Study guide
10.1 Sampling, Testing, and Soil Stabilization
PE Civil: Transportation Exam
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: Project Management
1.1 Quantity and Cost Estimating 1.2 Project Scheduling and CPM 1.3 Engineering Economic Analysis
2 Chapter 2: Traffic Engineering - Capacity and Flow
2.1 Uninterrupted Flow Capacity and Level of Service (LOS) 2.2 Interrupted Flow on Segment Streets 2.3 Intersection Capacity and LOS 2.4 Nonmotorized Facilities Analysis
3 Chapter 3: Traffic Engineering - Studies and Safety
3.1 Traffic Volume, Speed, and Planning Studies 3.2 Traffic Forecasts and Monitoring 3.3 Traffic Safety and Collision Analysis 3.4 Highway Safety and Crash Modification Factors (CMFs)
4 Chapter 4: Roadside and Cross-Section Design
4.1 Forgiving Roadside and Clear Zone Design 4.2 Barrier Design and Length of Need 4.3 Cross-Section Design Elements 4.4 Nonmotorized Design Considerations
5 Chapter 5: Horizontal Alignment Design
5.1 Circular Curve Elements and Calculations 5.2 Design Speed and Superelevation Design 5.3 Horizontal Sight Distance and Obstructions
6 Chapter 6: Vertical Alignment Design
6.1 Grades, Slopes, and Profile Design 6.2 Crest Vertical Curve Geometry and Sight Distance 6.3 Sag Vertical Curve Geometry and Sight Distance 6.4 Vertical Clearance Under Structures
7 Chapter 7: Intersection Geometry and Layout
7.1 At-Grade Intersection Design and Roundabouts 7.2 Intersection Sight Distance and Sight Triangles 7.3 Interchange Ramps and Terminal Geometry
8 Chapter 8: Traffic Signals
8.1 Traffic Signal Timing and Phasing 8.2 Traffic Signal Warrants (MUTCD) 8.3 Traffic Signal Design and Preemption
9 Chapter 9: Traffic Control Design
9.1 Permanent Signing Design and Standards 9.2 Pavement Marking Layout and Rules 9.3 Temporary Traffic Control and Work Zones
10 Chapter 10: Geotechnical and Pavements
10.1 Sampling, Testing, and Soil Stabilization 10.2 Fundamental Soil Properties and Mass Balance 10.3 Compaction, Excavation, and Mass Diagrams 10.4 Flexible and Rigid Pavement Design and ESALs
11 Chapter 11: Hydrology and Open-Channel Drainage
11.1 Rainfall Hydrology and Rational Method 11.2 Open-Channel Flow and Manning's Equation 11.3 Peak Flow Mitigation and Water-Quality
12 Chapter 12: Drainage Structures and Systems
12.1 Culvert Design and Inlet/Outlet Control 12.2 Stormwater Collection Systems and Inlet Capacities
10.1 Sampling, Testing, and Soil Stabilization
Key Takeaways Explain This Topic AI
USCS distinguishes coarse (>50% retained on No. 200) from fine soils (>=50% passing). The A-line is PI = 0.73(LL - 20).
AASHTO uses A-1 to A-7 groups. Group Index (GI) is GI = (F-35)[0.2 + 0.005(LL-40)] + 0.01(F-15)(PI-10). Excellent subgrades have GI = 0, poor subgrades GI >= 20.
Modified Proctor uses 56,250 ft-lb/ft3 of energy (5 layers, 25 blows, 10-lb hammer, 18-in drop), 4.5 times standard Proctor energy.
Resilient Modulus (Mr) is Mr = 1,500 * CBR for fine-grained soils with CBR <= 10, or Mr = 1,200 * R + 448 for R-value.
Lime stabilization works via cation exchange and pozzolanic reactions, requiring clay soils with PI > 10 and clay content > 25%.
Last updated: July 2026
10.1 Sampling, Testing, and Soil Stabilization
Characterizing and improving the subgrade is the foundation of transportation engineering. Subgrade soils must support pavement layers under dynamic traffic loads without excessive deformation.
Soil Classification Systems
Engineers classify soils to predict engineering behavior using two primary systems: the Unified Soil Classification System (USCS) and the AASHTO classification system.
Unified Soil Classification System (USCS)
USCS (ASTM D2487) categorizes soils based on grain size and plasticity. Soils are coarse-grained if > 50 % >50\% > 50% is retained on the No. 200 sieve ( 0.075 mm 0.075\text{ mm} 0.075 mm ), and fine-grained if ≥ 50 % \ge 50\% ≥ 50% passes.
