9.2 Engineering Management & Ethics

PRC Registered Electrical Engineer REE

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: Overview, RA 7920 & Electrical Engineering Ethics

1.1 PRC Board of Electrical Engineering & REE Examination Overview 1.2 Republic Act No. 7920 (New Electrical Engineering Law) & License Classes 1.3 Code of Ethics & Professional Practice for Electrical Engineers

2 Chapter 2: Math — Algebra, Trig & Geometry

2.1 Algebraic Equations, Polynomials & Complex Numbers 2.2 Trigonometry — Identities, Triangles & Spherical Trig 2.3 Analytic & Solid Geometry

3 Chapter 3: Engineering Mathematics — Calculus & Differential Equations

3.1 Differential Calculus, Limits, Derivatives & Applications 3.2 Integral Calculus, Integration Techniques & Area/Volume Applications 3.3 Ordinary Differential Equations & Initial-Value Problems

4 Chapter 4: Engineering Mathematics — Advanced Math & Transform Methods

4.1 Laplace Transforms, Inverse Transforms & Circuit Applications 4.2 Fourier Series, Fourier Transforms & Frequency-Domain Analysis 4.3 Vector Analysis, Linear Algebra, Matrices & Complex Analysis

5 Chapter 5: Engineering Mathematics — Probability, Statistics & Engineering Data Analysis

5.1 Probability Theory, Counting Techniques & Bayes' Theorem 5.2 Engineering Data Analysis I — Descriptive Statistics & Probability Distributions 5.3 Engineering Data Analysis II — Confidence Intervals, Hypothesis Testing & Regression

6 Chapter 6: Engineering Mathematics — Numerical Methods & Analysis

6.1 Numerical Root-Finding & Solution of Linear Systems 6.2 Interpolation, Numerical Integration & Numerical Solution of ODEs

7 Chapter 7: ESAS — Physics, Chemistry & Computer Fundamentals

7.1 Physics for Engineers 7.2 General Chemistry & Materials Science 7.3 Computer Fundamentals, Programming & Data Logic 7.4 Logic Circuits, Switching Theory & Microprocessor Systems

8 Chapter 8: ESAS — Mechanics & Thermal-Fluid Engineering

8.1 Engineering Mechanics — Statics & Dynamics 8.2 Strength of Materials & Mechanics of Deformable Bodies 8.3 Thermal-Fluid Engineering — Thermodynamics & Fluid Mechanics

9 Chapter 9: ESAS — Engineering Economics, Management & Contracts

9.1 Engineering Economics & Depreciation 9.2 Engineering Management & Ethics 9.3 Philippine Electrical Engineering Law, Code & Contracts 9.4 Technopreneurship 101 & Management of Engineering Projects

10 Chapter 10: PEC 1 — Safety, Sizing & Protection

10.1 PEC Fundamentals, Safety Standards & Grounding/Bonding 10.2 Conductor Sizing, Ampacity Adjustment & Voltage Drop 10.3 Overcurrent Protection, Branch Circuit & Feeder Sizing 10.4 Basic Occupational Safety & Health (BOSH) and Electrical Safety Standards

11 Chapter 11: PEC 1 & 2 — Equipment & Utility Systems

11.1 PEC Equipment Installation & Wiring Methods 11.2 Utility Systems, Transformers & Switchgear 11.3 Special Occupancies & Hazardous Locations

12 Chapter 12: Electrical Professional — DC & AC Circuit Fundamentals

12.1 DC Circuit Analysis & Network Theorems 12.2 Single-Phase AC Circuits & Phasor Analysis 12.3 Balanced & Unbalanced Three-Phase AC Circuits

13 Chapter 13: Electrical Professional — EM Fields & Transients

13.1 Electrostatics, Magnetostatics & Maxwell's Equations 13.2 Electromagnetic Waves & Transmission Line Fields 13.3 First-Order & Second-Order Circuit Transients

14 Chapter 14: Electrical Professional — Electronics, Industrial Electronics & Communications

14.1 Electronics 1 & 2 — Semiconductor Devices & Analog Circuits 14.2 Electrical Apparatus & Devices — Industrial Electronics & Power Converters 14.3 Fundamentals of Electronic Communications

