6.4 Construction Project Management, CPM/PERT, and Resource Scheduling
PRC Civil Engineer Licensure Examination CELE
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: Examination Overview, RA 544 & Professional Practice
1.1 CELE Structure, Format, Scoring, and 2026 Subject Order 1.2 Republic Act No. 544: The Civil Engineering Law and Board Regulations 1.3 Civil Engineering Ethics, Contracts, and Professional Practice
2 Chapter 2: Engineering Mathematics, Numerical Methods & Physics
2.1 Advanced Algebra, Progressions & Word Problems 2.2 Trigonometry and Analytical Geometry 2.3 Differential and Integral Calculus 2.4 Differential Equations and Numerical Methods 2.5 Series, Hyperbolic Functions, Multivariable Calculus, and Laplace Transforms 2.6 Numerical Methods: Linear Systems, Interpolation, Curve Fitting, and ODE Solvers 2.7 Physics for Engineers: Kinematics, Newton's Laws, Work-Energy, and Momentum
3 Chapter 3: Engineering Data Analysis & Engineering Economy
3.1 Engineering Data Analysis and Statistical Applications 3.2 Parameter Estimation, Linear Regression, Correlation, and Queuing Models 3.3 Engineering Economy: Time Value of Money and Interest Formulas 3.4 Project Evaluation, Depreciation, and Benefit-Cost Analysis
4 Chapter 4: Surveying Fundamentals, Construction Layout & Route Surveying
4.1 Errors, Corrections, and Pacing/Taping 4.2 Leveling, Earthworks, and Mass Haul Diagrams 4.3 Traverse Computations, Balancing, and Area Determinations 4.4 Route Surveying: Horizontal and Vertical Curves
5 Chapter 5: Highway & Transportation Engineering
5.1 Highway Geometric Design and Sight Distances 5.2 Traffic Engineering, Flow Fundamentals, and Pavement Design 5.3 Highway Policy, Route Location, Drainage, and Earthwork Slopes 5.4 Transportation Planning, Network Analysis, and Intermodal Systems
6 Chapter 6: Construction Materials, Methods, Management & Safety
6.1 Materials for Construction: Concrete, Formwork, Masonry, Steel, and Wood Products 6.2 Construction Equipment, Formwork, and Construction Methods 6.3 Construction Occupational Safety and Health: RA 11058 and DOLE DO 13 6.4 Construction Project Management, CPM/PERT, and Resource Scheduling 6.5 Construction Principles: Design Requirements, Project Organization, Cost Control, and Value Engineering 6.6 Quantity Surveying, Unit Cost Analysis, and Project Cost Estimates 6.7 Construction Trades and Specialties: Plumbing, Plastics, Doors and Windows, Finishes, and Electrical
7 Chapter 7: Fluid Properties, Hydrostatics & Buoyancy
7.1 Fluid Properties, Units, and Pressure Measurement 7.2 Hydrostatic Pressure on Plane and Curved Surfaces 7.3 Buoyancy, Flotation, and Accelerated Fluid Masses
8 Chapter 8: Hydrodynamics, Pipe Flow, Open Channels & Water Supply
8.1 Fluid Dynamics: Continuity and Energy Equations 8.2 Flow Measurement: Orifices, Weirs, and Venturi Meters 8.3 Fluid Flow in Pipes, Friction Losses, and Pipe Networks 8.4 Open Channel Flow, Manning's Equation, and Hydraulic Jump 8.5 Water Supply: Demand, Storage, Pumping, Distribution, and Treatment
9 Chapter 9: Soil Properties, Seepage & Stresses in Soil Mass
9.1 Soil Composition, Weight-Volume Phase Relationships 9.2 Soil Classification Systems (USCS & AASHTO) and Atterberg Limits 9.3 Soil Permeability, Seepage, Flow Nets, and Effective Stress 9.4 Stresses in Soil Mass, Stress Distribution, and Immediate and Secondary Settlement
10 Chapter 10: Consolidation, Soil Strength, Earth Pressures & Foundations
