Study guide
17.3 Power Plant Economics, Load Curves & Energy Conversion
PRC Registered Electrical Engineer REE
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: Overview, RA 7920 & Electrical Engineering Ethics
1.1 PRC Board of Electrical Engineering & REE Examination Overview 1.2 Republic Act No. 7920 (New Electrical Engineering Law) & License Classes 1.3 Code of Ethics & Professional Practice for Electrical Engineers
2 Chapter 2: Math — Algebra, Trig & Geometry
2.1 Algebraic Equations, Polynomials & Complex Numbers 2.2 Trigonometry — Identities, Triangles & Spherical Trig 2.3 Analytic & Solid Geometry
3 Chapter 3: Engineering Mathematics — Calculus & Differential Equations
3.1 Differential Calculus, Limits, Derivatives & Applications 3.2 Integral Calculus, Integration Techniques & Area/Volume Applications 3.3 Ordinary Differential Equations & Initial-Value Problems
4 Chapter 4: Engineering Mathematics — Advanced Math & Transform Methods
4.1 Laplace Transforms, Inverse Transforms & Circuit Applications 4.2 Fourier Series, Fourier Transforms & Frequency-Domain Analysis 4.3 Vector Analysis, Linear Algebra, Matrices & Complex Analysis
5 Chapter 5: Engineering Mathematics — Probability, Statistics & Engineering Data Analysis
5.1 Probability Theory, Counting Techniques & Bayes' Theorem 5.2 Engineering Data Analysis I — Descriptive Statistics & Probability Distributions 5.3 Engineering Data Analysis II — Confidence Intervals, Hypothesis Testing & Regression
6 Chapter 6: Engineering Mathematics — Numerical Methods & Analysis
6.1 Numerical Root-Finding & Solution of Linear Systems 6.2 Interpolation, Numerical Integration & Numerical Solution of ODEs
7 Chapter 7: ESAS — Physics, Chemistry & Computer Fundamentals
7.1 Physics for Engineers 7.2 General Chemistry & Materials Science 7.3 Computer Fundamentals, Programming & Data Logic 7.4 Logic Circuits, Switching Theory & Microprocessor Systems
8 Chapter 8: ESAS — Mechanics & Thermal-Fluid Engineering
8.1 Engineering Mechanics — Statics & Dynamics 8.2 Strength of Materials & Mechanics of Deformable Bodies 8.3 Thermal-Fluid Engineering — Thermodynamics & Fluid Mechanics
9 Chapter 9: ESAS — Engineering Economics, Management & Contracts
9.1 Engineering Economics & Depreciation 9.2 Engineering Management & Ethics 9.3 Philippine Electrical Engineering Law, Code & Contracts 9.4 Technopreneurship 101 & Management of Engineering Projects
10 Chapter 10: PEC 1 — Safety, Sizing & Protection
10.1 PEC Fundamentals, Safety Standards & Grounding/Bonding 10.2 Conductor Sizing, Ampacity Adjustment & Voltage Drop 10.3 Overcurrent Protection, Branch Circuit & Feeder Sizing 10.4 Basic Occupational Safety & Health (BOSH) and Electrical Safety Standards
11 Chapter 11: PEC 1 & 2 — Equipment & Utility Systems
11.1 PEC Equipment Installation & Wiring Methods 11.2 Utility Systems, Transformers & Switchgear 11.3 Special Occupancies & Hazardous Locations
12 Chapter 12: Electrical Professional — DC & AC Circuit Fundamentals
12.1 DC Circuit Analysis & Network Theorems 12.2 Single-Phase AC Circuits & Phasor Analysis 12.3 Balanced & Unbalanced Three-Phase AC Circuits
13 Chapter 13: Electrical Professional — EM Fields & Transients
13.1 Electrostatics, Magnetostatics & Maxwell's Equations 13.2 Electromagnetic Waves & Transmission Line Fields 13.3 First-Order & Second-Order Circuit Transients
14 Chapter 14: Electrical Professional — Electronics, Industrial Electronics & Communications
14.1 Electronics 1 & 2 — Semiconductor Devices & Analog Circuits 14.2 Electrical Apparatus & Devices — Industrial Electronics & Power Converters 14.3 Fundamentals of Electronic Communications
15 Chapter 15: Electrical Professional — Transformers & DC Machines
