15.2 Standard Costing & Variance Analysis
CPA Licensure Examination Philippines, CPALE
Track your progress as you read
Finished sections get a check mark.
1 Introduction & Overview of the CPALE
0.1 CPALE Structure, Qualification, and Examination Mechanics 0.2 Study Strategy, Subject Balance, and Time Management for the Three-Day Board Exam
2 FAR: Standard Setting, Conceptual Framework, Accounting Process & Financial Statements
1.1 Standard-Setting Bodies and Regulation of the Accountancy Profession 1.2 The Conceptual Framework for Financial Reporting 1.3 The Accounting Process: Journals, Worksheet, Adjusting, Closing, and Reversing Entries 1.4 Presentation of Financial Statements
3 FAR: Cash, Receivables & Financial Asset Investments
2.1 Cash, Cash Equivalents, Petty Cash, and Bank Reconciliation 2.2 Trade and Notes Receivables: Measurement, Expected Credit Losses, and Receivable Financing 2.3 Financial Asset Investments: FVPL, FVOCI, and Amortized Cost under PFRS 9
4 FAR: Inventories, Property, Plant & Equipment, and Investment Property
3.1 Inventories & Cost of Sales 3.2 Property, Plant and Equipment, Borrowing Costs, and Impairment 3.3 Investment Property and Agriculture (PAS 40 and PAS 41)
5 FAR: Intangibles, Held for Sale, Financial Liabilities & Provisions
4.1 Intangible Assets, Research and Development, and Goodwill 4.2 Non-Current Assets Held for Sale and Discontinued Operations (PFRS 5) 4.3 Financial Liabilities: Bonds Payable, Effective Interest, and Debt Restructuring 4.4 Provisions, Contingencies, Loyalty Programs, Warranties, and Unearned Revenue
6 FAR: Equity, Share-Based Payment, Leases, Income Taxes & Employee Benefits
5.1 Shareholders' Equity & Share-Based Payments 5.2 Leases under PFRS 16: Lessee, Lessor, and Sale-and-Leaseback 5.3 Income Taxes (PAS 12) and Employee Benefits (PAS 19)
7 FAR: EPS, Cash Flows, SMEs & Small Entities, and Interim Reporting
6.1 Earnings per Share and the Statement of Cash Flows 6.2 PFRS for SMEs, PFRS for Small Entities, and Micro Entities 6.3 Interim Financial Reporting (PAS 34) and Operating Segments (PFRS 8)
8 AFAR: Partnership Formation, Operations, Changes & Liquidation
7.1 Partnership Formation, Operations & Profit/Loss Allocation 7.2 Changes in Partnership Ownership: Admission, Retirement, Death, and Incorporation 7.3 Partnership Liquidation: Lump-Sum and Installment Methods
9 AFAR: Corporate Liquidation, Home Office & Branch, and Business Combinations
8.1 Corporate Liquidation & Statement of Affairs 8.2 Home Office, Branch & Agency Accounting 8.3 Business Combinations under PFRS 3
10 AFAR: Consolidation, Joint Arrangements & Associates
9.1 Consolidated Financial Statements under PFRS 10 & PAS 27 9.2 Joint Arrangements (PFRS 11): Joint Control, Joint Operations, and Joint Ventures 9.3 Investments in Associates and Joint Ventures: The Equity Method (PAS 28)
11 AFAR: Revenue Recognition and Construction Contracts
10.1 Revenue from Contracts with Customers: The Five-Step Model (PFRS 15) 10.2 Long-Term Construction Contracts: Measuring Progress, Contract Balances, and Losses 10.3 Special Revenue Issues under PFRS 15
12 AFAR: Franchises, Consignment, Foreign Currency & Derivatives
11.1 Franchise Operations and Consignment Sales 11.2 Foreign Currency Transactions and Translation (PAS 21 and PAS 29) 11.3 Derivatives and Hedge Accounting (PFRS 9)
13 AFAR: Government, Not-for-Profit, Insurance Contracts & Service Concessions
12.1 Government Accounting: The GAM for National Government Agencies 12.2 Not-for-Profit Organizations: Net Assets, Contributions, and Sector Types 12.3 Insurance Contracts (PFRS 17) and Service Concession Arrangements
14 AFAR: Cost Accounting Systems
13.1 Cost Accumulation Systems and Job Order Costing 13.2 Process Costing and Backflush Costing 13.3 Activity-Based Costing, Joint and By-Products, and Service Department Cost Allocation
15 MS: Management Accounting, Cost Behavior & CVP Analysis
14.1 The Role of Management Accounting, Professional Ethics, and Global Trends 14.2 Cost Classifications, Cost Behavior, and Cost Estimation 14.3 Cost-Volume-Profit (CVP) Analysis
16 MS: Variable Costing, Standard Costing & Budgeting
15.1 Variable Costing versus Absorption Costing 15.2 Standard Costing & Variance Analysis 15.3 Master Budgeting, Cash Budgets, and Flexible Budgets
17 MS: Performance Measurement and Relevant Costing
16.1 Responsibility Accounting, Segment Reporting, and Transfer Pricing 16.2 Balanced Scorecard, Operational Performance, and Emerging Trends 16.3 Relevant Costing & Short-Term Tactical Decisions
18 MS: Pricing, Quantitative Techniques & Financial Statement Analysis
17.1 Pricing Decisions & Profitability Analysis 17.2 Quantitative Techniques for Decision Making 17.3 Financial Statement Analysis & Ratio Analysis
19 MS: Working Capital Management and Capital Budgeting
18.1 Working Capital: Policies, Cash Conversion Cycle, and Cash Management 18.2 Working Capital: Receivables, Inventory, and Short-Term Financing 18.3 Capital Budgeting & Investment Decisions
20 MS: Risk, Cost of Capital, Financial Markets & Economics
