Study guide

17.2 Renewable Energy Systems & Geothermal Power Plants

PRC Registered Electrical Engineer REE

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: Overview, RA 7920 & Electrical Engineering Ethics

1.1 PRC Board of Electrical Engineering & REE Examination Overview 1.2 Republic Act No. 7920 (New Electrical Engineering Law) & License Classes 1.3 Code of Ethics & Professional Practice for Electrical Engineers

2 Chapter 2: Math — Algebra, Trig & Geometry

2.1 Algebraic Equations, Polynomials & Complex Numbers 2.2 Trigonometry — Identities, Triangles & Spherical Trig 2.3 Analytic & Solid Geometry

3 Chapter 3: Engineering Mathematics — Calculus & Differential Equations

3.1 Differential Calculus, Limits, Derivatives & Applications 3.2 Integral Calculus, Integration Techniques & Area/Volume Applications 3.3 Ordinary Differential Equations & Initial-Value Problems

4 Chapter 4: Engineering Mathematics — Advanced Math & Transform Methods

4.1 Laplace Transforms, Inverse Transforms & Circuit Applications 4.2 Fourier Series, Fourier Transforms & Frequency-Domain Analysis 4.3 Vector Analysis, Linear Algebra, Matrices & Complex Analysis

5 Chapter 5: Engineering Mathematics — Probability, Statistics & Engineering Data Analysis

5.1 Probability Theory, Counting Techniques & Bayes' Theorem 5.2 Engineering Data Analysis I — Descriptive Statistics & Probability Distributions 5.3 Engineering Data Analysis II — Confidence Intervals, Hypothesis Testing & Regression

6 Chapter 6: Engineering Mathematics — Numerical Methods & Analysis

6.1 Numerical Root-Finding & Solution of Linear Systems 6.2 Interpolation, Numerical Integration & Numerical Solution of ODEs

7 Chapter 7: ESAS — Physics, Chemistry & Computer Fundamentals

7.1 Physics for Engineers 7.2 General Chemistry & Materials Science 7.3 Computer Fundamentals, Programming & Data Logic 7.4 Logic Circuits, Switching Theory & Microprocessor Systems

8 Chapter 8: ESAS — Mechanics & Thermal-Fluid Engineering

8.1 Engineering Mechanics — Statics & Dynamics 8.2 Strength of Materials & Mechanics of Deformable Bodies 8.3 Thermal-Fluid Engineering — Thermodynamics & Fluid Mechanics

9 Chapter 9: ESAS — Engineering Economics, Management & Contracts

9.1 Engineering Economics & Depreciation 9.2 Engineering Management & Ethics 9.3 Philippine Electrical Engineering Law, Code & Contracts 9.4 Technopreneurship 101 & Management of Engineering Projects

10 Chapter 10: PEC 1 — Safety, Sizing & Protection

10.1 PEC Fundamentals, Safety Standards & Grounding/Bonding 10.2 Conductor Sizing, Ampacity Adjustment & Voltage Drop 10.3 Overcurrent Protection, Branch Circuit & Feeder Sizing 10.4 Basic Occupational Safety & Health (BOSH) and Electrical Safety Standards

11 Chapter 11: PEC 1 & 2 — Equipment & Utility Systems

11.1 PEC Equipment Installation & Wiring Methods 11.2 Utility Systems, Transformers & Switchgear 11.3 Special Occupancies & Hazardous Locations

12 Chapter 12: Electrical Professional — DC & AC Circuit Fundamentals

12.1 DC Circuit Analysis & Network Theorems 12.2 Single-Phase AC Circuits & Phasor Analysis 12.3 Balanced & Unbalanced Three-Phase AC Circuits

13 Chapter 13: Electrical Professional — EM Fields & Transients

13.1 Electrostatics, Magnetostatics & Maxwell's Equations 13.2 Electromagnetic Waves & Transmission Line Fields 13.3 First-Order & Second-Order Circuit Transients

14 Chapter 14: Electrical Professional — Electronics, Industrial Electronics & Communications

14.1 Electronics 1 & 2 — Semiconductor Devices & Analog Circuits 14.2 Electrical Apparatus & Devices — Industrial Electronics & Power Converters 14.3 Fundamentals of Electronic Communications

