12.4 Automated Traffic Signal Performance Measures (ATSPMs) & High-Resolution Data
Professional Traffic Operations Engineer PTOE
Track your progress as you read
Finished sections get a check mark.
1 Introduction & PTOE Exam Overview
1.1 The PTOE Credential: Certification Overview & Industry Value 1.2 Core Industry Reference Standards in Traffic Operations 1.3 Study Guide Architecture, Blueprint Alignment & Exam-Day Strategy
2 Domain 1: Traffic Flow Theory & Fundamental Concepts
2.1 Macroscopic Traffic Stream Models & Fundamental Diagram (q = k × u) 2.2 Microscopic Traffic Characteristics & Car-Following Models 2.3 Hydrodynamic Shockwave Analysis & Traffic Queuing Models
3 Domain 1: Highway & Interrupted Flow Capacity Analysis (HCM)
3.1 Basic Freeway Segments & Multilane Highways (HCM 7th Edition) 3.2 Freeway Weaving, Merging, and Diverging Segments 3.3 Signalized Intersection Capacity & Delay Modeling (HCM)
4 Domain 1: Managed Lanes, Transit Priority, TSMO & Travel Demand Management
4.1 Unsignalized Intersections (TWSC, AWSC) & Modern Roundabouts Capacity 4.2 Managed Lanes, HOV/HOT Operations, & Ramp Metering 4.3 Transit Priority & Multimodal Signal Operations (TSP) 4.4 Transportation Systems Management and Operations (TSMO) & Regional ITS 4.5 Travel Demand Management (TDM) & Trip Reduction Strategies
5 Domain 2: Geometric Design Controls, Criteria, & Sight Distance
5.1 Functional Classification, Design Controls, & Context-Sensitive Design 5.2 Sight Distance Principles: Stopping, Decision, & Passing (AASHTO) 5.3 Horizontal Alignment, Curve Radius, & Superelevation Design
6 Domain 2: Roadway Cross-Sections & Access Management
6.1 Vertical Alignment: Tangent Grades, Crest & Sag Vertical Curves 6.2 Roadway Cross-Section Elements & AASHTO Clear Zone Concepts 6.3 Access Management Principles & Driveway Spacing Criteria
7 Domain 2: Intersection & Interchange Geometric Design
7.1 Intersection Channelization, Turn Lane Design, & Storage Length 7.2 Interchange Configurations & Operational Comparisons (Diamond, Cloverleaf, SPUI) 7.3 Diverging Diamond Interchanges (DDI / DCMI) Operational Principles 7.4 Modern Roundabout Geometric Design Elements & Fastest Paths 7.5 Multimodal Geometric Design: Pedestrian Facilities, Bikeways, & ADA
8 Domain 3: Traffic Safety Concepts, Human Factors, & Safe System
8.1 The Safe System Approach & Vision Zero Principles 8.2 Human Factors, Driver Expectancy, & Perception-Reaction Time (PRT) 8.3 Crash Collision Typologies & Statistical Rate Formulations (MEV, MVMT)
9 Domain 3: Highway Safety Manual (HSM) Predictive Methods & EB
9.1 Highway Safety Manual (HSM) Predictive Methodology & Part C Models 9.2 Safety Performance Functions (SPFs) & Crash Modification Factors (CMFs) 9.3 Empirical Bayes (EB) Method & Regression-to-the-Mean (RTM) Correction 9.4 Economic Appraisal of Safety Projects (Benefit-Cost Analysis, NPV)
10 Domain 3: Safety Countermeasures & Road Safety Audits (RSA)
10.1 Roadway Departure Countermeasures (Rumble Strips, Safety Edge, Barriers) 10.2 Intersection Safety Countermeasures (Sight Triangles, Left-Turn Calming, Roundabouts) 10.3 Vulnerable Road User (VRU) Safety Countermeasures (PHB/HAWK, RRFB, Curb Extensions) 10.4 Road Safety Audits (RSAs) & Systemic Safety Analysis
11 Domain 4: Traffic Signal Warrants & Isolated Timing (MUTCD/ITE)
11.1 MUTCD Traffic Signal Warrants (Warrants 1 through 9) 11.2 Signal Phasing Principles & NEMA Dual-Ring Operations 11.3 Clearance Intervals (ITE Kinematic Equations) & Pedestrian Timing Parameters
12 Domain 4: Signal Coordination, Networks, & ATSPMs
12.1 Actuated Signal Controller Parameters (Passage Time, Gap Reduction, Max Recall) 12.2 Traffic Signal Coordination: Bandwidth, Offsets, & Progression Models 12.3 Traffic Responsive & Adaptive Traffic Signal Control Systems (ASCS) 12.4 Automated Traffic Signal Performance Measures (ATSPMs) & High-Resolution Data