19.1 Risk and Return, Leverage, and Cost of Capital 19.2 Financial Markets, Long-Term Financing, and Valuation 19.3 Microeconomics, Macroeconomics, and International Trade
21 AUD: Nature of Auditing, Regulation of the Profession & Code of Ethics
20.1 Nature of Auditing, Assurance, and Information Risk 20.2 The Regulatory Framework of the Accountancy Profession 20.3 Code of Ethics: Fundamental Principles, Conceptual Framework, and Threats
22 AUD: Independence, Quality Management & Engagement Planning
21.1 Independence: Financial Interests, Relationships, Rotation, Services, and Fees 21.2 Philippine Standards on Quality Management 21.3 Pre-Engagement Activities, Client Acceptance & Audit Planning
23 AUD: Audit Risk, Fraud, Materiality & Internal Control
22.1 Audit Risk Model and Fraud Risk 22.2 Materiality: Overall, Performance, and Clearly Trivial Thresholds 22.3 Understanding the Entity & Internal Control Evaluation
24 AUD: IT Environment, Audit Evidence & Sampling
23.1 Auditing in a Computer Information Systems (CIS) Environment 23.2 Audit Evidence, Assertions, Procedures, and Documentation 23.3 Audit Sampling: Attribute, Variable, and Monetary Unit Sampling
25 AUD: Business Process Audits and Auditing Practice Problems
24.1 Substantive Testing of Business Cycles 24.2 Auditing Practice: Cash and Receivables 24.3 Auditing Practice: Inventory, Property, and Liabilities
26 AUD: Completing the Audit, Reporting & Other Assurance Services
25.1 Completing the Audit, Subsequent Events & Going Concern 25.2 The Auditor's Report: Opinions, KAM, EOM, and Comparatives 25.3 Other Assurance and Related Services Engagements
27 TAX: Principles of Taxation and Assessment Remedies
26.1 Taxation: Nature, Inherent Powers, and Limitations 26.2 The Tax System: Canons, Double Taxation, Evasion, and Sources of Tax Law 26.3 Tax Remedies: Assessment, Protest, and Appeal
28 TAX: Refunds, Collection & Prescription, Gross Income, and Fringe Benefits
27.1 Tax Remedies: Refunds, Collection, and Prescription 27.2 Gross Income: Inclusions and Exclusions 27.3 De Minimis Benefits and the Fringe Benefits Tax
29 TAX: Individual and Corporate Income Taxation
28.1 Individual Income Tax: Classification, Rates, and the 8% Option 28.2 Individual Income Tax: Deductions, Passive Income, and Capital Gains 28.3 Corporate Income Taxation under the CREATE Law
30 TAX: Estate Tax, Donor's Tax, Withholding & Special Tax Laws
29.1 Estate Tax under the NIRC as Amended by the TRAIN Law 29.2 Donor's Tax under the NIRC as Amended by the TRAIN Law 29.3 Withholding Taxes, EOPT Compliance, and Special Tax Laws
31 TAX: Value-Added Tax and Percentage Taxes
30.1 Value-Added Tax: Nature, Registration, Output Tax, and Exemptions 30.2 Value-Added Tax: Input Tax, Allocation, Withholding, and Filing 30.3 Percentage Taxes & Other Business Taxes
32 TAX: Local Taxes, DST & Excise, and Incentives & Treaties
31.1 Local Taxation and Real Property Tax 31.2 Documentary Stamp Tax and Excise Taxes 31.3 Tax Incentives under CREATE MORE and Tax Treaties
33 RFBT: Law on Obligations
32.1 Obligations: Nature, Sources, and Effects 32.2 Kinds of Obligations 32.3 Extinguishment of Obligations
34 RFBT: Contracts, Defective Contracts & Sales
33.1 Law on Contracts: Essential Requisites & Performance 33.2 Defective Contracts 33.3 Sales: Nature, Object and Price, Delivery, and Double Sales
35 RFBT: Installment Sales, Credit Transactions & Partnerships
34.1 Sales: Warranties, Installment Sales, and Redemption 34.2 Credit Transactions & Security Mechanisms 34.3 Law on Partnerships
36 RFBT: Corporations - Nature, Incorporation & Board of Directors
35.1 Corporations: Nature, Separate Personality, Classes, and Nationality 35.2 Corporations: Incorporation, Articles and Bylaws, and Corporate Powers 35.3 Corporations: Board of Directors, Officers, and Fiduciary Duties
37 RFBT: Corporations - Stockholders, Capital & Corporate Changes
36.1 Corporations: Stockholders, Meetings, and One Person Corporations 36.2 Corporations: Capital Stock, Shares, and Subscriptions 36.3 Corporations: Mergers, Dissolution, Foreign Corporations, and SEC Powers
38 RFBT: Securities Regulation, Insurance & Cooperatives
37.1 Securities Regulation, Corporate Governance, and SRC Rule 68 37.2 Insurance Law 37.3 Cooperatives under the Philippine Cooperative Code (RA 9520)
39 RFBT: Banking Laws, AMLA & Bouncing Checks
38.1 Banking Laws, Bank Secrecy & PDIC 38.2 Anti-Money Laundering Act (AMLA) 38.3 Bouncing Checks Law (BP 22)
40 RFBT: Insolvency, Competition, Data Privacy & Labor Laws
39.1 Financial Rehabilitation and Insolvency Act (FRIA) 39.2 Competition, Consumer Protection, and Government Procurement 39.3 Data Privacy, Intellectual Property, and Electronic Commerce 39.4 Ease of Doing Business, Labor Standards, and Social Security
15.2 Standard Costing & Variance Analysis
Key Takeaways Explain This Topic AI
Standard costs serve as predetermined performance benchmarks established under efficient operating conditions, where currently attainable (practical) standards motivate realistic employee performance while ideal (perfection) standards frequently cause frustration and unfavorable variances.
