14.3 FAT, SAT & Final Acceptance Testing Criteria

ASIS Physical Security Professional PSP

Track your progress as you read

Finished sections get a check mark.

1 Introduction & Exam Overview

1.1 Current PSP Exam Facts 1.2 Eligibility, Fees, Scheduling & Recertification 1.3 Experience-Based Testing, References & Study Approach

2 Assessment Planning & Methods

2.1 Assessment Plan, Stakeholders, Budget & Resources 2.2 Inside-Out, Outside-In, Site-Specific & Functional Models 2.3 Qualitative vs Quantitative Assessment Methods 2.4 Standards, Regulations, Codes & Where to Find Them

3 Asset Identification & Valuation

3.1 Asset Types, Terminology, Value, Criticality & Loss Impact 3.2 Valuing Tangible and Intangible Assets for Operations 3.3 Criticality, Key Areas & Loss-Impact Prioritization

4 Threats, Hazards & Operating Environment

4.1 Criminal, Terrorist, Insider & Sociopolitical Threats 4.2 Natural Disasters, Accidental & Cyber-Physical Hazards 4.3 Geography, Crime, Socioeconomics & Existing Countermeasures 4.4 Neighbors, Competitors, Legal, Reputation & Supply Chain

5 Vulnerability Assessment & Surveys

5.1 Surveys, Interviews, Incident Data, Crime Stats & Benchmarking 5.2 Evaluating Technology, Personnel & Procedures 5.3 Plans, Schematics & Environmental/Site Factors

6 Risk Analysis & Countermeasure Selection

6.1 Risk Analysis Strategies, Principles & Data Interpretation 6.2 Threat/Hazard–Vulnerability Pairing & Loss Event Profiles 6.3 Matching Countermeasures to Specific Risks 6.4 ROI, Total Cost of Ownership, Privacy, PII & Life Safety

7 Performance Requirements & Security Concepts

7.1 Design Constraints & Incorporating Risk Analysis 7.2 CPTED, Defense-in-Depth, 4 Ds & Security Terminology 7.3 Operational, Functional, Performance Requirements, Codes & Metrics

8 Structural Measures & CPTED Application

8.1 Fences, Gates & Perimeter Barriers 8.2 Blast Mitigation, Ballistic Protection & Hostile Vehicle Mitigation 8.3 Lighting, Locks, Doors, Windows & Glazing 8.4 Applying CPTED to Site Planning & Landscaping

9 Electronic Security Systems

9.1 Electronic Access Control Architecture & Credentials 9.2 Biometrics, Electrified Locks, Anti-Passback & Mantraps 9.3 Video Surveillance Design, Storage & Analytics 9.4 Intrusion Detection Sensors & Alarm Communications

10 Screening, Communications, Power & Networks

10.1 Personnel, Package & Vehicle Screening and Visitor/Vendor Policy 10.2 Mass Notification, Audio Comms, Consoles & Central Stations 10.3 Data Storage, Retention, PII & Physical Network Security 10.4 Primary/Backup Power and Copper, Fiber & Wireless Transmission

11 System Design & Project Documentation

11.1 Pre-Design, Schematic, Construction Docs, Calculations & Drawings 11.2 CSI MasterFormat, Owner Standards & AIA MasterSpec 11.3 Systems Integration, Scheduling, Cost Estimation & Value Engineering

12 Pre-Bid Meetings & Solicitation Packages

12.1 Site Visits, RFIs, Substitution Requests & Pre-Bid Meetings 12.2 RFP, RFQ, IFB & Sole Source 12.3 SOW, Timelines, Costs, Personnel & Documentation 12.4 Evaluation Criteria, Technical Compliance & Contracting Ethics

13 Procurement Planning & Vendor Selection

13.1 Procurement Process for Security Goods & Services 13.2 Interviews, Due Diligence, References & Selection 13.3 Project Management Functions in Procurement

14 Installation, Commissioning & Acceptance

14.1 Installation & Inspection Techniques 14.2 Commissioning & Implementation-Phase Integration 14.3 FAT, SAT & Final Acceptance Testing Criteria 14.4 Punch Lists, As-Builts, Config Management & End-User Training

