4.4 Route Surveying: Horizontal and Vertical Curves

PRC Civil Engineer Licensure Examination CELE

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: Examination Overview, RA 544 & Professional Practice

1.1 CELE Structure, Format, Scoring, and 2026 Subject Order 1.2 Republic Act No. 544: The Civil Engineering Law and Board Regulations 1.3 Civil Engineering Ethics, Contracts, and Professional Practice

2 Chapter 2: Engineering Mathematics, Numerical Methods & Physics

2.1 Advanced Algebra, Progressions & Word Problems 2.2 Trigonometry and Analytical Geometry 2.3 Differential and Integral Calculus 2.4 Differential Equations and Numerical Methods 2.5 Series, Hyperbolic Functions, Multivariable Calculus, and Laplace Transforms 2.6 Numerical Methods: Linear Systems, Interpolation, Curve Fitting, and ODE Solvers 2.7 Physics for Engineers: Kinematics, Newton's Laws, Work-Energy, and Momentum

3 Chapter 3: Engineering Data Analysis & Engineering Economy

3.1 Engineering Data Analysis and Statistical Applications 3.2 Parameter Estimation, Linear Regression, Correlation, and Queuing Models 3.3 Engineering Economy: Time Value of Money and Interest Formulas 3.4 Project Evaluation, Depreciation, and Benefit-Cost Analysis

4 Chapter 4: Surveying Fundamentals, Construction Layout & Route Surveying

4.1 Errors, Corrections, and Pacing/Taping 4.2 Leveling, Earthworks, and Mass Haul Diagrams 4.3 Traverse Computations, Balancing, and Area Determinations 4.4 Route Surveying: Horizontal and Vertical Curves

5 Chapter 5: Highway & Transportation Engineering

5.1 Highway Geometric Design and Sight Distances 5.2 Traffic Engineering, Flow Fundamentals, and Pavement Design 5.3 Highway Policy, Route Location, Drainage, and Earthwork Slopes 5.4 Transportation Planning, Network Analysis, and Intermodal Systems

6 Chapter 6: Construction Materials, Methods, Management & Safety

6.1 Materials for Construction: Concrete, Formwork, Masonry, Steel, and Wood Products 6.2 Construction Equipment, Formwork, and Construction Methods 6.3 Construction Occupational Safety and Health: RA 11058 and DOLE DO 13 6.4 Construction Project Management, CPM/PERT, and Resource Scheduling 6.5 Construction Principles: Design Requirements, Project Organization, Cost Control, and Value Engineering 6.6 Quantity Surveying, Unit Cost Analysis, and Project Cost Estimates 6.7 Construction Trades and Specialties: Plumbing, Plastics, Doors and Windows, Finishes, and Electrical

7 Chapter 7: Fluid Properties, Hydrostatics & Buoyancy

7.1 Fluid Properties, Units, and Pressure Measurement 7.2 Hydrostatic Pressure on Plane and Curved Surfaces 7.3 Buoyancy, Flotation, and Accelerated Fluid Masses

8 Chapter 8: Hydrodynamics, Pipe Flow, Open Channels & Water Supply

8.1 Fluid Dynamics: Continuity and Energy Equations 8.2 Flow Measurement: Orifices, Weirs, and Venturi Meters 8.3 Fluid Flow in Pipes, Friction Losses, and Pipe Networks 8.4 Open Channel Flow, Manning's Equation, and Hydraulic Jump 8.5 Water Supply: Demand, Storage, Pumping, Distribution, and Treatment

9 Chapter 9: Soil Properties, Seepage & Stresses in Soil Mass

9.1 Soil Composition, Weight-Volume Phase Relationships 9.2 Soil Classification Systems (USCS & AASHTO) and Atterberg Limits 9.3 Soil Permeability, Seepage, Flow Nets, and Effective Stress 9.4 Stresses in Soil Mass, Stress Distribution, and Immediate and Secondary Settlement

10 Chapter 10: Consolidation, Soil Strength, Earth Pressures & Foundations

10.1 Soil Compaction and Soil Compressibility/Consolidation 10.2 Shear Strength of Soils and Mohr-Coulomb Failure Criteria 10.3 Lateral Earth Pressures (Rankine & Coulomb) and Retaining Walls 10.4 Shallow and Deep Foundation Bearing Capacity and Slope Stability

11 Chapter 11: Engineering Mechanics & Statics

11.1 Force Systems, Resultants, and Equilibrium of Rigid Bodies 11.2 Centroids, Moments of Inertia, and Friction 11.3 Cables, Trusses, and Internal Forces in Members