13 Domain 4: Signing, Markings, Work Zones, Grade Crossings & School Zones (MUTCD)
13.1 MUTCD Regulatory, Warning, & Guide Signs Principles and Placement 13.2 Sign Retroreflectivity Standards & Nighttime Visual Maintenance 13.3 Longitudinal Pavement Markings, Delineators, & Object Markers 13.4 Temporary Traffic Control (TTC) & Work Zone Safety (MUTCD Part 6) 13.5 Highway-Rail Grade Crossings: Warning Devices, Preemption & Storage 13.6 School Zone Traffic Control & Student Walk Route Planning
14 Domain 5: Traffic Studies & Applied Statistical Methods
14.1 Applied Statistical Distributions & Sample Size Determination 14.2 Spot Speed Studies, 85th Percentile Speed, & 10-mph Pace 14.3 Volume Count Methodologies & Expansion Factoring (ADT, AADT, PHF)
15 Domain 5: Traffic Impact Studies & Trip Generation (ITE)
15.1 Travel Time, Delay, & Intersection Queue Studies 15.2 Parking Supply, Duration, & Turnover Analysis 15.3 Traffic Impact Study (TIS) Scoping, Horizon Years, & Mitigation 15.4 ITE Trip Generation Handbook: Average Rates vs. Regression Equations
16 Domain 6: Environmental, Institutional, Ethics & Equity Issues
16.1 Vehicle Emissions, Air Quality Conformity, & Decarbonization 16.2 Traffic Noise Modeling (TNM) & Noise Abatement Criteria (NAC) 16.3 Long-Range Transportation Planning & the NEPA Environmental Review 16.4 Professional Engineering Ethics, Tort Liability, & Risk Management 16.5 Transportation Equity, Access & Multimodal Community Considerations
12.4 Automated Traffic Signal Performance Measures (ATSPMs) & High-Resolution Data
Key Takeaways Explain This Topic AI
Automated Traffic Signal Performance Measures (ATSPMs) extract high-resolution (100 ms / 10 Hz) timestamped controller event logs to generate continuous, objective operational analytics.
The Indiana DOT / Purdue University protocol standardizes controller enumerations into 4-digit event codes (e.g., Event 1: Phase ON, Event 7: Phase Green Termination, Event 82: Detector ON).
Purdue Coordination Diagrams (PCDs) plot vehicle arrival timestamps against cycle time and green intervals over 24 hours, directly visualizing progression quality, Arrivals on Green (AoG), and platoon dispersion.
Platoon Ratio (R_p = PAG / (g/C)) quantifies coordination effectiveness; R_p > 1.33 indicates dense platoon arrivals on green (HCM Arrival Type 5/6), whereas R_p < 0.67 indicates poor coordination with platoon arrivals on red.
Purdue Split Failure (PSF) metrics detect unserved demand and phase starvation when Green Occupancy Ratio (GOR >= 80%) is combined with Red Occupancy Ratio in the first 5 seconds of red (ROR_5 >= 80%).
Last updated: August 2026
12.4 Automated Traffic Signal Performance Measures (ATSPMs) & High-Resolution Data
PTOE Exam Focus: ATSPMs and high-resolution controller data represent a major modern advancement in Domain 4. Candidates must understand high-resolution controller event logging (100 ms / 10 Hz timestamps), Purdue Coordination Diagrams (PCDs), Platoon Ratio calculations ( R p = PAG g / C R_p = \frac{\text{PAG}}{g/C} R p = g / C PAG ), Purdue Split Failure (PSF) metrics (GOR and ROR 5 \text{ROR}_5 ROR 5 ), phase termination diagnostics (Gap-Out, Max-Out, Force-Off), and the FHWA Every Day Counts (EDC-4) framework.
1. High-Resolution Controller Event Logging & The Indiana Protocol
Traditionally, traffic signal operations were evaluated using infrequent, labor-intensive manual floating-car travel time studies or isolated 24-hour turning movement counts. Automated Traffic Signal Performance Measures (ATSPMs) —developed by Purdue University and the Indiana Department of Transportation (INDOT), and championed under FHWA's Every Day Counts (EDC-4) initiative—revolutionized signal operations.
