1 Introduction & Exam Overview

1.1 Current Exam Facts 1.2 Test-Day Tools, On-Screen References, and Calculators 1.3 CIRO vs CARO and the RETA Credential Path

2 IIAR and ASHRAE Standards

2.1 IIAR 2 and ASHRAE 15 Machinery-Room Design 2.2 IIAR 6 Inspection, Testing, and Maintenance 2.3 IIAR 7 Operating Procedures and IIAR 9 Existing Systems

3 OSHA Process Safety Management

3.1 PSM Applicability and the 14 Elements 3.2 Process Safety Information 3.3 Process Hazard Analysis 3.4 Operating Procedures, Training, Contractors, and PSSR

4 Integrity, Change, and Emergency Programs

4.1 Mechanical Integrity and Pressure-Relief Valves 4.2 Hot Work and Management of Change 4.3 Incident Investigation and Compliance Audits 4.4 Emergency Planning, EPA RMP, and the General Duty Clause

5 Ammonia Hazards and Machinery-Room Safety

5.1 Ammonia Properties, SDS, and Exposure Limits 5.2 Detection, Ventilation, and Emergency Shutdown 5.3 Eyewash, PPE, Materials Compatibility, and ASME B31.5 Piping

6 Three-Phase Motors and Starting

6.1 Three-Phase Motors, Nameplates, and FLA 6.2 Wye-Delta and Reduced-Voltage Starting 6.3 Voltage Unbalance 6.4 Single-Phasing, Rotation Checks, and Screw Compressors

7 Ladder Diagrams, VFDs, and Power

7.1 Ladder Diagrams, Seal-In Circuits, and Safety Interlocks 7.2 Variable-Frequency Drives in Refrigeration Plants 7.3 Power Factor, kW/HP, Overloads, and Machinery-Room Electrical Classification

8 Pressure-Enthalpy Diagrams and Properties

8.1 Reading the Ammonia P-h Diagram 8.2 Saturated Properties, psia vs psig, and Saturation Temperature 8.3 Superheat, Subcooling, and Flash Gas

9 Capacity, COP, and Efficiency

9.1 Enthalpy, Latent Heat, and Net Refrigerating Effect 9.2 COP, Tons of Refrigeration, and Heat Rejection Ratio 9.3 BHP/ton, Isentropic Efficiency, and Theoretical Discharge Temperature

10 Heat Transfer and Rejection

10.1 Q = UAΔT, LMTD, and Heat Exchangers 10.2 Condensers, Approach, and Wet-Bulb Limits 10.3 Specific Volume, Mass Flow, and Compression Ratio

11 System Screens and Performance KPIs

11.1 Using CIRO Operating Screens (normal vs abnormal) 11.2 kW/ton, BHP/ton, and KPI Dashboards 11.3 Power Cost, Demand Charges, and the Cost of Poor Operation

12 Approach, TD, and Oil-Cooling Diagnostics

12.1 Condenser Approach and Non-Condensables 12.2 Evaporator TD and Superheat Diagnostics 12.3 Thermosiphon Oil Coolers and Oil-Temperature Trends

13 Floating Head, Sequencing, and Slide Valves

13.1 Floating Head Pressure 13.2 Compressor Sequencing 13.3 Screw Slide-Valve Unloading and Feedback

14 Expansion Devices and DX Feed

14.1 Solenoid and TXV Pairs, Equalizers, and Hunting 14.2 Electronic Expansion Valves 14.3 Hand Expansion Valves and DX Coil Distribution

15 Pressure-Regulating and Pilot-Operated Valves

15.1 Back-Pressure Regulators 15.2 Crankcase Pressure Regulators and Gas-Pumped CPR Systems 15.3 Pilot-Operated Valves and High-to-Low Relief Regulators

16 Floats, Checks, Solenoid Failures, and Piping

16.1 High-Side Floats and High-Pressure Receivers 16.2 Check Valves, Discharge Checks, and Defrost Check Valves 16.3 Solenoid Failure Modes, Strainers, King Valves, and Ammonia Piping

17 Flooded and Liquid-Overfeed Basics

17.1 Flooded vs DX Advantages and Charge 17.2 Overfeed Ratios and Recirculation Rate 17.3 Surge Drums, Separators, and Wet Suction Returns

18 Pumps, Oil Management, and Level Control

18.1 Mechanical Liquid Pumps and NPSH 18.2 Oil Drain Pots, Rectifiers, and Thermosiphon Oil Management 18.3 Level Glasses, Float Switches, and High/Low Cutouts 18.4 Liquid-Line Sizing and High-/Low-Pressure Receivers

19 Two-Stage Compression and Intercoolers

19.1 Why Two-Stage: Compression Ratio and Discharge Temperature 19.2 Interstage Pressure Selection (Geometric Mean) 19.3 Open Flash Intercoolers 19.4 Closed Intercoolers and Two-Stage Troubleshooting

20 Cascade and Secondary Coolant Systems

20.1 NH3/CO2 Cascade Designs 20.2 Glycol and Brine Secondary Coolants (pH, freeze point, inhibitors) 20.3 Why Secondary Coolants and Glycol Testing/Maintenance

21 Evaporator Defrost

21.1 Hot-Gas Defrost Sequence 21.2 Defrost Drain Pressure-Relief Regulators and Soft Equalization 21.3 Time/Temperature Termination, Drain Pans, Water and Electric Defrost

20.3 Why Secondary Coolants and Glycol Testing/Maintenance

Key Takeaways Explain This Topic AI

Secondary loops keep ammonia (and often the entire vapor-compression charge) out of occupied production, shrink the ammonia inventory that lives in room coils, and let coil work proceed without ammonia pump-out.