15 Chapter 15: Electrical Professional — Transformers & DC Machines

15.1 Single-Phase & Three-Phase Transformers 15.2 Transformer Connections & Special Transformers 15.3 DC Generators & DC Motors

16 Chapter 16: Electrical Professional — AC Synchronous & Induction Machinery

16.1 Synchronous Generators (Alternators) 16.2 Synchronous Motors & Special AC Machines 16.3 Three-Phase & Single-Phase Induction Motors

17 Chapter 17: Electrical Professional — Power Plants & Energy Conversion

17.1 Hydroelectric, Thermal & Combined Cycle Power Plants 17.2 Renewable Energy Systems & Geothermal Power Plants 17.3 Power Plant Economics, Load Curves & Energy Conversion

18 Chapter 18: Electrical Professional — Transmission & Distribution

18.1 Transmission Line Parameters & Performance Models 18.2 Mechanical Overhead Line Design, Underground Cables & Insulators 18.3 Distribution Systems, Substation Layouts & Power Flow Control

19 Chapter 19: Electrical Professional — Power System Analysis

19.1 The Per-Unit System, Base Conversion & Impedance Diagrams 19.2 Symmetrical Components & Unbalanced Fault Analysis 19.3 Load Flow, Economic Dispatch & Power System Stability

20 Chapter 20: Electrical Professional — Protection, Control, Instrumentation & Illumination

20.1 Power System Protection & Protective Relaying 20.2 Industrial Motor Control, Logic Circuits & PLC Automation 20.3 Electrical Instrumentation, Transducers & Measurement Systems 20.4 Illumination Engineering, Lighting Design & Photometrics 20.5 Feedback Control Systems & Research Methods

9.2 Engineering Management & Ethics

Key Takeaways Explain This Topic AI

Engineering management integrates planning, organizing, staffing, leading, and controlling (POLC) to achieve project and organizational goals efficiently.

Project scheduling via CPM and PERT identifies the critical path (zero total float) and calculates expected task duration t e = a + 4 m + b 6 t_e = \frac{a + 4m + b}{6} t e ​ = 6 a + 4 m + b ​ with variance σ 2 = ( b − a 6 ) 2 \sigma^2 = \left(\frac{b - a}{6}\right)^2 σ 2 = ( 6 b − a ​ ) 2 .

Total float ( T F = L S − E S = L F − E F TF = LS - ES = LF - EF TF = L S − ES = L F − EF ) determines activity scheduling flexibility without delaying total project completion.

Economic Order Quantity ( E O Q = 2 D S H EOQ = \sqrt{\frac{2 D S}{H}} EOQ = H 2 D S ​ ​ ) balances inventory ordering costs against annual holding costs to minimize total inventory expense.

The Board of Electrical Engineering Code of Ethics mandates that public safety, health, and welfare remain the paramount consideration in all engineering decisions.

Last updated: August 2026

9.2 Engineering Management & Ethics

Engineering Management combines technical expertise with administrative control to organize human resources, capital, equipment, and materials effectively. For the REE Licensure Examination, candidates must understand managerial functions, decision-making models, network project management (CPM/PERT), inventory optimization, and the mandatory Code of Ethics for Electrical Engineers in the Philippines.

1. Management Functions & Organizational Structures

Management is defined as the process of achieving organizational goals through the efficient deployment of resources.

The Five Core Functions of Management (POLC)

Planning: Establishing organizational objectives, strategies, and operational plans. Includes forecasting, goal setting, and budgeting.

Organizing: Structuring tasks, assigning authority, and allocating resources. Designing organizational charts and defining lines of responsibility.

Staffing: Recruiting, selecting, training, evaluating, and compensating technical personnel and engineering staff.

Leading / Directing: Influencing, motivating, communicating with, and guiding team members toward goal accomplishment.

Controlling: Measuring actual operational performance against planned standards, identifying variances, and executing corrective actions.