Modern traffic signal controllers log internal state transitions and external detector actuations at 100-millisecond ( 10 Hz 10\text{ Hz} 10 Hz ) resolution. Each logged entry contains:
Timestamp: Exact date and time to the nearest 0.1 second 0.1\text{ second} 0.1 second .
Event Code: Standardized integer enumeration representing the controller state change.
Event Parameter: Phase number, detector channel, or overlap ID associated with the event. +-----------------------------------------------------------------------------------+
- | SAMPLE HIGH-RESOLUTION CONTROLLER EVENT LOG (100 ms) |
- | |
- | Timestamp Event Code Parameter Description |
- | ------------------------------------------------------------------------------- |
- | 2026-08-14 07:15:02.100 1 2 Phase 2 Green ON |
- | 2026-08-14 07:15:04.300 82 12 Detector Channel 12 ON (Veh) |
- | 2026-08-14 07:15:04.700 81 12 Detector Channel 12 OFF |
- | 2026-08-14 07:15:32.400 7 2 Phase 2 Green Term (Gap-Out) |
- | 2026-08-14 07:15:32.400 8 2 Phase 2 Yellow ON |
- | 2026-08-14 07:15:36.900 11 2 Phase 2 Red ON |
- +-----------------------------------------------------------------------------------+
- 2. Purdue Coordination Diagrams (PCDs)
The Purdue Coordination Diagram (PCD) is the foundational ATSPM visualization for evaluating signal progression and coordination quality. A PCD plots individual vehicle arrivals (recorded at advance setback detectors, typically 300 to 500 ft 300\text{ to }500\text{ ft} 300 to 500 ft upstream) relative to the start of the coordinated phase green interval for every cycle over a 24 -hour 24\text{-hour} 24 -hour period. Cycle Time (s) ^
100 | . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . (Red Interval)
| . . . . . . . . . . . . . . . . . .
- 60 |----------------------------------------------------------------- (Yellow / Red Onset)
- | * * * * * * * * * * * * * * * * * * * * *
- | * * * * * * * * * * * * * * * * * * * * * * * <--- DENSE PLATOON ON GREEN
- 20 |---* * * * * * * * * * * * * * * * * * * * * * * * -------------- (Green Start)
- | . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . (Red Arrivals)
- 0 +-----------------------------------------------------------------> Time of Day (24h)
- 00:00 06:00 12:00 18:00 24:00
Key Information Extracted from PCDs:
Arrivals on Green (AoG) vs. Arrivals on Red (AoR): Dots falling between the green onset line and yellow onset line represent vehicles arriving during green; dots outside represent arrivals during red.
Platoon Cohesion & Offset Quality: A tight cluster of vehicle arrivals starting immediately after green onset indicates an optimal progression offset. A platoon arriving before green onset reveals an offset that is "too late," forcing the platoon to stop and clear as a standing queue.
3. Platoon Ratio ( R p R_p R p ) & Arrivals on Green (AoG)
The Platoon Ratio ( R p R_p R p ) —defined in the Highway Capacity Manual (HCM)—quantifies the degree of vehicle platoon clustering arriving during the green interval: R p = PAG g / C R_p = \frac{\text{PAG}}{g/C} R p = g / C PAG
Where:
PAG \text{PAG} PAG = Percent of vehicles Arriving on Green ( PAG = Arrivals on Green Total Cycle Arrivals \text{PAG} = \frac{\text{Arrivals on Green}}{\text{Total Cycle Arrivals}} PAG = Total Cycle Arrivals Arrivals on Green )
g / C g/C g / C = Effective green ratio of the coordinated phase (effective green time g g g divided by cycle length C C C )
HCM Arrival Type Classification Matrix:
Arrival Type Platoon Ratio ( R p R_p R p ) Coordination Quality Operational Description
Arrival Type 1 R p ≤ 0.50 R_p \le 0.50 R p ≤ 0.50 Very Poor Dense platoon arriving at the beginning of the red interval; severe offset error.
Arrival Type 2 0.50 < R p ≤ 0.85 0.50 < R_p \le 0.85 0.50 < R p ≤ 0.85 Unfavorable Unfavorable progression; majority of platoon arrives during red.
Arrival Type 3 0.85 < R p ≤ 1.15 0.85 < R_p \le 1.15 0.85 < R p ≤ 1.15 Random Isolated / uncoordinated operation; random vehicle arrivals.
