Study guide
13.1 General Lighting and Receptacle Load
Texas Journeyman Electrician License Exam Exam
Track your progress as you read
Finished sections get a check mark.
1 Introduction & Exam Overview
1.1 About the Texas Journeyman Electrician Exam 1.2 The Two-Part Exam Format (Knowledge + Calculations) 1.3 Eligibility, Application & Scheduling
2 NEC Structure & Navigation
2.1 Key NEC Definitions (Article 100) 2.2 How the NEC is Organized 2.3 NEC Index and Quick Lookup Strategies 2.4 Reading Electrical Plans, Symbols, and Schedules
3 Electrical Theory & Fundamentals
3.1 Ohm's Law, Power, and Series/Parallel Circuits 3.2 Conductors, Resistance, and Voltage Drop 3.3 Three-Phase Systems and Power Factor
4 Services & Service Equipment
4.1 Service Entrance Conductors and Service Point 4.2 Service Disconnecting Means 4.3 Grounding Electrode Systems for Services 4.4 Service Load Calculations
5 Separately Derived Systems & Feeders
5.1 Separately Derived Systems 5.2 Feeder Sizing, Ampacity, and Tap Rules 5.3 Feeder Load Calculations
6 Branch Circuits & Receptacles
6.1 Branch Circuit Sizing and Conductor Selection 6.2 Receptacle Spacing and Required Outlets 6.3 GFCI and AFCI Requirements 6.4 Lighting Outlets and Switch-Controlled Circuits
7 Overcurrent Protection
7.1 Overcurrent Principles and OCPD Types 7.2 Small-Conductor and Continuous-Load Rules 7.3 Motor Overcurrent and Short-Circuit Protection
8 Wiring Methods, Conductors & Boxes
8.1 Wiring Methods and Raceways 8.2 Conductor Insulations and Ampacity 8.3 Conduit and Raceway Fill 8.4 Boxes and Box Fill 8.5 Cable Trays and Underground Wiring 8.6 Cabinets, Cutout Boxes, and Panelboards
9 Equipment Grounding & Bonding
9.1 Equipment Grounding Conductors 9.2 Bonding & the Effective Ground-Fault Current Path 9.3 Equipment and Box Grounding Connections
10 Equipment, Devices & Transformers
10.1 Luminaires and Lighting (NEC Article 410) 10.2 Switches and Device Wiring (NEC Articles 404 & 400) 10.3 Appliances and Utilization Equipment (NEC Articles 422 & 424) 10.4 Transformers (NEC Article 450) 10.5 Working Space and Equipment Access (NEC 110.26)
11 Motors & Generators
11.1 Motor Branch Circuits & Conductors 11.2 Motor Disconnects, Controllers & Starters 11.3 Generators & Emergency Systems
12 Control Devices & Disconnecting Means
12.1 General Disconnecting Means Principles 12.2 HVAC and Refrigeration Disconnects 12.3 Motor Control Circuits and VFDs
13 Dwelling Load Calculations
13.1 General Lighting and Receptacle Load 13.2 Appliance, Range, and Dryer Load 13.3 Neutral Load and Service Sizing
14 Commercial & Advanced Calculations
14.1 Commercial Lighting and Receptacle Load 14.2 Continuous Loads and Equipment Demand 14.3 Voltage Drop and Conductor Sizing 14.4 Commercial Building Load Capstone
15 Special Occupancies & Conditions
15.1 Hazardous (Classified) Locations — NEC Articles 500–506 15.2 Health Care Facilities — NEC Article 517 15.3 Pools, Spas, and Fountains — NEC Article 680 (Beyond GFCI) 15.4 Other Specific Occupancies — A Survey 15.5 Data Processing Rooms and Communications Systems
16 Renewable Energy Technologies
16.1 Solar PV Systems (Article 690) 16.2 Energy Storage and EV Charging (Articles 706, 625)
17 Exam Strategy & Final Review
17.1 Time Management and NEC Lookup Speed 17.2 Test Day and Final Practice
13.1 General Lighting and Receptacle Load
Key Takeaways Explain This Topic AI
2026 NEC 120.41 sets the dwelling general-lighting unit load at 2 VA per square foot, computed from outside floor dimensions excluding open porches and unfinished areas not adaptable for future use.
NEC 120.52(A) assigns 1500 VA to each 20 A small-appliance branch circuit (minimum 2 circuits); 120.52(B) assigns 1500 VA to the 20 A laundry branch circuit.
General lighting, small-appliance, and laundry loads are summed BEFORE the Table 120.45 dwelling demand factors are applied — never apply the factors to lighting alone.
Table 120.45 dwelling demand factors: first 3000 VA at 100%, 3001–120000 VA at 35%, over 120000 VA at 25%.
For a 2000 sq ft dwelling with 2 small-appliance circuits and 1 laundry circuit, the demand-factored general-lighting load is 4925 VA (8500 VA before demand factors).
Last updated: October 2026
Why This Matters for the TX Journeyman Exam
Dwelling load calculations are the heart of the exam's Calculations part (26 questions, 110 minutes). The standard method for a single-family dwelling is governed by NEC Article 120, Part III (Feeders and Services — Dwelling). Every service-load question on the exam starts with the same three building blocks: general lighting, small-appliance circuits, and the laundry circuit. Get the first step wrong and every downstream number — feeder size, service-disconnect rating, conductor selection — is wrong too.
