Study guide
14.2 Cost Classifications, Cost Behavior, and Cost Estimation
CPA Licensure Examination Philippines, CPALE
Track your progress as you read
Finished sections get a check mark.
1 Introduction & Overview of the CPALE
0.1 CPALE Structure, Qualification, and Examination Mechanics 0.2 Study Strategy, Subject Balance, and Time Management for the Three-Day Board Exam
2 FAR: Standard Setting, Conceptual Framework, Accounting Process & Financial Statements
1.1 Standard-Setting Bodies and Regulation of the Accountancy Profession 1.2 The Conceptual Framework for Financial Reporting 1.3 The Accounting Process: Journals, Worksheet, Adjusting, Closing, and Reversing Entries 1.4 Presentation of Financial Statements
3 FAR: Cash, Receivables & Financial Asset Investments
2.1 Cash, Cash Equivalents, Petty Cash, and Bank Reconciliation 2.2 Trade and Notes Receivables: Measurement, Expected Credit Losses, and Receivable Financing 2.3 Financial Asset Investments: FVPL, FVOCI, and Amortized Cost under PFRS 9
4 FAR: Inventories, Property, Plant & Equipment, and Investment Property
3.1 Inventories & Cost of Sales 3.2 Property, Plant and Equipment, Borrowing Costs, and Impairment 3.3 Investment Property and Agriculture (PAS 40 and PAS 41)
5 FAR: Intangibles, Held for Sale, Financial Liabilities & Provisions
4.1 Intangible Assets, Research and Development, and Goodwill 4.2 Non-Current Assets Held for Sale and Discontinued Operations (PFRS 5) 4.3 Financial Liabilities: Bonds Payable, Effective Interest, and Debt Restructuring 4.4 Provisions, Contingencies, Loyalty Programs, Warranties, and Unearned Revenue
6 FAR: Equity, Share-Based Payment, Leases, Income Taxes & Employee Benefits
5.1 Shareholders' Equity & Share-Based Payments 5.2 Leases under PFRS 16: Lessee, Lessor, and Sale-and-Leaseback 5.3 Income Taxes (PAS 12) and Employee Benefits (PAS 19)
7 FAR: EPS, Cash Flows, SMEs & Small Entities, and Interim Reporting
6.1 Earnings per Share and the Statement of Cash Flows 6.2 PFRS for SMEs, PFRS for Small Entities, and Micro Entities 6.3 Interim Financial Reporting (PAS 34) and Operating Segments (PFRS 8)
8 AFAR: Partnership Formation, Operations, Changes & Liquidation
7.1 Partnership Formation, Operations & Profit/Loss Allocation 7.2 Changes in Partnership Ownership: Admission, Retirement, Death, and Incorporation 7.3 Partnership Liquidation: Lump-Sum and Installment Methods
9 AFAR: Corporate Liquidation, Home Office & Branch, and Business Combinations
8.1 Corporate Liquidation & Statement of Affairs 8.2 Home Office, Branch & Agency Accounting 8.3 Business Combinations under PFRS 3
10 AFAR: Consolidation, Joint Arrangements & Associates
9.1 Consolidated Financial Statements under PFRS 10 & PAS 27 9.2 Joint Arrangements (PFRS 11): Joint Control, Joint Operations, and Joint Ventures 9.3 Investments in Associates and Joint Ventures: The Equity Method (PAS 28)
11 AFAR: Revenue Recognition and Construction Contracts
10.1 Revenue from Contracts with Customers: The Five-Step Model (PFRS 15) 10.2 Long-Term Construction Contracts: Measuring Progress, Contract Balances, and Losses 10.3 Special Revenue Issues under PFRS 15
12 AFAR: Franchises, Consignment, Foreign Currency & Derivatives
11.1 Franchise Operations and Consignment Sales 11.2 Foreign Currency Transactions and Translation (PAS 21 and PAS 29) 11.3 Derivatives and Hedge Accounting (PFRS 9)
13 AFAR: Government, Not-for-Profit, Insurance Contracts & Service Concessions
12.1 Government Accounting: The GAM for National Government Agencies 12.2 Not-for-Profit Organizations: Net Assets, Contributions, and Sector Types 12.3 Insurance Contracts (PFRS 17) and Service Concession Arrangements
14 AFAR: Cost Accounting Systems
