10.2 Long-Term Construction Contracts: Measuring Progress, Contract Balances, and Losses
CPA Licensure Examination Philippines, CPALE
Track your progress as you read
Finished sections get a check mark.
1 Introduction & Overview of the CPALE
0.1 CPALE Structure, Qualification, and Examination Mechanics 0.2 Study Strategy, Subject Balance, and Time Management for the Three-Day Board Exam
2 FAR: Standard Setting, Conceptual Framework, Accounting Process & Financial Statements
1.1 Standard-Setting Bodies and Regulation of the Accountancy Profession 1.2 The Conceptual Framework for Financial Reporting 1.3 The Accounting Process: Journals, Worksheet, Adjusting, Closing, and Reversing Entries 1.4 Presentation of Financial Statements
3 FAR: Cash, Receivables & Financial Asset Investments
2.1 Cash, Cash Equivalents, Petty Cash, and Bank Reconciliation 2.2 Trade and Notes Receivables: Measurement, Expected Credit Losses, and Receivable Financing 2.3 Financial Asset Investments: FVPL, FVOCI, and Amortized Cost under PFRS 9
4 FAR: Inventories, Property, Plant & Equipment, and Investment Property
3.1 Inventories & Cost of Sales 3.2 Property, Plant and Equipment, Borrowing Costs, and Impairment 3.3 Investment Property and Agriculture (PAS 40 and PAS 41)
5 FAR: Intangibles, Held for Sale, Financial Liabilities & Provisions
4.1 Intangible Assets, Research and Development, and Goodwill 4.2 Non-Current Assets Held for Sale and Discontinued Operations (PFRS 5) 4.3 Financial Liabilities: Bonds Payable, Effective Interest, and Debt Restructuring 4.4 Provisions, Contingencies, Loyalty Programs, Warranties, and Unearned Revenue
6 FAR: Equity, Share-Based Payment, Leases, Income Taxes & Employee Benefits
5.1 Shareholders' Equity & Share-Based Payments 5.2 Leases under PFRS 16: Lessee, Lessor, and Sale-and-Leaseback 5.3 Income Taxes (PAS 12) and Employee Benefits (PAS 19)
7 FAR: EPS, Cash Flows, SMEs & Small Entities, and Interim Reporting
6.1 Earnings per Share and the Statement of Cash Flows 6.2 PFRS for SMEs, PFRS for Small Entities, and Micro Entities 6.3 Interim Financial Reporting (PAS 34) and Operating Segments (PFRS 8)
8 AFAR: Partnership Formation, Operations, Changes & Liquidation
7.1 Partnership Formation, Operations & Profit/Loss Allocation 7.2 Changes in Partnership Ownership: Admission, Retirement, Death, and Incorporation 7.3 Partnership Liquidation: Lump-Sum and Installment Methods
9 AFAR: Corporate Liquidation, Home Office & Branch, and Business Combinations
8.1 Corporate Liquidation & Statement of Affairs 8.2 Home Office, Branch & Agency Accounting 8.3 Business Combinations under PFRS 3
10 AFAR: Consolidation, Joint Arrangements & Associates
9.1 Consolidated Financial Statements under PFRS 10 & PAS 27 9.2 Joint Arrangements (PFRS 11): Joint Control, Joint Operations, and Joint Ventures 9.3 Investments in Associates and Joint Ventures: The Equity Method (PAS 28)
11 AFAR: Revenue Recognition and Construction Contracts
10.1 Revenue from Contracts with Customers: The Five-Step Model (PFRS 15) 10.2 Long-Term Construction Contracts: Measuring Progress, Contract Balances, and Losses 10.3 Special Revenue Issues under PFRS 15
12 AFAR: Franchises, Consignment, Foreign Currency & Derivatives
11.1 Franchise Operations and Consignment Sales 11.2 Foreign Currency Transactions and Translation (PAS 21 and PAS 29) 11.3 Derivatives and Hedge Accounting (PFRS 9)
13 AFAR: Government, Not-for-Profit, Insurance Contracts & Service Concessions
12.1 Government Accounting: The GAM for National Government Agencies 12.2 Not-for-Profit Organizations: Net Assets, Contributions, and Sector Types 12.3 Insurance Contracts (PFRS 17) and Service Concession Arrangements
14 AFAR: Cost Accounting Systems