Direct material price variance (MPV) can be isolated at the point of purchase ( A Q purchased × [ A P − S P ] AQ_{\text{purchased}} \times [AP - SP] A Q purchased × [ A P − SP ] ) for prompt managerial feedback or at the point of issuance ( A Q used × [ A P − S P ] AQ_{\text{used}} \times [AP - SP] A Q used × [ A P − SP ] ), while material quantity variance (MQV) is strictly computed as S P × [ A Q used − S Q allowed ] SP \times [AQ_{\text{used}} - SQ_{\text{allowed}}] SP × [ A Q used − S Q allowed ] .
Direct labor variances isolate labor rate variance ( L R V = A H × [ A R − S R ] LRV = AH \times [AR - SR] L R V = A H × [ A R − SR ] ) caused by wage differentials or crew mix shifts, and labor efficiency variance ( L E V = S R × [ A H − S H ] LEV = SR \times [AH - SH] L E V = SR × [ A H − S H ] ) driven by worker skill, machine reliability, and material quality.
Factory overhead variance analysis can be structured into 2-way (Controllable vs Volume), 3-way (Spending, Variable Efficiency, Volume), or 4-way (Variable Spending, Fixed Spending, Variable Efficiency, Fixed Volume), where Volume Variance measures the under- or over-absorption of fixed overhead resulting from deviations from denominator activity.
When inputs can be substituted, the materials or labor quantity variance splits into a mix variance (proportion of inputs) and a yield variance (output obtained from total input).
Last updated: September 2026
Standard Costing & Variance Analysis
Standard costing is a foundational management control methodology that establishes predetermined cost benchmarks for direct materials, direct labor, and factory overhead against which actual operating performance is systematically measured. In the Philippine CPA Licensure Examination (CPALE), standard costing and variance analysis questions routinely test a candidate's mastery of variance decomposition, denominator activity adjustments, and the accounting disposition of cost variances under Philippine Accounting Standard (PAS) 2 (Inventories).
1. Nature, Purpose, and Establishment of Standard Costs
A standard cost is a carefully predetermined measure of what a unit of product or service should cost under specified operating conditions. While an estimated cost represents an anticipation of actual historical trends and a budget represents an aggregate operational plan expressed in monetary terms, a standard cost expresses a unit-level engineering and managerial benchmark.
Primary Purposes of a Standard Costing System
Management Control and Performance Evaluation : Enables the principle of management by exception , directing managerial attention strictly to significant deviations (variances) from standard.
Product Costing and Inventory Valuation : Simplifies cost accumulation records, as inventories of raw materials, work in process, and finished goods are carried at uniform standard costs.
Budget Preparation and Cash Forecasting : Provides validated unit inputs for master budgeting, cash planning, and flexible budget formulation.
Operational Cost Reduction : Encourages continuous improvement and highlights inefficient material conversion or labor downtime.
Setting Standards: Ideal vs Currently Attainable Standards
Standard Type Operational Definition Practical & Behavioral Implications
Ideal Standards (Perfection / Theoretical) Costs that can be achieved only under the most optimal operating conditions, assuming 100% capacity, zero machine breakdowns, zero material waste, and flawless worker execution. Discourages operating personnel due to constant failure to meet targets; results in perpetual unfavorable variances; unsuitable for realistic budgeting or cash forecasting.
Currently Attainable Standards (Practical / Normal) Efficient, realistic benchmarks achievable by operating personnel working at normal efficiency, incorporating allowances for routine machine maintenance, normal material shrinkage, and standard rest periods. Highly motivational for workforce performance; serves as a dependable baseline for pricing, cash budgeting, and variance analysis; standard approach adopted on the CPALE.
The Standard Cost Card
A standard cost card outlines the standard quantities ( S Q SQ SQ ) and standard rates ( S P SP SP , S R SR SR , P O H R POHR PO H R ) required to produce one unit of finished product:
Standard Unit Cost = ( S Q DM × S P DM ) + ( S H DL × S R DL ) + ( S H DL × V O H R ) + ( S H DL × F O H R ) \text{Standard Unit Cost} = (SQ_{\text{DM}} \times SP_{\text{DM}}) + (SH_{\text{DL}} \times SR_{\text{DL}}) + (SH_{\text{DL}} \times VOHR) + (SH_{\text{DL}} \times FOHR) Standard Unit Cost = ( S Q DM × S P DM ) + ( S H DL × S R DL ) + ( S H DL × V O H R ) + ( S H DL × FO H R )
2. Direct Material Variances
Direct material variance analysis decomposes the total direct material cost variance into price and quantity dimensions:
Total Material Variance = ( A Q × A P ) − ( S Q × S P ) \text{Total Material Variance} = (AQ \times AP) - (SQ \times SP) Total Material Variance = ( A Q × A P ) − ( SQ × SP ) Direct Material Variance Decomposition
- │
- ┌─────────────────────────┴─────────────────────────┐
- ▼ ▼
- Material Price Variance (MPV) Material Quantity Variance (MQV)
- Responsibility: Purchasing Responsibility: Production
- Formula: AQ * (AP - SP) Formula: SP * (AQ - SQ)
- Material Price Variance (MPV)
The Material Price Variance reflects the difference between the actual unit purchase price ( A P AP A P ) and the standard unit purchase price ( S P SP SP ), multiplied by actual quantity ( A Q AQ A Q ):
M P V = A Q × ( A P − S P ) = ( A Q × A P ) − ( A Q × S P ) MPV = AQ \times (AP - SP) = (AQ \times AP) - (AQ \times SP) MP V = A Q × ( A P − SP ) = ( A Q × A P ) − ( A Q × SP )
Unfavorable ( U U U ) : A P > S P AP > SP A P > SP (actual outlay exceeds standard expectation).
