Study guide
3.2 Traffic Forecasts and Monitoring
PE Civil: Transportation Exam
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: Project Management
1.1 Quantity and Cost Estimating 1.2 Project Scheduling and CPM 1.3 Engineering Economic Analysis
2 Chapter 2: Traffic Engineering - Capacity and Flow
2.1 Uninterrupted Flow Capacity and Level of Service (LOS) 2.2 Interrupted Flow on Segment Streets 2.3 Intersection Capacity and LOS 2.4 Nonmotorized Facilities Analysis
3 Chapter 3: Traffic Engineering - Studies and Safety
3.1 Traffic Volume, Speed, and Planning Studies 3.2 Traffic Forecasts and Monitoring 3.3 Traffic Safety and Collision Analysis 3.4 Highway Safety and Crash Modification Factors (CMFs)
4 Chapter 4: Roadside and Cross-Section Design
4.1 Forgiving Roadside and Clear Zone Design 4.2 Barrier Design and Length of Need 4.3 Cross-Section Design Elements 4.4 Nonmotorized Design Considerations
5 Chapter 5: Horizontal Alignment Design
5.1 Circular Curve Elements and Calculations 5.2 Design Speed and Superelevation Design 5.3 Horizontal Sight Distance and Obstructions
6 Chapter 6: Vertical Alignment Design
6.1 Grades, Slopes, and Profile Design 6.2 Crest Vertical Curve Geometry and Sight Distance 6.3 Sag Vertical Curve Geometry and Sight Distance 6.4 Vertical Clearance Under Structures
7 Chapter 7: Intersection Geometry and Layout
7.1 At-Grade Intersection Design and Roundabouts 7.2 Intersection Sight Distance and Sight Triangles 7.3 Interchange Ramps and Terminal Geometry
8 Chapter 8: Traffic Signals
8.1 Traffic Signal Timing and Phasing 8.2 Traffic Signal Warrants (MUTCD) 8.3 Traffic Signal Design and Preemption
9 Chapter 9: Traffic Control Design
9.1 Permanent Signing Design and Standards 9.2 Pavement Marking Layout and Rules 9.3 Temporary Traffic Control and Work Zones
10 Chapter 10: Geotechnical and Pavements
10.1 Sampling, Testing, and Soil Stabilization 10.2 Fundamental Soil Properties and Mass Balance 10.3 Compaction, Excavation, and Mass Diagrams 10.4 Flexible and Rigid Pavement Design and ESALs
11 Chapter 11: Hydrology and Open-Channel Drainage
11.1 Rainfall Hydrology and Rational Method 11.2 Open-Channel Flow and Manning's Equation 11.3 Peak Flow Mitigation and Water-Quality
12 Chapter 12: Drainage Structures and Systems
12.1 Culvert Design and Inlet/Outlet Control 12.2 Stormwater Collection Systems and Inlet Capacities
3.2 Traffic Forecasts and Monitoring
Key Takeaways Explain This Topic AI
Geometric growth models are best suited for rapidly expanding urban fringes, whereas arithmetic models are more appropriate for mature, built-out areas.
The four-step travel demand model consists of Trip Generation, Trip Distribution, Mode Choice, and Route Assignment, in that order.
User Equilibrium (Wardrop's First Principle) assumes no traveler can unilaterally reduce their travel time, resulting in equal travel times on all used routes.
The Bureau of Public Roads (BPR) link congestion function uses the capacity ratio ( V / C V/C V / C ) raised to the fourth power to model travel time delay.
Last updated: July 2026
- 3.2 Traffic Forecasts and Monitoring
- Long-Term Traffic Growth Forecasting
Estimating future traffic volumes is essential for highway capacity planning, geometric design, and economic feasibility studies. Growth models extrapolate historical traffic volumes to a future target year (typically a 20-year design horizon).
Arithmetic Growth Model
Arithmetic growth assumes a constant increase in the absolute number of vehicles each year. This model is typical for mature, built-out areas where land development has stabilized: V n = V 0 ( 1 + n ⋅ r ) V_n = V_0 (1 + n \cdot r) V n = V 0 ( 1 + n ⋅ r )
where:
V n V_n V n : Predicted volume in year n n n .
V 0 V_0 V 0 : Baseline volume in year 0.
n n n : Number of forecasting years.
r r r : Annual arithmetic growth rate (decimal).
Geometric (Exponential) Growth Model
Geometric growth assumes traffic increases at a rate proportional to its current volume, representing compound growth. This is appropriate for rapidly developing suburban areas or newly opened corridors: V n = V 0 ( 1 + r ) n V_n = V_0 (1 + r)^n V n = V 0 ( 1 + r ) n
where r r r is the annual geometric growth rate.
The Four-Step Travel Demand Model
For regional planning, traffic engineers use the traditional Four-Step Travel Demand Model to forecast traffic volumes based on land use and socio-economic forecasts.
