3.2 Project Planning & Control: Scope and WBS, Gantt Charts, Critical Chain (CCPM), Risk & Earned Value

PE Industrial and Systems Exam

Track your progress as you read

Finished sections get a check mark.

1 Exam Overview, Strategy & Systems Foundations

1.1 PE Industrial Exam Format, Official Specification & Reference Handbook Strategy 1.2 System Analysis Tools, Process Definition, Requirements Engineering & QFD 1.3 Performance Measures: Output, Productivity, OEE, Cost & Environmental Sustainability 1.4 Process Types (Discrete, Continuous, Manufacturing, Service) & Value Analysis/Engineering

2 Optimization, Queueing, Simulation, Networks & Markov Chains

2.1 Linear Programming Formulation, Graphical Solutions & Sensitivity Analysis 2.2 Queueing Theory Models (M/M/1, M/M/s) & Little's Law Applications 2.3 Discrete-Event Simulation, Random Variates & Model Validation 2.4 Graph Theory & Network Models: Shortest Path, Minimal Spanning Tree & Maximum Flow 2.5 Markov Chains: Transition Matrices, Steady-State Probabilities & Absorbing States 2.6 Decision Trees, Expected Value & Bottleneck Analysis (Theory of Constraints)

3 Project Management & Planning

3.1 Project Scheduling with CPM and PERT: Critical Path, Float, Probability & Crashing 3.2 Project Planning & Control: Scope and WBS, Gantt Charts, Critical Chain (CCPM), Risk & Earned Value

4 Facility Layout, Space, Capacity & Material Handling

4.1 Systematic Layout Planning (SLP) & Activity Relationship (REL) Analysis 4.2 Workstation Design, Aisle Sizing & Space Requirements Planning 4.3 Capacity Analysis: Machine Requirements, Scrap Allowances & Personnel Requirements 4.4 Material Handling Equipment Selection, Unit Loads & Handling Principles

5 Site Location, Warehousing & Facility Economics

5.1 Facility Location Models: Center of Gravity & Minisum / Minimax Distance 5.2 Warehousing Systems, Storage Assignment & Order Picking Operations 5.3 Facility Life-Cycle Economics, Replacement Analysis & Rearrangement Costs

6 Demand Forecasting, Production Planning, MRP & JIT

6.1 Demand Forecasting Methods: Moving Averages, Exponential Smoothing & Error Metrics 6.2 Aggregate Planning Strategies & Master Production Scheduling (MPS) 6.3 Material Requirements Planning (MRP), Bill of Materials & Capacity Planning 6.4 Just-in-Time & Lean Production Planning: Pull Systems, Kanban Sizing, Heijunka & SMED

7 Inventory Systems, Scheduling, Logistics & Transportation Modes

7.1 Deterministic Inventory Control: Classical EOQ, EPQ & Quantity Discounts 7.2 Stochastic Inventory Management: Safety Stock, Continuous / Periodic Review & Newsvendor 7.3 Production Sequencing, Dispatching Rules & Johnson's Algorithm 7.4 Supply Chain Logistics, Transportation Simplex & Distribution Network Design 7.5 Transportation Modes, Freight Economics & the Transshipment Model

8 Engineering Economics, Break-Even Analysis & Costing Systems

8.1 Equivalence, Cash Flow Analysis & Discounted Cash Flow Metrics (PW, FW, EAC) 8.2 Rate of Return Analysis (IRR, Incremental IRR) & Benefit-Cost (B/C) Ratios 8.3 Asset Depreciation (MACRS, Straight-Line), Tax Effects & Replacement Decisions 8.4 Break-Even Analysis, Technical Capability Assessment & Costing Systems (Traditional, ABC & Standard Costs)

9 Methods Engineering, Work Measurement, Learning Curves, Line Balancing & Process Planning

9.1 Methods Analysis, Process Charting & Motion Study (Therbligs, 5S) 9.2 Worker–Machine (Man–Machine) Charts, Multiple Activity Analysis & Synchronous Servicing 9.3 Time Study Fundamentals, Performance Rating & Allowance Factors 9.4 Predetermined Motion Time Systems (PMTS, MTM, MOST) & Work Sampling 9.5 Learning Curves: Unit and Cumulative-Average Models, Learning Rates & Applications 9.6 Assembly Line Balancing, Precedence Constraints & Efficiency Heuristics 9.7 Manufacturing & Service Process Planning: Operation Selection, Sequencing, Route Sheets, Fixturing & Mistake Proofing

10 Ergonomics, Human Capacity, Occupational Safety & DART Rates

10.1 Anthropometry, Percentile Design, Workstation Ergonomics & Link Analysis 10.2 Industrial Biomechanics, the NIOSH Lifting Equation & Lifting Aids 10.3 Limits of Human Capacity & Risk-Factor Tools: Work Physiology, Strength, Range of Motion, Vision, RULA & Slip Resistance 10.4 Environmental Ergonomics (Noise, Heat, Illumination), Human-Machine Systems & OSHA Safety 10.5 Safety Codes, Standards & Voluntary Guidelines (OSHA, ANSI, NIOSH, MIL-STD) and DART Rate Calculations