15 Chapter 15: Electrical Professional — Transformers & DC Machines

15.1 Single-Phase & Three-Phase Transformers 15.2 Transformer Connections & Special Transformers 15.3 DC Generators & DC Motors

16 Chapter 16: Electrical Professional — AC Synchronous & Induction Machinery

16.1 Synchronous Generators (Alternators) 16.2 Synchronous Motors & Special AC Machines 16.3 Three-Phase & Single-Phase Induction Motors

17 Chapter 17: Electrical Professional — Power Plants & Energy Conversion

17.1 Hydroelectric, Thermal & Combined Cycle Power Plants 17.2 Renewable Energy Systems & Geothermal Power Plants 17.3 Power Plant Economics, Load Curves & Energy Conversion

18 Chapter 18: Electrical Professional — Transmission & Distribution

18.1 Transmission Line Parameters & Performance Models 18.2 Mechanical Overhead Line Design, Underground Cables & Insulators 18.3 Distribution Systems, Substation Layouts & Power Flow Control

19 Chapter 19: Electrical Professional — Power System Analysis

19.1 The Per-Unit System, Base Conversion & Impedance Diagrams 19.2 Symmetrical Components & Unbalanced Fault Analysis 19.3 Load Flow, Economic Dispatch & Power System Stability

20 Chapter 20: Electrical Professional — Protection, Control, Instrumentation & Illumination

20.1 Power System Protection & Protective Relaying 20.2 Industrial Motor Control, Logic Circuits & PLC Automation 20.3 Electrical Instrumentation, Transducers & Measurement Systems 20.4 Illumination Engineering, Lighting Design & Photometrics 20.5 Feedback Control Systems & Research Methods

17.2 Renewable Energy Systems & Geothermal Power Plants

Key Takeaways Explain This Topic AI

Geothermal power plants in the Philippines utilize dry steam, single/double flash steam, and binary cycle (Organic Rankine Cycle) technologies to convert geothermal fluid heat into electricity with capacity factors exceeding 80 % – 90 % 80\%\text{--}90\% 80% – 90% .

Solar Photovoltaic (PV) array maximum power output is P mp = V oc ⋅ I sc ⋅ FF P_{\text{mp}} = V_{\text{oc}} \cdot I_{\text{sc}} \cdot \text{FF} P mp ​ = V oc ​ ⋅ I sc ​ ⋅ FF , where array efficiency is η = P mp G ⋅ A × 100 % \eta = \frac{P_{\text{mp}}}{G \cdot A} \times 100\% η = G ⋅ A P mp ​ ​ × 100% under Standard Test Conditions ( 1000 W/m 2 1000\ \text{W/m}^2 1000 W/m 2 , 25 ∘ C 25^\circ\text{C} 2 5 ∘ C , AM 1.5).

The theoretical upper limit of wind turbine power extraction is bounded by Betz's law at C p = 16 27 ≈ 59.3 % C_p = \frac{16}{27} \approx 59.3\% C p ​ = 27 16 ​ ≈ 59.3% , with available wind power following P wind = 1 2 ρ A v 3 P_{\text{wind}} = \frac{1}{2} \rho A v^3 P wind ​ = 2 1 ​ ρ A v 3 .

Binary cycle geothermal plants utilize low-boiling-point secondary working fluids (such as isobutane) in closed heat exchangers, enabling power generation from low-temperature reservoirs ( 100 – 180 ∘ C 100\text{--}180^\circ\text{C} 100 – 18 0 ∘ C ) with zero atmospheric emissions.

Battery Energy Storage Systems (BESS) provide rapid grid frequency regulation, ramping support, and peak shaving to integrate variable solar PV and wind generation into the electrical grid.

Last updated: August 2026

17.2 Renewable Energy Systems & Geothermal Power Plants

With renewable energy expansion accelerating under Republic Act 9513 (the Philippines Renewable Energy Act of 2008), renewable energy conversion systems form a substantial part of the modern PRC REE Board Examination . This section presents a technical examination of geothermal power generation, solar photovoltaic (PV) engineering, wind turbine aerodynamics, and battery energy storage systems (BESS).

1. Geothermal Energy Conversion Systems

The Philippines ranks among the world's top producers of geothermal power (with major fields in MakBan, Tiwi, Leyte, and Palinpinon). Geothermal energy extracts thermal energy stored in sub-surface rock and water reservoirs to generate electricity.