15.1 Single-Phase & Three-Phase Transformers 15.2 Transformer Connections & Special Transformers 15.3 DC Generators & DC Motors
16 Chapter 16: Electrical Professional — AC Synchronous & Induction Machinery
16.1 Synchronous Generators (Alternators) 16.2 Synchronous Motors & Special AC Machines 16.3 Three-Phase & Single-Phase Induction Motors
17 Chapter 17: Electrical Professional — Power Plants & Energy Conversion
17.1 Hydroelectric, Thermal & Combined Cycle Power Plants 17.2 Renewable Energy Systems & Geothermal Power Plants 17.3 Power Plant Economics, Load Curves & Energy Conversion
18 Chapter 18: Electrical Professional — Transmission & Distribution
18.1 Transmission Line Parameters & Performance Models 18.2 Mechanical Overhead Line Design, Underground Cables & Insulators 18.3 Distribution Systems, Substation Layouts & Power Flow Control
19 Chapter 19: Electrical Professional — Power System Analysis
19.1 The Per-Unit System, Base Conversion & Impedance Diagrams 19.2 Symmetrical Components & Unbalanced Fault Analysis 19.3 Load Flow, Economic Dispatch & Power System Stability
20 Chapter 20: Electrical Professional — Protection, Control, Instrumentation & Illumination
20.1 Power System Protection & Protective Relaying 20.2 Industrial Motor Control, Logic Circuits & PLC Automation 20.3 Electrical Instrumentation, Transducers & Measurement Systems 20.4 Illumination Engineering, Lighting Design & Photometrics 20.5 Feedback Control Systems & Research Methods
17.3 Power Plant Economics, Load Curves & Energy Conversion
Key Takeaways Explain This Topic AI
Load Factor ( LF = P avg P max \text{LF} = \frac{P_{\text{avg}}}{P_{\text{max}}} LF = P max P avg ) and Plant Capacity Factor ( PCF = P avg Installed Capacity \text{PCF} = \frac{P_{\text{avg}}}{\text{Installed Capacity}} PCF = Installed Capacity P avg ) measure generation asset utilization, with PCF = LF \text{PCF} = \text{LF} PCF = LF when reserve capacity is zero.
Diversity Factor ( DivF = ∑ P individual max P coincident max ≥ 1 \text{DivF} = \frac{\sum P_{\text{individual max}}}{P_{\text{coincident max}}} \ge 1 DivF = P coincident max ∑ P individual max ≥ 1 ) quantifies non-coincidence of consumer peak loads; higher diversity factors reduce system peak demand and capital investment in plant capacity.
Heat Rate ( HR = Heat Input (kJ) Electrical Output (kWh) \text{HR} = \frac{\text{Heat Input (kJ)}}{\text{Electrical Output (kWh)}} HR = Electrical Output (kWh) Heat Input (kJ) ) is inversely proportional to overall station thermal efficiency: η overall = 3600 HR (kJ/kWh) × 100 % = 3412 HR (BTU/kWh) × 100 % \eta_{\text{overall}} = \frac{3600}{\text{HR (kJ/kWh)}} \times 100\% = \frac{3412}{\text{HR (BTU/kWh)}} \times 100\% η overall = HR (kJ/kWh) 3600 × 100% = HR (BTU/kWh) 3412 × 100% .
Reserve Capacity ( Reserve = Installed Capacity − P max \text{Reserve} = \text{Installed Capacity} - P_{\text{max}} Reserve = Installed Capacity − P max ) provides spinning and cold reserve margins necessary to ensure grid reliability during forced generator outages and unexpected load spikes.
Generation costs are categorized into fixed, semi-fixed (demand-proportional), and running (energy-proportional) costs, determining tariff structures (two-part, block rate) and dispatch priority (base load vs. peaking plants).
Last updated: August 2026
17.3 Power Plant Economics, Load Curves & Energy Conversion
Power plant economic analysis and operational performance metrics are fundamental topics evaluated on the PRC Registered Electrical Engineer (REE) Licensure Examination . Engineers must be capable of evaluating chronological load curves, calculating load utilization factors, determining overall heat rates, and optimizing power station selection for base-load and peaking duties.