Arrival Type 4 1.15 < R p ≤ 1.50 1.15 < R_p \le 1.50 1.15 < R p ≤ 1.50 Favorable Favorable progression; moderate platoon arriving during green.
Arrival Type 5 1.50 < R p ≤ 2.00 1.50 < R_p \le 2.00 1.50 < R p ≤ 2.00 Highly Favorable Dense platoon arriving at the beginning/middle of green band.
Arrival Type 6 R p > 2.00 R_p > 2.00 R p > 2.00 Exceptional Exceptional progression; entire platoon arrives unobstructed on green with zero queue.
4. Purdue Split Failure (PSF) Metric
A Split Failure occurs when a signal phase does not provide sufficient green time to clear the standing queue, causing unserved vehicles to wait across multiple red cycles. ATSPMs detect split failures using stop-bar detector occupancy data: Green Occupancy Ratio (GOR) = Time Detector Occupied During Green Total Green Duration \text{Green Occupancy Ratio (GOR)} = \frac{\text{Time Detector Occupied During Green}}{\text{Total Green Duration}} Green Occupancy Ratio (GOR) = Total Green Duration Time Detector Occupied During Green Red Occupancy Ratio in First 5s ( ROR 5 ) = Time Detector Occupied in First 5s of Red 5.0 seconds \text{Red Occupancy Ratio in First 5s } (\text{ROR}_5) = \frac{\text{Time Detector Occupied in First 5s of Red}}{5.0\text{ seconds}} Red Occupancy Ratio in First 5s ( ROR 5 ) = 5.0 seconds Time Detector Occupied in First 5s of Red Green Occupancy Ratio (GOR) ^
- 100% |-------------------------------+-------------------------------+
- | QUADRANT II: | QUADRANT I: |
- | Heavy Green Demand, | TRUE SPLIT FAILURE |
- | Queue Cleared at Yellow | GOR >= 80% AND ROR_5 >= 80% |
- 80% |===============================+===============================|
- | QUADRANT III: | QUADRANT IV: |
- | Undersaturated Demand, | Slow Clear / Trapped Veh |
- | Low Occupancy | (False Split Failure) |
- 0% +-------------------------------+------------------------------->
- 0% 80% 100%
- Red Occupancy Ratio in First 5s (ROR_5)
Split Failure Engineering Criterion:
A phase experiences a Purdue Split Failure if and only if: GOR ≥ 80 % AND ROR 5 ≥ 80 % \text{GOR} \ge 80\% \quad \text{AND} \quad \text{ROR}_5 \ge 80\% GOR ≥ 80% AND ROR 5 ≥ 80%
If GOR ≥ 80 % \text{GOR} \ge 80\% GOR ≥ 80% but ROR 5 < 80 % \text{ROR}_5 < 80\% ROR 5 < 80% , the phase was fully utilized but successfully dissipated the queue at the end of green (no split failure).
Persistent split failures during peak hours indicate inadequate green split allocation or downstream queue spillback blockage.
5. Purdue Phase Diagrams (PPDs) & Phase Termination Diagnostics
Purdue Phase Diagrams track the duration and termination type of every phase green interval over time. Controllers log three distinct termination modes:
Gap-Out (Code 7): Green terminated normally when vehicle headways exceeded the passage time timer. High gap-out % indicates sufficient capacity.
Max-Out (Code 6): Green reached its G max G_{\max} G m a x limit while vehicle calls were still actively extending the phase. High max-out % indicates oversaturation or split deficit.
Force-Off (Code 9): Coordinated controller forcibly terminated an actuated non-coordinated phase at its scheduled cycle ring boundary.