12 Chapter 12: Strength of Materials

12.1 Axial Stress, Strain, and Deformation 12.2 Torsion, Flanged Bolt Couplings, and Thin-Walled Pressure Vessels 12.3 Beam Stresses: Flexural and Transverse Shear 12.4 Beam Deflections, Combined Stresses, and Mohr's Circle

13 Chapter 13: Structural Analysis & NSCP Load Criteria

13.1 Indeterminate Structures: Approximate and Classical Methods 13.2 Moment Distribution Method and Slope Deflection 13.3 Influence Lines for Determinate and Indeterminate Structures 13.4 NSCP Minimum Design Loads: Dead, Live, Wind, and Earthquake

14 Chapter 14: Reinforced Concrete Design (NSCP 2015 / USD)

14.1 Ultimate Strength Design (USD) Principles and Singly Reinforced Beams 14.2 Doubly Reinforced Beams and T-Beams 14.3 Shear and Diagonal Tension, Stirrup Design, and Development Length 14.4 Reinforced Concrete Columns and Isolated Footing Design

15 Chapter 15: Steel, Timber & Prestressed Design and Materials Testing

15.1 Structural Steel Tension Members and Connections 15.2 Structural Steel Compression Members and Beam Design 15.3 Timber Design Principles, Working Stress, and Sawn Lumber Beams 15.4 Prestressed Concrete Fundamentals and Prestress Losses 15.5 Construction Materials Testing and Concrete Mix Proportioning

4.4 Route Surveying: Horizontal and Vertical Curves

Key Takeaways Explain This Topic AI

A simple circular curve with radius R R R and intersection angle I I I has primary geometric parameters: Tangent T = R tan ⁡ ( I / 2 ) T = R \tan(I/2) T = R tan ( I /2 ) , External distance E = R ( sec ⁡ ( I / 2 ) − 1 ) E = R(\sec(I/2) - 1) E = R ( sec ( I /2 ) − 1 ) , Middle ordinate M = R ( 1 − cos ⁡ ( I / 2 ) ) M = R(1 - \cos(I/2)) M = R ( 1 − cos ( I /2 )) , Long chord C = 2 R sin ⁡ ( I / 2 ) C = 2R \sin(I/2) C = 2 R sin ( I /2 ) , and Length of curve L = 20 I D L = \frac{20 I}{D} L = D 20 I ​ under the metric arc standard.

Under the 20-meter arc definition used in Philippine practice, the degree of curve is related to radius by D = 1145.916 R D = \frac{1145.916}{R} D = R 1145.916 ​ ; stationing must strictly advance along the curved alignment: Sta PC = Sta PI − T \text{Sta PC} = \text{Sta PI} - T Sta PC = Sta PI − T and Sta PT = Sta PC + L \text{Sta PT} = \text{Sta PC} + L Sta PT = Sta PC + L .

Compound curves link two or more successive arcs curving in the same direction across a common tangent at the PCC, whereas reverse curves bend in opposite directions through a common PRC.

Symmetrical vertical parabolic curves maintain a constant rate of grade change r = g 2 − g 1 L r = \frac{g_2 - g_1}{L} r = L g 2 ​ − g 1 ​ ​ ; station elevations follow y = Elev PVC + g 1 x + r 2 x 2 y = \text{Elev PVC} + g_1 x + \frac{r}{2} x^2 y = Elev PVC + g 1 ​ x + 2 r ​ x 2 .

The highest point on a crest curve (or lowest point on a sag curve) occurs at a horizontal distance x 0 = − g 1 r = − g 1 L g 2 − g 1 = ∣ g 1 ∣ L ∣ g 1 ∣ + ∣ g 2 ∣ x_0 = -\frac{g_1}{r} = \frac{-g_1 L}{g_2 - g_1} = \frac{|g_1| L}{|g_1| + |g_2|} x 0 ​ = − r g 1 ​ ​ = g 2 ​ − g 1 ​ − g 1 ​ L ​ = ∣ g 1 ​ ∣ + ∣ g 2 ​ ∣ ∣ g 1 ​ ∣ L ​ from the PVC, provided the connecting tangent grades share opposite signs.

Last updated: October 2026

4.4 Route Surveying: Horizontal and Vertical Curves

Highway, railway, and canal routes consist of straight tangents joined by smooth geometric curves. Horizontal curves transition changes in direction on a horizontal plane, while vertical curves transition changes in longitudinal gradient on a vertical plane. Mastery of both curve geometries is vital for route design and the PRC CE Licensure Examination.

1. Simple Circular Horizontal Curves

A simple circular curve is a single circular arc connecting two straight tangents intersecting at a Point of Intersection (PI).

