Shop Drawings, Submittals, RFIs, and Delegated Design

PE Civil: Structural Exam

Track your progress as you read

Finished sections get a check mark.

1 Exam Identity and Reference Workflow

2026 PE Civil: Structural Identity, Format, and Scoring Electronic Handbook, Design Standards, Units, and Version Control

2 Chapter 2: Gravity and Construction Loads

2.1 Dead Loads and Self-Weight 2.2 Live Loads, Reduction, and Load Placement 2.3 Construction-Stage Loads

3 Environmental Loads

Wind Loads and Pressure Paths Seismic Loads and Lateral Force Distribution Snow, Rain, and Ice Loads

4 Moving, Impact, and Lateral Soil Loads

Vehicular, Crane, and Other Moving Loads Impact and Dynamic Allowances Earth Pressure and Surcharge Loads

5 Chapter 5: Load Paths and Combinations

5.1 Tributary Areas and Complete Vertical/Lateral Load Paths 5.2 Strength and Service Load Combinations

6 Reactions, Diagrams, and Basic Axial Effects

Free-Body Diagrams, Reactions, Shear, and Moment Qualitative Diagrams, Influence Lines, and Critical Placement Axial Tension, Compression, and Deformation

7 Chapter 7: Axial Systems and Shear Effects

7.1 Trusses, Braces, and Column Axial Force 7.2 Shear Stress, Shear Flow, and Built-Up Sections 7.3 One-Way, Two-Way, Punching, and Interface Shear Effects

8 Flexure

Section Properties and Elastic Flexural Stress Beam and Slab Flexural Load Effects Biaxial and Unsymmetrical Flexure

9 Combined Stress and Deflection

Combined Axial and Flexural Stress Principal Stress, Mohr's Circle, and Combined Shear Elastic Deflection Methods

10 Chapter 10: Serviceability, Torsion, and Stability

10.1 Serviceability: Deflection, Drift, Vibration, and Ponding 10.2 Torsion and Warping Effects 10.3 Buckling, Effective Length, and Second-Order Stability

11 Fatigue, Robustness, Thermal, and Bearing Effects

Fatigue and Progressive-Collapse Concepts Thermal Deformation and Bearing/Contact Stress

12 Inspections, Submittals, and Adjacent Facilities

Special Inspections and Verification Duties Shop Drawings, Submittals, RFIs, and Delegated Design Construction Effects on Adjacent Facilities

13 Chapter 13: Temporary Works and Safety

13.1 Formwork, Falsework, Scaffolding, Shoring/Reshoring, Bracing, and Anchorage 13.2 Construction, Roadside, and Work-Zone Safety

14 Soils and Core Concrete Properties

Soil Phase Relationships and Classification Soil Strength, Permeability, and Compressibility Fresh and Hardened Concrete Properties

15 Chapter 15: Prestressed Concrete and Steel Properties

15.1 Reinforced, Precast, Pretensioned, and Post-Tensioned Concrete Materials 15.2 Structural and Cold-Formed Steel Properties 15.3 Steel Toughness, Weldability, Corrosion, and Temperature Effects

16 Timber, Masonry, and Material Conformance

Timber Properties and ASD Design Values Masonry, CMU, Mortar, Grout, and Brick Veneer Properties Concrete and Masonry Test Methods Steel, Timber, and Other Material Specification Conformance

17 Horizontal Members I

Steel Beams and Girders Reinforced Concrete Beams and Slabs Timber and Masonry Horizontal Members

18 Chapter 18: Diaphragms and Vertical Members

18.1 Diaphragms, Collectors, Struts, and Composite Slabs 18.2 Steel Columns and Beam-Columns 18.3 Concrete Columns and Bearing Walls

19 Shear Walls, Trusses, and Frames

Shear Walls and Vertical Lateral Members Trusses and Braced Systems Moment Frames and Stability Systems

20 Composite/Bridge Systems and Bolted Connections

Composite Construction and Structural System Selection Bridge Systems and Load Distribution Bolted Steel Connections

21 Chapter 21: Welded, Embedded, and Anchored Connections

21.1 Welded Steel Connections 21.2 Bearing, Embedded, and Precast Connections 21.3 Anchors, Post-Installed Anchors, and Wood/Masonry Connections

22 Shallow Foundations

Isolated, Spread, and Strip Footings Combined and Strap Footings Mat Foundations and Foundation Slabs

23 Deep Foundations

Driven Piles: Axial Capacity and Settlement Drilled Shafts, Piers, and Caissons Pile Groups, Caps, and Lateral Deep-Foundation Response

24 Chapter 24: Retaining Structures

24.1 Lateral Earth/Water Pressure and Drainage 24.2 Sliding, Overturning, Bearing, and Global Stability 24.3 Concrete Cantilever, Gravity, and Basement Walls 24.4 Sheet-Pile, Anchored, and Mechanically Stabilized Earth Walls

Shop Drawings, Submittals, RFIs, and Delegated Design

Key Takeaways Explain This Topic AI

Shop drawings and product data explain how proposed work will satisfy the design documents, but they are not blanket replacements for the approved construction documents

Submittal review checks the stated scope for general conformance with design intent and coordination; it does not transfer contractor means, methods, sequencing, safety, or dimensional-control duties

An RFI requests clarification and creates a record, but the question itself is not authorization to change installed work

Substitutions require documented technical evaluation and approval by the parties authorized to accept changes, including the building official when approved documents are affected

Deferred submittals require prior building-official approval, listing on construction documents, responsible-design-professional review, and approval before installation

Delegated design assigns a defined component design to a qualified specialty designer while the design professional of record retains criteria and overall-system coordination duties

Last updated: July 2026

Shop Drawings, Submittals, RFIs, and Delegated Design

For July 2026 exam questions, use IBC 2018 , ACI 318-14 , AISC 15th Edition , and the PCI Design Handbook, 7th Edition (2010) where applicable. Material references and contract documents set different duties; a “reviewed” stamp is not universal approval.