10.1 Soil Compaction and Soil Compressibility/Consolidation 10.2 Shear Strength of Soils and Mohr-Coulomb Failure Criteria 10.3 Lateral Earth Pressures (Rankine & Coulomb) and Retaining Walls 10.4 Shallow and Deep Foundation Bearing Capacity and Slope Stability
11 Chapter 11: Engineering Mechanics & Statics
11.1 Force Systems, Resultants, and Equilibrium of Rigid Bodies 11.2 Centroids, Moments of Inertia, and Friction 11.3 Cables, Trusses, and Internal Forces in Members
12 Chapter 12: Strength of Materials
12.1 Axial Stress, Strain, and Deformation 12.2 Torsion, Flanged Bolt Couplings, and Thin-Walled Pressure Vessels 12.3 Beam Stresses: Flexural and Transverse Shear 12.4 Beam Deflections, Combined Stresses, and Mohr's Circle
13 Chapter 13: Structural Analysis & NSCP Load Criteria
13.1 Indeterminate Structures: Approximate and Classical Methods 13.2 Moment Distribution Method and Slope Deflection 13.3 Influence Lines for Determinate and Indeterminate Structures 13.4 NSCP Minimum Design Loads: Dead, Live, Wind, and Earthquake
14 Chapter 14: Reinforced Concrete Design (NSCP 2015 / USD)
14.1 Ultimate Strength Design (USD) Principles and Singly Reinforced Beams 14.2 Doubly Reinforced Beams and T-Beams 14.3 Shear and Diagonal Tension, Stirrup Design, and Development Length 14.4 Reinforced Concrete Columns and Isolated Footing Design
15 Chapter 15: Steel, Timber & Prestressed Design and Materials Testing
15.1 Structural Steel Tension Members and Connections 15.2 Structural Steel Compression Members and Beam Design 15.3 Timber Design Principles, Working Stress, and Sawn Lumber Beams 15.4 Prestressed Concrete Fundamentals and Prestress Losses 15.5 Construction Materials Testing and Concrete Mix Proportioning
6.4 Construction Project Management, CPM/PERT, and Resource Scheduling
Key Takeaways Explain This Topic AI
The Critical Path Method (CPM) establishes the deterministic minimum project duration along the critical path where Total Float is zero ( T F = 0 TF = 0 TF = 0 ), where T F = L S − E S = L F − E F TF = LS - ES = LF - EF TF = L S − ES = L F − EF .
Free Float ( F F = E S succ − E F FF = ES_{\text{succ}} - EF FF = E S succ − EF ) represents the slack an activity can absorb without delaying the early start of any immediate successor activity, satisfying the invariant F F ≤ T F FF \le TF FF ≤ TF .
The Program Evaluation and Review Technique (PERT) models duration uncertainty using a Beta distribution with expected duration t e = a + 4 m + b 6 t_e = \frac{a + 4m + b}{6} t e = 6 a + 4 m + b and variance σ 2 = ( b − a 6 ) 2 \sigma^2 = \left(\frac{b - a}{6}\right)^2 σ 2 = ( 6 b − a ) 2 .
Total project variance is the sum of variances of activities along the critical path ( σ proj 2 = ∑ σ crit 2 \sigma_{\text{proj}}^2 = \sum \sigma_{\text{crit}}^2 σ proj 2 = ∑ σ crit 2 ), allowing probabilistic project completion scheduling using standard normal Z Z Z -scores ( Z = T d − T e σ proj Z = \frac{T_d - T_e}{\sigma_{\text{proj}}} Z = σ proj T d − T e ).
Project crashing compresses project duration by accelerating critical path activities in order of ascending cost-slope ( Cost Slope = Crash Cost − Normal Cost Normal Time − Crash Time \text{Cost Slope} = \frac{\text{Crash Cost} - \text{Normal Cost}}{\text{Normal Time} - \text{Crash Time}} Cost Slope = Normal Time − Crash Time Crash Cost − Normal Cost ) to achieve target schedules at minimum direct cost.
