Study guide

8.5 Water Supply: Demand, Storage, Pumping, Distribution, and Treatment

PRC Civil Engineer Licensure Examination CELE

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: Examination Overview, RA 544 & Professional Practice

1.1 CELE Structure, Format, Scoring, and 2026 Subject Order 1.2 Republic Act No. 544: The Civil Engineering Law and Board Regulations 1.3 Civil Engineering Ethics, Contracts, and Professional Practice

2 Chapter 2: Engineering Mathematics, Numerical Methods & Physics

2.1 Advanced Algebra, Progressions & Word Problems 2.2 Trigonometry and Analytical Geometry 2.3 Differential and Integral Calculus 2.4 Differential Equations and Numerical Methods 2.5 Series, Hyperbolic Functions, Multivariable Calculus, and Laplace Transforms 2.6 Numerical Methods: Linear Systems, Interpolation, Curve Fitting, and ODE Solvers 2.7 Physics for Engineers: Kinematics, Newton's Laws, Work-Energy, and Momentum

3 Chapter 3: Engineering Data Analysis & Engineering Economy

3.1 Engineering Data Analysis and Statistical Applications 3.2 Parameter Estimation, Linear Regression, Correlation, and Queuing Models 3.3 Engineering Economy: Time Value of Money and Interest Formulas 3.4 Project Evaluation, Depreciation, and Benefit-Cost Analysis

4 Chapter 4: Surveying Fundamentals, Construction Layout & Route Surveying

4.1 Errors, Corrections, and Pacing/Taping 4.2 Leveling, Earthworks, and Mass Haul Diagrams 4.3 Traverse Computations, Balancing, and Area Determinations 4.4 Route Surveying: Horizontal and Vertical Curves

5 Chapter 5: Highway & Transportation Engineering

5.1 Highway Geometric Design and Sight Distances 5.2 Traffic Engineering, Flow Fundamentals, and Pavement Design 5.3 Highway Policy, Route Location, Drainage, and Earthwork Slopes 5.4 Transportation Planning, Network Analysis, and Intermodal Systems

6 Chapter 6: Construction Materials, Methods, Management & Safety

6.1 Materials for Construction: Concrete, Formwork, Masonry, Steel, and Wood Products 6.2 Construction Equipment, Formwork, and Construction Methods 6.3 Construction Occupational Safety and Health: RA 11058 and DOLE DO 13 6.4 Construction Project Management, CPM/PERT, and Resource Scheduling 6.5 Construction Principles: Design Requirements, Project Organization, Cost Control, and Value Engineering 6.6 Quantity Surveying, Unit Cost Analysis, and Project Cost Estimates 6.7 Construction Trades and Specialties: Plumbing, Plastics, Doors and Windows, Finishes, and Electrical

7 Chapter 7: Fluid Properties, Hydrostatics & Buoyancy

7.1 Fluid Properties, Units, and Pressure Measurement 7.2 Hydrostatic Pressure on Plane and Curved Surfaces 7.3 Buoyancy, Flotation, and Accelerated Fluid Masses

8 Chapter 8: Hydrodynamics, Pipe Flow, Open Channels & Water Supply

8.1 Fluid Dynamics: Continuity and Energy Equations 8.2 Flow Measurement: Orifices, Weirs, and Venturi Meters 8.3 Fluid Flow in Pipes, Friction Losses, and Pipe Networks 8.4 Open Channel Flow, Manning's Equation, and Hydraulic Jump 8.5 Water Supply: Demand, Storage, Pumping, Distribution, and Treatment

9 Chapter 9: Soil Properties, Seepage & Stresses in Soil Mass

9.1 Soil Composition, Weight-Volume Phase Relationships 9.2 Soil Classification Systems (USCS & AASHTO) and Atterberg Limits 9.3 Soil Permeability, Seepage, Flow Nets, and Effective Stress 9.4 Stresses in Soil Mass, Stress Distribution, and Immediate and Secondary Settlement

10 Chapter 10: Consolidation, Soil Strength, Earth Pressures & Foundations

10.1 Soil Compaction and Soil Compressibility/Consolidation 10.2 Shear Strength of Soils and Mohr-Coulomb Failure Criteria 10.3 Lateral Earth Pressures (Rankine & Coulomb) and Retaining Walls 10.4 Shallow and Deep Foundation Bearing Capacity and Slope Stability