13.1 Cost Accumulation Systems and Job Order Costing 13.2 Process Costing and Backflush Costing 13.3 Activity-Based Costing, Joint and By-Products, and Service Department Cost Allocation
15 MS: Management Accounting, Cost Behavior & CVP Analysis
14.1 The Role of Management Accounting, Professional Ethics, and Global Trends 14.2 Cost Classifications, Cost Behavior, and Cost Estimation 14.3 Cost-Volume-Profit (CVP) Analysis
16 MS: Variable Costing, Standard Costing & Budgeting
15.1 Variable Costing versus Absorption Costing 15.2 Standard Costing & Variance Analysis 15.3 Master Budgeting, Cash Budgets, and Flexible Budgets
17 MS: Performance Measurement and Relevant Costing
16.1 Responsibility Accounting, Segment Reporting, and Transfer Pricing 16.2 Balanced Scorecard, Operational Performance, and Emerging Trends 16.3 Relevant Costing & Short-Term Tactical Decisions
18 MS: Pricing, Quantitative Techniques & Financial Statement Analysis
17.1 Pricing Decisions & Profitability Analysis 17.2 Quantitative Techniques for Decision Making 17.3 Financial Statement Analysis & Ratio Analysis
19 MS: Working Capital Management and Capital Budgeting
18.1 Working Capital: Policies, Cash Conversion Cycle, and Cash Management 18.2 Working Capital: Receivables, Inventory, and Short-Term Financing 18.3 Capital Budgeting & Investment Decisions
20 MS: Risk, Cost of Capital, Financial Markets & Economics
19.1 Risk and Return, Leverage, and Cost of Capital 19.2 Financial Markets, Long-Term Financing, and Valuation 19.3 Microeconomics, Macroeconomics, and International Trade
21 AUD: Nature of Auditing, Regulation of the Profession & Code of Ethics
20.1 Nature of Auditing, Assurance, and Information Risk 20.2 The Regulatory Framework of the Accountancy Profession 20.3 Code of Ethics: Fundamental Principles, Conceptual Framework, and Threats
22 AUD: Independence, Quality Management & Engagement Planning
21.1 Independence: Financial Interests, Relationships, Rotation, Services, and Fees 21.2 Philippine Standards on Quality Management 21.3 Pre-Engagement Activities, Client Acceptance & Audit Planning
23 AUD: Audit Risk, Fraud, Materiality & Internal Control
22.1 Audit Risk Model and Fraud Risk 22.2 Materiality: Overall, Performance, and Clearly Trivial Thresholds 22.3 Understanding the Entity & Internal Control Evaluation
24 AUD: IT Environment, Audit Evidence & Sampling
23.1 Auditing in a Computer Information Systems (CIS) Environment 23.2 Audit Evidence, Assertions, Procedures, and Documentation 23.3 Audit Sampling: Attribute, Variable, and Monetary Unit Sampling
25 AUD: Business Process Audits and Auditing Practice Problems
24.1 Substantive Testing of Business Cycles 24.2 Auditing Practice: Cash and Receivables 24.3 Auditing Practice: Inventory, Property, and Liabilities
26 AUD: Completing the Audit, Reporting & Other Assurance Services
25.1 Completing the Audit, Subsequent Events & Going Concern 25.2 The Auditor's Report: Opinions, KAM, EOM, and Comparatives 25.3 Other Assurance and Related Services Engagements
27 TAX: Principles of Taxation and Assessment Remedies
26.1 Taxation: Nature, Inherent Powers, and Limitations 26.2 The Tax System: Canons, Double Taxation, Evasion, and Sources of Tax Law 26.3 Tax Remedies: Assessment, Protest, and Appeal
28 TAX: Refunds, Collection & Prescription, Gross Income, and Fringe Benefits
27.1 Tax Remedies: Refunds, Collection, and Prescription 27.2 Gross Income: Inclusions and Exclusions 27.3 De Minimis Benefits and the Fringe Benefits Tax
29 TAX: Individual and Corporate Income Taxation
28.1 Individual Income Tax: Classification, Rates, and the 8% Option 28.2 Individual Income Tax: Deductions, Passive Income, and Capital Gains 28.3 Corporate Income Taxation under the CREATE Law
30 TAX: Estate Tax, Donor's Tax, Withholding & Special Tax Laws