Last updated: October 2026
6.4 Construction Project Management, CPM/PERT, and Resource Scheduling
Project planning, scheduling, and control represent pivotal competencies assessed in the CELE Applied Mathematics and Construction cluster. Construction projects are complex, capital-intensive endeavors subject to strict contractual deadlines, financial liquidated damages, and resource constraints. Civil engineers utilize Critical Path Method (CPM) and Program Evaluation and Review Technique (PERT) network models to establish baseline project schedules, optimize equipment and labor allocations, manage risk, and execute schedule compression (crashing) at minimum additional cost.
Project Planning & Work Breakdown Structure (WBS)
A successful project begins with structured decomposition. The Work Breakdown Structure (WBS) is a deliverable-oriented hierarchical decomposition of the total project scope into manageable, measurable work packages:
- Level 1: Total Project (e.g., Multi-Storey Reinforced Concrete Hospital Facility)
- Level 2: Major Subprojects / Deliverables (e.g., Substructure, Superstructure, MEPFS, Architectural Finishes)
- Level 3: Work Packages (e.g., Pile Cap Foundation, Ground Floor Suspended Slab, Column Pours)
- Level 4: Field Activities (e.g., Formwork Erection, Rebar Tying, Concrete Pouring, Curing)
Each terminal activity in the WBS must have an assigned duration, quantifiable resource demand (crew, equipment, materials), predecessor relationships, and a responsible engineering supervisor.
Network Scheduling Logic: AOA vs AON
Two fundamental network diagramming conventions model activity dependencies:
Activity-on-Arrow (AOA) / Arrow Diagramming Method (ADM):
Arrows represent activities with defined durations.
Nodes (circles) represent discrete points in time ( events or milestones).
Dummy Activities: Dashed arrows with zero duration and zero resource demand introduced strictly to maintain logical dependencies or prevent two activities from sharing identical starting and ending nodes.
Activity-on-Node (AON) / Precedence Diagramming Method (PDM):
Nodes (boxes) represent activities.
Arrows represent precedence relationships.
Precedence types: Finish-to-Start (FS) (standard), Start-to-Start (SS) , Finish-to-Finish (FF) , and Start-to-Finish (SF) , optionally modified by positive leads or negative lags.
The Critical Path Method (CPM): Forward & Backward Pass
CPM is a deterministic scheduling algorithm that computes project duration and activity float values through two consecutive mathematical sweeps:
1. The Forward Pass (Early Dates)
The forward pass moves chronologically from project initiation to completion, determining the earliest possible time each activity can start and finish:
Early Start ( E S ES ES ): The earliest time an activity can commence, governed by the completion of all immediate predecessors: E S j = max { E F i } for all predecessors i ES_j = \max \{ EF_i \} \quad \text{for all predecessors } i E S j = max { E F i } for all predecessors i (For initial project activities with no predecessors, E S = 0 ES = 0 ES = 0 .)
Early Finish ( E F EF EF ): The earliest time an activity can finish: E F j = E S j + D j EF_j = ES_j + D_j E F j = E S j + D j Where D j D_j D j is the activity duration.
2. The Backward Pass (Late Dates)
The backward pass moves counter-chronologically from project completion back to the start, establishing the latest allowable time each activity can finish and start without delaying the overall project completion target ( T target = max E F T_{\text{target}} = \max EF T target = max EF ):
Late Finish ( L F LF L F ): The latest time an activity can finish without delaying any immediate successor: L F i = min { L S j } for all successors j LF_i = \min \{ LS_j \} \quad \text{for all successors } j L F i = min { L S j } for all successors j (For terminal activities, L F = E F project LF = EF_{\text{project}} L F = E F project .)