11 Chapter 11: Engineering Mechanics & Statics

11.1 Force Systems, Resultants, and Equilibrium of Rigid Bodies 11.2 Centroids, Moments of Inertia, and Friction 11.3 Cables, Trusses, and Internal Forces in Members

12 Chapter 12: Strength of Materials

12.1 Axial Stress, Strain, and Deformation 12.2 Torsion, Flanged Bolt Couplings, and Thin-Walled Pressure Vessels 12.3 Beam Stresses: Flexural and Transverse Shear 12.4 Beam Deflections, Combined Stresses, and Mohr's Circle

13 Chapter 13: Structural Analysis & NSCP Load Criteria

13.1 Indeterminate Structures: Approximate and Classical Methods 13.2 Moment Distribution Method and Slope Deflection 13.3 Influence Lines for Determinate and Indeterminate Structures 13.4 NSCP Minimum Design Loads: Dead, Live, Wind, and Earthquake

14 Chapter 14: Reinforced Concrete Design (NSCP 2015 / USD)

14.1 Ultimate Strength Design (USD) Principles and Singly Reinforced Beams 14.2 Doubly Reinforced Beams and T-Beams 14.3 Shear and Diagonal Tension, Stirrup Design, and Development Length 14.4 Reinforced Concrete Columns and Isolated Footing Design

15 Chapter 15: Steel, Timber & Prestressed Design and Materials Testing

15.1 Structural Steel Tension Members and Connections 15.2 Structural Steel Compression Members and Beam Design 15.3 Timber Design Principles, Working Stress, and Sawn Lumber Beams 15.4 Prestressed Concrete Fundamentals and Prestress Losses 15.5 Construction Materials Testing and Concrete Mix Proportioning

8.5 Water Supply: Demand, Storage, Pumping, Distribution, and Treatment

Key Takeaways Explain This Topic AI

Design demand is population × per capita consumption, scaled by peak factors for the maximum day and peak hour.

Distribution storage combines equalizing storage, fire reserve and emergency reserve.

Pump water power is γQH, and brake power is γQH divided by pump efficiency.

A settling basin removes particles whose settling velocity exceeds the overflow rate Q/A, independent of tank depth.

Geometric population growth projects P = P₀(1 + r)ⁿ, while arithmetic growth adds a constant number per year.

Last updated: October 2026

8.5 Water Supply: Demand, Storage, Pumping, Distribution, and Treatment

The 2022 HGE table of specifications gives Water Supply 8% of the subject, or 4 of its 50 items. That is as much as buoyancy and flotation, and more than hydrodynamics. The items are computational and draw directly on pipe flow (Section 8.3) and on pumps and the energy equation (Section 8.1).

Population Forecasting

  • Method Formula Use
  • Arithmetic P n = P 0 + n k a P_n = P_0 + n\,k_a P n ​ = P 0 ​ + n k a ​ Mature towns with steady growth

Geometric (uniform percentage) P n = P 0 ( 1 + r ) n P_n = P_0(1 + r)^n P n ​ = P 0 ​ ( 1 + r ) n Young, growing towns

Exponential (continuous) P n = P 0 e k n P_n = P_0 e^{kn} P n ​ = P 0 ​ e kn Equivalent to geometric growth with continuous compounding

Declining growth rate Growth slows as the population approaches a saturation value Large cities

Example. A town of 40,000 grew 3% per year. Projected to a 20-year design period: P = 40,000 ( 1.03 ) 20 = 72,244 P = 40{,}000(1.03)^{20} = 72{,}244 P = 40 , 000 ( 1.03 ) 20 = 72 , 244 . An arithmetic increase of 1,200 per year would give 40,000 + 20 ( 1,200 ) = 64,000 40{,}000 + 20(1{,}200) = 64{,}000 40 , 000 + 20 ( 1 , 200 ) = 64 , 000 .

