90 + 1.111 ) = 1.006 + 0.6 % +0.6\% + 0.6%
1.00 0 % 0\% 0% (Exact EOQ) 1 2 ( 1.00 + 1.00 ) = 1.000 \frac{1}{2}(1.00 + 1.00) = 1.000 2 1 ( 1.00 + 1.00 ) = 1.000 0.0 % 0.0\% 0.0% (Minimum)
1.10 + 10 % +10\% + 10% 1 2 ( 1.10 + 0.909 ) = 1.005 \frac{1}{2}(1.10 + 0.909) = 1.005 2 1 ( 1.10 + 0.909 ) = 1.005 + 0.5 % +0.5\% + 0.5%
1.20 + 20 % +20\% + 20% 1 2 ( 1.20 + 0.833 ) = 1.017 \frac{1}{2}(1.20 + 0.833) = 1.017 2 1 ( 1.20 + 0.833 ) = 1.017 + 1.7 % +1.7\% + 1.7%
1.25 + 25 % +25\% + 25% 1 2 ( 1.25 + 0.800 ) = 1.025 \frac{1}{2}(1.25 + 0.800) = 1.025 2 1 ( 1.25 + 0.800 ) = 1.025 + 2.5 % +2.5\% + 2.5%
1.50 + 50 % +50\% + 50% (Over-ordering) 1 2 ( 1.50 + 0.667 ) = 1.083 \frac{1}{2}(1.50 + 0.667) = 1.083 2 1 ( 1.50 + 0.667 ) = 1.083 + 8.3 % +8.3\% + 8.3%
2.00 + 100 % +100\% + 100% (Doubling lot) 1 2 ( 2.00 + 0.50 ) = 1.250 \frac{1}{2}(2.00 + 0.50) = 1.250 2 1 ( 2.00 + 0.50 ) = 1.250 + 25.0 % +25.0\% + 25.0%
Tip
The Flat-Bottom Property: Because the cost curve is exceptionally flat near the minimum, deviating from Q ∗ Q^* Q ∗ by up to ± 20 % \pm 20\% ± 20% incurs a negligible cost penalty of less than 2.5 % 2.5\% 2.5% . Engineers should confidently round lot sizes to match full pallet layers, tote capacities, or standard container packaging without fear of compromising economic performance.
4. The Economic Production Quantity (EPQ / POQ) Model
In internal manufacturing environments, items are produced incrementally over time rather than arriving instantaneously. The Economic Production Quantity (EPQ) model—also designated the Production Order Quantity (POQ) model—extends classical EOQ to account for a finite production rate p p p .
Model Assumptions & Mechanics
Production rate is p p p units per day (or annual production capacity P P P ).
Consumption demand rate is d d d units per day (or annual demand D D D ).
The manufacturing rate strictly exceeds the demand rate: p > d p > d p > d ( P > D P > D P > D ). If p ≤ d p \le d p ≤ d , the production facility can never satisfy demand, producing continuously with infinite backlogs.
The Operational Production Cycle
Each replenishment cycle T T T is divided into two distinct operating intervals:
Run Time ( t 1 t_1 t 1 ): The production equipment operates at rate p p p while demand simultaneously depletes stock at rate d d d . Inventory accumulates at the net buildup rate of ( p − d ) (p - d) ( p − d ) : t 1 = Q p t_1 = \frac{Q}{p} t 1 = p Q
Pure Depletion Time ( t 2 t_2 t 2 ): Production stops ( p = 0 p = 0 p = 0 ). Demand continues at rate d d d until inventory drops to zero: t 2 = I m a x d t_2 = \frac{I_{max}}{d} t 2 = d I ma x
The total cycle duration is:
T = t 1 + t 2 = Q p + I m a x d = Q d T = t_1 + t_2 = \frac{Q}{p} + \frac{I_{max}}{d} = \frac{Q}{d} T = t 1 + t 2 = p Q + d I ma x = d Q Inventory Level
- ^
- Imax | /\ /\
- | / \ / \
- | / \ / \
- | / \ / \
- | / Net \ Pure / \
- | / Buildup \ Depletion / \
- | / (p - d) \ (-d) / \
