1.3 Civil Engineering Ethics, Contracts, and Professional Practice

PRC Civil Engineer Licensure Examination CELE

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: Examination Overview, RA 544 & Professional Practice

1.1 CELE Structure, Format, Scoring, and 2026 Subject Order 1.2 Republic Act No. 544: The Civil Engineering Law and Board Regulations 1.3 Civil Engineering Ethics, Contracts, and Professional Practice

2 Chapter 2: Engineering Mathematics, Numerical Methods & Physics

2.1 Advanced Algebra, Progressions & Word Problems 2.2 Trigonometry and Analytical Geometry 2.3 Differential and Integral Calculus 2.4 Differential Equations and Numerical Methods 2.5 Series, Hyperbolic Functions, Multivariable Calculus, and Laplace Transforms 2.6 Numerical Methods: Linear Systems, Interpolation, Curve Fitting, and ODE Solvers 2.7 Physics for Engineers: Kinematics, Newton's Laws, Work-Energy, and Momentum

3 Chapter 3: Engineering Data Analysis & Engineering Economy

3.1 Engineering Data Analysis and Statistical Applications 3.2 Parameter Estimation, Linear Regression, Correlation, and Queuing Models 3.3 Engineering Economy: Time Value of Money and Interest Formulas 3.4 Project Evaluation, Depreciation, and Benefit-Cost Analysis

4 Chapter 4: Surveying Fundamentals, Construction Layout & Route Surveying

4.1 Errors, Corrections, and Pacing/Taping 4.2 Leveling, Earthworks, and Mass Haul Diagrams 4.3 Traverse Computations, Balancing, and Area Determinations 4.4 Route Surveying: Horizontal and Vertical Curves

5 Chapter 5: Highway & Transportation Engineering

5.1 Highway Geometric Design and Sight Distances 5.2 Traffic Engineering, Flow Fundamentals, and Pavement Design 5.3 Highway Policy, Route Location, Drainage, and Earthwork Slopes 5.4 Transportation Planning, Network Analysis, and Intermodal Systems

6 Chapter 6: Construction Materials, Methods, Management & Safety

6.1 Materials for Construction: Concrete, Formwork, Masonry, Steel, and Wood Products 6.2 Construction Equipment, Formwork, and Construction Methods 6.3 Construction Occupational Safety and Health: RA 11058 and DOLE DO 13 6.4 Construction Project Management, CPM/PERT, and Resource Scheduling 6.5 Construction Principles: Design Requirements, Project Organization, Cost Control, and Value Engineering 6.6 Quantity Surveying, Unit Cost Analysis, and Project Cost Estimates 6.7 Construction Trades and Specialties: Plumbing, Plastics, Doors and Windows, Finishes, and Electrical

7 Chapter 7: Fluid Properties, Hydrostatics & Buoyancy

7.1 Fluid Properties, Units, and Pressure Measurement 7.2 Hydrostatic Pressure on Plane and Curved Surfaces 7.3 Buoyancy, Flotation, and Accelerated Fluid Masses

8 Chapter 8: Hydrodynamics, Pipe Flow, Open Channels & Water Supply

8.1 Fluid Dynamics: Continuity and Energy Equations 8.2 Flow Measurement: Orifices, Weirs, and Venturi Meters 8.3 Fluid Flow in Pipes, Friction Losses, and Pipe Networks 8.4 Open Channel Flow, Manning's Equation, and Hydraulic Jump 8.5 Water Supply: Demand, Storage, Pumping, Distribution, and Treatment

9 Chapter 9: Soil Properties, Seepage & Stresses in Soil Mass

9.1 Soil Composition, Weight-Volume Phase Relationships 9.2 Soil Classification Systems (USCS & AASHTO) and Atterberg Limits 9.3 Soil Permeability, Seepage, Flow Nets, and Effective Stress 9.4 Stresses in Soil Mass, Stress Distribution, and Immediate and Secondary Settlement

10 Chapter 10: Consolidation, Soil Strength, Earth Pressures & Foundations

10.1 Soil Compaction and Soil Compressibility/Consolidation 10.2 Shear Strength of Soils and Mohr-Coulomb Failure Criteria 10.3 Lateral Earth Pressures (Rankine & Coulomb) and Retaining Walls 10.4 Shallow and Deep Foundation Bearing Capacity and Slope Stability

11 Chapter 11: Engineering Mechanics & Statics

11.1 Force Systems, Resultants, and Equilibrium of Rigid Bodies 11.2 Centroids, Moments of Inertia, and Friction 11.3 Cables, Trusses, and Internal Forces in Members