Geothermal Conversion Cycles GEOTHERMAL CONVERSION CYCLE SCHEMATICS

1. DRY STEAM PLANT: Reservoir Steam ===> Turbine ===> Condenser ===> Reinjection

  • 2. SINGLE-FLASH PLANT: High-P Hot Water ==> Flash Tank ==[Steam]==> Turbine
  • || [Brine]
  • v
  • Reinjection Well
  • 3. BINARY CYCLE (ORC): Geo Fluid ===> Heat Exchanger ===> Reinjection Well
  • | (Isobutane Loop)
  • v
  • Organic Turbine ===> Condenser

Geothermal Cycle Type Reservoir Fluid State & Temp Process Description Features & Applications

Dry Steam Superheated/Dry Steam ( > 200 ∘ C > 200^\circ\text{C} > 20 0 ∘ C ) Steam piped directly from production wells through steam separators to the turbine. Simplest cycle; requires rare vapor-dominated geothermal reservoirs.

Single-Flash Steam High-pressure liquid ( > 180 ∘ C > 180^\circ\text{C} > 18 0 ∘ C ) High-pressure geothermal brine flashes into steam in a lower-pressure separator vessel. Separated steam drives turbine; remaining brine is reinjected. Most common geothermal plant type worldwide and in the Philippines.

Double-Flash Steam High-pressure liquid ( > 230 ∘ C > 230^\circ\text{C} > 23 0 ∘ C ) Unflashed high-temperature brine from first flash vessel undergoes a second lower-pressure flash stage, driving a low-pressure turbine stage. Produces 15 % – 20 % 15\%\text{--}20\% 15% – 20% more power output than single-flash from the same geothermal fluid flow.

Binary Cycle (ORC) Low-to-Medium Temp Water ( 100 ∘ C– 180 ∘ C 100^\circ\text{C}\text{--}180^\circ\text{C} 10 0 ∘ C – 18 0 ∘ C ) Geothermal water passes through a heat exchanger to vaporize an organic working fluid (isobutane, pentane) with a low boiling point in a closed Organic Rankine Cycle. Enables power generation from low-temp resources; zero greenhouse gas emissions; complete fluid reinjection.

2. Solar Photovoltaic (PV) Engineering & Performance

Solar photovoltaic systems convert solar irradiance directly into direct current (DC) electricity via the photovoltaic effect in semiconductor p-n junctions.

Electrical Characteristics of Solar PV Cells

A solar cell's non-linear I – V I\text{--}V I – V characteristic curve under solar irradiance G G G (in W/m 2 \text{W/m}^2 W/m 2 ) is governed by the single-diode model equation: I = I L − I 0 [ exp ⁡ ( q ( V + I R s ) n k T ) − 1 ] − V + I R s R s h I = I_L - I_0 \left[ \exp\left(\frac{q (V + I R_s)}{n k T}\right) - 1 \right] - \frac{V + I R_s}{R_{sh}} I = I L ​ − I 0 ​ [ exp ( nk T q ( V + I R s ​ ) ​ ) − 1 ] − R s h ​ V + I R s ​ ​

Key Standard Test Condition (STC: 1000 W/m 2 1000\ \text{W/m}^2 1000 W/m 2 , cell temperature 25 ∘ C 25^\circ\text{C} 2 5 ∘ C , Air Mass 1.5 spectrum) parameters are:

V oc V_{\text{oc}} V oc ​ (Open-Circuit Voltage): Voltage across terminals when I = 0 I = 0 I = 0 .

I sc I_{\text{sc}} I sc ​ (Short-Circuit Current): Current flowing when terminals are shorted ( V = 0 V = 0 V = 0 ). Directly proportional to solar irradiance G G G .

P mp P_{\text{mp}} P mp ​ (Maximum Power Point): Peak power operating point where the product V × I V \times I V × I is maximized ( P mp = V mp × I mp P_{\text{mp}} = V_{\text{mp}} \times I_{\text{mp}} P mp ​ = V mp ​ × I mp ​ ).