29.1 Estate Tax under the NIRC as Amended by the TRAIN Law 29.2 Donor's Tax under the NIRC as Amended by the TRAIN Law 29.3 Withholding Taxes, EOPT Compliance, and Special Tax Laws
31 TAX: Value-Added Tax and Percentage Taxes
30.1 Value-Added Tax: Nature, Registration, Output Tax, and Exemptions 30.2 Value-Added Tax: Input Tax, Allocation, Withholding, and Filing 30.3 Percentage Taxes & Other Business Taxes
32 TAX: Local Taxes, DST & Excise, and Incentives & Treaties
31.1 Local Taxation and Real Property Tax 31.2 Documentary Stamp Tax and Excise Taxes 31.3 Tax Incentives under CREATE MORE and Tax Treaties
33 RFBT: Law on Obligations
32.1 Obligations: Nature, Sources, and Effects 32.2 Kinds of Obligations 32.3 Extinguishment of Obligations
34 RFBT: Contracts, Defective Contracts & Sales
33.1 Law on Contracts: Essential Requisites & Performance 33.2 Defective Contracts 33.3 Sales: Nature, Object and Price, Delivery, and Double Sales
35 RFBT: Installment Sales, Credit Transactions & Partnerships
34.1 Sales: Warranties, Installment Sales, and Redemption 34.2 Credit Transactions & Security Mechanisms 34.3 Law on Partnerships
36 RFBT: Corporations - Nature, Incorporation & Board of Directors
35.1 Corporations: Nature, Separate Personality, Classes, and Nationality 35.2 Corporations: Incorporation, Articles and Bylaws, and Corporate Powers 35.3 Corporations: Board of Directors, Officers, and Fiduciary Duties
37 RFBT: Corporations - Stockholders, Capital & Corporate Changes
36.1 Corporations: Stockholders, Meetings, and One Person Corporations 36.2 Corporations: Capital Stock, Shares, and Subscriptions 36.3 Corporations: Mergers, Dissolution, Foreign Corporations, and SEC Powers
38 RFBT: Securities Regulation, Insurance & Cooperatives
37.1 Securities Regulation, Corporate Governance, and SRC Rule 68 37.2 Insurance Law 37.3 Cooperatives under the Philippine Cooperative Code (RA 9520)
39 RFBT: Banking Laws, AMLA & Bouncing Checks
38.1 Banking Laws, Bank Secrecy & PDIC 38.2 Anti-Money Laundering Act (AMLA) 38.3 Bouncing Checks Law (BP 22)
40 RFBT: Insolvency, Competition, Data Privacy & Labor Laws
39.1 Financial Rehabilitation and Insolvency Act (FRIA) 39.2 Competition, Consumer Protection, and Government Procurement 39.3 Data Privacy, Intellectual Property, and Electronic Commerce 39.4 Ease of Doing Business, Labor Standards, and Social Security
10.2 Long-Term Construction Contracts: Measuring Progress, Contract Balances, and Losses
Key Takeaways Explain This Topic AI
Percentage of completion under the cost-to-cost method equals cumulative costs incurred to date divided by total estimated contract costs.
Uninstalled materials and abnormal wasted costs are excluded from the cost-to-cost computation; uninstalled goods controlled by the customer may be recognized at zero margin.
When construction in progress (costs plus recognized profit) exceeds progress billings, the net amount is a contract asset; when billings exceed it, the net amount is a contract liability.
When total estimated costs exceed the contract price, the entire expected loss is recognized immediately, together with a reversal of profit recognized in prior years.
A decline in expected profit on a still-profitable contract is recognized as a cumulative catch-up adjustment in the current period.
Last updated: September 2026
Long-Term Construction Contracts: Measuring Progress, Contract Balances, and Losses
Long-term construction contracts are the classic over-time revenue problem in AFAR (syllabus topic 4.1.2.9). This section measures progress with output and input methods, applies the cost-to-cost formula with its exclusions, presents contract assets and contract liabilities, and handles contracts that become less profitable or loss-making, with a three-year worked example.