The thermodynamic penalty is extra ΔT: ammonia must evaporate colder than the glycol, which is already colder than the room air, so compressor lift and BHP/ton rise.

Pump energy is real load—the kW becomes heat in the glycol—and brine/glycol chemistry is a second utility the plant must staff.

Plate-HX glycol chillers buy close approach in a small footprint; watch leaving-glycol minus ammonia-evaporating temperature, strainers, flow proving, and freeze-up of the pack if suction is pulled below the glycol freeze point.

Testing and maintenance are operations: log freeze point, pH, inhibitor, conductivity, makeup, and chiller approach; never use city-water makeup or mixed glycols to ‘fix’ a loop.

Last updated: September 2026

Direct ammonia in production coils is efficient: one ΔT from air to evaporating ammonia. Plants still install secondary coolant systems —and CIRO tests them—because ammonia in occupied space is the hazard that drives architecture, not the extra pump. This section is the why , the energy and temperature penalties , plate-heat-exchanger glycol chillers , and how glycol testing and maintenance (the chemistry in 20.2) become an operating discipline instead of a forgotten drum on the mezzanine.

Why plants accept a secondary loop

Keep ammonia out of occupied and production areas. A coil leak in a packaging room is then glycol or brine, not an anhydrous ammonia release over people and product. Detectors, evacuation, and product hold still exist for the engine room; they are not triggered by every pinhole in a production coil. That is the same logic as NH3/CO2 cascade, with a pumped liquid instead of a second vapor-compression circuit.

Smaller ammonia charge. The ammonia inventory lives in the chiller package, vessels, and high side in the machinery room. Production coils are full of glycol, not R-717. Charge reduction can be part of staying closer to—or in some designs under—the 10,000 lb PSM/RMP threshold. Count pounds. A large flooded chiller and condenser still add up. Secondary is not a magic exemption from IIAR 2 or PSM if you remain above threshold.

Simpler coil maintenance. Production air units can be washed, gasketed, or isolated and drained without hot work and ammonia pump-out on every coil job. Valve stations in the room are glycol valves. That matters in food plants that open coolers for sanitation constantly.

Freeze protection. Water coils freeze and split. Inhibited glycol (or brine) lets room coils and piping sit below 32°F. Blast cells and dock coils that see below-freezing air need a freeze point below the lowest fluid temperature , not a 20% mix that only burst-protects a rooftop coil in winter.

Glycol coils typically defrost with water, electric, or warm glycol , not ammonia hot gas in the occupied space. Defrost sequence details are Chapter 21; the architectural point is that you moved the ammonia phase-change out of the room .

Cascade, two-stage, and secondary are three answers to the same cold-product problem. Cascade puts CO2 in the rooms. Two-stage puts ammonia in the rooms with a better compression ratio. Secondary puts pumped liquid in the rooms and keeps the phase-change in the engine room. CIRO expects you to pick the architecture that matches the hazard, then operate the extra ΔT, the extra pumps, and the extra chemistry as if they were as important as suction pressure—because they are.

The penalties you pay

Secondary is not free refrigeration.

Extra ΔT (colder ammonia). Heat must cross two exchangers: process air to glycol in the room coil, then glycol to ammonia (or CO2) in the chiller. Each has an approach. If the room needs 20°F air, glycol may leave the coil at 12°F, and ammonia may need to evaporate at 5°F or lower depending on the plate chiller. Direct ammonia might have evaporated at 10–12°F for the same air. Colder suction is more compressor work (higher specific volume, more BHP/ton). Operators who fix a warm room by dropping the chiller setpoint without checking glycol flow, approach, and freeze point are often hiding a dirty plate pack or a weak mix.

Work a stacked-approach example (illustrative). Air off the coil must be 0°F. Coil TD is 10°F, so glycol enters the coil near −10°F. The return glycol is −4°F. The plate chiller holds 6°F approach, so ammonia evaporates near −16°F . A direct ammonia coil with the same 10°F TD might have evaporated near −10°F . That extra 6°F of ammonia lift is the secondary penalty before you even turn the pumps on. If the pack fouls and approach opens to 12°F, ammonia is at −22°F and the screw is doing blast-freezer work to hold a cooler.