- 0 +----+--------------+-------+--------------+---> Time
- |<--- t1 ----->|<- t2 >|
- |<------- T ---------->|
- Maximum and Average Inventory Levels
The maximum inventory level I m a x I_{max} I ma x is reached at the exact moment production ceases at time t 1 t_1 t 1 :
I m a x = t 1 ( p − d ) = ( Q p ) ( p − d ) = Q ( 1 − d p ) = Q ( 1 − D P ) I_{max} = t_1 (p - d) = \left( \frac{Q}{p} \right) (p - d) = Q \left( 1 - \frac{d}{p} \right) = Q \left( 1 - \frac{D}{P} \right) I ma x = t 1 ( p − d ) = ( p Q ) ( p − d ) = Q ( 1 − p d ) = Q ( 1 − P D )
Because inventory rises linearly from 0 0 0 to I m a x I_{max} I ma x and falls linearly back to 0 0 0 , the average inventory held across the entire cycle is:
I ˉ = I m a x 2 = Q 2 ( 1 − d p ) \bar{I} = \frac{I_{max}}{2} = \frac{Q}{2} \left( 1 - \frac{d}{p} \right) I ˉ = 2 I ma x = 2 Q ( 1 − p d )
Derivation of Optimal Production Lot Size
The Total Relevant Cost equation balances annual machine setup costs with annual holding costs:
T R C ( Q ) = D Q S + Q 2 H ( 1 − d p ) TRC(Q) = \frac{D}{Q}S + \frac{Q}{2} H \left( 1 - \frac{d}{p} \right) TRC ( Q ) = Q D S + 2 Q H ( 1 − p d )
Differentiating with respect to Q Q Q and equating to zero:
d ( T R C ) d Q = − D Q 2 S + H 2 ( 1 − d p ) = 0 \frac{d(TRC)}{dQ} = -\frac{D}{Q^2}S + \frac{H}{2} \left( 1 - \frac{d}{p} \right) = 0 d Q d ( TRC ) = − Q 2 D S + 2 H ( 1 − p d ) = 0
D Q S = Q 2 H ( 1 − d p ) \frac{D}{Q}S = \frac{Q}{2} H \left( 1 - \frac{d}{p} \right) Q D S = 2 Q H ( 1 − p d )
Solving for Q Q Q yields the optimal Economic Production Quantity ( E P Q EPQ EPQ ):
E P Q = Q p ∗ = 2 D S H ( 1 − d p ) = 2 D S H ( 1 − D P ) EPQ = Q_p^* = \sqrt{\frac{2DS}{H \left( 1 - \frac{d}{p} \right)}} = \sqrt{\frac{2DS}{H \left( 1 - \frac{D}{P} \right)}} EPQ = Q p ∗ = H ( 1 − p d ) 2 D S = H ( 1 − P D ) 2 D S
Comparing EPQ and EOQ
Defining the production buildup factor ψ = 1 − d p < 1 \psi = \sqrt{1 - \frac{d}{p}} < 1 ψ = 1 − p d < 1 :
E P Q = E O Q 1 − d p EPQ = \frac{EOQ}{\sqrt{1 - \frac{d}{p}}} EPQ = 1 − p d EOQ
Because ( 1 − d / p ) < 1 (1 - d/p) < 1 ( 1 − d / p ) < 1 , the divisor is less than 1, proving that E P Q > E O Q EPQ > EOQ EPQ > EOQ . Under finite production replenishment, batches are larger than purchase orders, yet maximum inventory I m a x I_{max} I ma x and average inventory I ˉ \bar{I} I ˉ are strictly lower than their EOQ counterparts due to concurrent consumption during production.
5. Quantity Discount Valuation Models
Suppliers frequently offer price discounts to incentivize larger order sizes. Lower purchase prices reduce material acquisition expenditures and annual ordering frequency, but elevate average inventory and annual holding costs.
All-Units vs. Incremental Discounts
Industrial pricing contracts follow two primary structures:
All-Units Quantity Discounts: The discounted unit price applies to every single unit purchased in the order, provided the lot size meets or exceeds the price breakpoint threshold q k q_k q k .