1. Long-Term Construction Contracts: Methods of Measuring Progress
For performance obligations satisfied over time, revenue is recognized by measuring progress toward complete satisfaction of the obligation. PFRS 15 categorizes progress measurement into two primary families:
1. Output Methods
Output methods recognize revenue based on direct measurements of the value to the customer of the goods or services transferred to date relative to the remaining goods or services promised:
- Surveys of performance completed by independent engineers or architects;
- Appraisals of results achieved;
- Milestones reached;
Units produced or units delivered.
Limitation: Output methods may not be representative if the output selected fails to measure goods or services for which control has transferred (e.g., work-in-progress that has not yet reached a formal milestone).
2. Input Methods (The Cost-to-Cost Method)
Input methods recognize revenue based on the entity's efforts or inputs toward satisfying a performance obligation relative to total expected inputs. In the CPALE, the cost-to-cost method is the predominant input method tested.
Percentage of Completion = Cumulative Incurred Contract Costs to Date Total Estimated Contract Costs \text{Percentage of Completion} = \frac{\text{Cumulative Incurred Contract Costs to Date}}{\text{Total Estimated Contract Costs}} Percentage of Completion = Total Estimated Contract Costs Cumulative Incurred Contract Costs to Date
Total Estimated Contract Costs = Cumulative Incurred Costs to Date + Estimated Costs to Complete \text{Total Estimated Contract Costs} = \text{Cumulative Incurred Costs to Date} + \text{Estimated Costs to Complete} Total Estimated Contract Costs = Cumulative Incurred Costs to Date + Estimated Costs to Complete
Mandatory Exclusions from the Cost-to-Cost Formula
To ensure that inputs faithfully depict the transfer of control, the following costs must be excluded from both the numerator (costs incurred to date) and denominator (total estimated costs) when calculating the percentage of completion:
Abnormal Inefficiencies: Substantial wasted materials, idle labor, strike-related down-time, or scrap costs that were not anticipated in the contract price. These costs are expensed immediately in profit or loss.
Uninstalled Materials: Materials delivered to the job site that the contractor controls but has not yet installed, used, or applied in construction (e.g., elevators, structural steel, or electrical transformers stored on site). If uninstalled materials are significant and the customer obtains control upon delivery, revenue is recognized on those materials only to the extent of costs incurred (i.e., zero gross profit recognized on uninstalled materials).
2. Contract Asset vs. Contract Liability Mechanics
Under PFRS 15, the relationship between cumulative revenue recognized (or cumulative costs incurred plus cumulative recognized gross profit) and cumulative progress billings dictates balance sheet presentation. Contract Asset vs. Contract Liability
- │
- ┌─────────────────────────┴─────────────────────────┐
- ▼ ▼
- CIP > Progress Billings Progress Billings > CIP
- Cumulative Revenue > Billings Billings > Cumulative Revenue
- NET CONTRACT ASSET NET CONTRACT LIABILITY
- "Gross amounts due from customers" "Gross amounts due to customers"
- Definitions and Accounting Terminology
Construction in Progress (CIP): An inventory/asset accumulation account debited for actual contract costs incurred and debited for recognized gross profit (or credited for recognized gross loss).
Progress Billings: A contra-construction account credited when billings are rendered to the client according to contractual progress or milestones.
Contract Asset: An entity's right to consideration in exchange for goods or services that the entity has transferred to a customer when that right is conditioned on something other than the passage of time (e.g., future performance or final certification). On the statement of financial position, a net debit balance (CIP minus Progress Billings > 0) is presented as a Contract Asset .
Contract Liability: An entity's obligation to transfer goods or services to a customer for which the entity has received consideration (or an amount is due) from the customer. A net credit balance (Progress Billings minus CIP > 0) is presented as a Contract Liability (or Unearned Contract Revenue).
Accounts Receivable: Recognized when an invoice or billing represents an unconditional right to consideration, where only the passage of time is required before payment is due.
Net Balance = Construction in Progress (Costs + Cumulative Gross Profit) − Progress Billings \text{Net Balance} = \text{Construction in Progress (Costs + Cumulative Gross Profit)} - \text{Progress Billings} Net Balance = Construction in Progress (Costs + Cumulative Gross Profit) − Progress Billings
3. Accounting for Contract Losses
PFRS 15, in conjunction with PAS 37 (Provisions, Contingent Liabilities and Contingent Assets), establishes uncompromising rules for contract losses.