Late Start ( L S LS L S ): The latest time an activity can start without delaying project completion: L S i = L F i − D i LS_i = LF_i - D_i L S i = L F i − D i
Mathematical Float / Slack Analysis
Float represents the scheduling flexibility of an activity. CELE board problems test four distinct mathematical classifications of float:
1. Total Float ( T F TF TF )
Total Float is the total time an activity can be delayed from its Early Start without delaying the overall project completion deadline:
- T F = L S − E S = L F − E F TF = LS - ES = LF - EF TF = L S − ES = L F − EF
- 2. Free Float ( F F FF FF )
Free Float is the time an activity can be delayed without delaying the Early Start of any immediately succeeding activity :
F F i = min j ∈ succ { E S j } − E F i FF_i = \min_{j \in \text{succ}} \{ ES_j \} - EF_i F F i = min j ∈ succ { E S j } − E F i
Note
Free Float can never exceed Total Float ( F F ≤ T F FF \le TF FF ≤ TF ). If an activity has zero Total Float ( T F = 0 TF = 0 TF = 0 ), its Free Float must also be zero ( F F = 0 FF = 0 FF = 0 ).
3. Interfering Float ( I n t F IntF I n tF )
Interfering Float is the difference between Total Float and Free Float. It represents the portion of Total Float whose consumption will delay the early start of subsequent activities without delaying overall project completion:
- I n t F = T F − F F IntF = TF - FF I n tF = TF − FF
- 4. Independent Float ( I F IF I F )
Independent Float is the slack available when all predecessors finish at their latest dates ( L F LF L F ) and all successors start at their earliest dates ( E S ES ES ):
I F i = max ( 0 , min j ∈ succ { E S j } − max k ∈ pred { L F k } − D i ) IF_i = \max \left( 0, \min_{j \in \text{succ}} \{ ES_j \} - \max_{k \in \text{pred}} \{ LF_k \} - D_i \right) I F i = max ( 0 , min j ∈ succ { E S j } − max k ∈ pred { L F k } − D i )
Identification of the Critical Path
The Critical Path is the continuous sequence of connected activities through the network with zero Total Float ( T F = 0 TF = 0 TF = 0 ) . It is the longest path in terms of cumulative duration and dictates the absolute minimum time required to complete the project.
Program Evaluation and Review Technique (PERT)
Unlike deterministic CPM, PERT accounts for uncertainty in activity durations (e.g., severe weather, subsurface anomalies, supply chain delays) by modeling each task via a Beta probability distribution defined by three subjective time estimates:
Optimistic Time ( a a a ): The minimum possible duration assuming everything proceeds exceptionally well (1 in 100 probability of finishing faster).
Most Likely Time ( m m m ): The modal duration representing the most frequent duration under normal working conditions.
Pessimistic Time ( b b b ): The maximum duration assuming adverse conditions encounter continuous difficulties (1 in 100 probability of finishing slower).
1. PERT Expected Mean Duration ( t e t_e t e )
The expected mean duration is a weighted average that assigns four times greater statistical weight to the modal value m m m :
- t e = a + 4 m + b 6 t_e = \frac{a + 4m + b}{6} t e = 6 a + 4 m + b
- 2. Activity Variance ( σ 2 \sigma^2 σ 2 ) and Standard Deviation ( σ \sigma σ )
Assuming the range ( b − a ) (b - a) ( b − a ) spans approximately six standard deviations ( 6 σ 6\sigma 6 σ ) of the unimodal Beta distribution:
σ = b − a 6 \sigma = \frac{b - a}{6} σ = 6 b − a σ 2 = ( b − a 6 ) 2 = ( b − a ) 2 36 \sigma^2 = \left( \frac{b - a}{6} \right)^2 = \frac{(b - a)^2}{36} σ 2 = ( 6 b − a ) 2 = 36 ( b − a ) 2
3. Total Project Variance & Central Limit Theorem
By the Central Limit Theorem , the sum of independent random variables along the critical path converges to a Normal Distribution , regardless of the underlying activity distributions:
Expected Project Completion Time ( T e T_e T e ): T e = ∑ i ∈ critical t e , i T_e = \sum_{i \in \text{critical}} t_{e,i} T e = ∑ i ∈ critical t e , i
Total Project Variance ( σ proj 2 \sigma_{\text{proj}}^2 σ proj 2 ): σ proj 2 = ∑ i ∈ critical σ i 2 \sigma_{\text{proj}}^2 = \sum_{i \in \text{critical}} \sigma_i^2 σ proj 2 = ∑ i ∈ critical σ i 2
Project Standard Deviation ( σ proj \sigma_{\text{proj}} σ proj ): σ proj = ∑ i ∈ critical σ i 2 \sigma_{\text{proj}} = \sqrt{\sum_{i \in \text{critical}} \sigma_i^2} σ proj = ∑ i ∈ critical σ i 2
Warning
Never sum standard deviations directly! You must sum the individual activity variances along the critical path and then take the square root of that sum to find σ proj \sigma_{\text{proj}} σ proj .
