12.2 Site Planning Process: From Analysis to Concept

PRC Architect Licensure Examination ALE

Track your progress as you read

Finished sections get a check mark.

1 Introduction

About the PRC Architect Licensure Examination (ALE) How the ALE Is Organized & Scored

2 Chapter 1: Philippine & World Architectural History

1.1 Pre-Colonial & Spanish Colonial Philippine Architecture 1.2 American Colonial Period, Filipino Modernism & National Artists for Architecture 1.3 World Architectural History: Classical Through Modern Movements

3 Chapter 2: Architectural Theory & Planning Principles

2.1 Architectural Theories & Design Philosophies 2.2 Urban & Regional Planning Principles 2.3 Environmental Psychology & Human Behavior in Design

4 Chapter 3: RA 9266 and the Legal Framework of Practice

3.1 RA 9266: The Architecture Act of 2004 3.2 The PRBoA, Licensure & Scope of Practice 3.3 Code of Ethical Conduct for Architects

5 Chapter 4: Professional Practice, Contracts & UAP Standards

4.1 UAP Standards of Professional Practice (SPP Documents) 4.2 Contract Documents, Delivery Methods & Specifications 4.3 Professional Liability, Insurance & Construction Administration

6 Chapter 5: Structural Conceptualization & Systems

5.1 Structural Loads & Systems 5.2 Seismic Design Principles & the NSCP (Seismic Zone 4) 5.3 Structural Materials: Concrete, Steel, Timber & Masonry

7 Chapter 6: Building Materials & Construction Methods

6.1 Building Materials & Specifications 6.2 Construction Methods, Sequencing, QC & Safety 6.3 Building Envelope: Waterproofing, Doors, Windows & Roofing

8 Chapter 7: Building Utilities

7.1 Plumbing & Sanitary Systems 7.2 Electrical Systems & Illumination Design 7.3 HVAC, Mechanical Systems & Acoustics

9 Chapter 8: PD 1096 — The National Building Code

8.1 PD 1096 Development Controls: PSO, TGFA, FLAR & Setbacks 8.2 PD 1096 Fire Safety, Light, Ventilation & Occupancy 8.3 Applying PD 1096: Worked Examples & Common Exam Traps

10 Chapter 9: Site Analysis & Climate-Responsive Design

9.1 Site Analysis: Topography, Environmental Factors & Context 9.2 Tropical Climate-Responsive Design 9.3 Sustainable & Green Design Principles

11 Chapter 10: Programming & Space Planning

10.1 Space Programming & Functional Relationships 10.2 Circulation Systems & Spatial Organization 10.3 Building Typologies & User Requirements

12 Chapter 11: Zoning, Development Controls & Accessibility

11.1 Zoning Regulations, Setbacks & Site Development 11.2 BP 344 Accessibility Law & Universal Design 11.3 Life Safety, Egress & Fire-Code Compliance in Design

13 Chapter 12: Urban Design & Site Planning Process

12.1 Urban Design Principles & Site Development Concepts 12.2 Site Planning Process: From Analysis to Concept 12.3 Landscape Architecture & Site Development Elements

14 Chapter 13: Architectural Graphics, Presentation & Design Exam Strategy

13.1 Architectural Graphics: Plans, Sections, Elevations & Scales 13.2 Presentation Techniques & Design Communication 13.3 The ALE Design Exam Format: Problem-Solving Approach 13.4 Design Strategy & Time Management

12.2 Site Planning Process: From Analysis to Concept

Key Takeaways Explain This Topic AI

The Allowable Maximum Building Footprint (AMBF) equals Total Lot Area (TLA) multiplied by the zone's Percentage of Site Occupancy (PSO); the remaining area is mandatory open space for setbacks, parking, and landscaping.

Rule VII, Section 707, Item 4 (Table VII.4) of the Revised IRR of PD 1096 sets minimum parking slot counts by occupancy type and floor area.

If adequate public parking exists within 200 meters of a site, only 30% of the computed on-site parking requirement must still be provided on the premises.

PD 957/BP 220 subdivisions of one hectare or more must reserve at least 30% of gross area as open space, with 3.5% to 9% specifically for parks and playgrounds based on density.

Site planning proceeds iteratively: bubble-diagram synthesis, buildable-envelope math, circulation and parking layout, open-space allocation, then a dimensioned, resolved site development plan.

Last updated: July 2026

Site Planning Process: From Analysis to Concept

Quick Answer: The ALE tests site planning as a step-by-step method: synthesize site analysis into a concept, establish the buildable envelope using PD 1096 development controls (PSO, AMBF, FLAR, TGFA), diagram zoning, circulation, and parking, allocate open space, then iterate from a rough bubble diagram toward a resolved, dimensioned site development plan.