Scenario A: Profitable Contract Overall, Current Period Loss
If revised cost estimates reduce the overall anticipated contract gross profit, but the total contract remains profitable (Total Contract Price > Total Estimated Costs):
The cumulative gross profit to date is recomputed using the new, lower overall profit percentage.
The current period gross profit is computed as: Cumulative Gross Profit to Date − Prior Years’ Cumulative Recognized Gross Profit \text{Cumulative Gross Profit to Date} - \text{Prior Years' Cumulative Recognized Gross Profit} Cumulative Gross Profit to Date − Prior Years’ Cumulative Recognized Gross Profit .
This calculation frequently yields a negative gross profit (a gross loss) for the current period, adjusting for over-recognition in prior years.
Scenario B: Unprofitable Contract (Onerous Contract / Total Expected Loss)
When current estimates indicate that Total Estimated Contract Costs exceed Total Contract Price , the contract has become an onerous contract .
The Absolute PFRS Rule: The entire expected contract loss must be recognized immediately in full in the period in which the loss becomes evident, regardless of the percentage of completion!
Total Expected Loss = Total Estimated Contract Costs − Contract Price \text{Total Expected Loss} = \text{Total Estimated Contract Costs} - \text{Contract Price} Total Expected Loss = Total Estimated Contract Costs − Contract Price
Current Period Loss Recognized = Total Expected Contract Loss + Prior Years’ Cumulative Recognized Gross Profit \text{Current Period Loss Recognized} = \text{Total Expected Contract Loss} + \text{Prior Years' Cumulative Recognized Gross Profit} Current Period Loss Recognized = Total Expected Contract Loss + Prior Years’ Cumulative Recognized Gross Profit
Balance Sheet Effect of Expected Losses
The provision for the contract loss is credited directly to Construction in Progress (CIP) . If the accumulated loss write-down causes the net contract balance to become a credit, or if Progress Billings exceed the reduced CIP, the excess is presented as a Provision for Onerous Contracts (Contract Liability) .
4. Comprehensive Worked Example: PFRS 15 Cost-to-Cost, Contract Asset/Liability & Full Contract Loss
On February 1, 2024, Makati Infrastructure Builders Corp. enters into a non-cancellable contract to construct an elevated expressway bypass for the Department of Public Works and Highways (DPWH) for a fixed contract price of PHP 30,000,000 . The contract qualifies for revenue recognition over time under PFRS 15.
- Contract Operational Data (2024 to 2026): Contract Data 2024 2025 2026
- Costs incurred during the year PHP 7,200,000 PHP 11,800,000 PHP 12,000,000
- Estimated costs to complete 16,800,000 13,000,000 0
- Progress billings during year 8,000,000 12,000,000 10,000,000
- Cash collections during year 6,500,000 11,500,000 12,000,000
Special Condition in 2025: Severe subsoil instability in late 2025 required foundational redesign, driving cumulative costs incurred to PHP 19,000,000 and estimated costs to complete to PHP 13,000,000 (Total estimated costs = PHP 32,000,000). Total contract price remains PHP 30,000,000.
