5.3 Highway Policy, Route Location, Drainage, and Earthwork Slopes

PRC Civil Engineer Licensure Examination CELE

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: Examination Overview, RA 544 & Professional Practice

1.1 CELE Structure, Format, Scoring, and 2026 Subject Order 1.2 Republic Act No. 544: The Civil Engineering Law and Board Regulations 1.3 Civil Engineering Ethics, Contracts, and Professional Practice

2 Chapter 2: Engineering Mathematics, Numerical Methods & Physics

2.1 Advanced Algebra, Progressions & Word Problems 2.2 Trigonometry and Analytical Geometry 2.3 Differential and Integral Calculus 2.4 Differential Equations and Numerical Methods 2.5 Series, Hyperbolic Functions, Multivariable Calculus, and Laplace Transforms 2.6 Numerical Methods: Linear Systems, Interpolation, Curve Fitting, and ODE Solvers 2.7 Physics for Engineers: Kinematics, Newton's Laws, Work-Energy, and Momentum

3 Chapter 3: Engineering Data Analysis & Engineering Economy

3.1 Engineering Data Analysis and Statistical Applications 3.2 Parameter Estimation, Linear Regression, Correlation, and Queuing Models 3.3 Engineering Economy: Time Value of Money and Interest Formulas 3.4 Project Evaluation, Depreciation, and Benefit-Cost Analysis

4 Chapter 4: Surveying Fundamentals, Construction Layout & Route Surveying

4.1 Errors, Corrections, and Pacing/Taping 4.2 Leveling, Earthworks, and Mass Haul Diagrams 4.3 Traverse Computations, Balancing, and Area Determinations 4.4 Route Surveying: Horizontal and Vertical Curves

5 Chapter 5: Highway & Transportation Engineering

5.1 Highway Geometric Design and Sight Distances 5.2 Traffic Engineering, Flow Fundamentals, and Pavement Design 5.3 Highway Policy, Route Location, Drainage, and Earthwork Slopes 5.4 Transportation Planning, Network Analysis, and Intermodal Systems

6 Chapter 6: Construction Materials, Methods, Management & Safety

6.1 Materials for Construction: Concrete, Formwork, Masonry, Steel, and Wood Products 6.2 Construction Equipment, Formwork, and Construction Methods 6.3 Construction Occupational Safety and Health: RA 11058 and DOLE DO 13 6.4 Construction Project Management, CPM/PERT, and Resource Scheduling 6.5 Construction Principles: Design Requirements, Project Organization, Cost Control, and Value Engineering 6.6 Quantity Surveying, Unit Cost Analysis, and Project Cost Estimates 6.7 Construction Trades and Specialties: Plumbing, Plastics, Doors and Windows, Finishes, and Electrical

7 Chapter 7: Fluid Properties, Hydrostatics & Buoyancy

7.1 Fluid Properties, Units, and Pressure Measurement 7.2 Hydrostatic Pressure on Plane and Curved Surfaces 7.3 Buoyancy, Flotation, and Accelerated Fluid Masses

8 Chapter 8: Hydrodynamics, Pipe Flow, Open Channels & Water Supply

8.1 Fluid Dynamics: Continuity and Energy Equations 8.2 Flow Measurement: Orifices, Weirs, and Venturi Meters 8.3 Fluid Flow in Pipes, Friction Losses, and Pipe Networks 8.4 Open Channel Flow, Manning's Equation, and Hydraulic Jump 8.5 Water Supply: Demand, Storage, Pumping, Distribution, and Treatment

9 Chapter 9: Soil Properties, Seepage & Stresses in Soil Mass

9.1 Soil Composition, Weight-Volume Phase Relationships 9.2 Soil Classification Systems (USCS & AASHTO) and Atterberg Limits 9.3 Soil Permeability, Seepage, Flow Nets, and Effective Stress 9.4 Stresses in Soil Mass, Stress Distribution, and Immediate and Secondary Settlement

10 Chapter 10: Consolidation, Soil Strength, Earth Pressures & Foundations

10.1 Soil Compaction and Soil Compressibility/Consolidation 10.2 Shear Strength of Soils and Mohr-Coulomb Failure Criteria 10.3 Lateral Earth Pressures (Rankine & Coulomb) and Retaining Walls 10.4 Shallow and Deep Foundation Bearing Capacity and Slope Stability

11 Chapter 11: Engineering Mechanics & Statics

11.1 Force Systems, Resultants, and Equilibrium of Rigid Bodies 11.2 Centroids, Moments of Inertia, and Friction 11.3 Cables, Trusses, and Internal Forces in Members