This chapter covers single-family dwellings only . Multifamily demand factors (Table 120.84) are covered in Chapter 5. Service-disconnect rules (230.70–230.79) and OCPD standard ratings (240.6(A)) are covered in Chapters 4 and 7 — referenced here, not re-taught.
General Lighting Unit Load — NEC 120.41
For a dwelling feeder or service calculation, 2026 NEC 120.41 uses 2 VA per square foot . This is separate from 120.13 , which retains 3 VA per square foot for determining the minimum number of general-purpose dwelling branch circuits. Do not use the service-load density to reduce the required circuit count.
For example, a 2,000 ft² dwelling has a 4,000 VA lighting/receptacle component for its feeder or service calculation. Its minimum general-purpose branch-circuit calculation instead starts with 6,000 VA: at 120 V that is 50 A, requiring four 15 A circuits or three 20 A circuits when rounded up. The specifically required small-appliance, laundry, bathroom and garage circuits are additional.
Floor Area — What Counts and What Does Not
The floor area is computed from the outside dimensions of each floor (the building footprint), not interior room measurements. Under 2026 NEC 120.5(C), the following spaces are excluded from the dwelling floor area:
- Open porches
- Unfinished areas not adaptable for future use as a habitable room or occupiable space, such as an unused attic
- Detached garages (stated explicitly in 2026 NEC 120.5(C))
An attached garage is included . Use the floor-area exclusions in the current edition rather than a remembered rule from an older book.
Space Included in floor area?
- Living areas, bedrooms, kitchens, bathrooms Yes
- Finished basement (habitable) Yes
- Open porches No
- Attached garage Yes
- Detached garage No
- Unfinished basement adaptable for future use Yes
- Unused attic not adaptable for future use No
- Formula: General lighting load (VA) = floor area (ft²) × 2 VA/ft²
- Small-Appliance and Laundry Loads — NEC 120.52
- 120.52(A) — Small-Appliance Circuit Load
A dwelling unit requires a minimum of two 20 A small-appliance branch circuits serving the kitchen, dining room, pantry, and similar areas (per 210.11(C)(1)). NEC 120.52(A) assigns each small-appliance branch circuit a load of 1500 VA .
- Minimum: 2 circuits × 1500 VA = 3000 VA
- Additional small-appliance circuits (beyond the minimum 2) each add 1500 VA
- 120.52(B) — Laundry Circuit Load
A dwelling requires at least one 20 A laundry branch circuit (per 210.11(C)(2)). NEC 120.52(B) assigns this circuit a load of 1500 VA .
The Critical Combination Rule
NEC 120.52 states that the small-appliance and laundry loads are combined with the general lighting load before the Table 120.45 demand factors are applied. A common exam error is applying Table 120.45 to the general lighting alone and then adding the small-appliance and laundry loads afterward — that understates the demand-factored load.
Table 120.45 — Dwelling Lighting-Load Demand Factors
Once the general lighting + small-appliance + laundry loads are summed, the Table 120.45 demand factors are applied to the combined total. The brackets for dwelling units are:
- Portion of Load (VA) Demand Factor
- First 3000 VA 100%
- 3001 – 120000 VA 35%
- Over 120000 VA 25%
These demand factors recognize that not every lighting and receptacle load in a dwelling operates simultaneously. The 35% bracket covers the vast majority of single-family homes — only very large dwellings exceed 120000 VA in the combined lighting/small-appliance/laundry subtotal.
Worked Example: 2000 sq ft Single-Family Dwelling
Given: A 2000 sq ft single-family dwelling with 2 small-appliance branch circuits and 1 laundry branch circuit.
Step 1 — General lighting load:
- Formula: floor area × 2 VA/ft²
- Substitution: 2000 ft² × 2 VA/ft² = 4000 VA
Step 2 — Small-appliance load (120.52(A)):
2 circuits × 1500 VA = 3000 VA
Step 3 — Laundry load (120.52(B)):
1 circuit × 1500 VA = 1500 VA
Step 4 — Combined subtotal (before demand factors):
4000 + 3000 + 1500 = 8500 VA
Step 5 — Apply Table 120.45 demand factors:
- Portion VA Demand Factor Demand Load
- First 3000 VA 3000 100% 3000 VA
- Remaining 5500 VA 5500 35% 1925 VA
- Total 8500 4925 VA
Arithmetic check on the remainder: 8500 − 3000 = 5500 VA; 5500 × 0.35 = 1925 VA.
Result: The demand-factored general-lighting load for this dwelling is 4925 VA . This number carries forward to the total service-load calculation in Section 13.3.
Exam Trap: Forgetting to Combine Before Applying Demand Factors
If you applied Table 120.45 to only the 4000 VA general-lighting load, you would get:
- First 3000 @ 100% = 3000 VA
- Remaining 1000 @ 35% = 350 VA
- Subtotal = 3350 VA
- Then add small-appliance (3000) + laundry (1500) = 7850 VA
That answer (7850 VA) is wrong — it overstates the load because the demand factors must be applied to the combined 8500 VA, not to lighting alone. The correct answer is 4925 VA.