Fill Factor (FF) & Module Efficiency ( η \eta η )

The Fill Factor (FF) quantifies the squareness of the I – V I\text{--}V I – V curve: FF = P mp V oc ⋅ I sc = V mp ⋅ I mp V oc ⋅ I sc \text{FF} = \frac{P_{\text{mp}}}{V_{\text{oc}} \cdot I_{\text{sc}}} = \frac{V_{\text{mp}} \cdot I_{\text{mp}}}{V_{\text{oc}} \cdot I_{\text{sc}}} FF = V oc ​ ⋅ I sc ​ P mp ​ ​ = V oc ​ ⋅ I sc ​ V mp ​ ⋅ I mp ​ ​

Typical silicon PV modules have Fill Factors between 0.70 0.70 0.70 and 0.85 0.85 0.85 ( 70 % – 85 % 70\%\text{--}85\% 70% – 85% ).

Module conversion efficiency η pv \eta_{\text{pv}} η pv ​ under STC irradiance G = 1000 W/m 2 G = 1000\ \text{W/m}^2 G = 1000 W/m 2 for gross surface area A A A (in m 2 \text{m}^2 m 2 ) is: η pv = P mp G ⋅ A × 100 % = V oc ⋅ I sc ⋅ FF G ⋅ A × 100 % \eta_{\text{pv}} = \frac{P_{\text{mp}}}{G \cdot A} \times 100\% = \frac{V_{\text{oc}} \cdot I_{\text{sc}} \cdot \text{FF}}{G \cdot A} \times 100\% η pv ​ = G ⋅ A P mp ​ ​ × 100% = G ⋅ A V oc ​ ⋅ I sc ​ ⋅ FF ​ × 100%

Maximum Power Point Tracking (MPPT) & Inverters

Because solar irradiance and ambient temperatures fluctuate continuously, grid-tied PV inverters employ MPPT algorithms (such as Perturb & Observe or Incremental Conductance) to dynamically adjust DC terminal operating voltage V mp V_{\text{mp}} V mp ​ , extracting peak available DC power before converting it into 60 Hz 60\ \text{Hz} 60 Hz AC electricity.

3. Wind Energy Conversion Systems (WECS)

Wind turbines extract kinetic energy from moving air masses and convert it into mechanical torque, which drives an electric generator.

Available Power in Wind & Betz's Law

The kinetic energy of air mass m m m moving at velocity v v v is E k = 1 2 m v 2 E_k = \frac{1}{2} m v^2 E k ​ = 2 1 ​ m v 2 . The mass flow rate through a rotor swept area A = π R 2 A = \pi R^2 A = π R 2 (where R R R is blade length in meters) is m ˙ = ρ A v \dot{m} = \rho A v m ˙ = ρ A v . Thus, total theoretical power P wind P_{\text{wind}} P wind ​ available in an unperturbed wind stream is: P wind = 1 2 ρ A v 3 ( Watts, W ) P_{\text{wind}} = \frac{1}{2} \rho A v^3 \quad (\text{Watts, W}) P wind ​ = 2 1 ​ ρ A v 3 ( Watts, W )

where:

ρ \rho ρ = air density ( 1.225 kg/m 3 1.225\ \text{kg/m}^3 1.225 kg/m 3 at standard sea-level conditions)

A A A = rotor swept area = π R 2 = π D 2 4 \pi R^2 = \frac{\pi D^2}{4} π R 2 = 4 π D 2 ​ ( m 2 \text{m}^2 m 2 )

  • v v v = free-stream wind speed (m/s)
  • Betz Limit ( C p C_p C p ​ Max)

According to Betz's Law , fluid momentum mechanics dictates that a wind turbine rotor cannot extract more than 16 27 \frac{16}{27} 27 16 ​ ( 59.26 % 59.26\% 59.26% ) of the kinetic energy in the wind stream. The ratio of extracted shaft power to total wind power is the Power Coefficient ( C p C_p C p ​ ) : C p = P rotor P wind ≤ C p , Betz = 16 27 ≈ 0.5926 C_p = \frac{P_{\text{rotor}}}{P_{\text{wind}}} \le C_{p,\text{Betz}} = \frac{16}{27} \approx 0.5926 C p ​ = P wind ​ P rotor ​ ​ ≤ C p , Betz ​ = 27 16 ​ ≈ 0.5926

Accounting for aerodynamic drag, tip-loss, gearbox efficiency η m \eta_m η m ​ , and generator efficiency η g \eta_g η g ​ , practical wind turbine electrical power output is: P e = 1 2 ρ A v 3 ⋅ C p ⋅ η m ⋅ η g P_e = \frac{1}{2} \rho A v^3 \cdot C_p \cdot \eta_m \cdot \eta_g P e ​ = 2 1 ​ ρ A v 3 ⋅ C p ​ ⋅ η m ​ ⋅ η g ​ WIND TURBINE POWER CURVE REGIONS

