Study guide
19.3 Treatment and Process Sizing Workbook
NCEES PE Civil: Water Resources and Environmental Exam Exam
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: NCEES WRE Exam Spec and Reference Strategy
1.1 NCEES WRE Format 1.2 Reference Handbook and Units 1.3 Blueprint Prioritization
2 Chapter 6: WRE Project Planning, Cost, and Engineering Economics
6.1 Quantity Takeoff and Unit Basis 6.2 Cost Estimating and Bid Item Logic 6.3 Schedules, Sequencing, and Critical Path 6.4 Present Worth, Life-Cycle Cost, and Sustainability
3 Chapter 7: Soil Mechanics for WRE Problems
7.1 Lateral Earth Pressure and Retaining Situations 7.2 Consolidation, Compaction, and Settlement 7.3 Bearing Capacity and Slope Stability 7.4 Soil Data, Boring Logs, and Unit Conversions
4 Chapter 8: WRE Analysis and Hydraulic Design Foundations
8.1 Mass Balance and Hydraulic Loading 8.2 Solids Loading and Sludge Mass Balance 8.3 Hydraulic Flow Measurement and Instrumentation 8.4 Design Checks, Safety Factors, and Reasonableness
5 Chapter 9: WRE Hydrology, Runoff, and Storage Routing
9.1 Design Storms, IDF, and Time of Concentration 9.2 Rational Method and Peak Flow Limits 9.3 NRCS Curve Number and Unit Hydrographs 9.4 Detention, Retention, and Routing Checks
6 Chapter 10: Closed Conduit and Open Channel Hydraulics
10.1 Continuity, Energy, and HGL/EGL 10.2 Pipe Flow Losses, Pumps, and Net Head 10.3 Manning, Open Channel, and Critical Flow 10.4 Culverts, Weirs, Orifices, and Control Sections
7 Chapter 11: Groundwater, Wells, and Aquifer Flow
11.1 Darcy Law, Gradient, and Flow Area 11.2 Confined and Unconfined Aquifers and Storage 11.3 Well Drawdown, Specific Capacity, and Interference 11.4 Contaminant Transport and Dewatering Decisions
8 Chapter 12: Water Quality Chemistry and Pollutant Loading
12.1 Concentration, Load, and Mass-Rate Conversions 12.2 BOD, CBOD, DO, and Oxygen Demand 12.3 Nutrients, pH, Alkalinity, and Buffering 12.4 Pollutant Allocation, TMDL, and Water Quality Criteria
9 Chapter 13: Water Treatment Processes and Design Checks
13.1 Coagulation, Flocculation, and Sedimentation 13.2 Filtration, Disinfection, and CT Logic 13.3 Softening, Iron, Manganese, and Chemical Feed 13.4 Treatment Plant Hydraulics and Operations
10 Chapter 14: Wastewater Collection, Treatment, and Sludge
14.1 Collection-System Hydraulics and Infiltration 14.2 Preliminary, Primary, and Secondary Treatment 14.3 Nutrient Removal and Effluent Quality 14.4 Sludge Processing, Digestion, and Dewatering
11 Chapter 3: Water Quality, Treatment, and Sitework
Water Quality and Regulation Drinking Water and Wastewater Treatment Project Sitework and Final Review
12 Chapter 15: Sitework, Drainage, and Erosion Control
15.1 Grading, Cut/Fill, and Earthwork Balancing 15.2 Storm Drain Inlets and Minor Systems 15.3 Erosion, Sediment Control, and BMPs 15.4 Permitting, Constructability, and Field Adjustments
13 Chapter 4: Materials, Analysis, and Design for WRE
4.1 Materials and Pipe Selection 4.2 Analysis and Design Workflow 4.3 Site-Civil Constructability
14 Chapter 16: Materials, Pipes, Standards, and Reference Navigation
16.1 Pipe Material Selection and Failure Modes 16.2 Concrete, Soil, and Geosynthetic Materials 16.3 Design Standard Navigation and Revision Years 16.4 Reference Search Drills and Unit Checks
15 Chapter 18: Pumps, Distribution, and Collection Systems
18.1 Pump Curves, System Curves, and Operating Point 18.2 Water Distribution Pressure, Demand, and Storage 18.3 Sewer Collection, Lift Stations, and Force Mains 18.4 Transient, Surge, and Operational Troubleshooting
16 Chapter 19: WRE Calculation Workbook and Unit Drills
19.1 Flow, Concentration, and Load Workbook 19.2 Hydraulics Energy and Head Workbook 19.3 Treatment and Process Sizing Workbook 19.4 Error Patterns and Repair Drills
17 Chapter 5: Mixed Practice, Units, and Final Review
Formula Selection and Units Mixed WRE Mock Review Exam Day and Spec Transition
18 Chapter 17: Full-Length WRE Mixed Practice and Final Review
17.1 Eighty-Question Mock Exam Plan 17.2 Miss-Log Diagnostics by Domain 17.3 Calculator, Reference, and Break Strategy 17.4 Final-Week Current vs 2027 Spec Check
19.3 Treatment and Process Sizing Workbook
Key Takeaways Explain This Topic AI
Match each process to its controlling rate: clarifiers use surface overflow rate, filters use hydraulic loading, contact basins use CT.
Typical design values: secondary clarifier SOR 400-800 gpd/ft2, rapid filter 2-5 gpm/ft2, F/M ratio 0.2-0.5 lb BOD/lb MLVSS-day.