Incremental Quantity Discounts: The discounted price applies only to units ordered in excess of the breakpoint threshold, preserving higher prices for baseline units (similar to marginal income tax brackets). All-Units Discount Cost Curve: Incremental Discount Cost Curve:
- Total Purchase Cost ($) Total Purchase Cost ($)
- ^
- | / Tier 1: C1 ^
- | / | / Slope C2
- | / | /
- | / / Tier 2: C2 | Breakpoint / (C2 < C1)
- | / / | . /
- | / / | / /
- | / / | / Slope C1 /
- | / / | / /
- +------+---------------------> Q +--+----------+----------> Q
- q1 (Price Drops) q1 q2
- The 4-Step All-Units Discount Algorithm
To identify the global cost-minimizing order quantity under an all-units discount schedule with price tiers C 1 > C 2 > ⋯ > C m C_1 > C_2 > \dots > C_m C 1 > C 2 > ⋯ > C m and breakpoints q 1 = 0 < q 2 < ⋯ < q m q_1 = 0 < q_2 < \dots < q_m q 1 = 0 < q 2 < ⋯ < q m :
Calculate Feasible EOQ for Each Tier: Starting at the lowest price tier m m m (highest volume discount), compute: E O Q k = 2 D S i C k EOQ_k = \sqrt{\frac{2DS}{i C_k}} EO Q k = i C k 2 D S
Check Feasibility: Determine whether E O Q k EOQ_k EO Q k falls within its valid interval [ q k , q k + 1 ) [q_k, q_{k+1}) [ q k , q k + 1 ) :
If E O Q k ≥ q k + 1 EOQ_k \ge q_{k+1} EO Q k ≥ q k + 1 , discard it (a lower price tier is available and better).
If q k ≤ E O Q k < q k + 1 q_k \le EOQ_k < q_{k+1} q k ≤ EO Q k < q k + 1 , E O Q k EOQ_k EO Q k is feasible . Proceed to step 3.
If E O Q k < q k EOQ_k < q_k EO Q k < q k , E O Q k EOQ_k EO Q k is infeasible at price C k C_k C k . The minimum quantity required to qualify for price C k C_k C k is the breakpoint quantity q k q_k q k .
Compute Total Annual Cost ( T C TC TC ): The total cost must include acquisition purchase price, because D ⋅ C k D \cdot C_k D ⋅ C k varies between tiers: T C ( Q ) = D ⋅ C k + D Q S + Q 2 ( i C k ) TC(Q) = D \cdot C_k + \frac{D}{Q}S + \frac{Q}{2}(i C_k) TC ( Q ) = D ⋅ C k + Q D S + 2 Q ( i C k ) Calculate T C ( Q ) TC(Q) TC ( Q ) for:
The lowest-price feasible E O Q k EOQ_k EO Q k .
All price breakpoints q j q_j q j that offer lower unit prices than the feasible E O Q k EOQ_k EO Q k .
Select Global Optimum: The candidate order quantity yielding the lowest total annual cost T C ( Q ) TC(Q) TC ( Q ) is the optimal order quantity Q ∗ Q^* Q ∗ .
6. Planned Backorders / Shortage Models
In certain industrial environments—such as custom capital machinery, aerospace components, or high-value engineered assemblies—stockouts do not result in lost sales. Instead, customers accept delayed delivery, creating planned backorders .
Model Parameters
Shortage cost rate C b C_b C b ($/unit backordered per year).
Q Q Q = Total replenishment batch quantity.
B B B = Maximum backorder quantity accumulated at the end of a cycle.
- I m a x = Q − B I_{max} = Q - B I ma x = Q − B = Maximum on-hand physical inventory. Inventory Level
- ^
- Imax |\ /\
- | \ / \
- | \ / \
- 0 +---\---------------/------\-------------------> Time
- | \ / \
- B | \___________/ \
- v Max Backorder
- Cost Formulation and Optimal Values
Over the cycle T = Q / D T = Q/D T = Q / D , inventory is positive for time t 1 = ( Q − B ) / D t_1 = (Q - B)/D t 1 = ( Q − B ) / D and in backorder for time t 2 = B / D t_2 = B/D t 2 = B / D . The Total Relevant Cost equation is:
T R C ( Q , B ) = D Q S + ( Q − B ) 2 2 Q H + B 2 2 Q C b TRC(Q, B) = \frac{D}{Q}S + \frac{(Q - B)^2}{2Q}H + \frac{B^2}{2Q}C_b TRC ( Q , B ) = Q D S + 2 Q ( Q − B ) 2 H + 2 Q B 2 C b
Taking partial derivatives with respect to Q Q Q and B B B , setting them to zero, and solving simultaneously yields:
Q ∗ = 2 D S H × H + C b C b = E O Q × 1 + H C b Q^* = \sqrt{\frac{2DS}{H}} \times \sqrt{\frac{H + C_b}{C_b}} = EOQ \times \sqrt{1 + \frac{H}{C_b}} Q ∗ = H 2 D S × C b H + C b = EOQ × 1 + C b H
B ∗ = Q ∗ ( H H + C b ) = 2 D S C b × H H + C b B^* = Q^* \left( \frac{H}{H + C_b} \right) = \sqrt{\frac{2DS}{C_b}} \times \sqrt{\frac{H}{H + C_b}} B ∗ = Q ∗ ( H + C b H ) = C b 2 D S × H + C b H
I m a x ∗ = Q ∗ − B ∗ = Q ∗ ( C b H + C b ) I_{max}^* = Q^* - B^* = Q^* \left( \frac{C_b}{H + C_b} \right) I ma x ∗ = Q ∗ − B ∗ = Q ∗ ( H + C b C b )
Engineering Insights
Because ( H + C b ) / C b > 1 \sqrt{(H + C_b)/C_b} > 1 ( H + C b ) / C b > 1 , the optimal lot size under planned backorders is strictly larger than classical EOQ ( Q ∗ > E O Q Q^* > EOQ Q ∗ > EOQ ).