Year 1 (2024) Calculations:
Total Estimated Costs: Total Costs = PHP 7,200,000 + PHP 16,800,000 = PHP 24,000,000 \text{Total Costs} = \text{PHP }7{,}200{,}000 + \text{PHP }16{,}800{,}000 = \text{PHP }24{,}000{,}000 Total Costs = PHP 7 , 200 , 000 + PHP 16 , 800 , 000 = PHP 24 , 000 , 000
Total Expected Contract Profit: Total Expected Profit = PHP 30,000,000 − PHP 24,000,000 = PHP 6,000,000 \text{Total Expected Profit} = \text{PHP }30{,}000{,}000 - \text{PHP }24{,}000{,}000 = \text{PHP }6{,}000{,}000 Total Expected Profit = PHP 30 , 000 , 000 − PHP 24 , 000 , 000 = PHP 6 , 000 , 000
Percentage of Completion: POC 2024 = PHP 7,200,000 PHP 24,000,000 = 30.00 % \text{POC}_{2024} = \frac{\text{PHP }7{,}200{,}000}{\text{PHP }24{,}000{,}000} = 30.00\% POC 2024 = PHP 24 , 000 , 000 PHP 7 , 200 , 000 = 30.00%
Revenue and Gross Profit Recognized in 2024: Revenue 2024 = 30 % × PHP 30,000,000 = PHP 9,000,000 \text{Revenue}_{2024} = 30\% \times \text{PHP }30{,}000{,}000 = \text{PHP }9{,}000{,}000 Revenue 2024 = 30% × PHP 30 , 000 , 000 = PHP 9 , 000 , 000 Cost of Construction 2024 = PHP 7,200,000 \text{Cost of Construction}_{2024} = \text{PHP }7{,}200{,}000 Cost of Construction 2024 = PHP 7 , 200 , 000 Gross Profit Recognized 2024 = PHP 9,000,000 − PHP 7,200,000 = PHP 1,800,000 \text{Gross Profit Recognized}_{2024} = \text{PHP }9{,}000{,}000 - \text{PHP }7{,}200{,}000 = \text{PHP }1{,}800{,}000 Gross Profit Recognized 2024 = PHP 9 , 000 , 000 − PHP 7 , 200 , 000 = PHP 1 , 800 , 000
Balance Sheet Presentation at December 31, 2024: CIP Balance = Costs Incurred (PHP 7,200,000) + Profit (PHP 1,800,000) = PHP 9,000,000 \text{CIP Balance} = \text{Costs Incurred (PHP 7,200,000)} + \text{Profit (PHP 1,800,000)} = \text{PHP }9{,}000{,}000 CIP Balance = Costs Incurred (PHP 7,200,000) + Profit (PHP 1,800,000) = PHP 9 , 000 , 000 Progress Billings = PHP 8,000,000 \text{Progress Billings} = \text{PHP }8{,}000{,}000 Progress Billings = PHP 8 , 000 , 000 Net Balance = PHP 9,000,000 − PHP 8,000,000 = PHP 1,000,000 (Debit) \text{Net Balance} = \text{PHP }9{,}000{,}000 - \text{PHP }8{,}000{,}000 = \text{PHP }1{,}000{,}000 \text{ (Debit)} Net Balance = PHP 9 , 000 , 000 − PHP 8 , 000 , 000 = PHP 1 , 000 , 000 (Debit) Presentation: Net Contract Asset of PHP 1,000,000 .
Year 2 (2025) Calculations (Full Contract Loss Scenario):
Cumulative Costs Incurred to Date: Cumulative Costs = PHP 7,200,000 + PHP 11,800,000 = PHP 19,000,000 \text{Cumulative Costs} = \text{PHP }7{,}200{,}000 + \text{PHP }11{,}800{,}000 = \text{PHP }19{,}000{,}000 Cumulative Costs = PHP 7 , 200 , 000 + PHP 11 , 800 , 000 = PHP 19 , 000 , 000
Total Estimated Costs: Total Costs = PHP 19,000,000 + PHP 13,000,000 = PHP 32,000,000 \text{Total Costs} = \text{PHP }19{,}000{,}000 + \text{PHP }13{,}000{,}000 = \text{PHP }32{,}000{,}000 Total Costs = PHP 19 , 000 , 000 + PHP 13 , 000 , 000 = PHP 32 , 000 , 000
Total Expected Contract Loss: Expected Total Loss = PHP 30,000,000 − PHP 32,000,000 = − PHP 2,000,000 \text{Expected Total Loss} = \text{PHP }30{,}000{,}000 - \text{PHP }32{,}000{,}000 = -\text{PHP }2{,}000{,}000 Expected Total Loss = PHP 30 , 000 , 000 − PHP 32 , 000 , 000 = − PHP 2 , 000 , 000
Gross Loss to Recognize in 2025: Because the entire expected loss of PHP 2,000,000 must be recognized immediately: Current Loss Recognized = Total Expected Loss (PHP 2,000,000) + 2024 Profit Recognized (PHP 1,800,000) = PHP 3,800,000 \text{Current Loss Recognized} = \text{Total Expected Loss (PHP 2,000,000)} + \text{2024 Profit Recognized (PHP 1,800,000)} = \text{PHP }3{,}800{,}000 Current Loss Recognized = Total Expected Loss (PHP 2,000,000) + 2024 Profit Recognized (PHP 1,800,000) = PHP 3 , 800 , 000
Revenue Recognized in 2025:
Physical completion percentage based on cost inputs: POC = PHP 19,000,000 PHP 32,000,000 = 59.375 % \text{POC} = \frac{\text{PHP }19{,}000{,}000}{\text{PHP }32{,}000{,}000} = 59.375\% POC = PHP 32 , 000 , 000 PHP 19 , 000 , 000 = 59.375%
Cumulative Revenue to Date: 59.375 % × PHP 30,000,000 = PHP 17,812,500 59.375\% \times \text{PHP }30{,}000{,}000 = \text{PHP }17{,}812{,}500 59.375% × PHP 30 , 000 , 000 = PHP 17 , 812 , 500 .
