Study guide

7.2 Small-Conductor and Continuous-Load Rules

Texas Journeyman Electrician License Exam Exam

Track your progress as you read

Finished sections get a check mark.

1 Introduction & Exam Overview

1.1 About the Texas Journeyman Electrician Exam 1.2 The Two-Part Exam Format (Knowledge + Calculations) 1.3 Eligibility, Application & Scheduling

2 NEC Structure & Navigation

2.1 Key NEC Definitions (Article 100) 2.2 How the NEC is Organized 2.3 NEC Index and Quick Lookup Strategies 2.4 Reading Electrical Plans, Symbols, and Schedules

3 Electrical Theory & Fundamentals

3.1 Ohm's Law, Power, and Series/Parallel Circuits 3.2 Conductors, Resistance, and Voltage Drop 3.3 Three-Phase Systems and Power Factor

4 Services & Service Equipment

4.1 Service Entrance Conductors and Service Point 4.2 Service Disconnecting Means 4.3 Grounding Electrode Systems for Services 4.4 Service Load Calculations

5 Separately Derived Systems & Feeders

5.1 Separately Derived Systems 5.2 Feeder Sizing, Ampacity, and Tap Rules 5.3 Feeder Load Calculations

6 Branch Circuits & Receptacles

6.1 Branch Circuit Sizing and Conductor Selection 6.2 Receptacle Spacing and Required Outlets 6.3 GFCI and AFCI Requirements 6.4 Lighting Outlets and Switch-Controlled Circuits

7 Overcurrent Protection

7.1 Overcurrent Principles and OCPD Types 7.2 Small-Conductor and Continuous-Load Rules 7.3 Motor Overcurrent and Short-Circuit Protection

8 Wiring Methods, Conductors & Boxes

8.1 Wiring Methods and Raceways 8.2 Conductor Insulations and Ampacity 8.3 Conduit and Raceway Fill 8.4 Boxes and Box Fill 8.5 Cable Trays and Underground Wiring 8.6 Cabinets, Cutout Boxes, and Panelboards

9 Equipment Grounding & Bonding

9.1 Equipment Grounding Conductors 9.2 Bonding & the Effective Ground-Fault Current Path 9.3 Equipment and Box Grounding Connections

10 Equipment, Devices & Transformers

10.1 Luminaires and Lighting (NEC Article 410) 10.2 Switches and Device Wiring (NEC Articles 404 & 400) 10.3 Appliances and Utilization Equipment (NEC Articles 422 & 424) 10.4 Transformers (NEC Article 450) 10.5 Working Space and Equipment Access (NEC 110.26)

11 Motors & Generators

11.1 Motor Branch Circuits & Conductors 11.2 Motor Disconnects, Controllers & Starters 11.3 Generators & Emergency Systems

12 Control Devices & Disconnecting Means

12.1 General Disconnecting Means Principles 12.2 HVAC and Refrigeration Disconnects 12.3 Motor Control Circuits and VFDs

13 Dwelling Load Calculations

13.1 General Lighting and Receptacle Load 13.2 Appliance, Range, and Dryer Load 13.3 Neutral Load and Service Sizing

14 Commercial & Advanced Calculations

14.1 Commercial Lighting and Receptacle Load 14.2 Continuous Loads and Equipment Demand 14.3 Voltage Drop and Conductor Sizing 14.4 Commercial Building Load Capstone

15 Special Occupancies & Conditions

15.1 Hazardous (Classified) Locations — NEC Articles 500–506 15.2 Health Care Facilities — NEC Article 517 15.3 Pools, Spas, and Fountains — NEC Article 680 (Beyond GFCI) 15.4 Other Specific Occupancies — A Survey 15.5 Data Processing Rooms and Communications Systems

16 Renewable Energy Technologies

16.1 Solar PV Systems (Article 690) 16.2 Energy Storage and EV Charging (Articles 706, 625)

17 Exam Strategy & Final Review

17.1 Time Management and NEC Lookup Speed 17.2 Test Day and Final Practice

7.2 Small-Conductor and Continuous-Load Rules

Key Takeaways Explain This Topic AI

NEC 240.4(D) caps OCPD at 15 A for 14 AWG copper, 20 A for 12 AWG copper, and 30 A for 10 AWG copper; aluminum one size larger (12 AWG AL = 15 A, 10 AWG AL = 20 A, 8 AWG AL = 30 A).