13.1 Cost Accumulation Systems and Job Order Costing 13.2 Process Costing and Backflush Costing 13.3 Activity-Based Costing, Joint and By-Products, and Service Department Cost Allocation
15 MS: Management Accounting, Cost Behavior & CVP Analysis
14.1 The Role of Management Accounting, Professional Ethics, and Global Trends 14.2 Cost Classifications, Cost Behavior, and Cost Estimation 14.3 Cost-Volume-Profit (CVP) Analysis
16 MS: Variable Costing, Standard Costing & Budgeting
15.1 Variable Costing versus Absorption Costing 15.2 Standard Costing & Variance Analysis 15.3 Master Budgeting, Cash Budgets, and Flexible Budgets
17 MS: Performance Measurement and Relevant Costing
16.1 Responsibility Accounting, Segment Reporting, and Transfer Pricing 16.2 Balanced Scorecard, Operational Performance, and Emerging Trends 16.3 Relevant Costing & Short-Term Tactical Decisions
18 MS: Pricing, Quantitative Techniques & Financial Statement Analysis
17.1 Pricing Decisions & Profitability Analysis 17.2 Quantitative Techniques for Decision Making 17.3 Financial Statement Analysis & Ratio Analysis
19 MS: Working Capital Management and Capital Budgeting
18.1 Working Capital: Policies, Cash Conversion Cycle, and Cash Management 18.2 Working Capital: Receivables, Inventory, and Short-Term Financing 18.3 Capital Budgeting & Investment Decisions
20 MS: Risk, Cost of Capital, Financial Markets & Economics
19.1 Risk and Return, Leverage, and Cost of Capital 19.2 Financial Markets, Long-Term Financing, and Valuation 19.3 Microeconomics, Macroeconomics, and International Trade
21 AUD: Nature of Auditing, Regulation of the Profession & Code of Ethics
20.1 Nature of Auditing, Assurance, and Information Risk 20.2 The Regulatory Framework of the Accountancy Profession 20.3 Code of Ethics: Fundamental Principles, Conceptual Framework, and Threats
22 AUD: Independence, Quality Management & Engagement Planning
21.1 Independence: Financial Interests, Relationships, Rotation, Services, and Fees 21.2 Philippine Standards on Quality Management 21.3 Pre-Engagement Activities, Client Acceptance & Audit Planning
23 AUD: Audit Risk, Fraud, Materiality & Internal Control
22.1 Audit Risk Model and Fraud Risk 22.2 Materiality: Overall, Performance, and Clearly Trivial Thresholds 22.3 Understanding the Entity & Internal Control Evaluation
24 AUD: IT Environment, Audit Evidence & Sampling
23.1 Auditing in a Computer Information Systems (CIS) Environment 23.2 Audit Evidence, Assertions, Procedures, and Documentation 23.3 Audit Sampling: Attribute, Variable, and Monetary Unit Sampling
25 AUD: Business Process Audits and Auditing Practice Problems
24.1 Substantive Testing of Business Cycles 24.2 Auditing Practice: Cash and Receivables 24.3 Auditing Practice: Inventory, Property, and Liabilities
26 AUD: Completing the Audit, Reporting & Other Assurance Services
25.1 Completing the Audit, Subsequent Events & Going Concern 25.2 The Auditor's Report: Opinions, KAM, EOM, and Comparatives 25.3 Other Assurance and Related Services Engagements
27 TAX: Principles of Taxation and Assessment Remedies
26.1 Taxation: Nature, Inherent Powers, and Limitations 26.2 The Tax System: Canons, Double Taxation, Evasion, and Sources of Tax Law 26.3 Tax Remedies: Assessment, Protest, and Appeal
28 TAX: Refunds, Collection & Prescription, Gross Income, and Fringe Benefits
27.1 Tax Remedies: Refunds, Collection, and Prescription 27.2 Gross Income: Inclusions and Exclusions 27.3 De Minimis Benefits and the Fringe Benefits Tax
29 TAX: Individual and Corporate Income Taxation
28.1 Individual Income Tax: Classification, Rates, and the 8% Option 28.2 Individual Income Tax: Deductions, Passive Income, and Capital Gains 28.3 Corporate Income Taxation under the CREATE Law
30 TAX: Estate Tax, Donor's Tax, Withholding & Special Tax Laws