Primary Geometric Elements

Point of Intersection (PI or Vertex V): The point where the back tangent and forward tangent intersect.

Point of Curvature (PC): The point where the alignment transitions from the back tangent into the circular arc.

Point of Tangency (PT): The point where the circular arc ends and transitions into the forward tangent.

Intersection Angle ( I I I or Δ \Delta Δ ): The deflection angle between the tangents, identical to the central angle subtended by the arc.

Radius of Curvature ( R R R ): The radius of the circular arc.

Degree of Curve ( D D D ): The measure of curvature sharpness. In metric Philippine practice, the 20-meter Arc Definition defines D D D as the central angle subtended by a 20.00 -m 20.00\text{-m} 20.00 -m arc: D 20 = 360 ∘ 2 π R ⟹ D = 1145.916 R ( degrees ) \frac{D}{20} = \frac{360^\circ}{2 \pi R} \implies D = \frac{1145.916}{R} \quad (\text{degrees}) 20 D ​ = 2 π R 36 0 ∘ ​ ⟹ D = R 1145.916 ​ ( degrees ) R = 1145.916 D ( meters ) R = \frac{1145.916}{D} \quad (\text{meters}) R = D 1145.916 ​ ( meters ) (Note: Traditional 100-ft English practice uses D = 5729.58 / R D = 5729.58 / R D = 5729.58/ R .)

Mathematical Formulas for Simple Curves

Tangent Distance: T = R tan ⁡ ( I 2 ) \text{Tangent Distance: } T = R \tan\left( \frac{I}{2} \right) Tangent Distance: T = R tan ( 2 I ​ )

External Distance: E = R [ sec ⁡ ( I 2 ) − 1 ] = R [ 1 cos ⁡ ( I / 2 ) − 1 ] = T tan ⁡ ( I 4 ) \text{External Distance: } E = R \left[ \sec\left( \frac{I}{2} \right) - 1 \right] = R \left[ \frac{1}{\cos(I/2)} - 1 \right] = T \tan\left( \frac{I}{4} \right) External Distance: E = R [ sec ( 2 I ​ ) − 1 ] = R [ c o s ( I /2 ) 1 ​ − 1 ] = T tan ( 4 I ​ )

Middle Ordinate: M = R [ 1 − cos ⁡ ( I 2 ) ] = E cos ⁡ ( I 2 ) \text{Middle Ordinate: } M = R \left[ 1 - \cos\left( \frac{I}{2} \right) \right] = E \cos\left( \frac{I}{2} \right) Middle Ordinate: M = R [ 1 − cos ( 2 I ​ ) ] = E cos ( 2 I ​ )

Long Chord: C = 2 R sin ⁡ ( I 2 ) \text{Long Chord: } C = 2 R \sin\left( \frac{I}{2} \right) Long Chord: C = 2 R sin ( 2 I ​ )

Length of Curve: L = R ⋅ I radians = π R I ∘ 180 ∘ = 20 I D \text{Length of Curve: } L = R \cdot I_{\text{radians}} = \frac{\pi R I^\circ}{180^\circ} = \frac{20 I}{D} Length of Curve: L = R ⋅ I radians ​ = 18 0 ∘ π R I ∘ ​ = D 20 I ​

Stationing of Simple Curves

In route surveying, stationing measures actual ground travel distance along the centerline. Because the alignment travels along the arc rather than the tangents: Station PC = Station PI − T \text{Station PC} = \text{Station PI} - T Station PC = Station PI − T Station PT = Station PC + L \text{Station PT} = \text{Station PC} + L Station PT = Station PC + L

Caution

Classic CELE Board Trap: Never calculate Station PT \text{Station PT} Station PT as Station PI + T \text{Station PI} + T Station PI + T ! Because L < 2 T L < 2T L < 2 T , traveling around the arc is shorter than walking to the vertex and back ( 2 T − L 2T - L 2 T − L represents the tangent overrun or stationing equation discrepancy).

Curve Layout by Deflection Angles

To stake intermediate points at station interval d d d along the curve with an instrument set up at the PC: Deflection Angle δ = d 20 × ( D 2 ) \text{Deflection Angle } \delta = \frac{d}{20} \times \left( \frac{D}{2} \right) Deflection Angle δ = 20 d ​ × ( 2 D ​ ) Chord Length c = 2 R sin ⁡ δ \text{Chord Length } c = 2 R \sin \delta Chord Length c = 2 R sin δ

  • 2. Compound and Reverse Horizontal Curves
  • 1. Compound Curves

A compound curve consists of two or more consecutive circular arcs of different radii curving in the same direction, joining at a common Point of Compound Curvature (PCC) .