Favorable ( F F F ) : A P < S P AP < SP A P < SP (actual outlay is less than standard expectation).
Point of Purchase vs Point of Issuance
On the CPALE, the timing of MPV isolation is a critical distinction:
Point of Purchase (Standard Practice) : M P V = A Q purchased × ( A P − S P ) MPV = AQ_{\text{purchased}} \times (AP - SP) MP V = A Q purchased × ( A P − SP ) . Raw Materials Inventory is recorded at standard cost upon receipt. This isolates the purchasing variance immediately, providing timely feedback to procurement officers.
Point of Issuance (Consumption) : M P V = A Q used × ( A P − S P ) MPV = AQ_{\text{used}} \times (AP - SP) MP V = A Q used × ( A P − SP ) . Raw Materials Inventory is recorded at actual cost, and MPV is deferred until materials are requisitioned into production. This delays variance reporting and impairs managerial accountability.
Material Quantity (Usage) Variance (MQV)
The Material Quantity Variance evaluates operational efficiency in the factory, comparing the actual quantity of materials requisitioned ( A Q used AQ_{\text{used}} A Q used ) against the standard quantity allowed ( S Q SQ SQ ) for actual production, valued at standard price ( S P SP SP ):
M Q V = S P × ( A Q used − S Q ) = ( A Q used × S P ) − ( S Q × S P ) MQV = SP \times (AQ_{\text{used}} - SQ) = (AQ_{\text{used}} \times SP) - (SQ \times SP) MQ V = SP × ( A Q used − SQ ) = ( A Q used × SP ) − ( SQ × SP )
Standard Quantity Allowed ( S Q ) = Actual Output in Units × Standard Quantity per Unit \text{Standard Quantity Allowed } (SQ) = \text{Actual Output in Units} \times \text{Standard Quantity per Unit} Standard Quantity Allowed ( SQ ) = Actual Output in Units × Standard Quantity per Unit
Critical Exam Rule : Never compute S Q SQ SQ using budgeted or planned units. S Q SQ SQ is always the standard input allowed for the actual units produced during the period.
Operational Causes of Material Variances
Price Variance Causes : Market price fluctuations, purchasing higher or lower quality grades, changes in vendor volume discounts, expedited shipping freight charges, purchasing from unauthorized suppliers.
Quantity Variance Causes : Substandard material grades (often caused by purchasing cheap materials, generating a favorable MPV but an unfavorable MQV), untrained machine operators, poorly maintained machinery, altered production specifications, scrap and shrinkage.
3. Direct Labor Variances
Direct labor variance analysis isolates the economic impact of wage rate differentials and labor productivity:
Total Labor Variance = ( A H × A R ) − ( S H × S R ) \text{Total Labor Variance} = (AH \times AR) - (SH \times SR) Total Labor Variance = ( A H × A R ) − ( S H × SR )
Labor Rate Variance (LRV)
The Labor Rate Variance isolates the difference between the actual hourly wage rate paid ( A R AR A R ) and the standard hourly wage rate ( S R SR SR ), multiplied by actual direct labor hours worked ( A H AH A H ):
L R V = A H × ( A R − S R ) = ( A H × A R ) − ( A H × S R ) LRV = AH \times (AR - SR) = (AH \times AR) - (AH \times SR) L R V = A H × ( A R − SR ) = ( A H × A R ) − ( A H × SR )
Unfavorable ( U U U ) : A R > S R AR > SR A R > SR (overtime premiums, wage hikes, using higher-skilled workers for low-skill tasks).
Favorable ( F F F ) : A R < S R AR < SR A R < SR (using lower-skilled or apprentice workers, favorable market wage shifts).
Labor Efficiency Variance (LEV)
The Labor Efficiency Variance (or labor usage variance) measures the productivity of the workforce by comparing actual hours worked ( A H AH A H ) against standard hours allowed ( S H SH S H ), valued at the standard hourly wage rate ( S R SR SR ):
L E V = S R × ( A H − S H ) = ( A H × S R ) − ( S H × S R ) LEV = SR \times (AH - SH) = (AH \times SR) - (SH \times SR) L E V = SR × ( A H − S H ) = ( A H × SR ) − ( S H × SR )
Standard Hours Allowed ( S H ) = Actual Output in Units × Standard Labor Hours per Unit \text{Standard Hours Allowed } (SH) = \text{Actual Output in Units} \times \text{Standard Labor Hours per Unit} Standard Hours Allowed ( S H ) = Actual Output in Units × Standard Labor Hours per Unit
Operational Causes of Labor Variances
Rate Variance Drivers : Assignment of higher-grade technicians to routine assembly jobs, unexpected overtime penalties due to rushed customer orders, negotiated statutory wage increases.
Efficiency Variance Drivers : Inadequate worker training, poor supervision, machine breakdowns causing idle time, defective raw materials requiring excessive re-work, optimized workflow ergonomics.
4. Factory Overhead Variance Analysis
Factory overhead variance analysis is among the most heavily tested areas in the CPALE Management Services syllabus. Overhead includes both variable and fixed components that behave differently relative to operational activity.