  • Power Output (kW)
  • ^ Cut-Out Speed (e.g. 25 m/s)
  • | Rated Power | (Turbine Feathered/Stops)
  • P_rated +---------------+--------------|
  • | / |
  • | / |
  • | / (Region 2) |
  • | (Region 1) / |
  • 0 +---------------o-------------------|------------------> Wind Speed (m/s)
  • Cut-In Speed
  • (e.g. 3-4 m/s)
  • Wind Turbine Operational Regions

Cut-In Wind Speed ( v in ≈ 3 – 4 m/s v_{\text{in}} \approx 3\text{--}4\ \text{m/s} v in ​ ≈ 3 – 4 m/s ): Minimum wind speed at which the turbine begins producing net electrical power.

Rated Wind Speed ( v rated ≈ 11 – 14 m/s v_{\text{rated}} \approx 11\text{--}14\ \text{m/s} v rated ​ ≈ 11 – 14 m/s ): Wind speed at which the turbine reaches its full rated electrical generator capacity ( P rated P_{\text{rated}} P rated ​ ).

Cut-Out Wind Speed ( v out ≈ 25 m/s v_{\text{out}} \approx 25\ \text{m/s} v out ​ ≈ 25 m/s ): Maximum safe operating wind speed. Blades are feathered (pitched out of wind) and mechanical brakes are applied to protect structural components from storm damage.

4. Battery Energy Storage Systems (BESS)

Grid-scale Battery Energy Storage Systems (BESS) play an essential role in stabilizing utility grids with high penetrations of intermittent solar and wind generation.

Primary Applications: Frequency Regulation (fast primary response within milliseconds), Ramp Rate Control, Peak Shaving, and Load Shifting.

Round-Trip Efficiency (RTE): BESS efficiency measures net energy delivered during discharge relative to energy absorbed during charging: RTE = E discharge E charge × 100 % \text{RTE} = \frac{E_{\text{discharge}}}{E_{\text{charge}}} \times 100\% RTE = E charge ​ E discharge ​ ​ × 100% Lithium-ion BESS facilities achieve high round-trip efficiencies of 85 % 85\% 85% to 92 % 92\% 92% .

  • Solved Board Exam Examples
  • Example 1: Solar PV Array Sizing & Peak Output

Problem: A commercial solar PV system consists of 120 crystalline silicon modules. Each module has STC parameters: V oc = 45.0 V V_{\text{oc}} = 45.0\ \text{V} V oc ​ = 45.0 V , I sc = 10.2 A I_{\text{sc}} = 10.2\ \text{A} I sc ​ = 10.2 A , V mp = 37.5 V V_{\text{mp}} = 37.5\ \text{V} V mp ​ = 37.5 V , and I mp = 9.6 A I_{\text{mp}} = 9.6\ \text{A} I mp ​ = 9.6 A . Each module has dimensions 1.7 m × 1.0 m 1.7\ \text{m} \times 1.0\ \text{m} 1.7 m × 1.0 m . Calculate: (a) Fill Factor (FF) of a single module, (b) STC maximum peak power rating per module, (c) Total array STC peak power output in kW p \text{kW}_p kW p ​ , and (d) Module conversion efficiency η pv \eta_{\text{pv}} η pv ​ .

Solution:

Calculate module peak power output P mp P_{\text{mp}} P mp ​ : P mp = V mp × I mp = 37.5 V × 9.6 A = 360 W p P_{\text{mp}} = V_{\text{mp}} \times I_{\text{mp}} = 37.5\ \text{V} \times 9.6\ \text{A} = 360\ \text{W}_p P mp ​ = V mp ​ × I mp ​ = 37.5 V × 9.6 A = 360 W p ​

Calculate Fill Factor (FF): FF = P mp V oc ⋅ I sc = 360 45.0 × 10.2 = 360 459 = 0.7843 ( 78.43 % ) \text{FF} = \frac{P_{\text{mp}}}{V_{\text{oc}} \cdot I_{\text{sc}}} = \frac{360}{45.0 \times 10.2} = \frac{360}{459} = 0.7843 \quad (78.43\%) FF = V oc ​ ⋅ I sc ​ P mp ​ ​ = 45.0 × 10.2 360 ​ = 459 360 ​ = 0.7843 ( 78.43% )

