7.3 Kanban & Lean

Project Management Professional PMP

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: Introduction & Fundamentals

1.1 About the PMP Exam 1.2 What is a Project? 1.3 Project, Program & Portfolio Management 1.4 The Project Manager Role 1.5 PMBOK 7 Principles Overview 1.6 Performance Domains Overview 1.7 What Changed in the July 2026 PMP Exam

2 Chapter 2: People Domain Part 1

2.1 Managing Conflict 2.2 Leading a Team 2.3 Supporting Team Performance 2.4 Empowering Team Members 2.5 Training & Development 2.6 Building a Team 2.7 Removing Impediments

3 Chapter 3: People Domain Part 2

3.1 Negotiating Project Agreements 3.2 Collaborating with Stakeholders 3.3 Building Shared Understanding 3.4 Engaging Virtual Teams 3.5 Defining Team Ground Rules 3.6 Mentoring Stakeholders 3.7 Emotional Intelligence

4 Chapter 4: Process Domain - Planning

4.1 Determining Project Methodology 4.2 Integrating Project Planning 4.3 Planning & Managing Scope 4.4 Planning & Managing Schedule 4.5 Planning & Managing Budget 4.6 Planning & Managing Quality 4.7 Planning & Managing Resources 4.8 Planning & Managing Procurement

5 Chapter 5: Process Domain - Execution & Control

5.1 Executing with Urgency for Value 5.2 Managing Communications 5.3 Assessing & Managing Risks 5.4 Engaging Stakeholders 5.5 Managing Project Changes 5.6 Establishing Project Governance 5.7 Managing Project Issues 5.8 Managing Project Artifacts 5.9 Knowledge Transfer & Closure

6 Chapter 6: Business Environment Domain

6.1 Planning & Managing Compliance 6.2 Evaluating & Delivering Benefits 6.3 External Environment Changes 6.4 Supporting Organizational Change

7 Chapter 7: Agile & Hybrid Approaches

7.1 Agile Mindset & Values 7.2 Scrum Framework 7.3 Kanban & Lean 7.4 Extreme Programming (XP) 7.5 Hybrid Project Management 7.6 Agile Planning & Estimation 7.7 Agile Metrics & Tools

8 Chapter 8: Predictive (Waterfall) Approaches

8.1 Predictive Lifecycle 8.2 Scope Management 8.3 Schedule Management 8.4 Cost Management 8.5 Quality Management 8.6 Risk Management Process 8.7 Procurement & Contracts 8.8 Change Control

7.3 Kanban & Lean

Key Takeaways Explain This Topic AI

Kanban is a continuous flow method that visualizes work, limits work-in-progress (WIP), and optimizes flow

WIP limits can increase team throughput by 40% while reducing delivery time by up to 60%

Little's Law states: Lead Time = WIP / Throughput -- reducing WIP reduces lead time

Lean principles focus on eliminating waste (muda), overburden (muri), and unevenness (mura)

  • Unlike Scrum's fixed sprints, Kanban enables continuous delivery without prescribed iterations
  • Last updated: January 2026

Kanban and Lean provide complementary approaches to optimizing workflow and eliminating waste. For the PMP exam, understanding these methods helps answer questions about flow-based project management and continuous improvement.

Kanban Origins

Kanban originated in the Toyota Production System (TPS) , developed by Taiichi Ohno in the 1940s-1960s. The word "kanban" means "visual signal" or "card" in Japanese. Toyota used physical cards to signal when more parts were needed, creating a "pull system" that reduced inventory and improved efficiency.

David J. Anderson later adapted these principles for knowledge work, creating the Kanban Method for software development and project management.

The Four Core Kanban Principles

  • Principle Description
  • Visualize the Work Make work visible using a Kanban board
  • Limit Work in Progress (WIP) Set explicit limits on concurrent work
  • Focus on Flow Measure and optimize the flow of work
  • Continuous Improvement Continuously analyze and improve the process
  • Additional Foundation Principles
  • Start with what you know : Begin with current processes
  • Pursue incremental change : Make small, evolutionary improvements
  • Respect the current process : Don't disrupt what's working
  • Encourage leadership at all levels : Anyone can suggest improvements
  • The Kanban Board
  • A Kanban board visualizes work flowing through stages: | BACKLOG | TO DO | IN PROGRESS | REVIEW | DONE |
  • | | | WIP: 3 | WIP: 2 | |
  • |-----------|---------|---------------|----------|----------|
  • | Item 8 | Item 6 | Item 3 | Item 2 | Item 1 |
  • | Item 9 | Item 7 | Item 4 | | |
  • | Item 10 | | Item 5 | | |

Each column represents a workflow state. Cards move from left to right as work progresses.