Denominator Activity and Predetermined Overhead Rates
Overhead rates are established prior to the operating period based on a denominator activity level (normal capacity or practical capacity):
Variable Overhead Rate ( V O H R ) = Budgeted Variable Overhead at Normal Capacity Denominator Hours ( D H ) \text{Variable Overhead Rate } (VOHR) = \frac{\text{Budgeted Variable Overhead at Normal Capacity}}{\text{Denominator Hours } (DH)} Variable Overhead Rate ( V O H R ) = Denominator Hours ( DH ) Budgeted Variable Overhead at Normal Capacity
Fixed Overhead Rate ( F O H R ) = Budgeted Fixed Overhead Denominator Hours ( D H ) \text{Fixed Overhead Rate } (FOHR) = \frac{\text{Budgeted Fixed Overhead}}{\text{Denominator Hours } (DH)} Fixed Overhead Rate ( FO H R ) = Denominator Hours ( DH ) Budgeted Fixed Overhead
Total Standard Overhead Rate ( S O H R ) = V O H R + F O H R \text{Total Standard Overhead Rate } (SOHR) = VOHR + FOHR Total Standard Overhead Rate ( SO H R ) = V O H R + FO H R
Applied Factory Overhead = S H × S O H R = ( S H × V O H R ) + ( S H × F O H R ) \text{Applied Factory Overhead} = SH \times SOHR = (SH \times VOHR) + (SH \times FOHR) Applied Factory Overhead = S H × SO H R = ( S H × V O H R ) + ( S H × FO H R )
Total Overhead Variance (Under/Overapplied) = Actual Total Overhead − Applied Total Overhead \text{Total Overhead Variance (Under/Overapplied)} = \text{Actual Total Overhead} - \text{Applied Total Overhead} Total Overhead Variance (Under/Overapplied) = Actual Total Overhead − Applied Total Overhead
If Actual OH > Applied OH \text{Actual OH} > \text{Applied OH} Actual OH > Applied OH : Underapplied Overhead (Unfavorable).
If Actual OH < Applied OH \text{Actual OH} < \text{Applied OH} Actual OH < Applied OH : Overapplied Overhead (Favorable).
Four-Way Overhead Variance Analysis
Four-way analysis provides the most detailed breakdown by splitting both variable and fixed overhead into spending and volume/efficiency components:
Variable Overhead Spending Variance : VOH Spending = Actual VOH − ( A H × V O H R ) \text{VOH Spending} = \text{Actual VOH} - (AH \times VOHR) VOH Spending = Actual VOH − ( A H × V O H R ) Measures price deviations for indirect materials, lubricants, and utility rate variations per labor hour.
Fixed Overhead Spending (Budget) Variance : FOH Spending = Actual FOH − Budgeted FOH \text{FOH Spending} = \text{Actual FOH} - \text{Budgeted FOH} FOH Spending = Actual FOH − Budgeted FOH Reflects deviations between actual fixed costs (e.g., factory insurance, supervisory salaries) and predetermined budget allowances.
Variable Overhead Efficiency Variance : VOH Efficiency = ( A H − S H ) × V O H R \text{VOH Efficiency} = (AH - SH) \times VOHR VOH Efficiency = ( A H − S H ) × V O H R Measures the variable overhead consumed or saved strictly as a result of using more or fewer labor/machine hours than standard.
Fixed Overhead Volume Variance : FOH Volume = Budgeted FOH − ( S H × F O H R ) = ( D H − S H ) × F O H R \text{FOH Volume} = \text{Budgeted FOH} - (SH \times FOHR) = (DH - SH) \times FOHR FOH Volume = Budgeted FOH − ( S H × FO H R ) = ( DH − S H ) × FO H R Measures the cost of capacity underutilization ( D H > S H DH > SH DH > S H , Unfavorable) or overutilization ( D H < S H DH < SH DH < S H , Favorable). Fixed overhead has no efficiency variance because fixed costs do not vary with operating hours.
Three-Way Overhead Variance Analysis
Combines the variable and fixed spending variances into a single spending variance:
Overhead Spending Variance : Spending Variance = Actual Total OH − Budget Allowed on Actual Hours (BAAH) \text{Spending Variance} = \text{Actual Total OH} - \text{Budget Allowed on Actual Hours (BAAH)} Spending Variance = Actual Total OH − Budget Allowed on Actual Hours (BAAH) BAAH = Budgeted FOH + ( A H × V O H R ) \text{BAAH} = \text{Budgeted FOH} + (AH \times VOHR) BAAH = Budgeted FOH + ( A H × V O H R )
Variable Overhead Efficiency Variance : Efficiency Variance = ( A H − S H ) × V O H R \text{Efficiency Variance} = (AH - SH) \times VOHR Efficiency Variance = ( A H − S H ) × V O H R
Fixed Overhead Volume Variance : Volume Variance = Budgeted FOH − ( S H × F O H R ) = ( D H − S H ) × F O H R \text{Volume Variance} = \text{Budgeted FOH} - (SH \times FOHR) = (DH - SH) \times FOHR Volume Variance = Budgeted FOH − ( S H × FO H R ) = ( DH − S H ) × FO H R
Two-Way Overhead Variance Analysis
Combines spending and efficiency into a single controllable metric:
Controllable (Budget) Variance : Controllable Variance = Actual Total OH − Budget Allowed on Standard Hours (BASH) \text{Controllable Variance} = \text{Actual Total OH} - \text{Budget Allowed on Standard Hours (BASH)} Controllable Variance = Actual Total OH − Budget Allowed on Standard Hours (BASH) BASH = Budgeted FOH + ( S H × V O H R ) \text{BASH} = \text{Budgeted FOH} + (SH \times VOHR) BASH = Budgeted FOH + ( S H × V O H R ) Note : Controllable Variance equals VOH Spending + FOH Spending + VOH Efficiency \text{VOH Spending} + \text{FOH Spending} + \text{VOH Efficiency} VOH Spending + FOH Spending + VOH Efficiency .