15 Security Personnel Requirements

15.1 Roles, Limits, Proprietary vs Contract Staffing 15.2 Recruiting, KPIs, Discipline & Professional Development 15.3 Post Orders, Uniforms/Equipment & Non-Security Awareness

16 Lifecycle Maintenance & Program Evaluation

16.1 Preventive/Corrective Maintenance, Calibration, Service Agreements & Warranties 16.2 Upgrade Training, System Evaluation & Replacement

14.3 FAT, SAT & Final Acceptance Testing Criteria

Key Takeaways Explain This Topic AI

Factory acceptance testing (FAT) proves a staged or factory system against written scripts before shipment; it does not replace site testing.

Site acceptance testing (SAT) proves the installed system on this site, with owner witness and recorded results, against the same design intent.

Life-safety and high-security portals are typically tested at 100 percent; sampling interior identical readers does not excuse sampling delayed-egress or fire-release interfaces.

Unresolved life-safety items—maglock fire release, delayed egress, inoperative egress hardware, elevator-recall conflicts—block final acceptance even if cameras look sharp.

Substantial completion is not a waiver of SAT, fail criteria, or remaining life-safety defects, and it is not by itself final system acceptance.

Last updated: September 2026

Factory acceptance testing (FAT) , site acceptance testing (SAT) , and final system acceptance are three different contractual proofs. Independent ExamFinch teaching for published PSP Domain 3 Task 3 knowledge is that mixing them is how an owner signs for a warehouse demo and occupies a building whose maglocks still ignore the fire alarm. This section is the criteria language: what is tested, where, by whom, against which script, and what happens when a result is a fail.

FAT is not SAT, and neither is automatic final acceptance

FAT happens before the system is the owner’s problem on this floor plate. Typical FAT is a staged head-end, a representative door kit, simulated inputs, failover, reporting, and software version checks at the vendor’s facility or a staging room. FAT is valuable for custom integration, uncommon software loads, and owner witness of a workflow before crates ship. FAT is a ship hold when scripts fail. FAT is not a photograph of a brochure rack. Commodity cameras with no custom code may have little FAT beyond production testing; an integrated ACS/VSS/IDS head-end with SOC maps usually deserves a real FAT. Passing FAT means the staged system met the scripts in that room. It does not mean the homeruns, hardware coordination, or elevator recall on this site work.

SAT happens on the installed system: these doors, these cameras, this fire-alarm interface, this elevator, this SOC. SAT uses test scripts with numbered steps, expected results, and a pass/fail rule written before the test, not invented when a lock sticks. SAT is where installation quality from 14.1 and commissioning integration from 14.2 become contractual evidence. A start-up sheet that says “Door 4 OK” with no expected result is not a script.

Final system acceptance is the owner’s (or the contractually designated representative’s) written decision that the system meets the contract, punch items that were allowed to remain are listed, training and close-out from 14.4 are complete enough to occupy, and remaining work is warranty or listed exceptions— not hidden life-safety defects. Final acceptance can follow SAT immediately on a small job. On a large job it follows punch closure, training, as-builts, and often a burn-in period. SAT pass plus a handshake is not automatically final acceptance if the contract listed other deliverables.

Proof Where What it can show What it cannot show

FAT Factory or staging Software, I/O logic, failover, sample devices against scripts This site’s pathways, hardware stacks, AHJ interfaces

SAT Installed site This system, these portals, these integrations, owner-witnessed That punch, training, passwords, and as-builts are complete

Final acceptance Contract close Owner takes the system as meeting the agreement A waiver of remaining life-safety fails

Scripts, sampling versus 100 percent, fail criteria, witness, records

Test scripts are the acceptance instrument. Each script names the device or interface, preconditions (door closed, schedule in night mode, fire panel normal), action (present a revoked badge, open without grant, trip a pull station in a coordinated fire test), expected result (deny, forced-open within n seconds, maglock release, camera call-up), and recording fields (time, tester, witness, pass/fail, notes). Scripts come from the specification and the commissioning plan, not from memory. If the specification required encrypted reader traffic, the script includes a supervision or crypto check, not only a green LED.