The total intersection angle is the sum of component central angles: I = I 1 + I 2 I = I_1 + I_2 I = I 1 ​ + I 2 ​ .

At the PCC, the curves share a single common tangent ( V 1 V 2 V_1 V_2 V 1 ​ V 2 ​ ): T common = t 1 + t 2 = R 1 tan ⁡ ( I 1 2 ) + R 2 tan ⁡ ( I 2 2 ) T_{\text{common}} = t_1 + t_2 = R_1 \tan\left( \frac{I_1}{2} \right) + R_2 \tan\left( \frac{I_2}{2} \right) T common ​ = t 1 ​ + t 2 ​ = R 1 ​ tan ( 2 I 1 ​ ​ ) + R 2 ​ tan ( 2 I 2 ​ ​ )

In the vertex triangle formed by the PI and the two tangent points V 1 V_1 V 1 ​ and V 2 V_2 V 2 ​ , the Law of Sines is used to solve for overall tangents T 1 T_1 T 1 ​ (back tangent) and T 2 T_2 T 2 ​ (forward tangent): V 1 PI sin ⁡ I 2 = V 2 PI sin ⁡ I 1 = T common sin ⁡ ( 180 ∘ − I ) \frac{V_1 \text{PI}}{\sin I_2} = \frac{V_2 \text{PI}}{\sin I_1} = \frac{T_{\text{common}}}{\sin(180^\circ - I)} s i n I 2 ​ V 1 ​ PI ​ = s i n I 1 ​ V 2 ​ PI ​ = s i n ( 18 0 ∘ − I ) T common ​ ​ T 1 = t 1 + V 1 PI , T 2 = t 2 + V 2 PI T_1 = t_1 + V_1 \text{PI}, \quad T_2 = t_2 + V_2 \text{PI} T 1 ​ = t 1 ​ + V 1 ​ PI , T 2 ​ = t 2 ​ + V 2 ​ PI

2. Reverse Curves

A reverse curve consists of two consecutive circular arcs turning in opposite directions, joining at a Point of Reverse Curvature (PRC) . While avoided in high-speed highway design due to instantaneous reversal of superelevation, reverse curves are widely applied in railway yards, mountainous access roads, and canal alignments.

Reverse Curve Connecting Parallel Tangents

When two parallel tangents separated by perpendicular offset distance p p p are connected by a reverse curve: p = R 1 ( 1 − cos ⁡ I 1 ) + R 2 ( 1 − cos ⁡ I 2 ) p = R_1 (1 - \cos I_1) + R_2 (1 - \cos I_2) p = R 1 ​ ( 1 − cos I 1 ​ ) + R 2 ​ ( 1 − cos I 2 ​ ) If both arcs have equal radii ( R 1 = R 2 = R R_1 = R_2 = R R 1 ​ = R 2 ​ = R ) and equal central angles ( I 1 = I 2 = I I_1 = I_2 = I I 1 ​ = I 2 ​ = I ): p = 2 R ( 1 − cos ⁡ I ) p = 2 R (1 - \cos I) p = 2 R ( 1 − cos I ) R = p 2 ( 1 − cos ⁡ I ) R = \frac{p}{2 (1 - \cos I)} R = 2 ( 1 − c o s I ) p ​ Total Length L total = 2 L = 2 ( π R I ∘ 180 ∘ ) \text{Total Length } L_{\text{total}} = 2 L = 2 \left( \frac{\pi R I^\circ}{180^\circ} \right) Total Length L total ​ = 2 L = 2 ( 18 0 ∘ π R I ∘ ​ )

3. Vertical Parabolic Curves

Vertical curves provide gradual transitions between intersecting roadway gradients ( g 1 g_1 g 1 ​ and g 2 g_2 g 2 ​ , expressed as percentages or decimals). The parabolic profile provides a constant rate of change of grade, guaranteeing uniform vertical acceleration for passenger comfort and clear sight distances.

Symmetrical Vertical Curves

A symmetrical vertical curve has equal horizontal tangent lengths on either side of the Point of Vertical Intersection (PVI), meaning the curve extends L / 2 L/2 L /2 before and L / 2 L/2 L /2 after the PVI:

PVC (Point of Vertical Curvature): Station PVC = Station PVI − L 2 \text{Station PVC} = \text{Station PVI} - \frac{L}{2} Station PVC = Station PVI − 2 L ​

PVT (Point of Vertical Tangency): Station PVT = Station PVI + L 2 = Station PVC + L \text{Station PVT} = \text{Station PVI} + \frac{L}{2} = \text{Station PVC} + L Station PVT = Station PVI + 2 L ​ = Station PVC + L

Rate of Change of Grade ( r r r ): r = g 2 − g 1 L r = \frac{g_2 - g_1}{L} r = L g 2 ​ − g 1 ​ ​ (Where g 1 , g 2 g_1, g_2 g 1 ​ , g 2 ​ are algebraic tangent grades; e.g., + 4 % = + 0.04 +4\% = +0.04 + 4% = + 0.04 , − 2 % = − 0.02 -2\% = -0.02 − 2% = − 0.02 .)