Common Organizational Structures

Structure Type Organizational Characteristics Primary Advantage Primary Disadvantage

Functional Grouped by technical specialization (e.g., Design, Construction, Testing) High technical specialization and skill depth Communication silos across functional departments

Line and Staff Direct scalar chain of command supplemented by staff advisory specialists Clear lines of authority and specialized advice Potential conflict between line managers and staff advisors

Matrix Dual reporting structure (Functional Manager + Project Manager) Efficient resource sharing and flexible project deployment Dual-boss confusion and potential authority conflicts

Projectized Dedicated project teams grouped under autonomous Project Managers High project focus and fast decision-making Resource duplication and team isolation between projects

Decision-Making Under Risk and Uncertainty

When evaluating decisions under probabilistic risk:

Expected Monetary Value (EMV): EMV = ∑ i = 1 n P ( S i ) ⋅ V ( S i ) \text{EMV} = \sum_{i=1}^n P(S_i) \cdot V(S_i) EMV = i = 1 ∑ n ​ P ( S i ​ ) ⋅ V ( S i ​ ) where P ( S i ) P(S_i) P ( S i ​ ) is probability of state of nature i i i , and V ( S i ) V(S_i) V ( S i ​ ) is payout value.

2. Project Management & Network Scheduling (CPM / PERT)

Complex electrical engineering projects (such as substation construction or power plant overhauls) rely on network analysis techniques.

Critical Path Method (CPM)

CPM assumes deterministic activity durations to calculate project completion time and schedule slack.

Early Start ( E S ES ES ): Earliest time an activity can begin: E S = max ⁡ ( EF of immediate predecessors ) ES = \max(\text{EF of immediate predecessors}) ES = max ( EF of immediate predecessors ) .

Early Finish ( E F EF EF ): E F = E S + Duration EF = ES + \text{Duration} EF = ES + Duration .

Late Finish ( L F LF L F ): Latest time an activity can finish without delaying project completion: L F = min ⁡ ( LS of immediate successors ) LF = \min(\text{LS of immediate successors}) L F = min ( LS of immediate successors ) .

Late Start ( L S LS L S ): L S = L F − Duration LS = LF - \text{Duration} L S = L F − Duration .

Slack / Float Definitions

Total Float ( T F TF TF ): Time an activity can be delayed without delaying project completion date: T F = L S − E S = L F − E F TF = LS - ES = LF - EF TF = L S − ES = L F − EF

Free Float ( F F FF FF ): Time an activity can be delayed without delaying the early start of any immediate successor: F F = min ⁡ ( E S successor ) − E F FF = \min(ES_{\text{successor}}) - EF FF = min ( E S successor ​ ) − EF

Critical Path: The sequence of dependent activities with zero total float ( T F = 0 TF = 0 TF = 0 ). It dictates the minimum project duration.

Program Evaluation and Review Technique (PERT)

PERT accounts for probabilistic duration uncertainty using three time estimates for each activity:

  • a a a = Optimistic time
  • m m m = Most likely time

b b b = Pessimistic time Expected Activity Duration ( t e ) = a + 4 m + b 6 \text{Expected Activity Duration } (t_e) = \frac{a + 4m + b}{6} Expected Activity Duration ( t e ​ ) = 6 a + 4 m + b ​ Activity Variance ( σ 2 ) = ( b − a 6 ) 2 \text{Activity Variance } (\sigma^2) = \left( \frac{b - a}{6} \right)^2 Activity Variance ( σ 2 ) = ( 6 b − a ​ ) 2

Project Completion Probability: The total critical path expected duration T E = ∑ t e T_E = \sum t_e T E ​ = ∑ t e ​ and path variance σ P 2 = ∑ σ critical 2 \sigma_P^2 = \sum \sigma_{\text{critical}}^2 σ P 2 ​ = ∑ σ critical 2 ​ . Standard normal variable Z Z Z for target date T D T_D T D ​ : Z = T D − T E σ P 2 Z = \frac{T_D - T_E}{\sqrt{\sigma_P^2}} Z = σ P 2 ​ ​ T D ​ − T E ​ ​

Project Crashing (Cost-Time Trade-Off)

Accelerating project completion by adding resources to critical path activities: Crash Cost Slope = Crash Cost − Normal Cost Normal Time − Crash Time \text{Crash Cost Slope} = \frac{\text{Crash Cost} - \text{Normal Cost}}{\text{Normal Time} - \text{Crash Time}} Crash Cost Slope = Normal Time − Crash Time Crash Cost − Normal Cost ​

Rule: Crash the critical path activity having the lowest crash cost slope first.