12 Chapter 12: Strength of Materials

12.1 Axial Stress, Strain, and Deformation 12.2 Torsion, Flanged Bolt Couplings, and Thin-Walled Pressure Vessels 12.3 Beam Stresses: Flexural and Transverse Shear 12.4 Beam Deflections, Combined Stresses, and Mohr's Circle

13 Chapter 13: Structural Analysis & NSCP Load Criteria

13.1 Indeterminate Structures: Approximate and Classical Methods 13.2 Moment Distribution Method and Slope Deflection 13.3 Influence Lines for Determinate and Indeterminate Structures 13.4 NSCP Minimum Design Loads: Dead, Live, Wind, and Earthquake

14 Chapter 14: Reinforced Concrete Design (NSCP 2015 / USD)

14.1 Ultimate Strength Design (USD) Principles and Singly Reinforced Beams 14.2 Doubly Reinforced Beams and T-Beams 14.3 Shear and Diagonal Tension, Stirrup Design, and Development Length 14.4 Reinforced Concrete Columns and Isolated Footing Design

15 Chapter 15: Steel, Timber & Prestressed Design and Materials Testing

15.1 Structural Steel Tension Members and Connections 15.2 Structural Steel Compression Members and Beam Design 15.3 Timber Design Principles, Working Stress, and Sawn Lumber Beams 15.4 Prestressed Concrete Fundamentals and Prestress Losses 15.5 Construction Materials Testing and Concrete Mix Proportioning

1.3 Civil Engineering Ethics, Contracts, and Professional Practice

Key Takeaways Explain This Topic AI

Section 4 of RA 544 directs the Board of Civil Engineering to adopt a code of ethics for the practice of civil engineering.

The Board's Code of Ethics makes it unprofessional to compete for a professional engagement by cutting charges after learning another engineer's fee.

Civil Code Article 1723 makes the designer liable for collapse within 15 years of completion due to defective plans or ground.

Under Article 1723, an action for a building collapse must be brought within ten years following the collapse.

RA 12009 (July 20, 2024) lets the BAC award infrastructure contracts to the LCRB or the MEARB.

Last updated: October 2026

1.3 Civil Engineering Ethics, Contracts, and Professional Practice

Civil engineers design and supervise work on which public safety depends. Three bodies of rules govern how they practice:

the Code of Ethics adopted by the Board of Civil Engineering under Section 4 of RA 544;

the Civil Code of the Philippines (RA 386) , which fixes liability for defective buildings and the rules on construction contracts;

the procurement law for government projects, now the New Government Procurement Act (RA 12009) .

Contract conditions also appear in the AMSTHC table of specifications under construction principles, for example "review general conditions of the construction contract."

The Board's Code of Ethics

The Code of Ethics published by PRC for the Board of Civil Engineering is short. It lists acts that are "unprofessional and inconsistent with honorable and dignified bearing for any registered Civil Engineer." The word clients in the Code includes employers. Under the Code, it is unprofessional to:

Prohibited conduct What it protects

Act for clients other than as a faithful agent or trustee , or accept remuneration other than stated charges Loyalty; no hidden commissions from suppliers or contractors

Injure, falsely or maliciously, the professional reputation, prospects or business of another engineer Fair dealing among engineers

Try to supplant another engineer after definite steps toward that engineer's employment Respect for existing engagements

Take part in competitive bidding on a price basis to secure a professional engagement Selection on qualifications, not fee alone

Compete for employment by reducing one's usual charges after being told another engineer's charges No underbidding

Review the work of another engineer for the same client without that engineer's knowledge or consent, unless that engineer's connection has ended Professional courtesy and accountability

Advertise in self-laudatory language or in a manner derogatory to the profession's dignity Truthful public statements

Use the advantages of a salaried position to compete unfairly with engineers in private practice Fair competition

Act in any manner that brings discredit on the honor or dignity of the profession General duty of professional conduct

Many engineering codes also state the overriding principle that engineers hold paramount the safety, health and welfare of the public. ASCE's Code of Ethics is one example. In Philippine practice, that principle is enforced through RA 544 itself: Section 23 requires plans signed and sealed by a civil engineer and work under a civil engineer's direct supervision. The Board may suspend or revoke certificates for unprofessional or dishonorable conduct.