From Analysis to Concept: The Synthesis Step

Site analysis generates raw data: sun path, prevailing wind, topography, soil, drainage, adjacent land uses, vehicular access points, utility connections, easements, and views. Site planning is the discipline of converting that raw data into a workable design concept. The critical skill the ALE tests is synthesis : an examinee must look at a site analysis summary and identify the two or three findings that most constrain or unlock the design. For example, a site showing a steep slope toward the rear, a busy arterial road on the north frontage, and a floodway easement along the south boundary should immediately suggest a concept with vehicular access from the arterial, building mass held away from the floodway, and a stepped or terraced form responding to the slope. A site concept is normally expressed first as a simple diagram - bubbles and arrows - before any dimensioned decision is made.

Step 1: Establish the Buildable Envelope

Before diagramming anything, the architect must know how much of the lot can legally be built on. This is governed by PD 1096 development controls:

  • Term Definition Formula
  • Total Lot Area (TLA) The full area of the site -

Percentage of Site Occupancy (PSO) Maximum ground coverage allowed for the zone classification PSO = AMBF / TLA

  • Allowable Maximum Building Footprint (AMBF) Maximum ground-floor footprint permitted AMBF = TLA x PSO
  • Floor-Lot Area Ratio (FLAR) Maximum total floor area relative to lot size FLAR = TGFA / TLA
  • Total Gross Floor Area (TGFA) Total enclosed floor area across all levels TGFA = FLAR x TLA

The area outside the AMBF footprint is the mandatory open space available for setbacks, parking, driveways, and landscaping. Fixing these numbers first prevents an examinee from sketching a footprint or floor count the zone classification does not actually allow.

Step 2: Functional and Zoning Diagrams

With the buildable envelope established, the next step is a functional (bubble) diagram that assigns rough zones to the site without committing to exact geometry: building footprint zone, vehicular entry/exit and parking zone, service/loading zone, pedestrian entry and forecourt zone, and open space/green zone. At this stage, relationships matter more than dimensions - the service and loading zone should bubble adjacent to the kitchen or stockroom side of the building and away from the main pedestrian entrance, while the parking zone should bubble near the vehicular access point identified in site analysis rather than forcing traffic to cross the site.

Step 3: Vehicular and Pedestrian Circulation

Circulation is resolved once the functional diagram fixes rough zones. Vehicular circulation should generally use a single, clearly marked entry/exit, or a one-way in/out pair, that aligns with the site analysis findings on street traffic direction and sight distance, and should be separated as much as possible from the primary pedestrian path so cars and pedestrians do not conflict at the main entrance. Pedestrian circulation should connect the public sidewalk to the building entrance along the shortest comfortable, shaded route - ideally through the semi-public forecourt or arcade discussed in the previous section rather than across a parking aisle.

Step 4: Parking Layout

Parking requirements are computed from Rule VII, Section 707, Item 4 (Table VII.4) of the Revised Implementing Rules and Regulations of PD 1096, which sets minimum parking slots by occupancy type and floor area. Two computational rules are commonly tested: a computed fractional requirement of 0.50 or above rounds up to one additional slot, and where an adequate public parking facility exists within 200 meters of the site, only 30% of the computed on-site parking requirement need actually be provided on the premises. Once the required slot count is known, parking is laid out with clear aisles and accessible slots nearest the accessible building entrance per BP 344, with paving, lighting, and drainage as required - always positioned so parking does not become the dominant visual element at the street frontage.

Step 5: Open Space and Green Space Allocation

The area remaining after subtracting the building footprint, parking, and circulation is allocated to usable and green open space. For an ALE design problem, open space should be purposeful, not leftover: a functional courtyard, garden, or outdoor gathering space tied to the building's use, rather than an unusable sliver against the property line. Where a project falls under subdivision rules (PD 957/BP 220), a minimum of 30% of gross area for projects of one hectare or more must be reserved as open space, with a density-based sliding scale of roughly 3.5% to 9% specifically for parks and playgrounds.

Step 6: Iterating from Rough Concept to Resolved Plan

Site planning is iterative, not linear. After the first bubble diagram and rough zoning are drawn, the architect tests the concept against the buildable envelope numbers (Step 1), refines circulation (Step 3), and re-checks that the building footprint, parking, and open space actually fit within the site boundaries and setbacks. Each iteration should resolve conflicts identified in the previous round - a parking layout blocking the pedestrian path, a footprint exceeding AMBF, an open space that ends up unusably narrow - until the diagram becomes a dimensioned, code-compliant site development plan ready for the next stage of architectural design. On the ALE's design problem-solving component, examinees are expected to show this progression, not present a single finished plan with no evidence of the underlying process.