Identify the document and its purpose

Item Purpose Key control

Shop drawing or placing drawing Show fabrication, assembly, reinforcement placement, connections, dimensions, or installation details Must conform to design requirements and coordinated field information

Product data or sample Document proposed product characteristics or appearance Compare with specified performance and approved substitutions

RFI Ask a focused question about an ambiguity, conflict, or missing condition No change is authorized until an authorized response says so

Substitution request Propose a product, material, or system different from the specified basis Requires documented equivalency and formal acceptance

Deferred submittal Submit a permitted design portion after the initial permit package Follow IBC 2018 prior-approval, review, forwarding, and installation rules

Delegated-design package Provide specialty calculations and documents for a defined design scope Qualified specialty designer works from criteria set by the design professional of record

Shop drawings are prepared by or for the contractor, fabricator, supplier, or specialty entity to translate the design into producible and installable information. They supplement communication but do not silently amend the permitted design.

A disciplined submittal workflow

Contractor coordination: verify field dimensions, fabrication, interfaces, and marked deviations before forwarding.

Design review: check the assigned scope for general conformance, structural criteria, interfaces, and deviations.

Disposition: record an unambiguous review status and any required resubmission.

Code approval: forward deferred or revised documents through the required channel.

Field control: release the current approved revision and remove superseded sheets.

Review does not ordinarily relieve the contractor of fabrication accuracy, field measurements, coordination, sequencing, or safe means and methods. It also does not transfer the construction-document designer's responsibility. Review should identify a recognized design conflict but is not exhaustive checking of every dimension.

RFIs and substitutions

An RFI should identify the drawing or specification location, describe the conflict, explain schedule impact, and, if useful, present a proposed resolution clearly labeled as a proposal. The RFI is a question, not a change order or revised design. The response should come from the party authorized to interpret or modify the design and should state whether revised calculations, drawings, pricing, or building-official review are required. Incorporate accepted changes into controlled project records.

A substitution is more than an RFI with a product name. Evaluate geometry, loads and load path, strength, stiffness, durability, fire resistance, interfaces, testing or evaluation reports, availability, and effects on other trades. If an anchor system, precast connection, steel grade, or reinforcement layout changes an approved design, formal design review and possibly revised permit documents are needed. “Equal strength” alone may miss stiffness, ductility, edge distance, installation, or inspection requirements.

Deferred submittals under IBC 2018

IBC 2018 defines a deferred submittal as a portion of the design not submitted with the initial permit application but submitted within a specified time. Deferral requires prior approval by the building official. The registered design professional in responsible charge lists deferred items on the construction documents.

The deferred package goes to that design professional for review. After finding it in general conformance with the building design , the design professional forwards it to the building official with that notation. The item must not be installed until the building official approves the deferred documents. Calling a late shop drawing “deferred” does not legalize an unapproved installation.

Delegated design without wholesale transfer

Delegated design assigns a defined component or system portion to a qualified specialty registered design professional. The design professional of record establishes the design criteria and interfaces needed for that portion: governing loads and combinations, performance, geometry, support conditions, movement compatibility, materials, and connection assumptions. The specialty designer performs the delegated analysis, prepares signed and sealed documents where required, and coordinates its boundaries.

The design professional of record reviews the package for general conformance with the overall building design. That review does not make the record designer the specialty designer of the delegated calculations. Conversely, delegation does not transfer responsibility for overall structural criteria, incomplete interfaces, or the remainder of the building to the specialty designer. A delegated component may also be a deferred submittal, but the terms are not synonyms: one describes design responsibility; the other describes permit timing.

Scenario: precast connection conflict

Suppose a precast cladding support is a listed deferred, delegated item. The construction documents give design forces, allowable movement, supporting-edge geometry, and durability criteria. The specialty engineer designs the connection and submits calculations and shop drawings through the contractor. The record engineer finds general conformance, and the building official approves the package before installation.

In the field, the contractor discovers that the approved anchor conflicts with reinforcement. The crew proposes moving the anchor 4 in and drilling a new hole. The proper response is to stop that affected installation, document the conflict in an RFI, and route it to the authorized designers. The specialty engineer evaluates the changed eccentricity and edge distance; the record engineer evaluates the supporting member and overall interface; revised approval is obtained as required. A shop-drawing review stamp did not preapprove an arbitrary relocation, and a verbal field suggestion does not replace controlled revision.

Exam decision test

Ask four questions: What document is this? Who prepared it? Who has authority to approve the specific issue? Has the approved change reached the current field set? Correct answers preserve the contractor's control of construction, the specialty designer's defined scope, the record professional's system responsibility, and the building official's approval role.