12 Chapter 12: Strength of Materials

12.1 Axial Stress, Strain, and Deformation 12.2 Torsion, Flanged Bolt Couplings, and Thin-Walled Pressure Vessels 12.3 Beam Stresses: Flexural and Transverse Shear 12.4 Beam Deflections, Combined Stresses, and Mohr's Circle

13 Chapter 13: Structural Analysis & NSCP Load Criteria

13.1 Indeterminate Structures: Approximate and Classical Methods 13.2 Moment Distribution Method and Slope Deflection 13.3 Influence Lines for Determinate and Indeterminate Structures 13.4 NSCP Minimum Design Loads: Dead, Live, Wind, and Earthquake

14 Chapter 14: Reinforced Concrete Design (NSCP 2015 / USD)

14.1 Ultimate Strength Design (USD) Principles and Singly Reinforced Beams 14.2 Doubly Reinforced Beams and T-Beams 14.3 Shear and Diagonal Tension, Stirrup Design, and Development Length 14.4 Reinforced Concrete Columns and Isolated Footing Design

15 Chapter 15: Steel, Timber & Prestressed Design and Materials Testing

15.1 Structural Steel Tension Members and Connections 15.2 Structural Steel Compression Members and Beam Design 15.3 Timber Design Principles, Working Stress, and Sawn Lumber Beams 15.4 Prestressed Concrete Fundamentals and Prestress Losses 15.5 Construction Materials Testing and Concrete Mix Proportioning

5.3 Highway Policy, Route Location, Drainage, and Earthwork Slopes

Key Takeaways Explain This Topic AI

Presidential Decree No. 17 (1972), the Revised Philippine Highway Act, classifies roads by administrative responsibility, such as national, provincial, city, municipal and barangay roads.

RA 10752 (2016) governs right-of-way acquisition for national government infrastructure and was amended by RA 12289 on September 12, 2025.

Route location proceeds from reconnaissance to preliminary survey to final location survey, narrowing alternatives at each stage.

The rational method gives peak runoff Q = CiA/360 in m³/s, with i in mm/h and A in hectares.

Embankments are built in compacted layers on benched, stripped foundations, and cut slopes are set flatter in weaker or wetter soils.

Last updated: October 2026

5.3 Highway Policy, Route Location, Drainage, and Earthwork Slopes

The AMSTHC TOS area "Highway Engineering" has five competencies:

Recall highway policies and administration.

Review geometric design standards.

Determine route location.

Design and construct pavements.

Design drainage, foundations, embankments and cut slopes.

Section 5.1 covers geometric design and Section 5.2 covers pavements. This section covers the other three.

Highway Policy and Administration

  • Instrument What it does
  • RA 917 (1953), Philippine Highway Act Early framework for national and local highway programs and funding

PD 17 (1972), Revised Philippine Highway Act Classifies roads by administrative responsibility, such as national, provincial, city, municipal and barangay roads, and empowers the public works department to set standards

DPWH functional classification (from 2014) Divides national roads into primary , secondary and tertiary by function and connectivity, with a route-numbering system

RA 10752 (2016), Right-of-Way Act Sets how national government agencies acquire right-of-way: donation, negotiated sale based on market value, or expropriation

RA 12289 (September 12, 2025), ARROW Act Amends RA 10752, extending it to public-private partnership and public-service-provider projects and tightening control of developments within declared right-of-way

Planning and programming cycle. A typical cycle runs through the following stages:

Identify needs from traffic counts, road condition surveys and network gaps.

Prepare pre-feasibility and feasibility studies, including economic analysis and benefit-cost ratios.

Prepare detailed engineering design.

Acquire the right-of-way.

Procure and construct.

Maintain the road throughout its life.

Maintenance categories.

Routine maintenance includes vegetation control, ditch cleaning and pothole patching.

Periodic maintenance includes resealing and overlays.

Rehabilitation and reconstruction restore a pavement that has failed structurally.

Route Location

Route location balances construction cost, user cost, safety and environmental impact. Surveys move from broad to precise in three stages:

Reconnaissance. Study maps, satellite imagery and the terrain to identify feasible corridors and controls. Controls include fixed points such as river crossings and passes, and areas to avoid such as protected areas, unstable slopes and dense settlements.

Preliminary survey. Run traverses and levels along the most promising corridors, prepare strip topographic maps, and compare alternatives. Comparison criteria include length, ruling grade, earthwork, number of bridges and cost.