  • 3. Inventory Control & Operations Management
  • Economic Order Quantity (EOQ)

EOQ balances annual inventory ordering costs against annual storage/holding costs to find the optimal batch purchase size.

  • D D D = Annual demand (units/year)
  • S S S = Cost per order placed (PHP/order)
  • H H H = Annual holding/carrying cost per unit (PHP/unit/year)
  • C C C = Unit purchase price

i i i = Holding cost rate ( H = i ⋅ C H = i \cdot C H = i ⋅ C ) EOQ = 2 D S H = 2 D S i C \text{EOQ} = \sqrt{\frac{2 D S}{H}} = \sqrt{\frac{2 D S}{i C}} EOQ = H 2 D S ​ ​ = i C 2 D S ​ ​ Total Annual Inventory Cost ( T C ) = D Q S + Q 2 H + D C \text{Total Annual Inventory Cost } (TC) = \frac{D}{Q} S + \frac{Q}{2} H + D C Total Annual Inventory Cost ( TC ) = Q D ​ S + 2 Q ​ H + D C Optimal Order Frequency ( N ) = D EOQ , Reorder Point ( R O P ) = d daily × Lead Time \text{Optimal Order Frequency } (N) = \frac{D}{\text{EOQ}}, \quad \text{Reorder Point } (ROP) = d_{\text{daily}} \times \text{Lead Time} Optimal Order Frequency ( N ) = EOQ D ​ , Reorder Point ( ROP ) = d daily ​ × Lead Time

Total Quality Management (TQM) & ISO Standards

ISO 9001: Quality management systems standards focusing on customer satisfaction, process approach, continuous improvement, and leadership commitment.

Occupational Safety and Health Standards (OSHS): Mandated safety guidelines enforced by the Department of Labor and Employment (DOLE) under RA 11058.

4. Code of Ethics for Electrical Engineers in the Philippines

In the Philippines, professional ethics for electrical practitioners are codified in the Revised Code of Ethics for Licensed Electrical Engineering Practitioners , Annex "A" of PRB of Electrical Engineering Resolution No. 65, series of 2024 , which repealed Board Resolution No. 08 (s. 2011). It binds PEEs, REEs and RMEs alike and is organised into Article I (Professional Life), Article II (Relation with Client and Employer), Article III (Relation with Fellow Engineers) and Article IV (Penal Provisions).

Fundamental Principles & Statutory Obligations

Obligations to Public Health, Safety & Welfare:

Electrical engineers must hold paramount the safety, health, and welfare of the public in the performance of professional duties.

If an engineer's professional judgment is overruled under circumstances that endanger safety, life, or property, they must notify their employer, client, and proper administrative authorities immediately.

Obligations to Clients and Employers:

Perform services only in areas of technical competence.

Act as faithful agents or trustees for each employer or client.

Maintain absolute confidentiality regarding proprietary business affairs or technical processes of clients or employers.

Avoid conflicts of interest; disclose any financial interests, business affiliations, or connections that could influence professional judgment.

Obligations to the Profession & Colleagues:

Uphold the dignity, honor, and integrity of the electrical engineering profession.

Refuse kickbacks, bribes, secret commissions, or soliciting financial inducements.

Never attempt to injure maliciously or falsely, directly or indirectly, the professional reputation, prospects, practice, or employment of another engineer.

Sign and seal only those electrical plans, documents, and specifications that were prepared directly by the engineer or under their immediate supervision.

  • Solved Board Exam Examples
  • Example 1: PERT Network Analysis & Critical Path

Problem: An electrical substation construction project comprises five sequential activities with duration parameters in days:

  • Activity Predecessor Optimistic ( a a a ) Most Likely ( m m m ) Pessimistic ( b b b )
  • A None 2 4 6
  • B A 3 6 9
  • C A 2 5 8
  • D B 4 7 10
  • E C, D 1 2 3

Calculate the expected duration t e t_e t e ​ for each activity, identify the critical path, and determine total project expected completion time.

