6.6 Quantity Surveying, Unit Cost Analysis, and Project Cost Estimates
PRC Civil Engineer Licensure Examination CELE
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: Examination Overview, RA 544 & Professional Practice
1.1 CELE Structure, Format, Scoring, and 2026 Subject Order 1.2 Republic Act No. 544: The Civil Engineering Law and Board Regulations 1.3 Civil Engineering Ethics, Contracts, and Professional Practice
2 Chapter 2: Engineering Mathematics, Numerical Methods & Physics
2.1 Advanced Algebra, Progressions & Word Problems 2.2 Trigonometry and Analytical Geometry 2.3 Differential and Integral Calculus 2.4 Differential Equations and Numerical Methods 2.5 Series, Hyperbolic Functions, Multivariable Calculus, and Laplace Transforms 2.6 Numerical Methods: Linear Systems, Interpolation, Curve Fitting, and ODE Solvers 2.7 Physics for Engineers: Kinematics, Newton's Laws, Work-Energy, and Momentum
3 Chapter 3: Engineering Data Analysis & Engineering Economy
3.1 Engineering Data Analysis and Statistical Applications 3.2 Parameter Estimation, Linear Regression, Correlation, and Queuing Models 3.3 Engineering Economy: Time Value of Money and Interest Formulas 3.4 Project Evaluation, Depreciation, and Benefit-Cost Analysis
4 Chapter 4: Surveying Fundamentals, Construction Layout & Route Surveying
4.1 Errors, Corrections, and Pacing/Taping 4.2 Leveling, Earthworks, and Mass Haul Diagrams 4.3 Traverse Computations, Balancing, and Area Determinations 4.4 Route Surveying: Horizontal and Vertical Curves
5 Chapter 5: Highway & Transportation Engineering
5.1 Highway Geometric Design and Sight Distances 5.2 Traffic Engineering, Flow Fundamentals, and Pavement Design 5.3 Highway Policy, Route Location, Drainage, and Earthwork Slopes 5.4 Transportation Planning, Network Analysis, and Intermodal Systems
6 Chapter 6: Construction Materials, Methods, Management & Safety
6.1 Materials for Construction: Concrete, Formwork, Masonry, Steel, and Wood Products 6.2 Construction Equipment, Formwork, and Construction Methods 6.3 Construction Occupational Safety and Health: RA 11058 and DOLE DO 13 6.4 Construction Project Management, CPM/PERT, and Resource Scheduling 6.5 Construction Principles: Design Requirements, Project Organization, Cost Control, and Value Engineering 6.6 Quantity Surveying, Unit Cost Analysis, and Project Cost Estimates 6.7 Construction Trades and Specialties: Plumbing, Plastics, Doors and Windows, Finishes, and Electrical
7 Chapter 7: Fluid Properties, Hydrostatics & Buoyancy
7.1 Fluid Properties, Units, and Pressure Measurement 7.2 Hydrostatic Pressure on Plane and Curved Surfaces 7.3 Buoyancy, Flotation, and Accelerated Fluid Masses
8 Chapter 8: Hydrodynamics, Pipe Flow, Open Channels & Water Supply
8.1 Fluid Dynamics: Continuity and Energy Equations 8.2 Flow Measurement: Orifices, Weirs, and Venturi Meters 8.3 Fluid Flow in Pipes, Friction Losses, and Pipe Networks 8.4 Open Channel Flow, Manning's Equation, and Hydraulic Jump 8.5 Water Supply: Demand, Storage, Pumping, Distribution, and Treatment
9 Chapter 9: Soil Properties, Seepage & Stresses in Soil Mass
9.1 Soil Composition, Weight-Volume Phase Relationships 9.2 Soil Classification Systems (USCS & AASHTO) and Atterberg Limits 9.3 Soil Permeability, Seepage, Flow Nets, and Effective Stress 9.4 Stresses in Soil Mass, Stress Distribution, and Immediate and Secondary Settlement
10 Chapter 10: Consolidation, Soil Strength, Earth Pressures & Foundations
10.1 Soil Compaction and Soil Compressibility/Consolidation 10.2 Shear Strength of Soils and Mohr-Coulomb Failure Criteria 10.3 Lateral Earth Pressures (Rankine & Coulomb) and Retaining Walls 10.4 Shallow and Deep Foundation Bearing Capacity and Slope Stability
11 Chapter 11: Engineering Mechanics & Statics
11.1 Force Systems, Resultants, and Equilibrium of Rigid Bodies 11.2 Centroids, Moments of Inertia, and Friction 11.3 Cables, Trusses, and Internal Forces in Members
12 Chapter 12: Strength of Materials
12.1 Axial Stress, Strain, and Deformation 12.2 Torsion, Flanged Bolt Couplings, and Thin-Walled Pressure Vessels 12.3 Beam Stresses: Flexural and Transverse Shear 12.4 Beam Deflections, Combined Stresses, and Mohr's Circle