General Parabolic Elevation Equation

The elevation y y y of any station located at horizontal distance x x x from the PVC ( 0 ≤ x ≤ L 0 \le x \le L 0 ≤ x ≤ L ) is: y ( x ) = Elev PVC + g 1 x + r 2 x 2 = Elev PVC + g 1 x + ( g 2 − g 1 2 L ) x 2 y(x) = \text{Elev}_{\text{PVC}} + g_1 x + \frac{r}{2} x^2 = \text{Elev}_{\text{PVC}} + g_1 x + \left( \frac{g_2 - g_1}{2 L} \right) x^2 y ( x ) = Elev PVC ​ + g 1 ​ x + 2 r ​ x 2 = Elev PVC ​ + g 1 ​ x + ( 2 L g 2 ​ − g 1 ​ ​ ) x 2

Tangent Offset Method

The vertical offset y ′ y' y ′ from the tangent line to the curve at distance x x x from PVC is: y ′ ( x ) = a x 2 = ( g 2 − g 1 2 L ) x 2 y'(x) = a x^2 = \left( \frac{g_2 - g_1}{2 L} \right) x^2 y ′ ( x ) = a x 2 = ( 2 L g 2 ​ − g 1 ​ ​ ) x 2 At the PVI ( x = L / 2 x = L/2 x = L /2 ), the external offset is: E v = ( g 2 − g 1 ) L 8 = A L 800 ( with A = ∣ g 2 − g 1 ∣ in % E_v = \frac{(g_2 - g_1) L}{8} = \frac{A L}{800} \quad (\text{with } A = |g_2 - g_1| \text{ in } \% E v ​ = 8 ( g 2 ​ − g 1 ​ ) L ​ = 800 A L ​ ( with A = ∣ g 2 ​ − g 1 ​ ∣ in %

Location of the Summit (Crest) or Invert (Sag)

The highest point on a crest curve (or lowest point on a sag curve) occurs where the instantaneous slope is zero ( d y d x = 0 \frac{dy}{dx} = 0 d x d y ​ = 0 ): d y d x = g 1 + r x = 0 ⟹ x 0 = − g 1 r = − g 1 L g 2 − g 1 \frac{dy}{dx} = g_1 + r x = 0 \implies x_0 = -\frac{g_1}{r} = \frac{-g_1 L}{g_2 - g_1} d x d y ​ = g 1 ​ + r x = 0 ⟹ x 0 ​ = − r g 1 ​ ​ = g 2 ​ − g 1 ​ − g 1 ​ L ​ When grades have opposite signs, this simplifies using absolute magnitudes: x 0 = ∣ g 1 ∣ L ∣ g 1 ∣ + ∣ g 2 ∣ x_0 = \frac{|g_1| L}{|g_1| + |g_2|} x 0 ​ = ∣ g 1 ​ ∣ + ∣ g 2 ​ ∣ ∣ g 1 ​ ∣ L ​ Station of High/Low Point = Station PVC + x 0 \text{Station of High/Low Point} = \text{Station PVC} + x_0 Station of High/Low Point = Station PVC + x 0 ​ Elevation of High/Low Point = Elev PVC + g 1 x 0 + r 2 x 0 2 \text{Elevation of High/Low Point} = \text{Elev}_{\text{PVC}} + g_1 x_0 + \frac{r}{2} x_0^2 Elevation of High/Low Point = Elev PVC ​ + g 1 ​ x 0 ​ + 2 r ​ x 0 2 ​

Note

If g 1 g_1 g 1 ​ and g 2 g_2 g 2 ​ share the same sign (e.g., + 4 % +4\% + 4% transitioning to + 1 % +1\% + 1% ), the curve has no internal turning point; the lowest point is at the PVC and the highest point is at the PVT.

  • 4. Comprehensive Worked Examples
  • Worked Example 1: Simple Horizontal Circular Curve

Problem: A proposed provincial bypass alignment has an intersection angle I = 42 ∘ 00 ′ I = 42^\circ 00' I = 4 2 ∘ 0 0 ′ and a degree of curve D = 5 ∘ 00 ′ D = 5^\circ 00' D = 5 ∘ 0 0 ′ based on the metric 20-meter arc definition ( D = 1145.916 / R D = 1145.916 / R D = 1145.916/ R ). The PI is located at Station 14 + 280.00 14 + 280.00 14 + 280.00 with an elevation of 85.40 m 85.40\text{ m} 85.40 m . Calculate:

Radius R R R , Tangent distance T T T , and Length of curve L L L .