4. Probability of Meeting a Target Completion Date ( T d T_d T d )
The probability of completing the project on or before a specified contract deadline T d T_d T d is evaluated using the standard normal distribution Z Z Z -score:
Z = T d − T e σ proj Z = \frac{T_d - T_e}{\sigma_{\text{proj}}} Z = σ proj T d − T e
Standard Normal Z Z Z -Score Cumulative Probability P ( z ≤ Z ) P(z \le Z) P ( z ≤ Z ) Practical Interpretation
- Z = − 2.00 Z = -2.00 Z = − 2.00 2.28 % 2.28\% 2.28% Severe schedule overrun risk
- Z = − 1.00 Z = -1.00 Z = − 1.00 15.87 % 15.87\% 15.87% High probability of late finish
- Z = 0.00 Z = 0.00 Z = 0.00 50.00 % 50.00\% 50.00% T d = T e T_d = T_e T d = T e ; exactly an even chance
- Z = + 1.00 Z = +1.00 Z = + 1.00 84.13 % 84.13\% 84.13% Standard contract safety buffer
- Z = + 1.645 Z = +1.645 Z = + 1.645 95.00 % 95.00\% 95.00% High-confidence delivery milestone
- Z = + 2.00 Z = +2.00 Z = + 2.00 97.72 % 97.72\% 97.72% Near-certain on-time project completion
- Project Crashing & Cost-Slope Optimization
Project Crashing is the method of shortening project duration by allocating additional labor, equipment, or premium overtime to critical activities at minimum incremental direct cost.
Cost Slope Formulation
Each activity possesses a normal operating state and a crashed operating state:
- Normal Duration ( N D N_D N D ) and Normal Cost ( N C N_C N C )
- Crash Duration ( C D C_D C D ) and Crash Cost ( C C C_C C C )
The cost slope represents the marginal cost incurred to accelerate an activity by one unit of time (e.g., PHP per day):
Cost Slope = Crash Cost − Normal Cost Normal Duration − Crash Duration = Δ C Δ D \text{Cost Slope} = \frac{\text{Crash Cost} - \text{Normal Cost}}{\text{Normal Duration} - \text{Crash Duration}} = \frac{\Delta C}{\Delta D} Cost Slope = Normal Duration − Crash Duration Crash Cost − Normal Cost = Δ D Δ C
Crashing Algorithm Protocol
Identify the critical path(s) using normal durations.
Crash only critical path activities . Shortening non-critical activities increases cost without accelerating the project schedule.
Among eligible critical activities, select the activity with the lowest cost slope .
Shorten that activity up to its maximum crash limit ( N D − C D N_D - C_D N D − C D ) or until a parallel path becomes critical.
When multiple paths become critical simultaneously, shorten activities in parallel across all critical paths or accelerate an activity shared by all critical paths.
Continue until the target duration is achieved or all critical activities reach their crash limits.
- Step-by-Step Worked Problem Examples
- Worked Example 1: Deterministic CPM Forward/Backward Pass
Problem: A reinforced concrete bridge pier construction package involves six activities with the following dependencies and durations:
- Activity Description Predecessor Duration (Days)
- A Excavation & Cofferdam None 5
- B Driven Steel Piling A 8
- C Dewatering & Subgrade Seal A 4
- D Pile Cap Rebar & Concrete B 6
- E Cofferdam Bracing & Grouting C 5
- F Pier Shaft Formwork & Pour D, E 7
Perform complete CPM forward and backward passes. Identify all early/late dates, floats, the critical path, and total project duration.
