5.2 Design Speed and Superelevation Design
PE Civil: Transportation Exam
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: Project Management
1.1 Quantity and Cost Estimating 1.2 Project Scheduling and CPM 1.3 Engineering Economic Analysis
2 Chapter 2: Traffic Engineering - Capacity and Flow
2.1 Uninterrupted Flow Capacity and Level of Service (LOS) 2.2 Interrupted Flow on Segment Streets 2.3 Intersection Capacity and LOS 2.4 Nonmotorized Facilities Analysis
3 Chapter 3: Traffic Engineering - Studies and Safety
3.1 Traffic Volume, Speed, and Planning Studies 3.2 Traffic Forecasts and Monitoring 3.3 Traffic Safety and Collision Analysis 3.4 Highway Safety and Crash Modification Factors (CMFs)
4 Chapter 4: Roadside and Cross-Section Design
4.1 Forgiving Roadside and Clear Zone Design 4.2 Barrier Design and Length of Need 4.3 Cross-Section Design Elements 4.4 Nonmotorized Design Considerations
5 Chapter 5: Horizontal Alignment Design
5.1 Circular Curve Elements and Calculations 5.2 Design Speed and Superelevation Design 5.3 Horizontal Sight Distance and Obstructions
6 Chapter 6: Vertical Alignment Design
6.1 Grades, Slopes, and Profile Design 6.2 Crest Vertical Curve Geometry and Sight Distance 6.3 Sag Vertical Curve Geometry and Sight Distance 6.4 Vertical Clearance Under Structures
7 Chapter 7: Intersection Geometry and Layout
7.1 At-Grade Intersection Design and Roundabouts 7.2 Intersection Sight Distance and Sight Triangles 7.3 Interchange Ramps and Terminal Geometry
8 Chapter 8: Traffic Signals
8.1 Traffic Signal Timing and Phasing 8.2 Traffic Signal Warrants (MUTCD) 8.3 Traffic Signal Design and Preemption
9 Chapter 9: Traffic Control Design
9.1 Permanent Signing Design and Standards 9.2 Pavement Marking Layout and Rules 9.3 Temporary Traffic Control and Work Zones
10 Chapter 10: Geotechnical and Pavements
10.1 Sampling, Testing, and Soil Stabilization 10.2 Fundamental Soil Properties and Mass Balance 10.3 Compaction, Excavation, and Mass Diagrams 10.4 Flexible and Rigid Pavement Design and ESALs
11 Chapter 11: Hydrology and Open-Channel Drainage
11.1 Rainfall Hydrology and Rational Method 11.2 Open-Channel Flow and Manning's Equation 11.3 Peak Flow Mitigation and Water-Quality
12 Chapter 12: Drainage Structures and Systems
12.1 Culvert Design and Inlet/Outlet Control 12.2 Stormwater Collection Systems and Inlet Capacities
5.2 Design Speed and Superelevation Design
Key Takeaways Explain This Topic AI
The minimum radius equation is R = V^2 / (15 * (e + f)) in USCS and R = V^2 / (127 * (e + f)) in metric units.
Maximum side friction factors (f_max) decrease as design speed increases to protect driver comfort.
The transition length consists of Tangent Runout (L_t) and Superelevation Runoff (L_r), with L_t = (e_NC / e_d) * L_r.
Standard AASHTO design places 2/3 of the superelevation runoff on the tangent before the PC and 1/3 on the curve.
Maximum superelevation rate (e_max) is typically capped at 6% or 8% in regions prone to ice and snow to prevent slow vehicles from sliding.
Last updated: July 2026
5.2 Design Speed and Superelevation Design
When a vehicle travels around a horizontal curve, it experiences centrifugal force that acts to push the vehicle radially outward. To maintain safety, stability, and passenger comfort, transportation engineers must counter this force. This is accomplished through a combination of two elements: the superelevation rate (e), which is the cross-slope of the road tilted inward, and the side friction factor (f), which represents the friction developed between the vehicle’s tires and the wet pavement surface.
The Minimum Radius Equation
The fundamental relationship governing vehicle stability on a horizontal curve is derived from the balance of lateral forces in circular motion. Under the AASHTO design guidelines (commonly referred to as the Green Book) and the NCEES PE Civil Reference Handbook, the minimum radius of curvature (R_min) for a given design speed (V) is determined using the following formula:
R = V^2 / (15 * (e + f))
Where:
- R = Radius of the curve (feet)
- V = Design speed of the highway (miles per hour, mph)
- e = Superelevation rate (expressed as a decimal, e.g., 0.06 for 6%)
- f = Side friction factor (dimensionless decimal)
Note
For SI units, the formula is:
R = V^2 / (127 * (e + f))
Where R is in meters and V is in kilometers per hour (km/h). Ensure you verify the units of the inputs on the exam before selecting a formula.