Solution:

Calculate expected duration t e = a + 4 m + b 6 t_e = \frac{a + 4m + b}{6} t e ​ = 6 a + 4 m + b ​ :

t e , A = 2 + 4 ( 4 ) + 6 6 = 24 6 = 4 days t_{e,A} = \frac{2 + 4(4) + 6}{6} = \frac{24}{6} = 4\ \text{days} t e , A ​ = 6 2 + 4 ( 4 ) + 6 ​ = 6 24 ​ = 4 days

t e , B = 3 + 4 ( 6 ) + 9 6 = 36 6 = 6 days t_{e,B} = \frac{3 + 4(6) + 9}{6} = \frac{36}{6} = 6\ \text{days} t e , B ​ = 6 3 + 4 ( 6 ) + 9 ​ = 6 36 ​ = 6 days

t e , C = 2 + 4 ( 5 ) + 8 6 = 30 6 = 5 days t_{e,C} = \frac{2 + 4(5) + 8}{6} = \frac{30}{6} = 5\ \text{days} t e , C ​ = 6 2 + 4 ( 5 ) + 8 ​ = 6 30 ​ = 5 days

t e , D = 4 + 4 ( 7 ) + 10 6 = 42 6 = 7 days t_{e,D} = \frac{4 + 4(7) + 10}{6} = \frac{42}{6} = 7\ \text{days} t e , D ​ = 6 4 + 4 ( 7 ) + 10 ​ = 6 42 ​ = 7 days

t e , E = 1 + 4 ( 2 ) + 3 6 = 12 6 = 2 days t_{e,E} = \frac{1 + 4(2) + 3}{6} = \frac{12}{6} = 2\ \text{days} t e , E ​ = 6 1 + 4 ( 2 ) + 3 ​ = 6 12 ​ = 2 days

Evaluate potential network paths:

Path 1 (A-C-E): Duration = t e , A + t e , C + t e , E = 4 + 5 + 2 = 11 days t_{e,A} + t_{e,C} + t_{e,E} = 4 + 5 + 2 = 11\ \text{days} t e , A ​ + t e , C ​ + t e , E ​ = 4 + 5 + 2 = 11 days .

Path 2 (A-B-D-E): Duration = t e , A + t e , B + t e , D + t e , E = 4 + 6 + 7 + 2 = 19 days t_{e,A} + t_{e,B} + t_{e,D} + t_{e,E} = 4 + 6 + 7 + 2 = 19\ \text{days} t e , A ​ + t e , B ​ + t e , D ​ + t e , E ​ = 4 + 6 + 7 + 2 = 19 days .

Conclusion: The Critical Path is A-B-D-E with a total expected project completion duration of 19 days .

Example 2: EOQ Calculation for Transformer Oil Spares

Problem: An electric utility consumes D = 1 , 200 drums D = 1,200\ \text{drums} D = 1 , 200 drums of insulating transformer oil per year. The procurement cost per order is S = PHP 1 , 500 S = \text{PHP }1,500 S = PHP 1 , 500 , and the annual carrying/holding cost per drum is H = PHP 100 H = \text{PHP }100 H = PHP 100 . Determine:

The Economic Order Quantity (EOQ).

The optimal number of orders placed per year.

Solution:

Calculate EOQ: EOQ = 2 D S H = 2 × 1 , 200 × 1 , 500 100 = 3 , 600 , 000 100 = 36 , 000 = 189.736 ≈ 190 drums \text{EOQ} = \sqrt{\frac{2 D S}{H}} = \sqrt{\frac{2 \times 1,200 \times 1,500}{100}} = \sqrt{\frac{3,600,000}{100}} = \sqrt{36,000} = 189.736 \approx 190\ \text{drums} EOQ = H 2 D S ​ ​ = 100 2 × 1 , 200 × 1 , 500 ​ ​ = 100 3 , 600 , 000 ​ ​ = 36 , 000 ​ = 189.736 ≈ 190 drums

Optimal number of orders per year ( N N N ): N = D EOQ = 1 , 200 189.736 = 6.324 ≈ 6.3 orders/year N = \frac{D}{\text{EOQ}} = \frac{1,200}{189.736} = 6.324 \approx 6.3\ \text{orders/year} N = EOQ D ​ = 189.736 1 , 200 ​ = 6.324 ≈ 6.3 orders/year

Loading diagram... Critical Path Method (A-B-D-E) Activity-on-Node Network