Solution:
Forward Pass ( E S , E F ES, EF ES , EF ):
- Activity A: E S = 0 , E F = 0 + 5 = 5 ES = 0, \; EF = 0 + 5 = 5 ES = 0 , EF = 0 + 5 = 5
- Activity B: E S = 5 , E F = 5 + 8 = 13 ES = 5, \; EF = 5 + 8 = 13 ES = 5 , EF = 5 + 8 = 13
- Activity C: E S = 5 , E F = 5 + 4 = 9 ES = 5, \; EF = 5 + 4 = 9 ES = 5 , EF = 5 + 4 = 9
- Activity D: E S = 13 , E F = 13 + 6 = 19 ES = 13, \; EF = 13 + 6 = 19 ES = 13 , EF = 13 + 6 = 19
- Activity E: E S = 9 , E F = 9 + 5 = 14 ES = 9, \; EF = 9 + 5 = 14 ES = 9 , EF = 9 + 5 = 14
Activity F: E S = max ( E F D , E F E ) = max ( 19 , 14 ) = 19 , E F = 19 + 7 = 26 ES = \max(EF_D, EF_E) = \max(19, 14) = 19, \; EF = 19 + 7 = 26 ES = max ( E F D , E F E ) = max ( 19 , 14 ) = 19 , EF = 19 + 7 = 26 Project Duration = 26 Days .
Backward Pass ( L F , L S LF, LS L F , L S ) with L F F = 26 LF_F = 26 L F F = 26 :
Activity F: L F = 26 , L S = 26 − 7 = 19 LF = 26, \; LS = 26 - 7 = 19 L F = 26 , L S = 26 − 7 = 19
Activity D: L F = L S F = 19 , L S = 19 − 6 = 13 LF = LS_F = 19, \; LS = 19 - 6 = 13 L F = L S F = 19 , L S = 19 − 6 = 13
Activity E: L F = L S F = 19 , L S = 19 − 5 = 14 LF = LS_F = 19, \; LS = 19 - 5 = 14 L F = L S F = 19 , L S = 19 − 5 = 14
Activity B: L F = L S D = 13 , L S = 13 − 8 = 5 LF = LS_D = 13, \; LS = 13 - 8 = 5 L F = L S D = 13 , L S = 13 − 8 = 5
Activity C: L F = L S E = 14 , L S = 14 − 4 = 10 LF = LS_E = 14, \; LS = 14 - 4 = 10 L F = L S E = 14 , L S = 14 − 4 = 10
Activity A: L F = min ( L S B , L S C ) = min ( 5 , 10 ) = 5 , L S = 5 − 5 = 0 LF = \min(LS_B, LS_C) = \min(5, 10) = 5, \; LS = 5 - 5 = 0 L F = min ( L S B , L S C ) = min ( 5 , 10 ) = 5 , L S = 5 − 5 = 0
Float Computations:
Act Dur ES EF LS LF Total Float ( L S − E S LS - ES L S − ES ) Free Float ( E S succ − E F ES_{\text{succ}} - EF E S succ − EF ) Critical?
- A 5 0 5 0 5 0 min ( 5 , 5 ) − 5 = 0 \min(5, 5) - 5 = 0 min ( 5 , 5 ) − 5 = 0 Yes
- B 8 5 13 5 13 0 13 − 13 = 0 13 - 13 = 0 13 − 13 = 0 Yes
- C 4 5 9 10 14 5 9 − 9 = 0 9 - 9 = 0 9 − 9 = 0 No
- D 6 13 19 13 19 0 19 − 19 = 0 19 - 19 = 0 19 − 19 = 0 Yes
- E 5 9 14 14 19 5 19 − 14 = 5 19 - 14 = 5 19 − 14 = 5 No
- F 7 19 26 19 26 0 26 − 26 = 0 26 - 26 = 0 26 − 26 = 0 Yes
Critical Path: A — B — D — F (Total duration = 26 Days ).