1. Load Curves & Key Power Station Operating Factors
A chronological load curve plots power demand (kW or MW) on the vertical axis against time (hours) on the horizontal axis over a 24-hour day, month, or year. 24-HOUR CHRONOLOGICAL LOAD CURVE & METRICS
- Power Demand (MW)
- ^
- 100 + - - - - - - - - - - - - - - - - - - - - - -/------\ Peak Load (P_max)
- | / \
- 80 + - - - - - - - - - - - - - - - - - - - - -/ \
- | Average Load (P_avg) / \
- 60 +========================================/==============\=====
- | / \
- 40 +-------------------. / \
- | \ / \
- 20 + \______________/ \________
- 0 +---|-------|-------|-------|-------|-------|-------|-------|-------|---> Time (Hours)
- 00:00 03:00 06:00 09:00 12:00 15:00 18:00 21:00 24:00
- Essential Mathematical Metrics & Definitions
1. Average Load ( P avg P_{\text{avg}} P avg ) P avg = Total Energy Generated in T Hours (kWh) T Hours P_{\text{avg}} = \frac{\text{Total Energy Generated in } T \text{ Hours (kWh)}}{T \text{ Hours}} P avg = T Hours Total Energy Generated in T Hours (kWh)
2. Load Factor (LF)
The ratio of average load to peak maximum demand P max P_{\text{max}} P max over a specified time period: LF = P avg P max = Total Energy Generated in T Hours P max × T \text{LF} = \frac{P_{\text{avg}}}{P_{\text{max}}} = \frac{\text{Total Energy Generated in } T \text{ Hours}}{P_{\text{max}} \times T} LF = P max P avg = P max × T Total Energy Generated in T Hours
Since P avg ≤ P max P_{\text{avg}} \le P_{\text{max}} P avg ≤ P max , LF ≤ 1.0 \text{LF} \le 1.0 LF ≤ 1.0 (or ≤ 100 % \le 100\% ≤ 100% ).
3. Connected Load ( P conn P_{\text{conn}} P conn )
The continuous nameplate rating sum of all electrical equipment and loads connected to the utility supply system.
4. Demand Factor (DF)
The ratio of actual peak maximum demand P max P_{\text{max}} P max to total connected load P conn P_{\text{conn}} P conn : DF = P max P conn ≤ 1.0 \text{DF} = \frac{P_{\text{max}}}{P_{\text{conn}}} \le 1.0 DF = P conn P max ≤ 1.0
5. Diversity Factor (DivF)
The ratio of the sum of individual non-coincident maximum demands of all sub-circuits or consumers to the simultaneous coincident maximum demand P coincident max P_{\text{coincident max}} P coincident max of the entire system: Diversity Factor (DivF) = ∑ i = 1 n P individual max , i P coincident max ≥ 1.0 \text{Diversity Factor (DivF)} = \frac{\sum_{i=1}^{n} P_{\text{individual max}, i}}{P_{\text{coincident max}}} \ge 1.0 Diversity Factor (DivF) = P coincident max ∑ i = 1 n P individual max , i ≥ 1.0
Key Principle: A high Diversity Factor ( > 1.0 > 1.0 > 1.0 ) means individual consumer peaks occur at different times during the day. This reduces coincident station peak load P max P_{\text{max}} P max , allowing utilities to install smaller generator capacities, lowering capital investment per kW.
6. Plant Capacity Factor (PCF)
The ratio of actual energy generated over a given period to the maximum possible energy that could have been produced if the plant operated continuously at its full installed nameplate capacity ( C installed C_{\text{installed}} C installed ): PCF = Actual Energy Generated in T Hours C installed × T = P avg C installed \text{PCF} = \frac{\text{Actual Energy Generated in } T \text{ Hours}}{C_{\text{installed}} \times T} = \frac{P_{\text{avg}}}{C_{\text{installed}}} PCF = C installed × T Actual Energy Generated in T Hours = C installed P avg
7. Reserve Capacity Reserve Capacity = C installed − P max \text{Reserve Capacity} = C_{\text{installed}} - P_{\text{max}} Reserve Capacity = C installed − P max
Relationship between LF, PCF, and Reserve: PCF = LF × ( P max C installed ) \text{PCF} = \text{LF} \times \left( \frac{P_{\text{max}}}{C_{\text{installed}}} \right) PCF = LF × ( C installed P max )
If Installed Capacity equals Peak Load ( C installed = P max C_{\text{installed}} = P_{\text{max}} C installed = P max ), then PCF = LF \text{PCF} = \text{LF} PCF = LF and Reserve Capacity is zero.