29.1 Estate Tax under the NIRC as Amended by the TRAIN Law 29.2 Donor's Tax under the NIRC as Amended by the TRAIN Law 29.3 Withholding Taxes, EOPT Compliance, and Special Tax Laws
31 TAX: Value-Added Tax and Percentage Taxes
30.1 Value-Added Tax: Nature, Registration, Output Tax, and Exemptions 30.2 Value-Added Tax: Input Tax, Allocation, Withholding, and Filing 30.3 Percentage Taxes & Other Business Taxes
32 TAX: Local Taxes, DST & Excise, and Incentives & Treaties
31.1 Local Taxation and Real Property Tax 31.2 Documentary Stamp Tax and Excise Taxes 31.3 Tax Incentives under CREATE MORE and Tax Treaties
33 RFBT: Law on Obligations
32.1 Obligations: Nature, Sources, and Effects 32.2 Kinds of Obligations 32.3 Extinguishment of Obligations
34 RFBT: Contracts, Defective Contracts & Sales
33.1 Law on Contracts: Essential Requisites & Performance 33.2 Defective Contracts 33.3 Sales: Nature, Object and Price, Delivery, and Double Sales
35 RFBT: Installment Sales, Credit Transactions & Partnerships
34.1 Sales: Warranties, Installment Sales, and Redemption 34.2 Credit Transactions & Security Mechanisms 34.3 Law on Partnerships
36 RFBT: Corporations - Nature, Incorporation & Board of Directors
35.1 Corporations: Nature, Separate Personality, Classes, and Nationality 35.2 Corporations: Incorporation, Articles and Bylaws, and Corporate Powers 35.3 Corporations: Board of Directors, Officers, and Fiduciary Duties
37 RFBT: Corporations - Stockholders, Capital & Corporate Changes
36.1 Corporations: Stockholders, Meetings, and One Person Corporations 36.2 Corporations: Capital Stock, Shares, and Subscriptions 36.3 Corporations: Mergers, Dissolution, Foreign Corporations, and SEC Powers
38 RFBT: Securities Regulation, Insurance & Cooperatives
37.1 Securities Regulation, Corporate Governance, and SRC Rule 68 37.2 Insurance Law 37.3 Cooperatives under the Philippine Cooperative Code (RA 9520)
39 RFBT: Banking Laws, AMLA & Bouncing Checks
38.1 Banking Laws, Bank Secrecy & PDIC 38.2 Anti-Money Laundering Act (AMLA) 38.3 Bouncing Checks Law (BP 22)
40 RFBT: Insolvency, Competition, Data Privacy & Labor Laws
39.1 Financial Rehabilitation and Insolvency Act (FRIA) 39.2 Competition, Consumer Protection, and Government Procurement 39.3 Data Privacy, Intellectual Property, and Electronic Commerce 39.4 Ease of Doing Business, Labor Standards, and Social Security
14.2 Cost Classifications, Cost Behavior, and Cost Estimation
Key Takeaways Explain This Topic AI
Prime cost is direct materials plus direct labor; conversion cost is direct labor plus manufacturing overhead, so direct labor belongs to both.
Within the relevant range, total variable cost changes in proportion to activity and total fixed cost stays constant, while unit fixed cost falls as activity rises.
The high-low method picks the periods with the highest and lowest activity, not cost, and computes the variable rate as the change in cost divided by the change in activity.
Least-squares regression uses all observations; the coefficient of determination shows the share of cost variation explained by the activity driver.
Under a cumulative average-time learning curve, each doubling of cumulative output reduces the average time per unit to the learning rate times its previous level.
Last updated: September 2026
Cost Classifications, Cost Behavior, and Cost Estimation
Cost terms, behavior, and estimation techniques anchor the planning-and-control items of Management Services (syllabus topic 1.2.1). This section classifies costs for inventory valuation, decisions, and control, describes variable, fixed, mixed, and step costs within the relevant range, separates mixed costs with the high-low, scattergraph, and least-squares methods, and predicts costs with learning curves.