Indiana / Purdue High-Resolution Controller Event Enumeration Codes Reference
- Event Code Event Name Parameter Logged Engineering Diagnostic Function
- 1 Phase On (Green Start) Phase Number (1-16) Marks start of green interval for split and AoG calculations
7 Phase Green Termination (Gap-Out) Phase Number (1-16) Indicates phase ended due to passage timer expiration (adequate green)
6 Phase Green Termination (Max-Out) Phase Number (1-16) Indicates phase ended at G_max limit (capacity deficit / stuck loop)
9 Phase Green Termination (Force-Off) Phase Number (1-16) Indicates coordinated phase terminated at scheduled cycle boundary
- 8 Phase Yellow On Phase Number (1-16) Marks start of yellow change clearance interval
- 11 Phase Red On Phase Number (1-16) Marks start of red clearance interval
82 Detector On (Actuation) Detector Channel (1-64) Timestamp of vehicle arrival at advance or stop-bar detector
- 81 Detector Off (Clearance) Detector Channel (1-64) Timestamp of vehicle leaving detector (computes occupancy)
- 21 Pedestrian Walk On Pedestrian Phase (1-16) Calculates pedestrian service frequency and pedestrian delay
- 102 Preemption Call Active Preempt Channel (1-10) Tracks emergency vehicle preemption and railroad events
Loading diagram... Purdue Coordination Diagram (PCD) Arrival Tracking Architecture
HCM Platoon Ratio (Rp) Across Progression Quality Classifications
6. Worked Calculation Example: Platoon Ratio & Split Failure Diagnostic
Problem Statement:
A coordinated arterial intersection operates on a cycle length of C = 100 seconds C = 100\text{ seconds} C = 100 seconds . The coordinated Phase 2 through movement receives an effective green time of g = 40 seconds g = 40\text{ seconds} g = 40 seconds . High-resolution ATSPM advance detector data records 1 , 200 vehicles 1,200\text{ vehicles} 1 , 200 vehicles arriving on the approach during the peak hour, of which 780 vehicles 780\text{ vehicles} 780 vehicles arrive while the green indication is active.
Simultaneously, ATSPM stop-bar detector analysis on minor cross-street Phase 4 during a specific cycle shows:
- Phase 4 Green duration: G = 15 seconds G = 15\text{ seconds} G = 15 seconds
- Stop-bar detector occupied during green: 13.2 seconds 13.2\text{ seconds} 13.2 seconds
- Stop-bar detector occupied during first 5 seconds of red: 4.4 seconds 4.4\text{ seconds} 4.4 seconds
Calculate the green ratio ( g / C g/C g / C ) and the Percent of Arrivals on Green ( PAG \text{PAG} PAG ).
Compute the Platoon Ratio ( R p R_p R p ) and identify the corresponding HCM Arrival Type.
Compute the Green Occupancy Ratio ( GOR \text{GOR} GOR ) and Red Occupancy Ratio in the first 5 seconds ( ROR 5 \text{ROR}_5 ROR 5 ) for Phase 4, and determine if a Purdue Split Failure occurred.
Step-by-Step Solution:
Green Ratio ( g / C g/C g / C ) and Percent Arrivals on Green ( PAG \text{PAG} PAG ): g C = 40 s 100 s = 0.40 \frac{g}{C} = \frac{40\text{ s}}{100\text{ s}} = 0.40 C g = 100 s 40 s = 0.40 PAG = Arrivals on Green Total Arrivals = 780 veh 1200 veh = 0.65 (or 65.0 % ) \text{PAG} = \frac{\text{Arrivals on Green}}{\text{Total Arrivals}} = \frac{780\text{ veh}}{1200\text{ veh}} = 0.65\text{ (or }65.0\%\text{)} PAG = Total Arrivals Arrivals on Green = 1200 veh 780 veh = 0.65 (or 65.0% )
Platoon Ratio ( R p R_p R p ): R p = PAG g / C = 0.65 0.40 = 1.625 R_p = \frac{\text{PAG}}{g/C} = \frac{0.65}{0.40} = 1.625 R p = g / C PAG = 0.40 0.65 = 1.625
Assessment: Since 1.50 < R p ≤ 2.00 1.50 < R_p \le 2.00 1.50 < R p ≤ 2.00 , the approach operates at HCM Arrival Type 5 (Highly Favorable Progression with dense platoon arrival on green).
Phase 4 Split Failure Evaluation: GOR = 13.2 s 15.0 s = 0.88 = 88.0 % \text{GOR} = \frac{13.2\text{ s}}{15.0\text{ s}} = 0.88 = 88.0\% GOR = 15.0 s 13.2 s = 0.88 = 88.0% ROR 5 = 4.4 s 5.0 s = 0.88 = 88.0 % \text{ROR}_5 = \frac{4.4\text{ s}}{5.0\text{ s}} = 0.88 = 88.0\% ROR 5 = 5.0 s 4.4 s = 0.88 = 88.0%
Diagnostic: Since both GOR ≥ 80 % \text{GOR} \ge 80\% GOR ≥ 80% ( 88 % 88\% 88% ) and ROR 5 ≥ 80 % \text{ROR}_5 \ge 80\% ROR 5 ≥ 80% ( 88 % 88\% 88% ), Phase 4 experienced a verified Purdue Split Failure .