Pump energy. Circulating pumps add kW on the electric bill and dump that energy into the glycol as heat . Oversized pumps, missing VFDs, balancing valves wide open, and 50% PG at −10°F all inflate that penalty. Pump heat is load the chiller must remove. A round that ignores pump amps while staring at compressor kW/ton is missing half the secondary plant.

Brine and glycol maintenance. Chemistry, strainers, expansion tanks, air elimination, and leak cleanup are a second utility. A neglected loop fouls the chiller, corrodes pumps, and eventually freezes a coil. The maintenance cost is why some owners stay with direct ammonia and accept IIAR 2 evaporators in the rooms.

  • Item Direct NH3 coils Secondary glycol/brine
  • Refrigerant in occupied coils Ammonia None (coolant only)
  • Typical extra plant ΔT Coil TD only Coil TD plus chiller approach
  • Production leak Ammonia Glycol/brine (messy; not an NH3 release in the room)
  • Coil service Ammonia isolation, pump-out Drain/flush coolant; no NH3 in the coil
  • Added energy No coolant pump Pump kW plus extra compressor lift
  • Plate heat-exchanger glycol chillers

The engine-room machine that makes secondary work is usually an ammonia-to-glycol chiller . Gasketed plate heat exchangers (PHEs) dominate new installs because they are compact and can hold close approach (a few degrees Fahrenheit when clean and correctly selected).

Common industrial arrangements:

Gasketed PHE: both sides gasketed; can be opened for cleaning. Elastomers must be compatible with ammonia and the glycol. Wrong gaskets swell or crack.

Semi-welded (cassette) PHE: ammonia in welded channels, glycol in gasketed channels. A gasket failure dumps glycol, not ammonia, into the area around the pack—the usual reason food plants pay for cassettes.

Shell-and-tube flooded chiller: still common; larger ammonia charge in the shell; oil drainage like any flooded evaporator (oil sinks in ammonia).

Close approach is the sales pitch and the operating KPI. Leaving glycol temperature minus ammonia evaporating temperature is the chiller ΔT. If that number opens over months, suspect fouling, oil on the ammonia plates, air in the glycol, low glycol flow, or a freeze-point mix so viscous the plates cannot wet. Do not crank ammonia suction down as the first move; you risk freezing glycol in the pack if local plate temperature goes below the freeze point. A glycol freeze in a PHE can split plates—the same catastrophe as a water-chiller freeze, except you also dump glycol into the ammonia side or ammonia into the glycol side depending on which channel fails.

Plate chillers need strainers ahead of the pack, air separators , a closed expansion tank sized for the loop, and flow proving so the ammonia feed cannot pull the pack below freeze without flow. Low-flow is a freeze interlock, not a suggestion. Hydrostatic relief belongs on any isolatable liquid-full glycol volume and on the ammonia side if valves can trap liquid. Opening a pack that still has ammonia pressure is an incident, not a cleaning method.

On a CIRO operating screen, a secondary plant should show glycol supply and return temperatures, pump status or differential, chiller approach, and ammonia suction. A warm room with small glycol ΔT and high pump ΔP is a flow or air-bound problem. A warm room with large glycol ΔT and wide chiller approach is a dirty or oil-filmed pack, weak mix, or starved ammonia feed. Those two pictures are not the same setpoint chase.

Testing and maintenance as operations, not chemistry class

Section 20.2 is the lab sheet. The operator job is to run the program .

Keep a log : freeze point, pH, inhibitor, conductivity, makeup gallons, and chiller approach. CIRO-style what is wrong with this screen items are often a rising chiller approach with a falling freeze point after weeks of silent city-water makeup.

Sample from a flowing header , not a dead leg. Label EG vs PG so the lab uses the right table.

Never mix leftover glycol types to correct freeze point. Dump and recharge if the loop was cross-contaminated.

Treat expansion-tank level and automatic makeup as mechanical-integrity items. Blind city-water makeup is how freeze protection disappears.

After a production-coil leak, glycol in the drain is both a sanitation event and a concentration event: you lost fluid, then added water. Retest before you declare the freezer ready.

PHE service: isolate, relieve trapped liquid (glycol hydrostatic and ammonia hydrostatic are both real), follow lockout, and do not open a pack that still has ammonia pressure.

If inhibitor is depleted but freeze point is still correct, add inhibitor only as the vendor directs —many packages are not a grocery-store additive you dump until pH looks pretty. If chlorides, iron, or biological counts are out of band, the loop may need a controlled dump and recharge , not another drum of neat glycol. Premix at the specified concentration. Record what you did. The next operator, and the next PHA, should be able to see that the secondary system was treated as process equipment, not as a plumbing afterthought.

Secondary does not retire ammonia skill. The chiller is still an ammonia evaporator with oil, level, expansion devices, and relief. What you gained is that a failed production coil is a glycol event. What you must not give back is a frozen plate pack, a mixed-glycol science experiment, or an unmanned makeup line that quietly turns a −20°F freezer loop into 15% water.

Loading diagram... Indirect glycol system: ammonia stays in the machinery-room chiller

Illustrative stacked temperatures (°F) — extra ammonia lift from a secondary loop