As shortage penalty C b → ∞ C_b \to \infty C b → ∞ , ( H + C b ) / C b → 1 \sqrt{(H + C_b)/C_b} \to 1 ( H + C b ) / C b → 1 and B ∗ → 0 B^* \to 0 B ∗ → 0 , collapsing directly back to the classical EOQ model without shortages.
Permitting backorders reduces average physical holding inventory, thereby lowering total operating costs whenever carrying high physical inventory is more costly than customer delay penalties.
- 7. Worked Engineering Examples
- Example 1: EPQ Optimization for a Precision Machining Center
Problem Statement: A precision automotive components plant operates 250 days per year. A dedicated CNC machining cell produces cast iron engine mounts with the following parameters:
- Annual demand ( D D D ): 10,000 units/year
- Daily production rate ( p p p ): 200 units/day
- Cell setup cost ( S S S ): $200 per production changeover
- Unit manufacturing cost ( C C C ): $25.00 per unit
Annual inventory carrying charge ( i i i ): 20% per year ( H = 0.20 × $ 25.00 = $ 5.00 /unit-year H = 0.20 \times \text{\textdollar}25.00 = \text{\textdollar}5.00\text{/unit-year} H = 0.20 × $ 25.00 = $ 5.00 /unit-year )
Calculate:
Daily demand rate d d d and the buildup ratio ( 1 − d / p ) (1 - d/p) ( 1 − d / p ) .
The optimal Economic Production Quantity ( E P Q EPQ EPQ ).
The maximum on-hand inventory level ( I m a x I_{max} I ma x ).
Total annual setup and holding costs.
Length of the production run ( t 1 t_1 t 1 ) and total cycle time ( T T T ).
Step-by-Step Solution:
1. Daily demand rate and buildup factor: d = D Operating Days = 10 , 000 250 = 40 units/day d = \frac{D}{\text{Operating Days}} = \frac{10,000}{250} = 40\text{ units/day} d = Operating Days D = 250 10 , 000 = 40 units/day ( 1 − d p ) = 1 − 40 200 = 1 − 0.20 = 0.80 \left( 1 - \frac{d}{p} \right) = 1 - \frac{40}{200} = 1 - 0.20 = 0.80 ( 1 − p d ) = 1 − 200 40 = 1 − 0.20 = 0.80
2. Economic Production Quantity ( E P Q EPQ EPQ ): E P Q = 2 D S H ( 1 − d / p ) = 2 ( 10 , 000 ) ( 200 ) 5.00 ( 0.80 ) = 4 , 000 , 000 4.00 = 1 , 000 , 000 = 1 , 000 units EPQ = \sqrt{\frac{2DS}{H(1 - d/p)}} = \sqrt{\frac{2(10,000)(200)}{5.00(0.80)}} = \sqrt{\frac{4,000,000}{4.00}} = \sqrt{1,000,000} = 1,000\text{ units} EPQ = H ( 1 − d / p ) 2 D S = 5.00 ( 0.80 ) 2 ( 10 , 000 ) ( 200 ) = 4.00 4 , 000 , 000 = 1 , 000 , 000 = 1 , 000 units
3. Maximum on-hand inventory level ( I m a x I_{max} I ma x ): I m a x = E P Q ( 1 − d p ) = 1 , 000 × 0.80 = 800 units I_{max} = EPQ \left( 1 - \frac{d}{p} \right) = 1,000 \times 0.80 = 800\text{ units} I ma x = EPQ ( 1 − p d ) = 1 , 000 × 0.80 = 800 units