11 Statistical Process Control & Process Capability

11.1 Statistical Process Control for Variables (X-bar/R and X-bar/s Charts) 11.2 Statistical Process Control for Attributes (p, np, c, and u Charts) 11.3 Process Capability Indices (Cp, Cpk, Cpm, Pp, Ppk) & Sigma Levels

12 Design of Experiments, Acceptance Sampling & Quality Systems

12.1 Design of Experiments: 2^k Factorials, ANOVA & Taguchi Robust Design 12.2 Acceptance Sampling: OC Curves, AQL, LTPD, AOQL, Z1.4/MIL-STD-105E & Dodge-Romig 12.3 Quality Systems (Deming, TQM, ISO 9000, Benchmarking), Root Cause Analysis & DMAIC

13 Reliability Engineering & Maintenance Systems

13.1 Reliability Modeling, Failure Rates (lambda) & Life Distributions (Exponential, Weibull) 13.2 System Reliability Architecture: Series, Parallel, k-out-of-n & Redundancy 13.3 Equipment Maintenance Engineering, Availability (A), MTBF/MTTR & RCM

3.2 Project Planning & Control: Scope and WBS, Gantt Charts, Critical Chain (CCPM), Risk & Earned Value

Key Takeaways Explain This Topic AI

A work breakdown structure decomposes 100% of the project scope into deliverables and work packages; changes to scope go through formal change control to prevent scope creep.

Critical chain project management uses aggressive activity estimates, protects the chain with a project buffer at the end, adds feeding buffers where other chains join, and manages by buffer consumption.

A risk's expected monetary value is probability times impact, and the sum of expected values across identified risks is a common basis for a contingency reserve.

Earned value analysis uses CV = EV − AC, SV = EV − PV, CPI = EV ÷ AC, and SPI = EV ÷ PV; a CPI or SPI below 1.0 means over budget or behind schedule.

If current cost performance continues, the estimate at completion is EAC = BAC ÷ CPI.

Last updated: October 2026

3.2 Project Planning & Control

Schedule math is only part of project management. The NCEES specification also lists scope, cost, risk analysis, Gantt charts, and CCPM . Industrial engineers manage plant expansions, equipment installations, ERP rollouts, and improvement programs, and all of them are judged on scope, time, and cost.

1. Scope and the Work Breakdown Structure (WBS)

The scope statement defines deliverables, acceptance criteria, exclusions, assumptions, and constraints. The work breakdown structure decomposes that scope into deliverables and then into work packages small enough to estimate, schedule, and assign.

The 100% rule: the WBS includes all of the work in the scope, and only that work. Each level must add up exactly to its parent.

Work package size: a common rule of thumb is between 8 and 80 hours of effort, or no longer than one reporting period.

Scope creep is uncontrolled growth in scope. Prevent it with a baseline and a change control process: a change request is evaluated for its effect on cost, schedule, and risk and is approved or rejected, often by a change control board.

The triple constraint links scope, time, and cost. Changing one changes at least one of the others or the quality of the result.

2. Gantt Charts and Resource Leveling

A Gantt chart (named for Henry Gantt) draws each activity as a horizontal bar on a calendar, often with precedence arrows, milestones, and a progress line. It is easy to read for status reporting, but on its own it hides float and dependencies, which is why it is usually built from a CPM network. Using the project from the previous section (weeks): Activity Wk: 0 2 4 6 8 10 12 14

  • A Design ████████ (critical)
  • B Order robot ████████████░░ (1 wk float)
  • C Fixtures ████████████░░░░ (2 wk float)
  • D Floor prep ██████ (critical)
  • E Install ██████████ (critical)
  • F Test ████ (critical)
  • ░ = total float

Resource leveling shifts activities within their float so that resource use (crews, cranes, budget) does not exceed limits or swing sharply. Leveling that needs more than the available float lengthens the project. Resource conflicts can also make the "critical path" a resource chain rather than a pure precedence chain, which is the starting point for CCPM.

3. Critical Chain Project Management (CCPM)

Eliyahu Goldratt's Critical Chain (1997) applies the Theory of Constraints to projects. It argues that individual estimates hide large safety margins that are then wasted, because people start late (student syndrome), work expands to fill the time (Parkinson's law), and early finishes are not passed on.

CCPM practice:

Aggressive estimates: schedule each task at roughly a 50% confidence duration, often about half of the padded estimate.

Critical chain: the longest chain of dependent tasks considering both precedence and resource conflicts .

Project buffer: pool the removed safety into one buffer at the end of the critical chain.

Feeding buffers: place buffers where non-critical chains feed the critical chain, so their delays do not reach it.

Resource buffers: alert critical-chain resources before they are needed.

Buffer management: track buffer consumed against chain completed (a "fever chart"). Green means no action, yellow means plan recovery, and red means act.

Buffer sizing example. A critical chain has four tasks with padded estimates of 10, 8, 12, and 6 days (36 days total). Aggressive estimates of half each total 18 days, so the safety removed is 5, 4, 6, and 3 days.