Volume (Capacity / Denominator) Variance : Volume Variance = BASH − Applied Total OH = ( D H − S H ) × F O H R \text{Volume Variance} = \text{BASH} - \text{Applied Total OH} = (DH - SH) \times FOHR Volume Variance = BASH − Applied Total OH = ( DH − S H ) × FO H R
Comprehensive Variance Mapping Matrix
- 4-Way Analysis 3-Way Analysis 2-Way Analysis
- Variable Overhead Spending } Spending Variance } Controllable (Budget) Variance
- Fixed Overhead Spending / /
- Variable Overhead Efficiency Variable Overhead Efficiency /
- Fixed Overhead Volume Fixed Overhead Volume Volume (Denominator) Variance
- 5. Comprehensive Worked Computational Example
Scenario : Marikina Manufacturing Corporation manufactures specialized industrial valves. The standard cost card for one finished valve reflects the following standards:
Direct materials: 3 kg 3\text{ kg} 3 kg at PHP 60 / kg = PHP 180 \text{PHP }60/\text{kg} = \text{PHP }180 PHP 60/ kg = PHP 180
Direct labor: 2 hours 2\text{ hours} 2 hours at PHP 150 / hour = PHP 300 \text{PHP }150/\text{hour} = \text{PHP }300 PHP 150/ hour = PHP 300
Variable factory overhead: 2 direct labor hours 2\text{ direct labor hours} 2 direct labor hours at PHP 40 / hour = PHP 80 \text{PHP }40/\text{hour} = \text{PHP }80 PHP 40/ hour = PHP 80
Fixed factory overhead: 2 direct labor hours 2\text{ direct labor hours} 2 direct labor hours at PHP 70 / hour = PHP 140 \text{PHP }70/\text{hour} = \text{PHP }140 PHP 70/ hour = PHP 140
Denominator activity (Normal Capacity) : 10,000 direct labor hours 10{,}000\text{ direct labor hours} 10 , 000 direct labor hours ( 5,000 valves 5{,}000\text{ valves} 5 , 000 valves )
Budgeted Fixed Overhead : 10,000 hours × PHP 70 = PHP 700,000 10{,}000\text{ hours} \times \text{PHP }70 = \text{PHP }700{,}000 10 , 000 hours × PHP 70 = PHP 700 , 000
Actual Operating Results for the Month :
Actual valves produced: 4,800 units 4{,}800\text{ units} 4 , 800 units
Direct materials purchased: 16,000 kg 16{,}000\text{ kg} 16 , 000 kg at PHP 58 / kg = PHP 928,000 \text{PHP }58/\text{kg} = \text{PHP }928{,}000 PHP 58/ kg = PHP 928 , 000
Direct materials used: 14,900 kg 14{,}900\text{ kg} 14 , 900 kg
Direct labor payroll: 9,850 hours 9{,}850\text{ hours} 9 , 850 hours at PHP 154 / hour = PHP 1,516,900 \text{PHP }154/\text{hour} = \text{PHP }1{,}516{,}900 PHP 154/ hour = PHP 1 , 516 , 900
- Actual variable overhead: PHP 410,000 \text{PHP }410{,}000 PHP 410 , 000
- Actual fixed overhead: PHP 715,000 \text{PHP }715{,}000 PHP 715 , 000
- Total actual overhead: PHP 1,125,000 \text{PHP }1{,}125{,}000 PHP 1 , 125 , 000
- Step-by-Step Variance Calculations
- 1. Direct Material Variances
Standard Quantity Allowed ( S Q SQ SQ ) : 4,800 units × 3 kg = 14,400 kg 4{,}800\text{ units} \times 3\text{ kg} = 14{,}400\text{ kg} 4 , 800 units × 3 kg = 14 , 400 kg
MPV (Point of Purchase) : 16,000 kg × ( PHP 58 − PHP 60 ) = 16,000 × ( − PHP 2 ) = PHP 32,000 Favorable (F) 16{,}000\text{ kg} \times (\text{PHP }58 - \text{PHP }60) = 16{,}000 \times (-\text{PHP }2) = \text{PHP }32{,}000\text{ Favorable (F)} 16 , 000 kg × ( PHP 58 − PHP 60 ) = 16 , 000 × ( − PHP 2 ) = PHP 32 , 000 Favorable (F)
MPV (Point of Issuance) : 14,900 kg × ( PHP 58 − PHP 60 ) = 14,900 × ( − PHP 2 ) = PHP 29,800 Favorable (F) 14{,}900\text{ kg} \times (\text{PHP }58 - \text{PHP }60) = 14{,}900 \times (-\text{PHP }2) = \text{PHP }29{,}800\text{ Favorable (F)} 14 , 900 kg × ( PHP 58 − PHP 60 ) = 14 , 900 × ( − PHP 2 ) = PHP 29 , 800 Favorable (F)
Material Quantity Variance (MQV) : PHP 60 × ( 14,900 kg − 14,400 kg ) = PHP 60 × 500 kg = PHP 30,000 Unfavorable (U) \text{PHP }60 \times (14{,}900\text{ kg} - 14{,}400\text{ kg}) = \text{PHP }60 \times 500\text{ kg} = \text{PHP }30{,}000\text{ Unfavorable (U)} PHP 60 × ( 14 , 900 kg − 14 , 400 kg ) = PHP 60 × 500 kg = PHP 30 , 000 Unfavorable (U)
2. Direct Labor Variances
Standard Hours Allowed ( S H SH S H ) : 4,800 units × 2 hours = 9,600 hours 4{,}800\text{ units} \times 2\text{ hours} = 9{,}600\text{ hours} 4 , 800 units × 2 hours = 9 , 600 hours