2025 Revenue = Cumulative Revenue PHP 17,812,500 - 2024 Revenue PHP 9,000,000 = PHP 8,812,500 .
2025 Construction Expense = Revenue PHP 8,812,500 + Recognized Loss PHP 3,800,000 = PHP 12,612,500 .
Balance Sheet Presentation at December 31, 2025: Cumulative Costs Incurred = PHP 19,000,000 \text{Cumulative Costs Incurred} = \text{PHP }19{,}000{,}000 Cumulative Costs Incurred = PHP 19 , 000 , 000 Less: Cumulative Net Loss to Date = ( PHP 2,000,000 ) \text{Less: Cumulative Net Loss to Date} = (\text{PHP }2{,}000{,}000) Less: Cumulative Net Loss to Date = ( PHP 2 , 000 , 000 ) CIP Net Carrying Amount = PHP 17,000,000 \text{CIP Net Carrying Amount} = \text{PHP }17{,}000{,}000 CIP Net Carrying Amount = PHP 17 , 000 , 000 Cumulative Progress Billings = PHP 8,000,000 + PHP 12,000,000 = PHP 20,000,000 \text{Cumulative Progress Billings} = \text{PHP }8{,}000{,}000 + \text{PHP }12{,}000{,}000 = \text{PHP }20{,}000{,}000 Cumulative Progress Billings = PHP 8 , 000 , 000 + PHP 12 , 000 , 000 = PHP 20 , 000 , 000 Net Balance = CIP (PHP 17,000,000) − Billings (PHP 20,000,000) = − PHP 3,000,000 (Credit) \text{Net Balance} = \text{CIP (PHP 17,000,000)} - \text{Billings (PHP 20,000,000)} = -\text{PHP }3{,}000{,}000 \text{ (Credit)} Net Balance = CIP (PHP 17,000,000) − Billings (PHP 20,000,000) = − PHP 3 , 000 , 000 (Credit) Presentation: Net Contract Liability of PHP 3,000,000 .
Year 3 (2026) Calculations (Completion):
Cumulative Costs Incurred: PHP 19,000,000 + PHP 12,000,000 = PHP 31,000,000 \text{PHP }19{,}000{,}000 + \text{PHP }12{,}000{,}000 = \text{PHP }31{,}000{,}000 PHP 19 , 000 , 000 + PHP 12 , 000 , 000 = PHP 31 , 000 , 000 .
Actual Final Contract Loss: PHP 30,000,000 − PHP 31,000,000 = − PHP 1,000,000 \text{PHP }30{,}000{,}000 - \text{PHP }31{,}000{,}000 = -\text{PHP }1{,}000{,}000 PHP 30 , 000 , 000 − PHP 31 , 000 , 000 = − PHP 1 , 000 , 000 .
Gross Profit / Adjustment Recognized in 2026:
Since PHP 2,000,000 loss was recognized cumulatively through 2025, and actual final loss is only PHP 1,000,000, a gross gain of PHP 1,000,000 is recognized in 2026.
2026 Revenue = PHP 30,000,000 - PHP 17,812,500 = PHP 12,187,500 .
2026 Construction Expense = PHP 12,187,500 - PHP 1,000,000 = PHP 11,187,500 .