1. Trip Generation
This step determines the total number of trips produced by ( P i P_i P i ) and attracted to ( A j A_j A j ) each Traffic Analysis Zone (TAZ). Data inputs include population, number of households, income levels, and employment density. Linear regression is commonly applied: P i = f ( Households , Income ) P_i = f(\text{Households}, \text{Income}) P i = f ( Households , Income ) A j = f ( Employment , Commercial floor space ) A_j = f(\text{Employment}, \text{Commercial floor space}) A j = f ( Employment , Commercial floor space )
2. Trip Distribution
This step links the trip origins (productions) with destinations (attractions) to create an Origin-Destination (O-D) matrix. The Gravity Model is the primary method used, drawing an analogy to Newton's law of gravity: T i j = P i A j ⋅ F i j ⋅ K i j ∑ k A k ⋅ F i k ⋅ K i k T_{ij} = P_i \frac{A_j \cdot F_{ij} \cdot K_{ij}}{\sum_{k} A_k \cdot F_{ik} \cdot K_{ik}} T ij = P i ∑ k A k ⋅ F ik ⋅ K ik A j ⋅ F ij ⋅ K ij
where:
T i j T_{ij} T ij : Number of trips from zone i i i to zone j j j .
P i P_i P i : Trip productions in zone i i i .
A j A_j A j : Trip attractions in zone j j j .
F i j F_{ij} F ij : Friction factor, representing spatial separation (usually F i j = t i j − b F_{ij} = t_{ij}^{-b} F ij = t ij − b where t i j t_{ij} t ij is travel time and b b b is a calibration parameter).
K i j K_{ij} K ij : Socio-economic adjustment factor.
3. Mode Choice (Modal Split)
This step determines the travel mode (e.g., drive-alone, shared-ride, transit, non-motorized) chosen by travelers. Logit models compute probabilities based on mode utilities. A utility function U m U_m U m is defined for each mode: U m = a m − b ⋅ ( Travel Time ) − c ⋅ ( Travel Cost ) U_m = a_m - b \cdot (\text{Travel Time}) - c \cdot (\text{Travel Cost}) U m = a m − b ⋅ ( Travel Time ) − c ⋅ ( Travel Cost )
The probability P ( m ) P(m) P ( m ) of choosing mode m m m is: P ( m ) = e U m ∑ e U k P(m) = \frac{e^{U_m}}{\sum e^{U_k}} P ( m ) = ∑ e U k e U m
4. Traffic Assignment (Route Choice)
This final step assigns the O-D trip matrix to specific routes on the transportation network. Link travel times are adjusted as volumes increase to simulate congestion.
User Equilibrium (UE - Wardrop's First Principle): Traffic distributes such that travel times on all used routes between an origin and destination are equal and less than or equal to the travel time on any unused route. Under UE, no individual driver can unilaterally reduce their travel time by changing routes.
System Optimum (SO - Wardrop's Second Principle): Traffic distributes to minimize the total travel time of all vehicles in the network. This represents a cooperative state and is rarely achieved naturally.
To model the relationship between traffic volume and travel time delay, the Bureau of Public Roads (BPR) link congestion function is used: t a = t 0 [ 1 + α ( V C ) β ] t_a = t_0 \left[ 1 + \alpha \left( \frac{V}{C} \right)^\beta \right] t a = t 0 [ 1 + α ( C V ) β ]
where:
t a t_a t a : Link travel time under volume V V V .
t 0 t_0 t 0 : Free-flow travel time.
V V V : Traffic volume on the link.
C C C : Link capacity.
α , β \alpha, \beta α , β : Calibration parameters (standard default values: α = 0.15 \alpha = 0.15 α = 0.15 , β = 4.0 \beta = 4.0 β = 4.0 ).
Traffic Monitoring Methods and Data Collection
Traffic monitoring provides the baseline data needed for design and planning. Continuous data collection establishes seasonal trends, while short-term counts extend spatial coverage.
Equipment and Sensors
Intrusive Sensors (In-Roadway):
Inductive Loops: Wire loops cut into the pavement. They detect change in inductance caused by a passing metal vehicle. Used for count, occupancy, and speed (when configured in dual-loop speed traps).
Pneumatic Road Tubes: Flexible tubes placed across lanes. They register air pressure pulses as vehicle axles cross them. Ideal for short-term coverage counts (48-hour).
Non-Intrusive Sensors (Out-of-Roadway):
Radar/Microwave: Measures vehicle presence and speed via Doppler shift. Does not require pavement cuts.
Video Image Processing (VIP): Computer vision systems that analyze video feeds to count, classify, and track vehicles.
Probe Data (GPS/Bluetooth/Wi-Fi): Tracks MAC addresses or GPS location pings to measure segment travel times and O-D distributions.
Vehicle Miles of Travel (VMT)
A key metric for traffic monitoring, environmental planning, and highway funding is Vehicle Miles of Travel (VMT) . For a specific roadway segment, it is calculated as: V M T = A D T × L VMT = ADT \times L V MT = A D T × L
where L L L is the length of the segment in miles. VMT can be aggregated across a network or region to assess total travel demand.