13 Chapter 13: Structural Analysis & NSCP Load Criteria
13.1 Indeterminate Structures: Approximate and Classical Methods 13.2 Moment Distribution Method and Slope Deflection 13.3 Influence Lines for Determinate and Indeterminate Structures 13.4 NSCP Minimum Design Loads: Dead, Live, Wind, and Earthquake
14 Chapter 14: Reinforced Concrete Design (NSCP 2015 / USD)
14.1 Ultimate Strength Design (USD) Principles and Singly Reinforced Beams 14.2 Doubly Reinforced Beams and T-Beams 14.3 Shear and Diagonal Tension, Stirrup Design, and Development Length 14.4 Reinforced Concrete Columns and Isolated Footing Design
15 Chapter 15: Steel, Timber & Prestressed Design and Materials Testing
15.1 Structural Steel Tension Members and Connections 15.2 Structural Steel Compression Members and Beam Design 15.3 Timber Design Principles, Working Stress, and Sawn Lumber Beams 15.4 Prestressed Concrete Fundamentals and Prestress Losses 15.5 Construction Materials Testing and Concrete Mix Proportioning
6.6 Quantity Surveying, Unit Cost Analysis, and Project Cost Estimates
Key Takeaways Explain This Topic AI
A detailed estimate takes off quantities item by item in standard units and prices each with a unit cost built up from materials, labor and equipment.
Concrete is measured in cubic meters, formwork in square meters of contact area, reinforcement in kilograms, and masonry in square meters or pieces.
A detailed unit price analysis adds indirect costs (overhead, contingencies, miscellaneous and profit) and VAT to the direct cost of each pay item.
Quantity takeoff should follow a consistent sequence and measure net dimensions, with waste allowances added separately.
A preliminary estimate uses cost per square meter of floor area or per unit of capacity, while a detailed estimate requires complete plans and specifications.
Last updated: October 2026
6.6 Quantity Surveying, Unit Cost Analysis, and Project Cost Estimates
The AMSTHC TOS area "Quantity Surveying" has five competencies:
Understand methods used to prepare building, bridge and construction cost estimates.
Review specifications, plans and details.
Analyze and derive unit costs for labor, material and equipment.
Apply methods of estimating for detailed quantity surveys.
Create a summary of total project costs.
Types of Estimates
Estimate When used Basis Typical accuracy
Conceptual or order-of-magnitude Feasibility Cost per m² of floor area, per lane-km, per bed or per classroom Rough
Preliminary Schematic design Major elements and assemblies Moderate
Detailed (definitive) Bidding and contract award Complete takeoff of every pay item from final plans and specifications Best
Bridge estimates are often built per element: foundations by piles, substructure by concrete and reinforcement, superstructure by girders and deck, plus approaches and slope protection.
Reading Plans and Specifications
Plans give dimensions and quantities. Specifications give quality, materials, workmanship and the method of measurement and basis of payment for each pay item.
Check scale, units and revision status. Reconcile plan and detail conflicts using the contract's order of precedence (Section 1.3).
Note items that are easy to miss: excavation and backfill, formwork, lap splices and hooks, embedded items, waterproofing, curing, scaffolding and temporary works.
Quantity Takeoff Methods
- Work item Unit Takeoff rule
- Excavation m³ Net trench or pit volume, plus working space and slope where required
- Concrete m³ Net volume of each member; do not double-count beam-slab intersections
- Formwork m² Contact area of concrete with the forms
- Reinforcing steel kg Bar length × number × mass per meter, plus laps and hooks
- CHB masonry m² or pieces Net wall area × 12.5 blocks/m²
- Plastering, painting m² Net area of each face finished
Worked takeoff: isolated footing and pedestal. The footing is 2.0 × 2.0 × 0.40 m 2.0 \times 2.0 \times 0.40\text{ m} 2.0 × 2.0 × 0.40 m , and the pedestal is 0.40 × 0.40 × 1.20 m 0.40 \times 0.40 \times 1.20\text{ m} 0.40 × 0.40 × 1.20 m . Reinforcement is 10-16 mm bars each way in the footing, each 1.85 m 1.85\text{ m} 1.85 m long.