Work-in-Progress (WIP) Limits

WIP limits control how many work items can exist in each column simultaneously. They are the cornerstone of Kanban's effectiveness.

Why WIP Limits Matter

  • Benefit Impact
  • Increased throughput Teams can see up to 40% improvement
  • Reduced lead time Delivery time can decrease by up to 60%
  • Reduced context switching Focus on finishing, not starting
  • Exposed bottlenecks Problems become visible quickly
  • Improved quality Less rushed, more focused work
  • Little's Law

Little's Law provides the mathematical foundation for WIP limits:

Lead Time = WIP / Throughput

This means:

  • Reducing WIP reduces lead time (when throughput is constant)
  • WIP limits create a pull system rather than a push system
  • The goal is to optimize the whole system , not local efficiency
  • Setting WIP Limits
  • Consideration Guidance
  • Per workflow state Not per person
  • Start conservative Better to be too tight than too loose
  • Observe and adjust WIP limits are not fixed forever
  • Team capacity Consider available resources and skills
  • Flow Optimization

Kanban focuses on optimizing flow -- the smooth, predictable movement of work through the system.

Key Flow Metrics

  • Metric Definition Use
  • Lead Time Time from request to delivery Customer perspective
  • Cycle Time Time from work start to completion Team perspective
  • Throughput Number of items completed per time period Capacity measure
  • Work Item Age How long an item has been in progress Identifies stuck items
  • Bottleneck Identification

When work piles up in a column (exceeding WIP limits), it signals a bottleneck. The team should:

  • Stop starting new work
  • Swarm to clear the bottleneck
  • Analyze root cause
  • Implement systemic improvements
  • Lean Principles

Lean is the broader philosophy that Kanban draws from. Lean focuses on maximizing value while minimizing waste.

The Seven Wastes (Muda)

  • Waste In Knowledge Work
  • Transport Unnecessary handoffs between teams
  • Inventory Partially completed work
  • Motion Switching between tasks/tools
  • Waiting Delays for approvals, resources, or information
  • Overproduction Building features not yet needed
  • Over-processing Gold-plating or unnecessary complexity
  • Defects Rework, bugs, errors
  • Three Types of Waste
  • Type Japanese Term Description
  • Waste Muda Non-value-adding activities
  • Overburden Muri Unreasonable demands on people/systems
  • Unevenness Mura Inconsistent workload or output
  • Value Stream Mapping

Value Stream Mapping visualizes the entire flow of work from customer request to delivery, identifying:

  • Value-adding steps : Work the customer pays for
  • Non-value-adding steps : Waste to eliminate
  • Wait times : Delays between steps
  • Cycle times : Duration of each step
  • Value Stream Map Example Request -> [Wait 2d] -> Design -> [Wait 1d] -> Develop -> [Wait 3d] -> Test -> Deploy
  • (3h) (8h) (4h) (1h)
  • Total Lead Time: 6+ days
  • Value-Adding Time: 16 hours
  • Efficiency: ~33%
  • Kanban vs. Scrum
  • Aspect Kanban Scrum
  • Cadence Continuous flow Fixed-length sprints
  • Roles Flexible Product Owner, Scrum Master, Developers
  • Meetings As needed Prescribed events
  • Work limits WIP limits per column Sprint capacity
  • Change approach Can happen anytime Within sprint boundaries
  • Metrics focus Lead time, throughput Velocity, burndown
  • When to Use Kanban
  • Operations and support work
  • Continuous delivery environments
  • Work with highly variable priorities
  • Teams maintaining existing products
  • When sprints feel artificial
  • PMP Exam Tips

For the PMP exam, recognize Kanban scenarios by these keywords:

  • Visualize work on a board
  • Limit work-in-progress
  • Continuous flow (no fixed sprints)
  • Pull system vs. push system
  • Optimize flow, not utilization

When a question describes overloaded columns or slow flow , recommend:

  • Enforcing or lowering WIP limits
  • Focus on finishing before starting
  • Identify and address bottlenecks
  • Key Takeaways
  • Kanban visualizes work and limits WIP to optimize flow
  • Little's Law : Lead Time = WIP / Throughput
  • WIP limits can improve throughput by 40% and reduce lead time by 60%
  • Lean eliminates waste (muda, muri, mura)
  • Value stream mapping identifies improvement opportunities
  • Kanban enables continuous delivery without prescribed iterations

Loading diagram... Kanban Board with WIP Limits