Compute total array peak output power: P array = 120 × 360 W p = 43 , 200 W p = 43.2 kW p P_{\text{array}} = 120 \times 360\ \text{W}_p = 43,200\ \text{W}_p = 43.2\ \text{kW}_p P array ​ = 120 × 360 W p ​ = 43 , 200 W p ​ = 43.2 kW p ​

Calculate module conversion efficiency under G = 1000 W/m 2 G = 1000\ \text{W/m}^2 G = 1000 W/m 2 for module area A = 1.7 m 2 A = 1.7\ \text{m}^2 A = 1.7 m 2 : η pv = P mp G ⋅ A × 100 % = 360 W 1000 W/m 2 × 1.7 m 2 × 100 % = 360 1700 × 100 % = 21.18 % \eta_{\text{pv}} = \frac{P_{\text{mp}}}{G \cdot A} \times 100\% = \frac{360\ \text{W}}{1000\ \text{W/m}^2 \times 1.7\ \text{m}^2} \times 100\% = \frac{360}{1700} \times 100\% = 21.18\% η pv ​ = G ⋅ A P mp ​ ​ × 100% = 1000 W/m 2 × 1.7 m 2 360 W ​ × 100% = 1700 360 ​ × 100% = 21.18%

Example 2: Wind Turbine Electrical Power Output

Problem: A utility-scale wind turbine features a rotor diameter of 90 m 90\ \text{m} 90 m operating in standard air density ρ = 1.225 kg/m 3 \rho = 1.225\ \text{kg/m}^3 ρ = 1.225 kg/m 3 under a steady wind speed of 12 m/s 12\ \text{m/s} 12 m/s . The aerodynamic power coefficient is C p = 0.44 C_p = 0.44 C p ​ = 0.44 , gearbox efficiency is 96 % 96\% 96% , and generator efficiency is 95 % 95\% 95% . Determine: (a) Total wind power in the swept air stream, and (b) Net electrical power output in kW.

Solution:

Calculate swept rotor area A A A : A = π D 2 4 = π × ( 90 ) 2 4 = 6361.73 m 2 A = \frac{\pi D^2}{4} = \frac{\pi \times (90)^2}{4} = 6361.73\ \text{m}^2 A = 4 π D 2 ​ = 4 π × ( 90 ) 2 ​ = 6361.73 m 2

Compute total available power in unperturbed wind stream P wind P_{\text{wind}} P wind ​ : P wind = 1 2 ρ A v 3 = 0.5 × 1.225 × 6361.73 × ( 12 ) 3 P_{\text{wind}} = \frac{1}{2} \rho A v^3 = 0.5 \times 1.225 \times 6361.73 \times (12)^3 P wind ​ = 2 1 ​ ρ A v 3 = 0.5 × 1.225 × 6361.73 × ( 12 ) 3 P wind = 0.5 × 1.225 × 6361.73 × 1728 = 6 , 733 , 359 W = 6733.36 kW P_{\text{wind}} = 0.5 \times 1.225 \times 6361.73 \times 1728 = 6,733,359\ \text{W} = 6733.36\ \text{kW} P wind ​ = 0.5 × 1.225 × 6361.73 × 1728 = 6 , 733 , 359 W = 6733.36 kW

Calculate net electrical power output P e P_e P e ​ : P e = P wind × C p × η m × η g = 6733.36 kW × 0.44 × 0.96 × 0.95 P_e = P_{\text{wind}} \times C_p \times \eta_m \times \eta_g = 6733.36\ \text{kW} \times 0.44 \times 0.96 \times 0.95 P e ​ = P wind ​ × C p ​ × η m ​ × η g ​ = 6733.36 kW × 0.44 × 0.96 × 0.95 P e = 6733.36 × 0.40128 = 2701.96 kW ≈ 2.70 MW P_e = 6733.36 \times 0.40128 = 2701.96\ \text{kW} \approx 2.70\ \text{MW} P e ​ = 6733.36 × 0.40128 = 2701.96 kW ≈ 2.70 MW

Loading diagram... Solar Photovoltaic & Wind Energy Conversion Topologies

Typical Annual Plant Capacity Factors (%) for Renewable & Clean Energy Systems