Concrete: footing 2.0 ( 2.0 ) ( 0.40 ) = 1.600 m 3 2.0(2.0)(0.40) = 1.600\text{ m}^3 2.0 ( 2.0 ) ( 0.40 ) = 1.600 m 3 ; pedestal 0.40 ( 0.40 ) ( 1.20 ) = 0.192 m 3 0.40(0.40)(1.20) = 0.192\text{ m}^3 0.40 ( 0.40 ) ( 1.20 ) = 0.192 m 3 ; total 1.792 m 3 1.792\text{ m}^3 1.792 m 3 .
Formwork: footing sides 4 ( 2.0 ) ( 0.40 ) = 3.20 m 2 4(2.0)(0.40) = 3.20\text{ m}^2 4 ( 2.0 ) ( 0.40 ) = 3.20 m 2 ; pedestal sides 4 ( 0.40 ) ( 1.20 ) = 1.92 m 2 4(0.40)(1.20) = 1.92\text{ m}^2 4 ( 0.40 ) ( 1.20 ) = 1.92 m 2 ; total 5.12 m 2 5.12\text{ m}^2 5.12 m 2 .
Footing bars: 2 × 10 = 20 2 \times 10 = 20 2 × 10 = 20 bars × 1.85 m 1.85\text{ m} 1.85 m = 37.0 m 37.0\text{ m} 37.0 m , which at 1.58 kg/m 1.58\text{ kg/m} 1.58 kg/m is 58.5 kg 58.5\text{ kg} 58.5 kg .
Unit Cost Analysis
The detailed unit price analysis (DUPA) builds the cost of one unit of a pay item:
- Component How computed
- Materials Quantity of each material per unit × unit price, including waste allowance
- Labor Crew composition × daily rates ÷ crew output per day
- Equipment Equipment hours per unit × hourly rental or operating rate
- Direct cost Sum of the three
Indirect costs Overhead, contingencies, miscellaneous expenses and contractor's profit, as percentages of direct cost
- Value-added tax Applied to direct plus indirect cost
- Unit price (Direct + indirect + VAT) per unit
Government agencies prescribe indirect-cost percentages and DUPA formats for their projects. Use the percentages given in the problem or in the current agency guideline.
Example: one cubic meter of concrete. Assume 9 bags of cement at ₱280, 0.50 m 3 0.50\text{ m}^3 0.50 m 3 sand at ₱1,400 and 1.00 m 3 1.00\text{ m}^3 1.00 m 3 gravel at ₱1,600.
Materials: ₱4,820, from 9 ( 280 ) + 0.5 ( 1,400 ) + 1.0 ( 1,600 ) = 2,520 + 700 + 1,600 9(280) + 0.5(1{,}400) + 1.0(1{,}600) = 2{,}520 + 700 + 1{,}600 9 ( 280 ) + 0.5 ( 1 , 400 ) + 1.0 ( 1 , 600 ) = 2 , 520 + 700 + 1 , 600 .
Labor: a crew costing ₱8,000 per day places 8 m 3 8\text{ m}^3 8 m 3 per day, so ₱1,000 per m³.
Mixer: ₱300 per m³.
Direct cost: ₱6,120.
With 15% indirect costs: ₱7,038, from 6,120 × 1.15 6{,}120 \times 1.15 6 , 120 × 1.15 .
With 12% VAT: ₱7,883 per m³, from 7,038 × 1.12 7{,}038 \times 1.12 7 , 038 × 1.12 .
Summary of Total Project Costs
A bill of quantities lists every pay item with quantity, unit, unit price and amount. The summary groups items by division and adds the following:
- Line Example (₱)
- Earthworks 1,250,000
- Concrete and reinforcement 6,800,000
- Masonry and finishes 3,100,000
- Steel and roofing 2,400,000
- Plumbing, electrical and mechanical 2,950,000
- Total direct cost 16,500,000
- Indirect costs (overhead, contingency, miscellaneous, profit), say 15% 2,475,000
- Subtotal 18,975,000
- VAT 12% 2,277,000
- Total project cost 21,252,000
Cross-check with a cost per square meter . For a 1,200 m 2 1{,}200\text{ m}^2 1 , 200 m 2 building, ₱21.25 million is about ₱17,700/m². Compare that with similar recent projects to catch takeoff errors.
Tip
In board problems, read carefully whether VAT and indirect costs are already included in a given unit price, and whether waste allowances are to be added.