Coarse fraction division: Gravels (G) if > 50 % >50\% > 50% of the coarse fraction is retained on the No. 4 sieve ( 4.75 mm 4.75\text{ mm} 4.75 mm ); Sands (S) if ≥ 50 % \ge 50\% ≥ 50% passes.
Grading Coefficients: Well-graded soils have smooth grain size distributions. Well-graded gravel (GW) requires C u ≥ 4 C_u \ge 4 C u ≥ 4 and 1 ≤ C c ≤ 3 1 \le C_c \le 3 1 ≤ C c ≤ 3 . Well-graded sand (SW) requires C u ≥ 6 C_u \ge 6 C u ≥ 6 and 1 ≤ C c ≤ 3 1 \le C_c \le 3 1 ≤ C c ≤ 3 . Otherwise, they are poorly graded (GP or SP). C u = D 60 D 10 , C c = ( D 30 ) 2 D 10 × D 60 C_u = \frac{D_{60}}{D_{10}}, \quad C_c = \frac{(D_{30})^2}{D_{10} \times D_{60}} C u = D 10 D 60 , C c = D 10 × D 60 ( D 30 ) 2
Plasticity Chart: If fines exceed 12 % 12\% 12% , classification uses the A-line: P I = 0.73 ( L L − 20 ) PI = 0.73(LL - 20) P I = 0.73 ( LL − 20 ) . Clays (C) plot above the A-line with P I > 7 PI > 7 P I > 7 ; silts (M) plot below or have P I < 4 PI < 4 P I < 4 .
AASHTO Soil Classification System
AASHTO M 145 is tailored for highway subgrades, classifying soils into groups A-1 (best) through A-7 (worst). Granular materials have ≤ 35 % \le 35\% ≤ 35% passing the No. 200 sieve; silt-clay materials have > 35 % >35\% > 35% .
Group Index (GI): Used to evaluate soils within a group: G I = ( F − 35 ) [ 0.2 + 0.005 ( L L − 40 ) ] + 0.01 ( F − 15 ) ( P I − 10 ) GI = (F - 35)[0.2 + 0.005(LL - 40)] + 0.01(F - 15)(PI - 10) G I = ( F − 35 ) [ 0.2 + 0.005 ( LL − 40 )] + 0.01 ( F − 15 ) ( P I − 10 ) where F F F is percent passing the No. 200 sieve. If G I < 0 GI < 0 G I < 0 , report 0 0 0 . Round to the nearest integer. For A-1-a, A-1-b, A-3, A-2-4, and A-2-5, G I = 0 GI = 0 G I = 0 . For A-2-6 and A-2-7, use only the partial formula: G I = 0.01 ( F − 15 ) ( P I − 10 ) GI = 0.01(F - 15)(PI - 10) G I = 0.01 ( F − 15 ) ( P I − 10 ) .
- Laboratory Compaction and Strength Testing
- Proctor Compaction Test
Determines the relationship between moisture content ( w w w ) and compacted dry unit weight ( γ d \gamma_d γ d ) to identify the Optimum Moisture Content (OMC) and Maximum Dry Density (MDD).
Standard Proctor (ASTM D698): 12 , 400 ft-lb/ft 3 12,400\text{ ft-lb/ft}^3 12 , 400 ft-lb/ft 3 energy ( 5.5 -lb 5.5\text{-lb} 5.5 -lb hammer, 12 -in 12\text{-in} 12 -in drop, 3 3 3 layers, 25 25 25 blows/layer).
Modified Proctor (ASTM D1557): 56 , 250 ft-lb/ft 3 56,250\text{ ft-lb/ft}^3 56 , 250 ft-lb/ft 3 energy ( 10 -lb 10\text{-lb} 10 -lb hammer, 18 -in 18\text{-in} 18 -in drop, 5 5 5 layers, 25 25 25 blows/layer).
Zero Air Voids (ZAV) Curve: The theoretical dry density at 100 % 100\% 100% saturation ( S = 1 S=1 S = 1 ): γ z a v = G s γ w 1 + w G s \gamma_{zav} = \frac{G_s \gamma_w}{1 + w G_s} γ z a v = 1 + w G s G s γ w
California Bearing Ratio (CBR)
Measures soil penetration resistance compared to standard crushed rock plunger tests at a rate of 0.05 in/min 0.05\text{ in/min} 0.05 in/min . C B R ( % ) = ( Stress at 0.1 in 1 , 000 psi ) × 100 or ( Stress at 0.2 in 1 , 500 psi ) × 100 CBR (\%) = \left( \frac{\text{Stress at } 0.1\text{ in}}{1,000\text{ psi}} \right) \times 100 \quad \text{or} \quad \left( \frac{\text{Stress at } 0.2\text{ in}}{1,500\text{ psi}} \right) \times 100 CBR ( % ) = ( 1 , 000 psi Stress at 0.1 in ) × 100 or ( 1 , 500 psi Stress at 0.2 in ) × 100
Hveem R-Value
Measures lateral pressure transmitted through compacted soil under vertical load in a Hveem stabilometer. R-values range from 0 0 0 (liquid) to 100 100 100 (rigid solid).
