Study guide

11.6 Doors, Windows, Hardware & Interior Finishes

South Carolina General Contractor Exam

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: South Carolina Licensing Law & Board Regulations

1.1 Licensing Framework, Classifications & Scope 1.2 License Groups 1-5, Financial Limits & Bond Requirements 1.3 Qualifying Parties, Renewals & Enforcement Penalties

2 Chapter 2: Business Organization & Financial Management

2.1 Business Entities & South Carolina Registration 2.2 Construction Accounting Methods & Financial Statements 2.3 Tax Compliance: Payroll, Sales/Use & State Requirements

3 Chapter 3: Estimating, Bidding & Public Procurement

3.1 Quantity Takeoffs, Cost Classification & Overhead Allocation 3.2 Bid Preparation, Markup Calculation & Margin Analysis 3.3 Public Bidding & South Carolina Procurement Code

4 Chapter 4: Construction Contracts & Risk Allocation

4.1 Contract Types & Project Delivery Systems 4.2 Standard Contract Provisions & Risk Allocation 4.3 Change Orders, Claims, Delays & Dispute Resolution

5 Chapter 5: South Carolina Mechanics' Lien Law & Payment Rights

5.1 Mechanics' Lien Rights, Scope & Priority in South Carolina 5.2 Notice of Project Commencement & Notice of Furnishing 5.3 Lien Perfection, Foreclosure Deadlines & Prompt Pay Act

6 Chapter 6: Insurance & Surety Bonding

6.1 Commercial General Liability, Builders Risk & Property Coverage 6.2 Workers' Compensation & Statutory Employer Rules in South Carolina 6.3 Surety Bonds: Bid, Performance, Payment & The Little Miller Act

7 Chapter 7: Project Management, Scheduling & Quality Control

7.1 Project Administration, Submittals & Communication Protocols 7.2 CPM Scheduling: Critical Path, Float & Schedule Control 7.3 Quality Assurance, Inspection Standards & Project Closeout

8 Chapter 8: Labor Regulations & Environmental Compliance

8.1 Wage and Hour Laws, FLSA & Worker Classification 8.2 South Carolina Employment Laws, I-9 & Workplace Standards 8.3 Environmental Compliance: Stormwater, Lead RRP & Asbestos

9 Chapter 9: OSHA Safety Standards & Recordkeeping

9.1 OSHA Regulatory Framework, Inspections & Form 300 Recordkeeping 9.2 OSHA Focus Four Hazards & Jobsite Protection Standards 9.3 Excavations, Scaffolding & Fall Protection in Construction

10 Chapter 10: Site Work, Foundations, Concrete & Masonry

10.1 Site Preparation, Soil Mechanics & Foundation Systems 10.2 Concrete Construction, Mix Specifications & Quality Control 10.3 Masonry Materials, Mortar Types & Structural Masonry Walls

11 Chapter 11: Structural Framing, Carpentry, Building Envelope, Finishes & South Carolina Building Codes

11.1 Structural Steel, Heavy Timber & Framing Systems 11.2 Commercial Roofing, Thermal Insulation & Moisture Protection 11.3 South Carolina Building Code: Occupancy & Construction Types 11.4 Means of Egress, Fire Protection & Accessibility Standards 11.5 Wood Framing, Trusses & Carpentry 11.6 Doors, Windows, Hardware & Interior Finishes

11.6 Doors, Windows, Hardware & Interior Finishes

Key Takeaways Explain This Topic AI

Door hand is read from the outside or secure side: hinges on the left with the door swinging away is left-hand, and a door that swings toward you is a reverse (LHR or RHR).

Door and hardware practice calls for one hinge per 30 inches of door height, so a standard 7-foot door takes three hinges; BHMA Grade 1 hardware is the heaviest commercial duty.

NFPA 80 fire door assemblies must be labeled, self-closing, and positive-latching, with no more than 3/4 inch under the door, and they must be inspected at least annually.

IBC Section 2406 requires safety glazing in hazardous locations, including glazing in doors, glazing near doors, and large low panes next to walking surfaces.

Gypsum board finish Level 4 is the usual choice for flat paint, and Level 5 (a full skim coat) is used for gloss finishes or critical lighting (GA-214).

Last updated: September 2026

Where These Topics Appear

The PSI Limited Building Contractor outline has Doors and Windows (2 items) and Finishes (2 items) . The NASCLA unlimited exam tests the same subjects more heavily, as Doors, Windows and Glazing and as Finishes. Questions are practical: identify a door hand, count hinges, spot a hazardous glazing location, pick the right gypsum board, or name a drywall finish level.

  • Doors and Frames
  • Door types

Hollow metal steel doors and frames are graded by ANSI/SDI A250.8 duty levels: Level 1 standard duty (20-gauge faces), Level 2 heavy duty (18-gauge), Level 3 extra heavy duty (16-gauge), and Level 4 maximum duty.

Wood doors are flush solid-core (particleboard, structural composite lumber, or mineral core for fire ratings), flush hollow-core (light interior use), or stile-and-rail.

Aluminum storefront entrances are part of storefront systems (Section 11.2).