4. Annual setup and holding costs: Annual Setup Cost = D E P Q × S = 10 , 000 1 , 000 × $ 200 = 10 × $ 200 = $ 2,000 /year \text{Annual Setup Cost} = \frac{D}{EPQ} \times S = \frac{10,000}{1,000} \times \text{\textdollar}200 = 10 \times \text{\textdollar}200 = \text{\textdollar}2{,}000\text{/year} Annual Setup Cost = EPQ D × S = 1 , 000 10 , 000 × $ 200 = 10 × $ 200 = $ 2 , 000 /year Annual Holding Cost = I m a x 2 × H = 800 2 × $ 5.00 = 400 × $ 5.00 = $ 2,000 /year \text{Annual Holding Cost} = \frac{I_{max}}{2} \times H = \frac{800}{2} \times \text{\textdollar}5.00 = 400 \times \text{\textdollar}5.00 = \text{\textdollar}2{,}000\text{/year} Annual Holding Cost = 2 I ma x × H = 2 800 × $ 5.00 = 400 × $ 5.00 = $ 2 , 000 /year Total Relevant Cost = $ 2,000 + $ 2,000 = $ 4,000 /year \text{Total Relevant Cost} = \text{\textdollar}2{,}000 + \text{\textdollar}2{,}000 = \text{\textdollar}4{,}000\text{/year} Total Relevant Cost = $ 2 , 000 + $ 2 , 000 = $ 4 , 000 /year
5. Production duration and cycle time: t 1 = E P Q p = 1 , 000 200 = 5 operating days t_1 = \frac{EPQ}{p} = \frac{1,000}{200} = 5\text{ operating days} t 1 = p EPQ = 200 1 , 000 = 5 operating days t 2 = I m a x d = 800 40 = 20 operating days t_2 = \frac{I_{max}}{d} = \frac{800}{40} = 20\text{ operating days} t 2 = d I ma x = 40 800 = 20 operating days T = t 1 + t 2 = 5 + 20 = 25 operating days T = t_1 + t_2 = 5 + 20 = 25\text{ operating days} T = t 1 + t 2 = 5 + 20 = 25 operating days Or directly: T = E P Q d = 1 , 000 40 = 25 operating days \text{Or directly: } T = \frac{EPQ}{d} = \frac{1,000}{40} = 25\text{ operating days} Or directly: T = d EPQ = 40 1 , 000 = 25 operating days
The CNC cell runs production for 5 days, accumulating 800 units of maximum stock, and then shuts down for 20 days while assembly consumes the buffer at 40 units/day.
Example 2: All-Units Quantity Discount Evaluation
Problem Statement: An industrial plant requires D = 5 , 000 D = 5,000 D = 5 , 000 specialty valves annually. Ordering cost is S = S = S = $180 per order, and inventory holding rate is i = 20 % i = 20\% i = 20% . The supplier provides the following pricing tier:
Tier 1: Orders of 1 to 999 units ⟹ C 1 = $ 50.00 \implies C_1 = \text{\textdollar}50.00 ⟹ C 1 = $ 50.00 per unit
Tier 2: Orders of 1,000 or more units ⟹ C 2 = $ 45.00 \implies C_2 = \text{\textdollar}45.00 ⟹ C 2 = $ 45.00 per unit
Determine whether the company should take advantage of the discount.
Solution:
Step 1: Compute EOQ for Tier 2 ( C 2 = $ 45.00 C_2 = \text{\textdollar}45.00 C 2 = $ 45.00 ): H 2 = i × C 2 = 0.20 × $ 45.00 = $ 9.00 /unit-year H_2 = i \times C_2 = 0.20 \times \text{\textdollar}45.00 = \text{\textdollar}9.00\text{/unit-year} H 2 = i × C 2 = 0.20 × $ 45.00 = $ 9.00 /unit-year E O Q 2 = 2 ( 5 , 000 ) ( 180 ) 9.00 = 1 , 800 , 000 9.00 = 200 , 000 ≈ 447.21 units EOQ_2 = \sqrt{\frac{2(5,000)(180)}{9.00}} = \sqrt{\frac{1,800,000}{9.00}} = \sqrt{200,000} \approx 447.21\text{ units} EO Q 2 = 9.00 2 ( 5 , 000 ) ( 180 ) = 9.00 1 , 800 , 000 = 200 , 000 ≈ 447.21 units
Because 447 < 1 , 000 447 < 1,000 447 < 1 , 000 , E O Q 2 EOQ_2 EO Q 2 is infeasible ; the firm cannot buy 447 units at $45.00. The lowest order quantity to qualify for Tier 2 is the breakpoint q 2 = 1 , 000 q_2 = 1,000 q 2 = 1 , 000 units.