Note that Activity C has T F = 5 days TF = 5\text{ days} TF = 5 days , but F F = 0 days FF = 0\text{ days} FF = 0 days because delaying C immediately delays the early start of its successor E.
Worked Example 2: PERT Probabilistic Duration & Project Crashing
Problem: A critical path comprises three sequential activities with the following duration and cost parameters:
Critical Activity a a a (days) m m m (days) b b b (days) Normal Cost (PHP) Crash Dur ( C D C_D C D ) Crash Cost (PHP)
- 1 5 8 17 120,000 6 days 160,000
- 2 8 11 20 180,000 9 days 240,000
- 3 4 7 10 90,000 5 days 130,000
Calculate expected project duration T e T_e T e , project variance σ proj 2 \sigma_{\text{proj}}^2 σ proj 2 , and standard deviation σ proj \sigma_{\text{proj}} σ proj .
Determine the probability of completing the project within a contract deadline of T d = 30.0 days T_d = 30.0\text{ days} T d = 30.0 days .
Determine the minimum direct cost to crash the project by 2 days.
Solution:
PERT Expected Durations & Variances:
Activity 1: t e , 1 = 5 + 4 ( 8 ) + 17 6 = 54 6 = 9.0 days t_{e,1} = \frac{5 + 4(8) + 17}{6} = \frac{54}{6} = 9.0\text{ days} t e , 1 = 6 5 + 4 ( 8 ) + 17 = 6 54 = 9.0 days , σ 1 = 17 − 5 6 = 2.0 days \sigma_1 = \frac{17 - 5}{6} = 2.0\text{ days} σ 1 = 6 17 − 5 = 2.0 days , σ 1 2 = 4.0 days 2 \sigma_1^2 = 4.0\text{ days}^2 σ 1 2 = 4.0 days 2 .
Activity 2: t e , 2 = 8 + 4 ( 11 ) + 20 6 = 72 6 = 12.0 days t_{e,2} = \frac{8 + 4(11) + 20}{6} = \frac{72}{6} = 12.0\text{ days} t e , 2 = 6 8 + 4 ( 11 ) + 20 = 6 72 = 12.0 days , σ 2 = 20 − 8 6 = 2.0 days \sigma_2 = \frac{20 - 8}{6} = 2.0\text{ days} σ 2 = 6 20 − 8 = 2.0 days , σ 2 2 = 4.0 days 2 \sigma_2^2 = 4.0\text{ days}^2 σ 2 2 = 4.0 days 2 .
Activity 3: t e , 3 = 4 + 4 ( 7 ) + 10 6 = 42 6 = 7.0 days t_{e,3} = \frac{4 + 4(7) + 10}{6} = \frac{42}{6} = 7.0\text{ days} t e , 3 = 6 4 + 4 ( 7 ) + 10 = 6 42 = 7.0 days , σ 3 = 10 − 4 6 = 1.0 day \sigma_3 = \frac{10 - 4}{6} = 1.0\text{ day} σ 3 = 6 10 − 4 = 1.0 day , σ 3 2 = 1.0 days 2 \sigma_3^2 = 1.0\text{ days}^2 σ 3 2 = 1.0 days 2 .
Expected Total Duration: T e = 9.0 + 12.0 + 7.0 = 28.0 days T_e = 9.0 + 12.0 + 7.0 = 28.0\text{ days} T e = 9.0 + 12.0 + 7.0 = 28.0 days .
Project Variance: σ proj 2 = 4.0 + 4.0 + 1.0 = 9.0 days 2 \sigma_{\text{proj}}^2 = 4.0 + 4.0 + 1.0 = 9.0\text{ days}^2 σ proj 2 = 4.0 + 4.0 + 1.0 = 9.0 days 2 .
Project Standard Deviation: σ proj = 9.0 = 3.0 days \sigma_{\text{proj}} = \sqrt{9.0} = 3.0\text{ days} σ proj = 9.0 = 3.0 days .