Water Demand and Peaking Factors

Average day demand (ADD):

ADD = P × q (liters per capita per day) \text{ADD} = P \times q \quad \text{(liters per capita per day)} ADD = P × q (liters per capita per day)

Here q q q includes domestic use, commercial and institutional use, and an allowance for non-revenue water (leakage).

  • Demand condition Typical peaking factor Used for
  • Maximum day demand (MDD) about 1.2 to 1.5 × ADD Source, treatment plant and transmission main capacity
  • Peak hour demand (PHD) about 1.5 to 3.0 × ADD Distribution network sizing
  • Fire demand Fire flow for a set duration, added to MDD Distribution mains, hydrants, fire reserve

Smaller communities have higher peak factors, because their demand is less spread out over time.

Example. A population of 72,000 uses 150 L/capita/day.

ADD = 72,000 × 150 = 10.8 × 10 6 L/day = 10,800 m 3 / day = 0.125 m 3 / s = 72{,}000 \times 150 = 10.8 \times 10^6\text{ L/day} = 10{,}800\text{ m}^3/\text{day} = 0.125\text{ m}^3/\text{s} = 72 , 000 × 150 = 10.8 × 1 0 6 L/day = 10 , 800 m 3 / day = 0.125 m 3 / s .

With MDD = 1.3 × ADD, MDD = 0.1625 m 3 / s = 0.1625\text{ m}^3/\text{s} = 0.1625 m 3 / s .

With PHD = 2.0 × ADD, PHD = 0.250 m 3 / s = 0.250\text{ m}^3/\text{s} = 0.250 m 3 / s .

Storage

Elevated tanks and ground reservoirs hold three volumes:

Equalizing (operational) storage covers hourly demand above the steady supply rate. It is found from a mass diagram : plot cumulative supply and cumulative demand over a day. The required storage is the largest surplus plus the largest deficit, measured from the supply line. Rule-of-thumb values are often around 15% to 25% of MDD.

Fire reserve equals fire flow times fire duration.

Emergency reserve covers power or source outages.

Example. A pumping plant delivers a steady 500 m 3 / h 500\text{ m}^3/\text{h} 500 m 3 / h for 24 hours. Cumulative demand exceeds cumulative supply by at most 1,100 m 3 1{,}100\text{ m}^3 1 , 100 m 3 at 8 PM, and falls below it by at most 900 m 3 900\text{ m}^3 900 m 3 at 5 AM. Equalizing storage is 1,100 + 900 = 2,000 m 3 1{,}100 + 900 = 2{,}000\text{ m}^3 1 , 100 + 900 = 2 , 000 m 3 .

Pressure. An elevated tank's water surface sets the hydraulic grade line. Residual pressure at a service point is the HGL elevation minus ground elevation, less head losses. Distribution systems typically aim to keep enough residual pressure for upper-floor fixtures without excessive pressure that drives leakage.

Pumping

P water = γ Q H , P brake = γ Q H η p , P motor input = γ Q H η p η m P_{\text{water}} = \gamma Q H, \qquad P_{\text{brake}} = \frac{\gamma Q H}{\eta_p}, \qquad P_{\text{motor input}} = \frac{\gamma Q H}{\eta_p \eta_m} P water ​ = γ Q H , P brake ​ = η p ​ γ Q H ​ , P motor input ​ = η p ​ η m ​ γ Q H ​

Total dynamic head is H = ( static lift ) + ( friction losses ) + ( minor losses ) + ( velocity head at discharge, if free ) H = (\text{static lift}) + (\text{friction losses}) + (\text{minor losses}) + (\text{velocity head at discharge, if free}) H = ( static lift ) + ( friction losses ) + ( minor losses ) + ( velocity head at discharge, if free ) .

Example. A pump delivers 0.08 m 3 / s 0.08\text{ m}^3/\text{s} 0.08 m 3 / s from a well with its water level at elevation 12 m to a tank surface at elevation 52 m. Pipe losses total 6 m, and the pump efficiency is 0.75.

H = 40 + 6 = 46 m H = 40 + 6 = 46\text{ m} H = 40 + 6 = 46 m .

Brake power = 9.81 ( 0.08 ) ( 46 ) / 0.75 = 48.1 kW = 9.81(0.08)(46)/0.75 = 48.1\text{ kW} = 9.81 ( 0.08 ) ( 46 ) /0.75 = 48.1 kW .