8. Plant Use Factor (PUF) PUF = Actual Energy Generated in T Hours C installed × T operating \text{PUF} = \frac{\text{Actual Energy Generated in } T \text{ Hours}}{C_{\text{installed}} \times T_{\text{operating}}} PUF = C installed × T operating Actual Energy Generated in T Hours
where T operating T_{\text{operating}} T operating is the actual hours the plant was synchronized and running.
- 2. Power Station Performance Metrics: Heat Rate & Fuel Consumption
- Station Heat Rate (HR)
The Heat Rate (HR) measures the heat energy input (in kJ or BTU) required by a thermal power station to produce one kilowatt-hour ( 1 kWh 1\ \text{kWh} 1 kWh ) of electrical energy: Heat Rate (HR) = Total Heat Energy Input (kJ or BTU) Net Electrical Energy Output (kWh) \text{Heat Rate (HR)} = \frac{\text{Total Heat Energy Input (kJ or BTU)}}{\text{Net Electrical Energy Output (kWh)}} Heat Rate (HR) = Net Electrical Energy Output (kWh) Total Heat Energy Input (kJ or BTU)
Mathematical Relationship with Thermal Efficiency ( η overall \eta_{\text{overall}} η overall )
Since 1 kWh = 3 , 600 kJ = 3 , 412 BTU 1\ \text{kWh} = 3,600\ \text{kJ} = 3,412\ \text{BTU} 1 kWh = 3 , 600 kJ = 3 , 412 BTU : η overall = 3600 HR (in kJ/kWh) × 100 % \eta_{\text{overall}} = \frac{3600}{\text{HR (in kJ/kWh)}} \times 100\% η overall = HR (in kJ/kWh) 3600 × 100% η η overall = 3412 HR (in BTU/kWh) × 100 % \eta_{\eta_{\text{overall}}} = \frac{3412}{\text{HR (in BTU/kWh)}} \times 100\% η η overall = HR (in BTU/kWh) 3412 × 100%
Rule: A lower Heat Rate indicates a more efficient thermal power plant.
Specific Fuel Consumption (SFC) SFC = Mass of Fuel Consumed per Hour (kg/h) Electrical Output Power (kW) ( kg/kWh ) \text{SFC} = \frac{\text{Mass of Fuel Consumed per Hour (kg/h)}}{\text{Electrical Output Power (kW)}} \quad (\text{kg/kWh}) SFC = Electrical Output Power (kW) Mass of Fuel Consumed per Hour (kg/h) ( kg/kWh ) Heat Input Rate Q in = SFC × HHV ( kJ/kWh ) \text{Heat Input Rate } Q_{\text{in}} = \text{SFC} \times \text{HHV} \quad (\text{kJ/kWh}) Heat Input Rate Q in = SFC × HHV ( kJ/kWh )
- 3. Power Generation Economics & Tariff Calculations
- Cost of Electrical Energy Generation
Total annual power station operating cost C total C_{\text{total}} C total consists of three components:
Fixed Cost ( A A A ): Capital depreciation, debt interest, taxes, and insurance. Independent of peak load and energy output.
Semi-Fixed Cost ( B ⋅ P max B \cdot P_{\text{max}} B ⋅ P max ): Salaries, standing operational expenses, and proportional maintenance fees tied directly to maximum peak demand P max P_{\text{max}} P max (kW or MW).
Running / Operating Cost ( C ⋅ E C \cdot E C ⋅ E ): Fuel consumption, lubricating oils, chemical treatments, and active maintenance proportional to total energy generated E E E (kWh). Total Annual Cost: C total = A + B ⋅ P max + C ⋅ E ( Pesos, PHP ) \text{Total Annual Cost: } C_{\text{total}} = A + B \cdot P_{\text{max}} + C \cdot E \quad (\text{Pesos, } \text{PHP}) Total Annual Cost: C total = A + B ⋅ P max + C ⋅ E ( Pesos, PHP )
Utility Tariff Structures
Tariff Type Mathematical Formulation Characteristics & Target Customer
Flat Demand Tariff Bill = B ⋅ P max \text{Bill} = B \cdot P_{\text{max}} Bill = B ⋅ P max Charged strictly on maximum demand; no metering of kWh. Used for streetlights.