1. Systematic Cost Classifications
Cost is an economic resource sacrificed or forgone to achieve a specific objective. For the CPALE, costs must be classified according to the purpose for which they are analyzed: Cost Classifications
- │
- ┌───────────────────────────────────────┼───────────────────────────────────────┐
- ▼ ▼ ▼
- For Financial Valuation For Tactical Decisions For Control & Reporting
- (PAS 2 Inventory Costing) (Relevant Cost Analysis) (Responsibility Centers)
- ├─ Product vs Period ├─ Avoidable vs Unavoidable ├─ Controllable Costs
- ├─ Prime Costs ├─ Incremental / Differential └─ Uncontrollable Costs
- └─ Conversion Costs ├─ Sunk Costs (Irrelevant)
- └─ Opportunity Costs
- A. Classifications for Inventory Valuation (PAS 2 / Financial Reporting)
Product Costs (Inventoriable Costs): Expenditures directly or indirectly incurred to manufacture a product or bring inventory to its present location and condition. Capitalized into inventory accounts (Raw Materials, Work in Process, Finished Goods) on the Statement of Financial Position until the goods are sold:
Direct Materials (DM): Integral physical raw materials traceable directly to the finished product in an economically feasible manner (e.g., steel in automobile assembly, fabric in garment manufacturing).
Direct Labor (DL): Wages of manufacturing personnel who physically convert raw materials into finished units (e.g., assembly line workers, machinists).
Manufacturing Overhead (MOH): All indirect manufacturing costs that cannot be traced directly to specific units in an economically feasible manner. Includes indirect materials (lubricants, cleaning supplies), indirect labor (factory supervisors, maintenance crews), factory depreciation, factory utilities, and plant property taxes.
Period Costs: Non-manufacturing expenditures charged directly to expense in the period incurred because they do not provide future economic benefit beyond the current reporting period. Comprises Selling Expenses (advertising, sales commissions, delivery freight-out) and Administrative Expenses (executive salaries, corporate office rent, legal fees).
Prime Costs: The primary direct manufacturing expenditures: Prime Costs = Direct Materials + Direct Labor \text{Prime Costs} = \text{Direct Materials} + \text{Direct Labor} Prime Costs = Direct Materials + Direct Labor
Conversion Costs: The expenditures incurred to convert raw materials into finished goods: Conversion Costs = Direct Labor + Manufacturing Overhead \text{Conversion Costs} = \text{Direct Labor} + \text{Manufacturing Overhead} Conversion Costs = Direct Labor + Manufacturing Overhead
Important Exam Note: Direct labor is unique because it is simultaneously classified as both a prime cost and a conversion cost.
B. Classifications for Tactical Decision Making
Avoidable vs. Unavoidable Costs: Avoidable costs can be eliminated in whole or in part by choosing one alternative over another (e.g., dropping a product line eliminates its dedicated supervisor salary). Unavoidable costs persist regardless of the managerial decision chosen.
Incremental (Differential) Cost: The difference in total cost between two distinct decision alternatives.
Sunk Costs: Costs that have already been incurred by past actions and cannot be changed, altered, or recovered by any present or future decision (e.g., historical book value of old machinery, past research expenditures). Sunk costs are strictly irrelevant in all decision-making models.
Opportunity Costs: The potential economic benefit or contribution sacrificed or forgone when one alternative course of action is selected over the next best alternative. While not recorded in formal financial accounting ledgers under PFRS, opportunity costs are fundamental in managerial analysis.
Marginal Cost: The extra cost incurred to produce one additional unit of output.
C. Classifications for Operational Control
Controllable Costs: Expenditures over which a specific manager possesses significant authority to authorize, incur, or influence within a designated time horizon.
Uncontrollable Costs: Expenditures that cannot be significantly influenced by a specific manager within a given organizational rank or time frame (e.g., corporate headquarters rent allocated down to a local store manager).