External distance E E E and Middle ordinate M M M .

Centerline stationing of the PC and PT.

Solution:

Radius, Tangent, and Curve Length: R = 1145.916 D = 1145.916 5.00 = 229.183 m R = \frac{1145.916}{D} = \frac{1145.916}{5.00} = 229.183\text{ m} R = D 1145.916 ​ = 5.00 1145.916 ​ = 229.183 m T = R tan ⁡ ( I 2 ) = 229.183 × tan ⁡ ( 21 ∘ ) = 229.183 × 0.383864 = 87.975 m T = R \tan\left( \frac{I}{2} \right) = 229.183 \times \tan(21^\circ) = 229.183 \times 0.383864 = 87.975\text{ m} T = R tan ( 2 I ​ ) = 229.183 × tan ( 2 1 ∘ ) = 229.183 × 0.383864 = 87.975 m L = 20 I D = 20 × 42.00 5.00 = 168.000 m L = \frac{20 I}{D} = \frac{20 \times 42.00}{5.00} = 168.000\text{ m} L = D 20 I ​ = 5.00 20 × 42.00 ​ = 168.000 m (Verification: R ⋅ I rad = 229.183 × 42 π 180 = 229.183 × 0.733038 = 168.000 m R \cdot I_{\text{rad}} = 229.183 \times \frac{42 \pi}{180} = 229.183 \times 0.733038 = 168.000\text{ m} R ⋅ I rad ​ = 229.183 × 180 42 π ​ = 229.183 × 0.733038 = 168.000 m )

External Distance and Middle Ordinate: E = R [ 1 cos ⁡ ( 21 ∘ ) − 1 ] = 229.183 × [ 1 0.933580 − 1 ] = 229.183 × 0.071145 = 16.305 m E = R \left[ \frac{1}{\cos(21^\circ)} - 1 \right] = 229.183 \times \left[ \frac{1}{0.933580} - 1 \right] = 229.183 \times 0.071145 = 16.305\text{ m} E = R [ c o s ( 2 1 ∘ ) 1 ​ − 1 ] = 229.183 × [ 0.933580 1 ​ − 1 ] = 229.183 × 0.071145 = 16.305 m M = R [ 1 − cos ⁡ ( 21 ∘ ) ] = 229.183 × ( 1 − 0.933580 ) = 229.183 × 0.066420 = 15.222 m M = R [1 - \cos(21^\circ)] = 229.183 \times (1 - 0.933580) = 229.183 \times 0.066420 = 15.222\text{ m} M = R [ 1 − cos ( 2 1 ∘ )] = 229.183 × ( 1 − 0.933580 ) = 229.183 × 0.066420 = 15.222 m

Stationing: Station PC = Station PI − T = ( 14 + 280.00 ) − 87.98 = 14 + 192.02 \text{Station PC} = \text{Station PI} - T = (14 + 280.00) - 87.98 = 14 + 192.02 Station PC = Station PI − T = ( 14 + 280.00 ) − 87.98 = 14 + 192.02 Station PT = Station PC + L = ( 14 + 192.02 ) + 168.00 = 14 + 360.02 \text{Station PT} = \text{Station PC} + L = (14 + 192.02) + 168.00 = 14 + 360.02 Station PT = Station PC + L = ( 14 + 192.02 ) + 168.00 = 14 + 360.02

Worked Example 2: Symmetrical Vertical Crest Curve Summit

Problem: A vertical crest parabolic curve connects an ascending grade g 1 = + 4.0 % g_1 = +4.0\% g 1 ​ = + 4.0% with a descending grade g 2 = − 3.0 % g_2 = -3.0\% g 2 ​ = − 3.0% . The horizontal length of the curve is L = 280.00 m L = 280.00\text{ m} L = 280.00 m (14 full 20-m stations). The PVI is situated at Station 6 + 450.00 6 + 450.00 6 + 450.00 at elevation 128.500 m 128.500\text{ m} 128.500 m . Determine:

Stationing and elevations of the PVC and PVT.

The location (stationing) and elevation of the highest point (summit) on the curve.

The elevation of Station 6 + 400.00 6 + 400.00 6 + 400.00 on the curve.