Labor Rate Variance (LRV) : 9,850 hours × ( PHP 154 − PHP 150 ) = 9,850 × PHP 4 = PHP 39,400 Unfavorable (U) 9{,}850\text{ hours} \times (\text{PHP }154 - \text{PHP }150) = 9{,}850 \times \text{PHP }4 = \text{PHP }39{,}400\text{ Unfavorable (U)} 9 , 850 hours × ( PHP 154 − PHP 150 ) = 9 , 850 × PHP 4 = PHP 39 , 400 Unfavorable (U)
Labor Efficiency Variance (LEV) : PHP 150 × ( 9,850 hours − 9,600 hours ) = PHP 150 × 250 hours = PHP 37,500 Unfavorable (U) \text{PHP }150 \times (9{,}850\text{ hours} - 9{,}600\text{ hours}) = \text{PHP }150 \times 250\text{ hours} = \text{PHP }37{,}500\text{ Unfavorable (U)} PHP 150 × ( 9 , 850 hours − 9 , 600 hours ) = PHP 150 × 250 hours = PHP 37 , 500 Unfavorable (U)
Total Labor Variance : PHP 39,400 U + PHP 37,500 U = PHP 76,900 Unfavorable (U) \text{PHP }39{,}400\text{ U} + \text{PHP }37{,}500\text{ U} = \text{PHP }76{,}900\text{ Unfavorable (U)} PHP 39 , 400 U + PHP 37 , 500 U = PHP 76 , 900 Unfavorable (U)
3. Factory Overhead Variances
Overhead Applied : 9,600 SH × PHP 110 (SOHR) = PHP 1,056,000 9{,}600\text{ SH} \times \text{PHP }110\text{ (SOHR)} = \text{PHP }1{,}056{,}000 9 , 600 SH × PHP 110 (SOHR) = PHP 1 , 056 , 000
Total Overhead Variance : PHP 1,125,000 (Actual) − PHP 1,056,000 (Applied) = PHP 69,000 Underapplied (U) \text{PHP }1{,}125{,}000\text{ (Actual)} - \text{PHP }1{,}056{,}000\text{ (Applied)} = \text{PHP }69{,}000\text{ Underapplied (U)} PHP 1 , 125 , 000 (Actual) − PHP 1 , 056 , 000 (Applied) = PHP 69 , 000 Underapplied (U)
Four-Way Breakdown :
VOH Spending = Actual VOH ( PHP 410,000 ) − ( 9,850 AH × PHP 40 ) = 410,000 − 394,000 = PHP 16,000 U \text{VOH Spending} = \text{Actual VOH } (\text{PHP }410{,}000) - (9{,}850\text{ AH} \times \text{PHP }40) = 410{,}000 - 394{,}000 = \text{PHP }16{,}000\text{ U} VOH Spending = Actual VOH ( PHP 410 , 000 ) − ( 9 , 850 AH × PHP 40 ) = 410 , 000 − 394 , 000 = PHP 16 , 000 U
FOH Spending = Actual FOH ( PHP 715,000 ) − Budgeted FOH ( PHP 700,000 ) = PHP 15,000 U \text{FOH Spending} = \text{Actual FOH } (\text{PHP }715{,}000) - \text{Budgeted FOH } (\text{PHP }700{,}000) = \text{PHP }15{,}000\text{ U} FOH Spending = Actual FOH ( PHP 715 , 000 ) − Budgeted FOH ( PHP 700 , 000 ) = PHP 15 , 000 U
VOH Efficiency = ( 9,850 AH − 9,600 SH ) × PHP 40 = 250 × 40 = PHP 10,000 U \text{VOH Efficiency} = (9{,}850\text{ AH} - 9{,}600\text{ SH}) \times \text{PHP }40 = 250 \times 40 = \text{PHP }10{,}000\text{ U} VOH Efficiency = ( 9 , 850 AH − 9 , 600 SH ) × PHP 40 = 250 × 40 = PHP 10 , 000 U
FOH Volume = ( 10,000 DH − 9,600 SH ) × PHP 70 = 400 × 70 = PHP 28,000 U \text{FOH Volume} = (10{,}000\text{ DH} - 9{,}600\text{ SH}) \times \text{PHP }70 = 400 \times 70 = \text{PHP }28{,}000\text{ U} FOH Volume = ( 10 , 000 DH − 9 , 600 SH ) × PHP 70 = 400 × 70 = PHP 28 , 000 U Total 4-Way Sum = 16,000 U + 15,000 U + 10,000 U + 28,000 U = PHP 69,000 Unfavorable \text{Total 4-Way Sum} = 16{,}000\text{ U} + 15{,}000\text{ U} + 10{,}000\text{ U} + 28{,}000\text{ U} = \text{PHP }69{,}000\text{ Unfavorable} Total 4-Way Sum = 16 , 000 U + 15 , 000 U + 10 , 000 U + 28 , 000 U = PHP 69 , 000 Unfavorable
Three-Way Breakdown :
Spending Variance = Actual OH ( 1,125,000 ) − [ 700,000 + ( 9,850 × 40 ) ] = 1,125,000 − 1,094,000 = PHP 31,000 U \text{Spending Variance} = \text{Actual OH } (1{,}125{,}000) - [700{,}000 + (9{,}850 \times 40)] = 1{,}125{,}000 - 1{,}094{,}000 = \text{PHP }31{,}000\text{ U} Spending Variance = Actual OH ( 1 , 125 , 000 ) − [ 700 , 000 + ( 9 , 850 × 40 )] = 1 , 125 , 000 − 1 , 094 , 000 = PHP 31 , 000 U
VOH Efficiency = ( 9,850 − 9,600 ) × PHP 40 = PHP 10,000 U \text{VOH Efficiency} = (9{,}850 - 9{,}600) \times \text{PHP }40 = \text{PHP }10{,}000\text{ U} VOH Efficiency = ( 9 , 850 − 9 , 600 ) × PHP 40 = PHP 10 , 000 U
FOH Volume = ( 10,000 − 9,600 ) × PHP 70 = PHP 28,000 U \text{FOH Volume} = (10{,}000 - 9{,}600) \times \text{PHP }70 = \text{PHP }28{,}000\text{ U} FOH Volume = ( 10 , 000 − 9 , 600 ) × PHP 70 = PHP 28 , 000 U Total 3-Way Sum = 31,000 U + 10,000 U + 28,000 U = PHP 69,000 Unfavorable \text{Total 3-Way Sum} = 31{,}000\text{ U} + 10{,}000\text{ U} + 28{,}000\text{ U} = \text{PHP }69{,}000\text{ Unfavorable} Total 3-Way Sum = 31 , 000 U + 10 , 000 U + 28 , 000 U = PHP 69 , 000 Unfavorable
Two-Way Breakdown :