2. Cost Behavior Patterns & The Relevant Range
Cost behavior describes how an expenditure reacts or changes in total as the underlying activity volume fluctuates:
Cost Classification Total Cost Behavior Unit Cost Behavior
Variable Cost Changes in direct, linear proportion to changes in activity volume Remains constant per unit of activity
Fixed Cost Remains constant in total regardless of activity changes Varies inversely with activity volume ( F C / Q FC / Q FC / Q )
Mixed (Semi-Variable) Cost Increases with activity, but not in direct proportion ( y = a + b x y = a + bx y = a + b x ) Decreases per unit as volume expands, but not inversely
Fixed Cost Categories: Committed vs. Discretionary
Committed Fixed Costs: Long-term structural investments that cannot be significantly reduced in the short run without impairing the fundamental operating capability of the enterprise (e.g., plant depreciation, long-term lease contracts, property insurance).
Discretionary (Managed) Fixed Costs: Periodic outlays established by annual managerial decisions that can be adjusted in the short run with minimal permanent damage to core operating capacity (e.g., advertising campaigns, management training seminars, research and development programs).
Step Costs: Step-Variable vs. Step-Fixed
Step-Variable Costs: Expenditures that remain constant over very narrow activity intervals before jumping abruptly to a higher tier (e.g., quality inspection labor where one inspector can examine 200 units per shift; 201 units requires adding an immediate second inspector).
Step-Fixed Costs: Expenditures that remain fixed over wider operating ranges before stepping upward (e.g., plant supervisory salaries where one supervisor covers up to 10,000 machine hours; adding a second shift expands capacity but steps fixed supervision costs up by an entire salary block).
The Relevant Range
The relevant range is the bounded span of activity volume over which the entity's specific cost relationships, operational technology, unit variable costs, and total fixed costs remain valid and linear. Outside the relevant range, fixed costs step upward or downward, and variable costs may exhibit non-linear curved behavior due to overtime wage premiums or volume discounts.
3. Learning Curves as a Cost Prediction Technique
When workers repeat a task, the time per unit falls in a predictable pattern. Under the cumulative average-time model , each time cumulative output doubles , the cumulative average time per unit falls to a constant percentage (the learning rate) of its previous level:
Y = a X b , b = log ( learning rate ) log 2 Y = aX^{b}, \qquad b = \frac{\log(\text{learning rate})}{\log 2} Y = a X b , b = l o g 2 l o g ( learning rate )
where Y Y Y is the cumulative average time per unit, a a a the time for the first unit, and X X X the cumulative number of units.
Example (80% learning curve; first unit takes 100 hours).
- Cumulative Units Cumulative Average Hours per Unit Total Hours
- 1 100.0 100.0
- 2 80.0 160.0
- 4 64.0 256.0
- 8 51.2 409.6
The last four units need 409.6 - 256.0 = 153.6 hours, or 38.4 hours each. Learning curves affect labor-driven costs (direct labor and labor-related overhead), not materials, and are used in bidding, budgeting, and standard setting for new products.
4. Quantitative Methods for Mixed Cost Segregation
A mixed cost contains both a fixed base charge representing basic capacity readiness and a variable charge varying directly with activity:
y = a + b x y = a + bx y = a + b x
Where:
- y y y = Total mixed cost (the dependent variable)
- a a a = Total fixed cost (the vertical intercept)
- b b b = Variable cost per unit of activity (the slope of the cost line)
- x x x = Activity level or cost driver volume (the independent variable)
- A. The High-Low Method
The High-Low method is an algebraic technique that estimates fixed and variable components using only the two extreme data points of activity:
Step-by-Step Procedure:
Identify Extreme Points Based on Activity ( x x x ): Locate the periods exhibiting the highest activity level ( x high x_{\text{high}} x high ) and lowest activity level ( x low x_{\text{low}} x low ), along with their corresponding costs ( y high y_{\text{high}} y high and y low y_{\text{low}} y low ).
Critical CPALE Rule: The highest and lowest data points are determined strictly by the activity level ( x x x ) , never by the cost level ( y y y ). If the period with the highest cost does not correspond to the highest activity, that cost anomaly must not dictate the selection.
Calculate Variable Cost per Unit ( b b b ): b = Δ Cost Δ Activity = y high − y low x high − x low b = \frac{\Delta \text{ Cost}}{\Delta \text{ Activity}} = \frac{y_{\text{high}} - y_{\text{low}}}{x_{\text{high}} - x_{\text{low}}} b = Δ Activity Δ Cost = x high − x low y high − y low
Solve for Total Fixed Cost ( a a a ): Substitute the calculated variable rate ( b b b ) into either the high or low data point: a = y high − b ( x high ) or a = y low − b ( x low ) a = y_{\text{high}} - b(x_{\text{high}}) \quad \text{or} \quad a = y_{\text{low}} - b(x_{\text{low}}) a = y high − b ( x high ) or a = y low − b ( x low )
Establish the Cost Formula: y = a + b x y = a + bx y = a + b x .