Soil Resilient Modulus ( M r M_r M r )
The resilient modulus ( M r M_r M r ) measures soil elastic response under cyclic traffic loading: M r = σ d ϵ r M_r = \frac{\sigma_d}{\epsilon_r} M r = ϵ r σ d
where σ d \sigma_d σ d is cyclic deviator stress and ϵ r \epsilon_r ϵ r is recoverable axial strain. Standard correlations for subgrade design include:
For fine-grained soils ( C B R ≤ 10 CBR \le 10 CBR ≤ 10 ): M r (psi) = 1 , 500 × C B R M_r\text{ (psi)} = 1,500 \times CBR M r (psi) = 1 , 500 × CBR
From R-value: M r (psi) = 1 , 200 × R + 448 M_r\text{ (psi)} = 1,200 \times R + 448 M r (psi) = 1 , 200 × R + 448
Chemical Soil Stabilization
When subgrades are unstable, chemical stabilizers are mixed into the soil.
Lime Stabilization: Adding quicklime (CaO) or hydrated lime ( C a ( O H ) 2 Ca(OH)_2 C a ( O H ) 2 ) to clay soils ( P I > 10 PI > 10 P I > 10 , clay content > 25 % >25\% > 25% ). Cation exchange and flocculation occur immediately, reducing plasticity. Long-term pozzolanic reactions form cementing calcium silicates (C-S-H) and aluminates (C-A-H).
Cement Stabilization: Adding Portland cement to granular or low-plasticity silty soils. Hydration forms C-S-H gels independent of clay minerals, binding soil grains.
Fly Ash Stabilization: Class C fly ash (self-cementing, > 20 % >20\% > 20% CaO) is used for silts and sands. Class F fly ash requires lime or cement as an activator.
Soil Classification Example
Scenario: A subgrade soil has 55 % 55\% 55% passing the No. 200 sieve, L L = 48 LL = 48 LL = 48 , and P L = 24 PL = 24 P L = 24 . Find the AASHTO and USCS classification.
Solution:
AASHTO: Silt-clay material ( > 35 % >35\% > 35% passing No. 200). P I = L L − P L = 48 − 24 = 24 PI = LL - PL = 48 - 24 = 24 P I = LL − P L = 48 − 24 = 24 . Since L L = 48 > 40 LL = 48 > 40 LL = 48 > 40 and P I = 24 > 10 PI = 24 > 10 P I = 24 > 10 , the group is A-7. Since P I = 24 > L L − 30 PI = 24 > LL - 30 P I = 24 > LL − 30 ( 18 18 18 ), the soil is A-7-6 .
Calculate Group Index (GI): G I = ( 55 − 35 ) [ 0.2 + 0.005 ( 48 − 40 ) ] + 0.01 ( 55 − 15 ) ( 24 − 10 ) = 20 ( 0.24 ) + 0.01 ( 40 ) ( 14 ) = 4.8 + 5.6 = 10.4 GI = (55 - 35)[0.2 + 0.005(48 - 40)] + 0.01(55 - 15)(24 - 10) = 20(0.24) + 0.01(40)(14) = 4.8 + 5.6 = 10.4 G I = ( 55 − 35 ) [ 0.2 + 0.005 ( 48 − 40 )] + 0.01 ( 55 − 15 ) ( 24 − 10 ) = 20 ( 0.24 ) + 0.01 ( 40 ) ( 14 ) = 4.8 + 5.6 = 10.4 Rounding to the nearest integer yields GI = 10 . Classification is A-7-6 (10) .
USCS: Fine soil ( > 50 % >50\% > 50% passing No. 200). L L = 48 < 50 LL = 48 < 50 LL = 48 < 50 . Check A-line limit: 0.73 ( L L − 20 ) = 0.73 ( 48 − 20 ) = 20.44 0.73(LL - 20) = 0.73(48 - 20) = 20.44 0.73 ( LL − 20 ) = 0.73 ( 48 − 20 ) = 20.44 . Since P I = 24 > 20.44 PI = 24 > 20.44 P I = 24 > 20.44 , the soil plots above the A-line. Classification is CL (Lean Clay) .