Controllable Variance = Actual OH ( 1,125,000 ) − [ 700,000 + ( 9,600 × 40 ) ] = 1,125,000 − 1,084,000 = PHP 41,000 U \text{Controllable Variance} = \text{Actual OH } (1{,}125{,}000) - [700{,}000 + (9{,}600 \times 40)] = 1{,}125{,}000 - 1{,}084{,}000 = \text{PHP }41{,}000\text{ U} Controllable Variance = Actual OH ( 1 , 125 , 000 ) − [ 700 , 000 + ( 9 , 600 × 40 )] = 1 , 125 , 000 − 1 , 084 , 000 = PHP 41 , 000 U
Volume Variance = ( 10,000 DH − 9,600 SH ) × PHP 70 = PHP 28,000 U \text{Volume Variance} = (10{,}000\text{ DH} - 9{,}600\text{ SH}) \times \text{PHP }70 = \text{PHP }28{,}000\text{ U} Volume Variance = ( 10 , 000 DH − 9 , 600 SH ) × PHP 70 = PHP 28 , 000 U Total 2-Way Sum = 41,000 U + 28,000 U = PHP 69,000 Unfavorable \text{Total 2-Way Sum} = 41{,}000\text{ U} + 28{,}000\text{ U} = \text{PHP }69{,}000\text{ Unfavorable} Total 2-Way Sum = 41 , 000 U + 28 , 000 U = PHP 69 , 000 Unfavorable
6. Accounting Disposition of Variances
At the end of an accounting period, standard cost variances must be cleared from the ledger. Management and financial accountants follow distinct treatment based on materiality:
1. Direct Write-Off to Cost of Goods Sold
When Applied : Variances are immaterial or result from normal operational inefficiencies.
Accounting Treatment : Unfavorable variances are debited to Cost of Goods Sold (increasing expense), while favorable variances are credited to Cost of Goods Sold (reducing expense).
2. Proration Among WIP, Finished Goods, and COGS
When Applied : Variances are material or arise from significant misestimations of standard costs or capacity levels.
Mandate under PAS 2 (Inventories) : Under PAS 2, paragraph 13, normal capacity represents production expected to be achieved on average over several periods. The amount of fixed overhead allocated to each unit of production is not increased as a consequence of low production. Unallocated overheads (unfavorable volume variance) are recognized as an expense in the period in which they are incurred. However, when standards are revised or material price/quantity variances distort ending inventory valuations, variances are allocated proportionately based on the relative ending standard cost balances of:
- Work in Process (WIP) Inventory
- Finished Goods (FG) Inventory
- Cost of Goods Sold (COGS)
Note : Material Price Variance isolated at purchase is prorated across Raw Materials Inventory, WIP, Finished Goods, and COGS.
7. Materials Mix and Yield Variances
When two or more materials (or labor grades) can be substituted for each other, the quantity (usage) variance splits into a mix variance and a yield variance .
Mix variance = ∑ ( Actual qty in actual mix × Std price ) − ( Total actual qty × Std weighted average price ) \text{Mix variance} = \sum(\text{Actual qty in actual mix} \times \text{Std price}) - (\text{Total actual qty} \times \text{Std weighted average price}) Mix variance = ∑ ( Actual qty in actual mix × Std price ) − ( Total actual qty × Std weighted average price )
Yield variance = ( Total actual input − Std input allowed for actual output ) × Std weighted average price \text{Yield variance} = (\text{Total actual input} - \text{Std input allowed for actual output}) \times \text{Std weighted average price} Yield variance = ( Total actual input − Std input allowed for actual output ) × Std weighted average price
Example. The standard mix is 60% material A (PHP 10 per kg) and 40% material B (PHP 20 per kg), a weighted average of PHP 14 per kg of input, and 100 kg of input should yield 80 kg of output. Actual inputs were 700 kg of A and 300 kg of B (1,000 kg) to produce 820 kg of output.
- Variance Computation Amount
- Mix (700 x 10 + 300 x 20) - (1,000 x 14) = 13,000 - 14,000 PHP 1,000 favorable
- Yield (1,000 - 820 / 0.80) x 14 = (1,000 - 1,025) x 14 PHP 350 favorable
- Total quantity (usage) 13,000 - (1,025 x 14 = 14,350) PHP 1,350 favorable
A favorable mix variance here comes from using more of the cheaper material; it should be weighed against quality effects. Labor mix and yield variances are computed the same way, with labor grades and standard wage rates in place of materials and prices.