Door handing is read from the outside , which is the key or secure side:

  • Hinges on Door swings Hand
  • Left Away from you (inward) Left hand (LH)
  • Right Away from you (inward) Right hand (RH)
  • Left Toward you (outward) Left hand reverse (LHR)
  • Right Toward you (outward) Right hand reverse (RHR)
  • Hinges and hardware

Hardware practice calls for one hinge for every 30 inches of door height, or fraction of it . Doors up to 60 inches take two hinges, doors over 60 up to 90 inches take three, and doors over 90 up to 120 inches take four. A standard 3'-0" x 7'-0" door gets three hinges , typically 4-1/2" x 4-1/2" on a 1-3/4-inch door.

ANSI/BHMA A156 grades hardware for durability: Grade 1 is heavy commercial, Grade 2 light commercial, and Grade 3 residential.

Accessible doors need hardware that works without tight grasping, pinching, or twisting , such as levers or push bars, mounted 34 to 48 inches above the floor .

Fire door assemblies (NFPA 80)

The door, frame, hinges, latch, and closer must all be labeled or listed for the rating.

The door must be self-closing or automatic-closing and positive-latching .

Clearance under the door may not exceed 3/4 inch . Clearance at the head and jambs of steel doors is about 1/8 inch .

Field modifications not permitted by NFPA 80 or the labeling agency, such as enlarging vision lites or cutting in extra hardware preps, can void the label .

Fire door assemblies must be inspected and tested at least annually , and the results documented.

Windows and Glazing

Installing a flanged window in a water-resistive barrier (WRB) follows a shingle-lap sequence, so water that gets behind the cladding is always directed outward:

Install the sill flashing or sill pan first.

Set the window and fasten its flanges.

Apply jamb flashing over the side flanges.

Apply head flashing over the top flange.

Lap the WRB over the head flashing . Leave the bottom flange unsealed so the sill can drain.

Performance labels

NFRC labels report the U-factor (lower means better insulation) and the solar heat gain coefficient (SHGC) . A low SHGC matters in South Carolina's cooling-dominated Climate Zone 3.

Window performance classes and design-pressure grades are rated under AAMA/WDMA/CSA 101/I.S.2/A440 .

Safety glazing (IBC 2406) is required in hazardous locations. Tempered or laminated glazing must meet CPSC 16 CFR 1201 or ANSI Z97.1 and carry a permanent identifying mark. Hazardous locations include:

  • glazing in swinging, sliding, and bifold doors
  • glazing within a 24-inch arc of a door edge when its bottom edge is less than 60 inches above the floor

an individual pane larger than 9 square feet , with its bottom edge less than 18 inches and top edge more than 36 inches above the floor, and a walking surface within 36 inches horizontally (all four conditions)

glazing in guards and railings , in wet areas such as tub and shower enclosures, and next to stairways and ramps

Wind-borne debris regions (IBC 1609.2): In areas where the ultimate design wind speed is 130 mph or more within one mile of the coastal mean high-water line , or 140 mph or more anywhere , exterior glazing must be impact-resistant or protected by approved shutters. Impact resistance is tested under ASTM E1996 and E1886. Much of coastal South Carolina falls in these regions.

  • Interior Finishes
  • Gypsum board (ASTM C1396)

1/2-inch regular board is used for general walls.

5/8-inch Type X , a gypsum core with glass fibers, is used where a fire-resistance rating is required. Follow the tested assembly listing exactly.

Moisture- and mold-resistant board suits humid areas. Showers and other wet tile areas need cement board (ASTM C1325) or another tile backer.

A typical single-layer layout puts screws 12 inches on center on ceilings and 16 inches on center on walls with framing at 16 inches on center. Fire-rated listings may require closer spacing.

Finish levels (GA-214)

  • Level Treatment Typical use
  • 0 No taping Temporary work
  • 1 Tape set in compound Above ceilings, plenums
  • 2 Tape plus one coat Tile substrate, garages, warehouses
  • 3 Two coats Heavy textures
  • 4 Three coats on joints and fasteners Flat paint, light textures (most common)
  • 5 Level 4 plus a skim coat over the whole surface Gloss or semi-gloss paint, critical lighting
  • Suspended acoustical ceilings (ASTM C635 and C636)

Main runners hang from wires of at least 12 gauge , typically spaced no more than 4 feet on center along the runners.

Buildings in higher seismic design categories, which include parts of the Charleston area, need the ASTM E580 seismic installation details.

Floors, tile, and coatings

Test slab moisture before installing resilient flooring. Methods include in-situ relative humidity probes ( ASTM F2170 ) and calcium chloride tests ( ASTM F1869 ), checked against the flooring manufacturer's limits.

Tile installation follows ANSI A108/A118 and the TCNA Handbook. Ceramic tile floors generally need a substrate no more flexible than L/360 , and natural stone L/720 .

Paint and coatings depend on surface preparation and the specified dry-film thickness in mils . Check it with a wet-film gauge, where dry film equals wet film times the coating's volume solids.

Loading diagram... Flanged Window Flashing Sequence