Straight-Line Rate Bill = C ⋅ E \text{Bill} = C \cdot E Bill = C ⋅ E Uniform charge per kWh consumed. Simple residential billing.
Two-Part Tariff Bill = A 1 ⋅ kW (Demand) + B 1 ⋅ kWh (Energy) \text{Bill} = A_1 \cdot \text{kW (Demand)} + B_1 \cdot \text{kWh (Energy)} Bill = A 1 ⋅ kW (Demand) + B 1 ⋅ kWh (Energy) Separate demand charge (kW peak) and energy consumption charge (kWh). Standard commercial and industrial tariff.
Block Rate Tariff Tiered price per kWh Energy charged at progressively lower rates across consumption blocks. Encourages larger industrial loads.
4. Base Load vs. Peaking Power Plant Operational Economics BASE-LOAD VS. PEAKING PLANT COST STRUCTURES
- Total Cost per Year (PHP)
- ^
- | / Peaking Plant (High Fuel/Operating Cost)
- | / Low Fixed Capital Cost
- | /
- | /
- | /________ Base-Load Plant (High Fixed Capital Cost)
- | / Low Fuel/Operating Cost
- | /
- 0 +-----------o----------------------------------> Annual Energy Generated (kWh)
- Cross-Over Point
Base-Load Power Plants: High capital cost, low operating/fuel cost per kWh. Operate continuously near 100% capacity. Examples: Geothermal, Run-of-River Hydro, Nuclear, Large Coal.
Peaking Power Plants: Low capital cost, high operating/fuel cost per kWh. Started rapidly to supply short-duration peak loads. Examples: Open-Cycle Gas Turbines, Diesel Generator Sets, Pumped-Storage Hydro.
- Solved Board Exam Examples
- Example 1: Comprehensive Load Curve & Factor Evaluation
Problem: A regional grid power station supplies a city load with the following daily 24-hour demand profile:
- 00:00 to 06:00 (6 hours): 20 MW 20\ \text{MW} 20 MW
- 06:00 to 12:00 (6 hours): 60 MW 60\ \text{MW} 60 MW
- 12:00 to 18:00 (6 hours): 80 MW 80\ \text{MW} 80 MW
- 18:00 to 24:00 (6 hours): 40 MW 40\ \text{MW} 40 MW
The power plant installed generator capacity is 100 MW 100\ \text{MW} 100 MW . Calculate: (a) Total daily energy generated in MWh, (b) Daily average load, (c) Daily Load Factor (LF), (d) Plant Capacity Factor (PCF), and (e) Station Reserve Capacity.
Solution:
Calculate total energy generated E daily E_{\text{daily}} E daily : E daily = ( 20 × 6 ) + ( 60 × 6 ) + ( 80 × 6 ) + ( 40 × 6 ) E_{\text{daily}} = (20 \times 6) + (60 \times 6) + (80 \times 6) + (40 \times 6) E daily = ( 20 × 6 ) + ( 60 × 6 ) + ( 80 × 6 ) + ( 40 × 6 ) E daily = 120 + 360 + 480 + 240 = 1200 MWh = 1 , 200 , 000 kWh E_{\text{daily}} = 120 + 360 + 480 + 240 = 1200\ \text{MWh} = 1,200,000\ \text{kWh} E daily = 120 + 360 + 480 + 240 = 1200 MWh = 1 , 200 , 000 kWh
Calculate average load P avg P_{\text{avg}} P avg : P avg = 1200 MWh 24 h = 50 MW P_{\text{avg}} = \frac{1200\ \text{MWh}}{24\ \text{h}} = 50\ \text{MW} P avg = 24 h 1200 MWh = 50 MW
Determine peak maximum demand P max = 80 MW P_{\text{max}} = 80\ \text{MW} P max = 80 MW . Calculate Load Factor (LF): LF = P avg P max = 50 MW 80 MW = 0.625 ( 62.5 % ) \text{LF} = \frac{P_{\text{avg}}}{P_{\text{max}}} = \frac{50\ \text{MW}}{80\ \text{MW}} = 0.625 \quad (62.5\%) LF = P max P avg = 80 MW 50 MW = 0.625 ( 62.5% )