Solution:

PVC and PVT Elements: L 2 = 280.00 2 = 140.00 m \frac{L}{2} = \frac{280.00}{2} = 140.00\text{ m} 2 L ​ = 2 280.00 ​ = 140.00 m Station PVC = ( 6 + 450.00 ) − 140.00 = 6 + 310.00 \text{Station PVC} = (6 + 450.00) - 140.00 = 6 + 310.00 Station PVC = ( 6 + 450.00 ) − 140.00 = 6 + 310.00 Station PVT = ( 6 + 450.00 ) + 140.00 = 6 + 590.00 \text{Station PVT} = (6 + 450.00) + 140.00 = 6 + 590.00 Station PVT = ( 6 + 450.00 ) + 140.00 = 6 + 590.00 Elev PVC = Elev PVI − g 1 ( L 2 ) = 128.500 − ( 0.04 ) ( 140.00 ) = 128.500 − 5.600 = 122.900 m \text{Elev PVC} = \text{Elev PVI} - g_1 \left( \frac{L}{2} \right) = 128.500 - (0.04)(140.00) = 128.500 - 5.600 = 122.900\text{ m} Elev PVC = Elev PVI − g 1 ​ ( 2 L ​ ) = 128.500 − ( 0.04 ) ( 140.00 ) = 128.500 − 5.600 = 122.900 m Elev PVT = Elev PVI + g 2 ( L 2 ) = 128.500 + ( − 0.03 ) ( 140.00 ) = 128.500 − 4.200 = 124.300 m \text{Elev PVT} = \text{Elev PVI} + g_2 \left( \frac{L}{2} \right) = 128.500 + (-0.03)(140.00) = 128.500 - 4.200 = 124.300\text{ m} Elev PVT = Elev PVI + g 2 ​ ( 2 L ​ ) = 128.500 + ( − 0.03 ) ( 140.00 ) = 128.500 − 4.200 = 124.300 m

Summit Location and Elevation: r = g 2 − g 1 L = − 0.03 − ( + 0.04 ) 280.00 = − 0.07 280.00 = − 0.00025 m − 1 r = \frac{g_2 - g_1}{L} = \frac{-0.03 - (+0.04)}{280.00} = \frac{-0.07}{280.00} = -0.00025\text{ m}^{-1} r = L g 2 ​ − g 1 ​ ​ = 280.00 − 0.03 − ( + 0.04 ) ​ = 280.00 − 0.07 ​ = − 0.00025 m − 1 x 0 = ∣ g 1 ∣ L ∣ g 1 ∣ + ∣ g 2 ∣ = 4.0 × 280.00 4.0 + 3.0 = 1120 7.0 = 160.00 m from PVC x_0 = \frac{|g_1| L}{|g_1| + |g_2|} = \frac{4.0 \times 280.00}{4.0 + 3.0} = \frac{1120}{7.0} = 160.00\text{ m from PVC} x 0 ​ = ∣ g 1 ​ ∣ + ∣ g 2 ​ ∣ ∣ g 1 ​ ∣ L ​ = 4.0 + 3.0 4.0 × 280.00 ​ = 7.0 1120 ​ = 160.00 m from PVC Station Summit = ( 6 + 310.00 ) + 160.00 = 6 + 470.00 \text{Station Summit} = (6 + 310.00) + 160.00 = 6 + 470.00 Station Summit = ( 6 + 310.00 ) + 160.00 = 6 + 470.00 Elev Summit = Elev PVC + g 1 x 0 + r 2 x 0 2 \text{Elev Summit} = \text{Elev PVC} + g_1 x_0 + \frac{r}{2} x_0^2 Elev Summit = Elev PVC + g 1 ​ x 0 ​ + 2 r ​ x 0 2 ​ Elev Summit = 122.900 + ( 0.04 ) ( 160.00 ) + − 0.00025 2 ( 160.00 ) 2 \text{Elev Summit} = 122.900 + (0.04)(160.00) + \frac{-0.00025}{2} (160.00)^2 Elev Summit = 122.900 + ( 0.04 ) ( 160.00 ) + 2 − 0.00025 ​ ( 160.00 ) 2 Elev Summit = 122.900 + 6.400 − 0.000125 × 25 , 600 = 122.900 + 6.400 − 3.200 = 126.100 m \text{Elev Summit} = 122.900 + 6.400 - 0.000125 \times 25,600 = 122.900 + 6.400 - 3.200 = 126.100\text{ m} Elev Summit = 122.900 + 6.400 − 0.000125 × 25 , 600 = 122.900 + 6.400 − 3.200 = 126.100 m