Evaluation: The High-Low method is straightforward and cost-effective, but its major structural weakness is that it relies exclusively on two extreme observations that may represent non-representative statistical outliers, while discarding all intermediate data.
B. The Scattergraph (Visual Fit) Method
The analyst plots all historical data observations on an X − Y X-Y X − Y coordinate plane, visually inspects the dispersion of points, and draws a straight line that best fits the plotted points. The vertical intercept represents estimated fixed cost ( a a a ), and the slope represents variable cost per unit ( b b b ). While superior to the High-Low method in utilizing all data points, it suffers from visual subjectivity.
C. Least-Squares Regression Analysis
Least-Squares Regression is a statistical methodology that determines the line of best fit by mathematically minimizing the sum of the squared vertical deviations between actual observed costs ( y y y ) and the estimated regression line ( y ^ \hat{y} y ^ ):
min ∑ ( y − y ^ ) 2 \min \sum (y - \hat{y})^2 min ∑ ( y − y ^ ) 2
Regression Formulas:
b = n ∑ x y − ( ∑ x ) ( ∑ y ) n ∑ x 2 − ( ∑ x ) 2 b = \frac{n \sum xy - (\sum x)(\sum y)}{n \sum x^2 - (\sum x)^2} b = n ∑ x 2 − ( ∑ x ) 2 n ∑ x y − ( ∑ x ) ( ∑ y )
a = ∑ y − b ∑ x n = y ˉ − b x ˉ a = \frac{\sum y - b \sum x}{n} = \bar{y} - b \bar{x} a = n ∑ y − b ∑ x = y ˉ − b x ˉ
Where:
- n n n = Number of historical data observations
- y ˉ \bar{y} y ˉ = Mean of total costs
- x ˉ \bar{x} x ˉ = Mean of activity levels
Statistical Evaluation Parameters:
Correlation Coefficient ( r r r ): Measures the direction and strength of the linear association between the independent variable ( x x x ) and dependent variable ( y y y ): − 1.0 ≤ r ≤ + 1.0 -1.0 \le r \le +1.0 − 1.0 ≤ r ≤ + 1.0
r = + 1.0 r = +1.0 r = + 1.0 : Perfect positive linear correlation.
r = − 1.0 r = -1.0 r = − 1.0 : Perfect negative linear correlation.
r = 0.0 r = 0.0 r = 0.0 : No linear relationship.
Coefficient of Determination ( r 2 r^2 r 2 ): Computed by squaring the correlation coefficient ( r r r ): 0.0 ≤ r 2 ≤ 1.0 0.0 \le r^2 \le 1.0 0.0 ≤ r 2 ≤ 1.0 It measures the percentage of the total variation in the dependent variable ( y y y , total cost) that is explained by variation in the independent variable ( x x x , activity level). For example, an r 2 r^2 r 2 of 0.88 indicates that 88% of the change in maintenance costs is explained by changes in machine hours, while the remaining 12% is attributable to random noise or other unmodeled cost drivers.
Standard Error of the Estimate ( s e s_e s e ): Measures the standard deviation of data points around the fitted regression line, reflecting the precision of cost predictions.
5. Comprehensive Worked Example: High-Low Segregation & Regression Interpretation
Laguna Electronics Corporation operates an automated semiconductor fabrication plant in the Laguna Technopark. The accounting department recorded the following operating data for machine hours and total plant maintenance expenditures over the past six months:
- Month Machine Hours ( x x x ) Total Maintenance Cost ( y y y )
- January 4,200 PHP 310,000
- February 6,800 PHP 430,000
- March 3,900 PHP 295,000
- April 7,500 PHP 465,000
- May 5,400 PHP 370,000
- June 7,100 PHP 475,000
- Step 1: Identify Highest and Lowest Activity Levels
Highest Activity Level: April with 7,500 machine hours and cost of PHP 465,000 . (Notice that June has a higher cost of PHP 475,000, but April has the highest activity volume at 7,500 hours vs. June's 7,100 hours. The High-Low method requires selecting the extreme activity points!)