CT = disinfectant residual (mg/L) x contact time (min); meet the Surface Water Treatment Rule CT table for the target log inactivation.
Track load through removal: effluent load = influent load x (1 - removal fraction).
Chemical feed: product mass = active dose mass / fractional purity.
Last updated: June 2026
Match the process to the controlling rate
Treatment calculations are not all detention-time problems. A sedimentation basin is controlled by surface overflow rate (SOR) . A filter is controlled by hydraulic loading rate , headloss, and backwash. A chlorine contact basin is controlled by CT (concentration x time) and baffling. A biological reactor is controlled by organic loading, the food-to-microorganism (F/M) ratio , solids retention time (SRT), or aeration demand. The question signals the controlling rate if you read for process purpose.
Process sizing map with target design values
- Process Requested value Typical design range
- Rapid mix / flocculation volume, G value floc detention 20-30 min
- Sedimentation / clarification area or SOR secondary SOR 400-800 gpd/ft2
- Rapid sand filtration filter area or rate 2-5 gpm/ft2
- Disinfection dose, residual, CT per SWTR CT tables
- Activated sludge F/M, SRT, aeration F/M 0.2-0.5; SRT 5-15 day
- Sludge handling mass, volume, % solids thickened 2-6% solids
Start the workbook line with purpose . Settling -> SOR and area. Contact -> time and effective (baffled) volume. Mass removal -> load in, load out, removal fraction. Dosing -> is the dose active chemical, commercial product, or solution strength?
- Removal, CT, and chemical feed discipline
- Removal efficiency by load
Removal can apply to concentration or load when flow is constant, but the safe method tracks load : effluent load = influent load x (1 - removal). Example: 7,339 lb/day BOD in at 85% removal leaves 7,339 x 0.15 = 1,101 lb/day out; at 4.0 MGD the effluent concentration is 1,101 / (4.0 x 8.34) = 33 mg/L . With side streams, recycle, or changing flow, concentration-only shortcuts become risky.
CT for disinfection
Under the Surface Water Treatment Rule (SWTR) , CT = residual disinfectant (mg/L) x contact time T10 (min) . Required CT comes from the EPA tables and depends on pathogen, temperature, and pH. Example: a basin holds 0.5 MG with a baffling factor giving T10 = 30 min and a free-chlorine residual of 1.2 mg/L. CT achieved = 1.2 x 30 = 36 mg-min/L . Compare to the required CT (e.g., approximately 6 mg-min/L for 0.5-log Giardia at 10 C, pH 7) to confirm compliance.
Chemical feed workflow
Convert plant flow to the required time basis.
Multiply by target dose: lb/day = Q (MGD) x dose (mg/L) x 8.34.
Adjust for purity: product mass = active mass / fractional purity.
Convert to feed units (lb/day, gal/day, mL/min).
State whether the answer is active ingredient or delivered product.
Example: 2.0 MGD dosed at 8 mg/L active chlorine needs 2.0 x 8 x 8.34 = 133.4 lb/day active. If the product is 65% available chlorine, deliver 133.4 / 0.65 = 205 lb/day of product.
Sludge mass-volume relationships
Sludge problems hinge on the percent-solids identity : wet sludge volume (gal) = dry solids mass (lb) / (8.34 x percent solids fraction x specific gravity). For dilute sludge, specific gravity is near 1.0, so a shortcut is V (gal) = dry lb / (8.34 x Ps). Example: 2,000 lb/day of dry solids at 3% solids gives V = 2,000 / (8.34 x 0.03) = 7,994 gal/day . Thickening to 6% halves the volume to about 3,997 gal/day -- the inverse relationship between percent solids and volume is the single most-tested sludge concept. A common trap multiplies by the percent solids instead of dividing, producing a volume far too small to be physical.
Operational checks
Reject answers that violate operating sense: an SOR implying scour, a CT ignoring short-circuiting, or a sludge volume that inverts percent solids. Process sizing is a calculation plus an operating story. Build a four-column drill table (process, controlling rate, unknown, unit check) so you never force every treatment item into one detention-time equation.
Filtration and backwash drill
For a rapid sand filter, area = Q / hydraulic loading rate. Example: 3.0 MGD (2,083 gpm) at 4 gpm/ft2 needs 521 ft2 of filter area; split across two filters, each is about 260 ft2 (roughly 16 x 16 ft). Backwash demand is sized separately at a higher rate (commonly 15-20 gpm/ft2) for a short duration, and that backwash water becomes a recycle flow that must rejoin the plant mass balance. Always confirm whether the problem wants total filter area, area per unit, the number of filters, or the backwash flow -- the four-column table forces that read before you compute.
Activated-sludge loading worked example
The food-to-microorganism (F/M) ratio ties influent organic load to the biomass in the aeration basin: F/M = (Q x BOD) / (V x MLVSS), in consistent units of lb BOD/day per lb mixed-liquor volatile suspended solids. Example: 2.0 MGD at 200 mg/L BOD delivers 2.0 x 200 x 8.34 = 3,336 lb BOD/day. An aeration basin of 0.5 MG at 2,500 mg/L MLVSS holds 0.5 x 2,500 x 8.34 = 10,425 lb of biomass. F/M = 3,336 / 10,425 = 0.32 day^-1 , comfortably inside the 0.2-0.5 conventional range.
If a computed F/M lands at 5 or 0.02, suspect a units slip -- typically forgetting the 8.34 on one of the two terms, which is the most common activated-sludge setup error on the exam.