Elevation of Station 6+400.00: Distance from PVC: x = ( 6 + 400.00 ) − ( 6 + 310.00 ) = 90.00 m x = (6 + 400.00) - (6 + 310.00) = 90.00\text{ m} x = ( 6 + 400.00 ) − ( 6 + 310.00 ) = 90.00 m . y ( 90 ) = 122.900 + ( 0.04 ) ( 90.00 ) + − 0.00025 2 ( 90.00 ) 2 y(90) = 122.900 + (0.04)(90.00) + \frac{-0.00025}{2} (90.00)^2 y ( 90 ) = 122.900 + ( 0.04 ) ( 90.00 ) + 2 − 0.00025 ​ ( 90.00 ) 2 y ( 90 ) = 122.900 + 3.600 − 0.000125 × 8 , 100 = 122.900 + 3.600 − 1.0125 = 125.488 m y(90) = 122.900 + 3.600 - 0.000125 \times 8,100 = 122.900 + 3.600 - 1.0125 = 125.488\text{ m} y ( 90 ) = 122.900 + 3.600 − 0.000125 × 8 , 100 = 122.900 + 3.600 − 1.0125 = 125.488 m

5. Construction Layout and Survey Control

The table of specifications asks candidates to "explain layout techniques and field observations" and to "develop sound construction control methodologies." Layout means setting out the design on the ground. Control means keeping the work within tolerance as it rises.

Horizontal and vertical control

Control points. A network of fixed points with known coordinates and elevations is established and protected beyond the work area. Benchmarks are placed where traffic and excavation will not disturb them.

Total station stakeout. The instrument occupies a control point, backsights another, and turns computed angles and distances to each design point. Stakeout lists are prepared from design coordinates.

GNSS (RTK) stakeout. Real-time kinematic receivers give centimeter-level positions in open areas. They are less reliable under trees or beside tall buildings.

Setting out a building

Stake the main corners from the control network, then check the diagonals . A rectangle is square when both diagonals are equal.

Erect batter boards (offset boards) outside the excavation limits. Mark grid lines on them with nails, and stretch strings between nails to recover lines after digging.

Transfer elevations with a level to a datum mark on each batter board.

On upper floors, transfer grid lines vertically with a plumb laser or by total station from offset lines, rather than by measuring up from the floor below.

3-4-5 check. To square a corner with a tape, measure 3 m along one line and 4 m along the other. The hypotenuse should read 5 m. For larger corners use multiples, such as 6-8-10 or 9-12-15.

Highway and earthwork staking

Slope stakes mark where cut or fill slopes meet natural ground. They are marked with the cut or fill height and the offset from centerline.

Grade stakes and blue tops give finished subgrade elevations at stations and offsets.

Reference stakes are offset from the centerline so the line can be recovered after clearing.

Construction control and tolerances

As-built checks. After each lift or pour, survey the actual positions and elevations and compare them with the design. Approve the next stage only when the work is within the specified tolerances.

Settlement and deformation monitoring. Repeated leveling of settlement plates, survey pins on structures, and inclinometers near deep excavations detects movement early.

Redundancy. Close every level loop on a benchmark and every traverse on a known point. A layout that cannot be checked is not controlled.

6. Board Exam Traps & Practical Review Tips

Arc vs. Chord Definition: In Philippine CELE problems, always assume the 20-meter Arc Definition ( D = 1145.916 / R D = 1145.916 / R D = 1145.916/ R ) unless chord definition is explicitly specified. For chord definition, R = 10 sin ⁡ ( D / 2 ) R = \frac{10}{\sin(D/2)} R = s i n ( D /2 ) 10 ​ .

Station PT Trap: Never compute Sta PT = Sta PI + T \text{Sta PT} = \text{Sta PI} + T Sta PT = Sta PI + T . Always add curve length L L L to the PC station: Sta PT = Sta PC + L \text{Sta PT} = \text{Sta PC} + L Sta PT = Sta PC + L .

Sign of Grades: Pay rigorous attention to signs in vertical curve formulas. An ascending grade is positive ( + + + ), and a descending grade is negative ( − - − ). In the rate of change formula r = g 2 − g 1 L r = \frac{g_2 - g_1}{L} r = L g 2 ​ − g 1 ​ ​ , a crest curve produces a negative r r r , while a sag curve produces a positive r r r .

Summit/Invert Boundary: The computed high or low point distance x 0 x_0 x 0 ​ must fall within the physical curve limits ( 0 ≤ x 0 ≤ L 0 \le x_0 \le L 0 ≤ x 0 ​ ≤ L ). If x 0 < 0 x_0 < 0 x 0 ​ < 0 or x 0 > L x_0 > L x 0 ​ > L , the curve does not turn, and the maximum elevation occurs at one of the tangent terminals.

Loading diagram... Geometry of Simple Circular Horizontal Curve and Vertical Parabolic Curve