Lowest Activity Level: March with 3,900 machine hours and cost of PHP 295,000 .
Step 2: Compute Variable Cost per Machine Hour ( b b b )
b = y high − y low x high − x low = PHP 465,000 − PHP 295,000 7,500 hours − 3,900 hours = PHP 170,000 3,600 hours = PHP 47.2222 per machine hour b = \frac{y_{\text{high}} - y_{\text{low}}}{x_{\text{high}} - x_{\text{low}}} = \frac{\text{PHP }465{,}000 - \text{PHP }295{,}000}{7{,}500 \text{ hours} - 3{,}900 \text{ hours}} = \frac{\text{PHP }170{,}000}{3{,}600 \text{ hours}} = \text{PHP }47.2222 \text{ per machine hour} b = x high − x low y high − y low = 7 , 500 hours − 3 , 900 hours PHP 465 , 000 − PHP 295 , 000 = 3 , 600 hours PHP 170 , 000 = PHP 47.2222 per machine hour
Step 3: Compute Total Fixed Costs ( a a a )
Substituting into the highest activity point: a = y high − b ( x high ) = PHP 465,000 − ( PHP 47.2222 × 7,500 ) = PHP 465,000 − PHP 354,167 = PHP 110,833 a = y_{\text{high}} - b(x_{\text{high}}) = \text{PHP }465{,}000 - (\text{PHP }47.2222 \times 7{,}500) = \text{PHP }465{,}000 - \text{PHP }354{,}167 = \text{PHP }110{,}833 a = y high − b ( x high ) = PHP 465 , 000 − ( PHP 47.2222 × 7 , 500 ) = PHP 465 , 000 − PHP 354 , 167 = PHP 110 , 833
Verification using the lowest activity point: a = y low − b ( x low ) = PHP 295,000 − ( PHP 47.2222 × 3,900 ) = PHP 295,000 − PHP 184,167 = PHP 110,833 a = y_{\text{low}} - b(x_{\text{low}}) = \text{PHP }295{,}000 - (\text{PHP }47.2222 \times 3{,}900) = \text{PHP }295{,}000 - \text{PHP }184{,}167 = \text{PHP }110{,}833 a = y low − b ( x low ) = PHP 295 , 000 − ( PHP 47.2222 × 3 , 900 ) = PHP 295 , 000 − PHP 184 , 167 = PHP 110 , 833
Step 4: Formulate the Cost Equation and Budget Projection
The resulting mixed cost formula is: y = PHP 110,833 + PHP 47.2222 ( x ) y = \text{PHP }110{,}833 + \text{PHP }47.2222(x) y = PHP 110 , 833 + PHP 47.2222 ( x )
If the plant projects 6,500 machine hours for July, the forecasted maintenance cost is: y = PHP 110,833 + ( PHP 47.2222 × 6,500 ) = PHP 110,833 + PHP 306,944 = PHP 417,777 y = \text{PHP }110{,}833 + (\text{PHP }47.2222 \times 6{,}500) = \text{PHP }110{,}833 + \text{PHP }306{,}944 = \text{PHP }417{,}777 y = PHP 110 , 833 + ( PHP 47.2222 × 6 , 500 ) = PHP 110 , 833 + PHP 306 , 944 = PHP 417 , 777
Comparative Statistical Interpretation
If a Least-Squares Regression performed on all six months yielded a regression line of y = PHP 104,500 + PHP 48.80 ( x ) y = \text{PHP }104{,}500 + \text{PHP }48.80(x) y = PHP 104 , 500 + PHP 48.80 ( x ) with an r r r of 0.96 0.96 0.96 and an r 2 r^2 r 2 of 0.9216 0.9216 0.9216 :
The regression intercept indicates underlying baseline fixed capacity costs of PHP 104,500 per month.
The variable rate of PHP 48.80 per machine hour reflects the true statistical slope across all observations.
An r 2 r^2 r 2 of 0.9216 0.9216 0.9216 proves that 92.16% of the monthly variance in maintenance costs is directly explained by changes in machine operating hours, demonstrating high predictive reliability.