Calculate Plant Capacity Factor (PCF) with installed capacity C installed = 100 MW C_{\text{installed}} = 100\ \text{MW} C installed = 100 MW : PCF = P avg C installed = 50 MW 100 MW = 0.50 ( 50.0 % ) \text{PCF} = \frac{P_{\text{avg}}}{C_{\text{installed}}} = \frac{50\ \text{MW}}{100\ \text{MW}} = 0.50 \quad (50.0\%) PCF = C installed P avg = 100 MW 50 MW = 0.50 ( 50.0% )
Calculate Reserve Capacity: Reserve Capacity = C installed − P max = 100 MW − 80 MW = 20 MW \text{Reserve Capacity} = C_{\text{installed}} - P_{\text{max}} = 100\ \text{MW} - 80\ \text{MW} = 20\ \text{MW} Reserve Capacity = C installed − P max = 100 MW − 80 MW = 20 MW
Example 2: Diversity Factor & Substation Sizing
Problem: A municipal distribution substation feeds three commercial industrial loads with individual maximum peak demands of 1500 kW 1500\ \text{kW} 1500 kW , 2500 kW 2500\ \text{kW} 2500 kW , and 3000 kW 3000\ \text{kW} 3000 kW . The diversity factor between these loads is 1.40 1.40 1.40 . Calculate: (a) The coincident maximum peak demand on the substation, and (b) The required transformer capacity if a 20 % 20\% 20% reserve margin above coincident peak demand is required.
Solution:
Calculate the sum of individual maximum demands: ∑ P indiv = 1500 + 2500 + 3000 = 7000 kW \sum P_{\text{indiv}} = 1500 + 2500 + 3000 = 7000\ \text{kW} ∑ P indiv = 1500 + 2500 + 3000 = 7000 kW
Calculate coincident peak demand using Diversity Factor formula: Diversity Factor = ∑ P indiv P coincident max ⟹ 1.40 = 7000 kW P coincident max \text{Diversity Factor} = \frac{\sum P_{\text{indiv}}}{P_{\text{coincident max}}} \implies 1.40 = \frac{7000\ \text{kW}}{P_{\text{coincident max}}} Diversity Factor = P coincident max ∑ P indiv ⟹ 1.40 = P coincident max 7000 kW P coincident max = 7000 1.40 = 5000 kW P_{\text{coincident max}} = \frac{7000}{1.40} = 5000\ \text{kW} P coincident max = 1.40 7000 = 5000 kW
Calculate required transformer capacity with 20 % 20\% 20% reserve margin: Capacity = 5000 kW × 1.20 = 6000 kW \text{Capacity} = 5000\ \text{kW} \times 1.20 = 6000\ \text{kW} Capacity = 5000 kW × 1.20 = 6000 kW
Example 3: Heat Rate & Coal Consumption Calculation
Problem: A thermal steam power plant has an overall station efficiency of 33 % 33\% 33% . The coal burned has a heating value of 26 , 000 kJ/kg 26,000\ \text{kJ/kg} 26 , 000 kJ/kg . Determine: (a) The station Heat Rate in kJ/kWh \text{kJ/kWh} kJ/kWh , and (b) Specific Fuel Consumption in kg/kWh \text{kg/kWh} kg/kWh .
Solution:
Calculate station Heat Rate from overall efficiency: Heat Rate = 3600 η overall = 3600 0.33 = 10 , 909.09 kJ/kWh \text{Heat Rate} = \frac{3600}{\eta_{\text{overall}}} = \frac{3600}{0.33} = 10,909.09\ \text{kJ/kWh} Heat Rate = η overall 3600 = 0.33 3600 = 10 , 909.09 kJ/kWh
Calculate Specific Fuel Consumption (SFC): SFC = Heat Rate Heating Value = 10 , 909.09 kJ/kWh 26 , 000 kJ/kg = 0.4196 kg/kWh \text{SFC} = \frac{\text{Heat Rate}}{\text{Heating Value}} = \frac{10,909.09\ \text{kJ/kWh}}{26,000\ \text{kJ/kg}} = 0.4196\ \text{kg/kWh} SFC = Heating Value Heat Rate = 26 , 000 kJ/kg 10 , 909.09 kJ/kWh = 0.4196 kg/kWh