Probability of Finishing within T d = 30.0 days T_d = 30.0\text{ days} T d = 30.0 days : Z = T d − T e σ proj = 30.0 − 28.0 3.0 = 2.0 3.0 = + 0.67 Z = \frac{T_d - T_e}{\sigma_{\text{proj}}} = \frac{30.0 - 28.0}{3.0} = \frac{2.0}{3.0} = +0.67 Z = σ proj T d − T e = 3.0 30.0 − 28.0 = 3.0 2.0 = + 0.67 From the standard normal cumulative table, P ( Z ≤ + 0.67 ) ≈ 0.7486 = 74.86 % P(Z \le +0.67) \approx 0.7486 = 74.86\% P ( Z ≤ + 0.67 ) ≈ 0.7486 = 74.86% .
Project Crashing for 2-Day Reduction: Calculate cost slope for each critical activity:
Activity 1: Slope = 160 , 000 − 120 , 000 9 − 6 = 40 , 000 3 = 13 , 333.33 PHP/day \text{Slope} = \frac{160,000 - 120,000}{9 - 6} = \frac{40,000}{3} = 13,333.33\text{ PHP/day} Slope = 9 − 6 160 , 000 − 120 , 000 = 3 40 , 000 = 13 , 333.33 PHP/day (can crash 3 days).
Activity 2: Slope = 240 , 000 − 180 , 000 12 − 9 = 60 , 000 3 = 20 , 000.00 PHP/day \text{Slope} = \frac{240,000 - 180,000}{12 - 9} = \frac{60,000}{3} = 20,000.00\text{ PHP/day} Slope = 12 − 9 240 , 000 − 180 , 000 = 3 60 , 000 = 20 , 000.00 PHP/day (can crash 3 days).
Activity 3: Slope = 130 , 000 − 90 , 000 7 − 5 = 40 , 000 2 = 20 , 000.00 PHP/day \text{Slope} = \frac{130,000 - 90,000}{7 - 5} = \frac{40,000}{2} = 20,000.00\text{ PHP/day} Slope = 7 − 5 130 , 000 − 90 , 000 = 2 40 , 000 = 20 , 000.00 PHP/day (can crash 2 days).
Activity 1 has the lowest cost slope ( 13 , 333.33 PHP/day 13,333.33\text{ PHP/day} 13 , 333.33 PHP/day ). Crash Activity 1 by 2 days.
Incremental Crash Cost: 2 × 13 , 333.33 = 26 , 666.67 PHP 2 \times 13,333.33 = 26,666.67\text{ PHP} 2 × 13 , 333.33 = 26 , 666.67 PHP .
Total Direct Project Cost: ( 120 , 000 + 180 , 000 + 90 , 000 ) + 26 , 666.67 = 416 , 666.67 PHP (120,000 + 180,000 + 90,000) + 26,666.67 = 416,666.67\text{ PHP} ( 120 , 000 + 180 , 000 + 90 , 000 ) + 26 , 666.67 = 416 , 666.67 PHP .
CELE Board Exam Traps & Strategic Checklists
Warning
Standard Deviation Summation Trap: Never calculate project standard deviation as ∑ σ i \sum \sigma_i ∑ σ i . You must compute σ proj = ∑ σ i 2 \sigma_{\text{proj}} = \sqrt{\sum \sigma_i^2} σ proj = ∑ σ i 2 . For Worked Example 2, ∑ σ i = 2 + 2 + 1 = 5.0 days \sum \sigma_i = 2 + 2 + 1 = 5.0\text{ days} ∑ σ i = 2 + 2 + 1 = 5.0 days , which is radically incorrect compared to the true value 9.0 = 3.0 days \sqrt{9.0} = 3.0\text{ days} 9.0 = 3.0 days .
Crashing Non-Critical Tasks: An activity that possesses float does not govern project duration. Crashing a non-critical activity spends money with zero reduction in project completion time.
Free Float vs Total Float Confusion: Total Float is computed against the Late Start/Finish of the activity itself ( L S − E S LS - ES L S − ES or L F − E F LF - EF L F − EF ). Free Float is computed against the Early Start of the successor ( min E S succ − E F \min ES_{\text{succ}} - EF min E S succ − EF ).