Cut-and-paste method: buffer = 50% of the chain = 9 days, so the plan is 18 + 9 = 27 days .

Root-square-error method: buffer = 5 2 + 4 2 + 6 2 + 3 2 = 86 = 9.3 \sqrt{5^2 + 4^2 + 6^2 + 3^2} = \sqrt{86} = 9.3 5 2 + 4 2 + 6 2 + 3 2 ​ = 86 ​ = 9.3 days. Pooling works because tasks rarely all overrun at once.

Either way, the promised date is well under the 36 days obtained by adding padded estimates.

4. Project Risk Analysis

Risk management cycle: identify risks, assess probability and impact, plan responses, and monitor.

  • Response Threats Opportunities
  • Remove the uncertainty Avoid (change the plan) Exploit (make sure it happens)
  • Change probability or impact Mitigate Enhance
  • Give it to another party Transfer (insurance, fixed-price subcontract) Share (partnership)
  • Do nothing in advance Accept (passively, or actively with a reserve) Accept

A probability-impact matrix scores each risk (for example 1 to 5 on each scale) to rank them. For quantitative analysis, compute each risk's expected monetary value (EMV) :

E M V = P ( event ) × Impact EMV = P(\text{event}) \times \text{Impact} EM V = P ( event ) × Impact

Example:

Late robot delivery: 20% chance, $50,000 impact, EMV = $10,000.

Floor rework: 10% chance, $80,000 impact, EMV = $8,000.

An energy rebate (an opportunity): 30% chance of saving $20,000, EMV = −$6,000.

The net expected cost is $12,000, a reasonable starting contingency reserve. Decision trees and Monte Carlo schedule simulation extend the same idea.

5. Cost Control with Earned Value Management (EVM)

EVM combines scope, schedule, and cost into three measures, all in dollars:

PV (planned value): budgeted cost of work scheduled to date.

EV (earned value): budgeted cost of work actually performed (percent complete × BAC).

AC (actual cost): what that work actually cost.

BAC (budget at completion): the total budget.

  • Measure Formula Meaning when unfavorable
  • Cost variance C V = E V − A C CV = EV - AC C V = E V − A C Negative means over budget
  • Schedule variance S V = E V − P V SV = EV - PV S V = E V − P V Negative means behind schedule
  • Cost performance index C P I = E V / A C CPI = EV / AC CP I = E V / A C Below 1.0 means over budget
  • Schedule performance index S P I = E V / P V SPI = EV / PV SP I = E V / P V Below 1.0 means behind schedule

Estimate at completion E A C = B A C / C P I EAC = BAC / CPI E A C = B A C / CP I (if current cost performance continues) Forecast final cost

Estimate to complete E T C = E A C − A C ETC = EAC - AC ETC = E A C − A C Cost still needed

Variance at completion V A C = B A C − E A C VAC = BAC - EAC V A C = B A C − E A C Expected overrun if negative

To-complete performance index T C P I = ( B A C − E V ) / ( B A C − A C ) TCPI = (BAC - EV)/(BAC - AC) TCP I = ( B A C − E V ) / ( B A C − A C ) Efficiency needed to finish on budget

Worked example. A $200,000, 10-week automation project is reviewed at week 5. PV = $100,000, the work is 45% complete so EV = $90,000, and AC = $110,000.

C V = 90,000 − 110,000 = − $ 20,000 CV = 90{,}000 - 110{,}000 = -\text{\textdollar}20{,}000 C V = 90 , 000 − 110 , 000 = − $ 20 , 000 (over budget)

S V = 90,000 − 100,000 = − $ 10,000 SV = 90{,}000 - 100{,}000 = -\text{\textdollar}10{,}000 S V = 90 , 000 − 100 , 000 = − $ 10 , 000 (behind schedule)

C P I = 90,000 / 110,000 = 0.818 CPI = 90{,}000 / 110{,}000 = 0.818 CP I = 90 , 000/110 , 000 = 0.818 and S P I = 0.90 SPI = 0.90 SP I = 0.90

E A C = 200,000 / 0.818 = $ 244,444 EAC = 200{,}000 / 0.818 = \text{\textdollar}244{,}444 E A C = 200 , 000/0.818 = $ 244 , 444 , so V A C = − $ 44,444 VAC = -\text{\textdollar}44{,}444 V A C = − $ 44 , 444 and E T C = $ 134,444 ETC = \text{\textdollar}134{,}444 ETC = $ 134 , 444

T C P I = ( 200,000 − 90,000 ) / ( 200,000 − 110,000 ) = 1.22 TCPI = (200{,}000 - 90{,}000)/(200{,}000 - 110{,}000) = 1.22 TCP I = ( 200 , 000 − 90 , 000 ) / ( 200 , 000 − 110 , 000 ) = 1.22

Finishing on budget would require 22% better cost efficiency than planned for the rest of the project, while the team is currently 18% worse. That is unrealistic, so management should rebaseline the budget or reduce scope through change control.