Side Friction and Speed Relationship
The maximum allowable side friction factor (f_max) is not constant; it decreases as the design speed increases. This is a design decision based on driver comfort and vehicle handling characteristics. At higher speeds, passengers feel lateral acceleration more intensely, and tire-pavement friction capacity decreases. Typical values for f_max defined by AASHTO are summarized below:
- Design Speed (V, mph) Maximum Side Friction (f_max) Maximum Relative Gradient (Delta, %)
- 20 0.30 0.74
- 30 0.20 0.66
- 40 0.16 0.58
- 50 0.14 0.50
- 60 0.12 0.45
- 70 0.10 0.40
- 80 0.08 0.35
- Maximum Superelevation Rate (e_max)
The selection of the maximum superelevation rate (e_max) is governed by environmental and operational factors:
Climate and Icing : In regions subject to snow and ice, e_max is typically limited to 6% or 8%. This prevents slow-moving or stopped vehicles (such as heavy trucks or maintenance equipment) from sliding down the banked pavement toward the inside of the curve when the road is icy.
Terrain and Context : In rural areas with rolling or mountainous terrain and no ice, e_max up to 10% or 12% may be permitted to minimize earthwork. In contrast, urban areas with low-speed traffic, intersections, driveways, and pedestrian crossings typically limit e to 4% or 6% to facilitate cross-street alignments and avoid uneven sidewalk grades.
Superelevation Transition Layout
A roadway cannot transition instantly from a normal crown cross-slope (typically -2.0% for drainage) to the full design superelevation rate (e_d). This transition must occur over a calculated distance, which is divided into two distinct parts: Tangent Runout (L_t) and Superelevation Runoff (L_r).
1. Superelevation Runoff (L_r)
The superelevation runoff is the distance required to transition the outside lane(s) of the pavement from a flat (0.0%) cross-slope to the full design superelevation rate (e_d). According to the NCEES PE Civil Reference Handbook, the minimum length of runoff is calculated as:
L_r = (w * n_1 * e_d * b_w) / Delta
Where:
- w = Width of a design lane (typically 12 ft)
- n_1 = Number of lanes rotated (usually 1 for a standard two-lane highway rotated about the centerline)
- e_d = Design superelevation rate (expressed as a decimal)
b_w = Adjustment factor for the number of lanes rotated to account for larger pavement widths (AASHTO standard: 1.00 for 1 lane, 0.75 for 2 lanes, 0.67 for 3 lanes)
Delta = Maximum relative gradient (expressed as a decimal, representing the slope of the outer edge of pavement relative to the centerline profile; see speed-gradient table above)
2. Tangent Runout (L_t)
The tangent runout is the distance required to transition the outside lane from a normal crown cross-slope (e_NC, usually -2.0%) to a flat (0.0%) cross-slope. It is calculated proportionally based on the runoff length:
L_t = (e_NC / e_d) * L_r
Where e_NC is the normal crown rate (decimal) and e_d is the design superelevation rate (decimal).
Stationing of Superelevation Transitions
To balance steering comfort and passenger comfort, the transition length is distributed across the Point of Curvature (PC) and Point of Tangency (PT). The standard AASHTO practice is to locate two-thirds (2/3) of the superelevation runoff length (L_r) on the tangent section prior to the PC, and the remaining one-third (1/3) on the curve after the PC.
The critical stations along the transition are calculated as follows:
Normal Crown Ends (NC) : The point where the outside lane begins rotating.
Station NC = Station PC - (2/3) * L_r - L_t
Flat Crown (FC) : The point where the outside lane is flat (0%).
Station FC = Station PC - (2/3) * L_r
Reverse Crown (RC) : The point where the outside lane slope is equal but opposite to the inside lane (e.g., +2%).
Station RC = Station PC - (2/3) * L_r + L_t
Full Superelevation (FS) : The point where the entire pavement achieves the design superelevation rate (e_d).
Station FS = Station PC + (1/3) * L_r
The transition at the end of the curve (relative to the PT) is mirrored, with 1/3 of L_r on the curve before the PT and 2/3 of L_r plus L_t on the tangent after the PT.
Axis of Rotation Selection
The axis of rotation is the longitudinal line along the highway profile about which the pavement cross-section is rotated. The choice of axis affects the profile grade lines of the pavement edges:
Revolving about the Centerline : This is the most common method. The centerline profile remains unchanged, while the inner edge drops by w * e / 2 and the outer edge rises by w * e / 2. This minimizes the vertical displacement of the pavement edges and is visually pleasing.
Revolving about the Inner Edge : The inner edge profile remains at the design grade. The centerline and outer edge are raised. This is commonly used on divided highways with a median, or in flat terrain where dropping the inner edge would create drainage ponding.
Revolving about the Outer Edge : The outer edge profile remains at the design grade, while the centerline and inner edge are depressed. This is useful when matching the outside edge to existing roadside features or structures.