Step 2: Compute EOQ for Tier 1 ( C 1 = $ 50.00 C_1 = \text{\textdollar}50.00 C 1 = $ 50.00 ): H 1 = i × C 1 = 0.20 × $ 50.00 = $ 10.00 /unit-year H_1 = i \times C_1 = 0.20 \times \text{\textdollar}50.00 = \text{\textdollar}10.00\text{/unit-year} H 1 = i × C 1 = 0.20 × $ 50.00 = $ 10.00 /unit-year E O Q 1 = 2 ( 5 , 000 ) ( 180 ) 10.00 = 1 , 800 , 000 10.00 = 180 , 000 ≈ 424.26 units EOQ_1 = \sqrt{\frac{2(5,000)(180)}{10.00}} = \sqrt{\frac{1,800,000}{10.00}} = \sqrt{180,000} \approx 424.26\text{ units} EO Q 1 = 10.00 2 ( 5 , 000 ) ( 180 ) = 10.00 1 , 800 , 000 = 180 , 000 ≈ 424.26 units
Because 1 ≤ 424 < 1 , 000 1 \le 424 < 1,000 1 ≤ 424 < 1 , 000 , E O Q 1 = 424 EOQ_1 = 424 EO Q 1 = 424 is feasible in Tier 1.
Step 3: Compare Total Annual Costs including acquisition costs:
Total Cost at E O Q 1 = 424 EOQ_1 = 424 EO Q 1 = 424 units ( C 1 = $ 50.00 C_1 = \text{\textdollar}50.00 C 1 = $ 50.00 ): T C ( 424 ) = D ⋅ C 1 + D Q S + Q 2 H 1 TC(424) = D \cdot C_1 + \frac{D}{Q}S + \frac{Q}{2}H_1 TC ( 424 ) = D ⋅ C 1 + Q D S + 2 Q H 1 T C ( 424 ) = 5 , 000 ( 50.00 ) + 5 , 000 424 ( 180 ) + 424 2 ( 10.00 ) TC(424) = 5,000(50.00) + \frac{5,000}{424}(180) + \frac{424}{2}(10.00) TC ( 424 ) = 5 , 000 ( 50.00 ) + 424 5 , 000 ( 180 ) + 2 424 ( 10.00 ) T C ( 424 ) = 250 , 000 + 2 , 122.64 + 2 , 120.00 = $ 254,242.64 TC(424) = 250,000 + 2,122.64 + 2,120.00 = \text{\textdollar}254{,}242.64 TC ( 424 ) = 250 , 000 + 2 , 122.64 + 2 , 120.00 = $ 254 , 242.64
Total Cost at Breakpoint Q = 1 , 000 Q = 1,000 Q = 1 , 000 units ( C 2 = $ 45.00 C_2 = \text{\textdollar}45.00 C 2 = $ 45.00 ): T C ( 1 , 000 ) = D ⋅ C 2 + D Q S + Q 2 H 2 TC(1,000) = D \cdot C_2 + \frac{D}{Q}S + \frac{Q}{2}H_2 TC ( 1 , 000 ) = D ⋅ C 2 + Q D S + 2 Q H 2 T C ( 1 , 000 ) = 5 , 000 ( 45.00 ) + 5 , 000 1 , 000 ( 180 ) + 1 , 000 2 ( 9.00 ) TC(1,000) = 5,000(45.00) + \frac{5,000}{1,000}(180) + \frac{1,000}{2}(9.00) TC ( 1 , 000 ) = 5 , 000 ( 45.00 ) + 1 , 000 5 , 000 ( 180 ) + 2 1 , 000 ( 9.00 ) T C ( 1 , 000 ) = 225 , 000 + 900.00 + 4 , 500.00 = $ 230,400.00 TC(1,000) = 225,000 + 900.00 + 4,500.00 = \text{\textdollar}230{,}400.00 TC ( 1 , 000 ) = 225 , 000 + 900.00 + 4 , 500.00 = $ 230 , 400.00
Conclusion: Ordering Q ∗ = 1 , 000 Q^* = 1,000 Q ∗ = 1 , 000 units at the breakpoint saves the company $254,242.64 - $230,400.00 = $23,842.64 per year (a 9.4% total cost reduction), driven overwhelmingly by the $25,000 direct purchase discount which easily overcomes the $2,380 increase in annual inventory carrying cost.