Location survey. Stake the final centerline with curves and stationing. Set slope stakes, reference points and benchmarks for construction.

Location principles:

Keep grades within limits. The ruling grade is the maximum grade adopted for design. Long steep grades slow trucks and may need climbing lanes.

Balance cut and fill. Mass-haul analysis, covered in Section 4.2, keeps haul distances within the limit of economic haul.

Prefer good ground. Avoid swamps, landslide-prone slopes and repeated stream crossings. Cross rivers at right angles where the channel is narrow and stable.

Coordinate horizontal and vertical alignment. Avoid placing sharp horizontal curves at the crests of vertical curves.

Highway Drainage

Water is the main enemy of pavements: saturated subgrades lose strength, and surface water causes hydroplaning.

Surface runoff by the rational method

For small catchments, typically under about 80 hectares:

  • Q = C i A 360 Q = \frac{C\,i\,A}{360} Q = 360 C i A ​
  • Q Q Q = peak runoff ( m 3 / s \text{m}^3/\text{s} m 3 / s )
  • C C C = runoff coefficient: roughly 0.70 0.70 0.70 to 0.95 0.95 0.95 for pavement, lower for grass and forest

i i i = rainfall intensity ( mm/h \text{mm/h} mm/h ) for a duration equal to the time of concentration t c t_c t c ​

A A A = drainage area (hectares)

For mixed surfaces, use the area-weighted coefficient C = ∑ C j A j / ∑ A j C = \sum C_j A_j / \sum A_j C = ∑ C j ​ A j ​ / ∑ A j ​ .

Example. A 12 ha 12\text{ ha} 12 ha catchment has 4 ha 4\text{ ha} 4 ha of pavement ( C = 0.90 C = 0.90 C = 0.90 ) and 8 ha 8\text{ ha} 8 ha of grass ( C = 0.30 C = 0.30 C = 0.30 ). The design intensity at t c t_c t c ​ is 150 mm/h 150\text{ mm/h} 150 mm/h .

Weighted C = ( 3.6 + 2.4 ) / 12 = 0.50 C = (3.6 + 2.4)/12 = 0.50 C = ( 3.6 + 2.4 ) /12 = 0.50 .

Q = 0.50 ( 150 ) ( 12 ) / 360 = 2.50 m 3 / s Q = 0.50(150)(12)/360 = 2.50\text{ m}^3/\text{s} Q = 0.50 ( 150 ) ( 12 ) /360 = 2.50 m 3 / s .

Drainage elements

Cross slope (crown) sheds water to the edges: about 1.5% to 2% for paved lanes and steeper for gravel shoulders.

Side ditches are sized with Manning's equation (Section 8.4) for the design flow. They are lined where velocities would cause erosion.

Culverts (pipe or box) carry streams under the road. Their capacity depends on inlet or outlet control, and the headwater must stay below the road edge.

Subsurface drains (perforated pipes in filter material) lower the water table beneath the pavement. They are critical in cuts and on flat, wet ground.

Energy dissipators and riprap are placed at culvert outlets to prevent scour.

  • Foundations, Embankments and Cut Slopes
  • Embankment construction

Clear and grub the site, and strip topsoil and organic material from the embankment footprint.

On sloping ground steeper than about 1V:4H, cut benches so new fill keys into the existing slope.

Place fill in horizontal layers , typically about 150 to 200 mm compacted thickness. Compact each layer to the specified relative compaction before placing the next.

Do not use unsuitable materials, such as peat, highly plastic clay and organic soil, in the embankment.

On soft foundations , consider preloading with vertical drains, staged construction, or lightweight fill. Monitor settlement before paving.

Cut slopes and slope protection

Stable slope angles depend on material and water. Compact granular soils and sound rock stand steeper, while clays, weathered rock and wet ground need flatter slopes or benches.

  • Measure Purpose
  • Benches on high cuts Catch falling debris and break up runoff
  • Interceptor (crest) ditches Divert water before it reaches the slope face
  • Vegetation, coconut-fiber mats Surface erosion control
  • Riprap, grouted riprap, gabions Toe and stream-bank protection
  • Retaining walls, soil nails, rock bolts Where space is limited or slopes are steep
  • Horizontal drains Lower pore pressure inside the slope

For the slope-stability calculations themselves (infinite slopes, the Swedish circle, slices), see Section 10.4. For retaining walls, see Section 10.3.

Loading diagram... Route Location Survey Stages