Applying the Code

Fees. Quoting a lower fee after learning a colleague's charges, in order to take the job, is the underbidding the Code forbids. Price-only "bidding" for design services runs into the same rule.

Gifts and commissions. A supervising engineer who takes a "rebate" from a ready-mix supplier is no longer a faithful agent of the owner.

Peer review. A second engineer asked to check a structural design should first tell the engineer of record, unless that engagement has ended.

Pressure to cut safety. If an owner or contractor asks for reductions that violate the National Structural Code, the engineer documents the objection in writing and declines to seal non-compliant plans.

Liability for Collapse: Civil Code Article 1723

Article 1723 of the Civil Code reads:

The engineer or architect who drew up the plans and specifications for a building is liable for damages if within fifteen years from the completion of the structure, the same should collapse by reason of a defect in those plans and specifications, or due to the defects in the ground. The contractor is likewise responsible for the damages if the edifice falls, within the same period, on account of defects in the construction or the use of materials of inferior quality furnished by him, or due to any violation of the terms of the contract. If the engineer or architect supervises the construction, he shall be solidarily liable with the contractor.

Acceptance of the building, after completion, does not imply waiver of any of the cause of action by reason of any defect mentioned in the preceding paragraph.

The action must be brought within ten years following the collapse of the building.

  • Element Rule
  • Warranty window Collapse within 15 years from completion
  • Designer's liability Defects in plans and specifications, or defects in the ground
  • Contractor's liability Construction defects, inferior materials it furnished, or breach of contract terms
  • Supervising engineer or architect Solidarily liable with the contractor
  • Acceptance by owner Does not waive the cause of action
  • Prescription Action must be filed within 10 years after the collapse

Loading diagram...

Price changes in stipulated-price contracts: Article 1724

Article 1724 protects owners in fixed-price work. A contractor who agreed to build for a stipulated price, following agreed plans and specifications, may not withdraw or demand a higher price because labor or materials became more expensive. The exception is a change in the plans and specifications, but only when:

the change was authorized by the owner in writing , and

the additional price was determined in writing by both parties.

This is why change orders and variation orders must be documented and priced before the work is done.

Contract Documents and Delivery Systems

A construction contract is a set of documents. For private construction, CIAP Document 102 (Uniform General Conditions of Contract for Private Construction) is widely used. Government projects use the general and special conditions in the Philippine Bidding Documents. Typical components are:

Agreement or contract form. Parties, price, time, and the list of contract documents.

Conditions of contract. General conditions, plus special or particular conditions that modify them for the project.

Technical specifications. Materials, workmanship, and testing.

Drawings. Plans, elevations, sections, and details.

Bill of quantities and the contractor's bid. Detailed unit price analyses support each pay item.

Each contract states its own order of precedence for resolving conflicts, so always read that clause rather than relying on a general rule. Common contract terms include performance security, liquidated damages for delay, variation orders, extensions of time, retention, and the defects-liability period.

Delivery system Who designs Who builds Typical use

Design-bid-build Owner's consultant Contractor selected after design Most public works; clear checks between designer and builder

Design-build One entity Same entity Fast-track projects; owner needs strong quality oversight

Engineering-procurement-construction (EPC) Contractor Contractor, turnkey Plants, power stations, port facilities

Government Procurement: From RA 9184 to RA 12009

For two decades, government infrastructure was procured under RA 9184 (Government Procurement Reform Act, 2003). Under that law, civil works went to the Lowest Calculated Responsive Bid and consulting services to the Highest Rated Responsive Bid.

RA 12009, the New Government Procurement Act , became law on July 20, 2024 and revised RA 9184. Its implementing rules were approved in February 2025. Key points:

Award criteria for goods and infrastructure. At the pre-procurement conference, the Bids and Awards Committee decides, on the end-user's recommendation, whether the contract goes to the Lowest Calculated Responsive Bid (LCRB) or the Most Economically Advantageous Responsive Bid (MEARB) . MEARB weights technical and financial aspects, and the Government Procurement Policy Board may adopt other criteria such as the Most Advantageous Responsive Bid.

Consulting services remain evaluated on quality, leading to the Highest Rated Responsive Bid (HRRB) .

Post-qualification verifies the bidder with the lowest calculated bid, the most economically advantageous bid, or the highest rated bid before award. A bidder that fails is post-disqualified, and the next-ranked bidder is checked.

Transparency. Opportunities and awards continue to be posted on the government electronic procurement system (PhilGEPS).

Loading diagram... Government Infrastructure Procurement Under RA 12009