Cavitation. The available net positive suction head must exceed the pump's required NPSH, so suction lifts are kept short.

Distribution Systems

Layouts:

Branching (tree) systems are simple, but they have dead ends with stagnant water and a single supply path.

Grid or loop systems give two-way flow, better pressure and reliability, and are analyzed by the Hardy Cross method (Section 8.3).

Pipe sizing. Choose a diameter so the friction slope keeps pressures acceptable and velocities moderate, roughly 0.6 to 2 m/s. With Hazen-Williams:

h f = 10.67 L Q 1.852 C 1.852 D 4.87 h_f = \frac{10.67\, L\, Q^{1.852}}{C^{1.852} D^{4.87}} h f ​ = C 1.852 D 4.87 10.67 L Q 1.852 ​

Example. A 1,500 m 1{,}500\text{ m} 1 , 500 m main carries the peak-hour flow of 0.25 m 3 / s 0.25\text{ m}^3/\text{s} 0.25 m 3 / s , and the allowable head loss is 12 m with C = 130 C = 130 C = 130 . Solving for D:

D 4.87 = 10.67 ( 1,500 ) ( 0.25 ) 1.852 130 1.852 ( 12 ) = 16,005 ( 0.07651 ) 8,186 ( 12 ) = 0.01247 D^{4.87} = \frac{10.67(1{,}500)(0.25)^{1.852}}{130^{1.852}(12)} = \frac{16{,}005(0.07651)}{8{,}186(12)} = 0.01247 D 4.87 = 13 0 1.852 ( 12 ) 10.67 ( 1 , 500 ) ( 0.25 ) 1.852 ​ = 8 , 186 ( 12 ) 16 , 005 ( 0.07651 ) ​ = 0.01247

So D = 0.01247 1 / 4.87 = 0.406 m D = 0.01247^{1/4.87} = 0.406\text{ m} D = 0.0124 7 1/4.87 = 0.406 m . Select the next standard size, 450 mm.

Treatment Hydraulics

Process Design relation

Plain sedimentation Overflow (surface loading) rate v o = Q / A surface v_o = Q/A_{\text{surface}} v o ​ = Q / A surface ​ . Particles with settling velocity v s ≥ v o v_s \ge v_o v s ​ ≥ v o ​ are fully removed, and smaller ones are removed in the ratio v s / v o v_s/v_o v s ​ / v o ​ . Detention time t = V / Q t = V/Q t = V / Q .

Stokes' law for discrete particles v s = g ( ρ s − ρ w ) d 2 18 μ v_s = \dfrac{g(\rho_s - \rho_w)d^2}{18\mu} v s ​ = 18 μ g ( ρ s ​ − ρ w ​ ) d 2 ​

Coagulation and flocculation Chemicals such as alum destabilize fine particles, and slow mixing builds flocs that settle

Filtration Rapid sand filters run at roughly 5 5 5 to 15 m/h 15\text{ m/h} 15 m/h and are cleaned by backwashing; slow sand filters run far slower and rely on a biological layer

Disinfection Chlorination; effectiveness depends on concentration × contact time (CT)

Drinking-water quality limits in the Philippines are set by the Department of Health's Philippine National Standards for Drinking Water.

Example. A rectangular settling tank treats 0.20 m 3 / s 0.20\text{ m}^3/\text{s} 0.20 m 3 / s at an overflow rate of 30 m 3 / m 2 / day 30\text{ m}^3/\text{m}^2/\text{day} 30 m 3 / m 2 / day .

Surface area: A = 0.20 ( 86,400 ) / 30 = 576 m 2 A = 0.20(86{,}400)/30 = 576\text{ m}^2 A = 0.20 ( 86 , 400 ) /30 = 576 m 2 .

With a depth of 3.5 m, detention time is 576 ( 3.5 ) / 0.20 = 10,080 s = 2.8 h 576(3.5)/0.20 = 10{,}080\text{ s} = 2.8\text{ h} 576 ( 3.5 ) /0.20 = 10 , 080 s = 2.8 h .