Sampling versus 100 percent is a written risk decision, not a tired tester’s shortcut. Life-safety interfaces and high-security portals are 100 percent : every delayed-egress leaf, every maglock fire-release, every stair tower, every vault, every elevator recall related to security outputs. Identical interior office readers on the same typical may be sampled if the specification said so and the sample fails trigger 100 percent of that typical. Sampling ten percent of delayed-egress doors because they “are all the same model” is how one miswired leaf traps people. Exam stems that offer sampling as a way around life-safety testing are wrong.

Fail criteria must exist before SAT starts. Examples: any life-safety interface fail fails SAT; more than a stated percentage of functional (non-life-safety) fails fails SAT or forces a retest window; a single forced-open that does not alarm fails that portal and its typical until retested. “We’ll see how it feels” is not a criterion. Cosmetic issues (a scratched housing) go to punch with a severity class. They do not get relabeled as SAT fails to punish a contractor, and they do not get used to paper over a maglock that will not release.

Owner witness means the owner’s designated representative—often security operations, facilities, and, for life safety, sometimes the AHJ or fire-protection engineer—is present for the scripts that matter, or reviews recorded evidence the contract allowed. Vendor-only SAT with a selfie video is demonstration, not owner acceptance. Witnesses initial the script. If the witness is “whoever was in the lobby,” you do not have an owner witness.

Recording results is part of the test, not a lawsuit hobby. Keep dated sheets or an electronic log keyed to device IDs, expected versus actual, initials, and deficiency numbers that feed the punch list. If it is not recorded, it will be re-argued at occupancy. Record failures honestly. A tester who writes “pass” on a door that needed two tries taught the SOC that the log is fiction.

Worked hospital: FAT at the vendor showed map call-up on a staged Door 4. SAT on site found the real Door 4 maglock still energized when the fire alarm was tested. That is a SAT fail and a block on acceptance , not a punch-list paint item to be “caught in warranty.” The FAT pass remains true and irrelevant to the fire-release defect.

What substantial completion is not

Substantial completion is a construction-administration idea: the work is sufficiently complete that the owner can occupy or use it for its intended purpose, with remaining work as a punch list. Security practitioners get hurt when someone treats that certificate as final system acceptance or as permission to occupy with unresolved life-safety items . It is not.

Substantial completion is not :

A waiver of SAT scripts or recorded results.

Permission to occupy while maglock fire release, delayed egress, stair locks, or elevator recall still fail.

A finding that sampling 10 percent of life-safety doors was enough.

A substitute for owner witness.

Final acceptance of configuration, training, passwords, or as-builts that the contract still requires.

A statement that “the cameras look sharp, so the system is done.”

If an architect or owner’s project manager issues substantial completion while a delayed-egress leaf is inoperative, the physical security professional’s job is to document the life-safety block , notify the responsible parties, and refuse to treat that opening as accepted. Occupancy pressure is real. It does not rewrite the fire code or the specification’s shall-language on release.

Unresolved life-safety items block acceptance. That sentence is the exam’s bright line. Cosmetic punch can remain. Incomplete nice-to-have analytics can remain if the contract allowed it. A maglock that does not release on fire alarm, a door that does not let people out, a security output that inhibits elevator recall, or an inoperative egress device does not remain. Those items stop final acceptance and should stop occupancy of the affected area. Warranty language is for latent defects after a proper pass, not for known traps left in the path of egress.

The professional SAT close is a bound (or electronic) book: scripts, witness names, fail list classified as life-safety versus functional versus cosmetic, and a clear recommendation—accept, accept with listed exceptions that are not life-safety, or do not accept. Anything vaguer is how “substantial completion” gets used as a magic wand.

Loading diagram... FAT to SAT to punch to training to final acceptance

Read the mermaid left to right as a delivery chain, not as five labels for one afternoon. FAT can stop a shipment. SAT can stop occupancy. Punch without life-safety closure cannot proceed to a honest acceptance. Training and configuration turnover belong before the owner is told the system is theirs. If a stem skips from a factory demo to “the building is substantially complete, accept it,” look for the missing SAT, the missing witness, and the life-safety item still open.