240.4(D) does not apply to motors (430 Part XIII), A/C and refrigeration (440), or welders — those articles override the small-conductor cap.

240.4(B) next-size-up is allowed only when the conductor ampacity does not equal a standard OCPD rating and the next lower standard rating is the limit — you round UP, never down, and only one step.

Continuous loads require the OCPD and conductors to be sized at 125% of the continuous portion under 210.19(A) and 210.20(A).

Tap rules under 240.21 allow shorter conductor runs (10 ft, 25 ft, and the 800 A+ high-fault tap) to be sized smaller than the upstream OCPD.

Last updated: August 2026

Why This Matters for the TX Journeyman Exam

The Calculations part of the Texas Journeyman exam almost always includes one or two questions that hinge on 240.4(D) small-conductor limits and one or two on the 240.4(B) next-size-up rule. The Knowledge part tests the exceptions to 240.4(D). Miss the distinction between (B) and (D) and you will mis-size feeders and branch circuits across the entire exam.

NEC 240.4(A) — The General Rule

NEC 240.4(A) states the general rule: conductors shall be protected against overcurrent in accordance with their ampacities specified in 310.14. That sets the baseline — the OCPD rating cannot exceed the conductor ampacity — and 240.4(B), (D), and the tap rules in 240.21 are all exceptions and refinements to that general rule.

NEC 240.4(D) — Small-Conductor Limits

240.4(D) sets hard maximum OCPD sizes for small conductors, regardless of the ampacity shown in Table 310.16. The rule applies to copper and aluminum at the sizes listed.

  • Conductor Copper Aluminum/CU-Clad AL
  • 14 AWG 15 A —
  • 12 AWG 20 A 15 A
  • 10 AWG 30 A 20 A
  • 8 AWG — 30 A

Even though Table 310.16 lists 14 AWG copper THWN at 20 A (75 °C column) and 12 AWG at 30 A, 240.4(D) caps the OCPD at 15 A and 20 A respectively for these small conductors. The ampacity is not lowered — the OCPD is.

Exceptions to 240.4(D)

The small-conductor cap does not apply to specific equipment whose own article governs overcurrent. The exceptions the exam expects you to know:

Motors — governed by 430 Part III and Part XIII (branch-circuit short-circuit/ground-fault per 430.52, overload per 430.32). A 12 AWG copper conductor feeding a motor can be protected at more than 20 A under 430.52.

Air-conditioning and refrigeration equipment — governed by Article 440. The nameplate MCA and MOCP values control, not 240.4(D).

Electric welders — governed by Article 630. The conductor and OCPD are sized from the welder's rated primary current and duty cycle.

Tap conductors under 240.21.

If a question names a motor, an A/C condenser, or a welder, do not apply 240.4(D). Apply the equipment article.

NEC 240.4(B) — Next-Size-Up Rule

240.4(B) allows the OCPD to be raised to the next higher standard rating when the conductor ampacity does not equal a standard OCPD rating. Two conditions must both be met.

The conductor ampacity does not equal a standard rating listed in 240.6(A).

The next lower standard OCPD rating is the limiting value — i.e., the conductor ampacity falls between two standard ratings, so the next higher standard size is used.

The rule lets you round up one step to the next standard size only. You may never round down, and you may never go more than one step up. Above 800 A, 240.4(B) does not apply — the OCPD rating cannot exceed the conductor ampacity.

Worked Example — 240.4(B)

A feeder is run with 4 AWG copper THWN in a 75 °C raceway. Table 310.16 lists 4 AWG copper at 85 A in the 75 °C column. What is the maximum standard OCPD permitted?

Step 1 — Find the conductor ampacity. 4 AWG Cu THWN, 75 °C column = 85 A.

Step 2 — Check 240.6(A) standard ratings around 85 A. Standard ratings are ... 70, 80, 90, 100 ... 85 A is not a standard rating.

Step 3 — Apply 240.4(B). The conductor ampacity (85 A) falls between 80 A and 90 A. The next higher standard rating above 85 A is 90 A .

Result: The maximum OCPD is 90 A . The 80 A standard breaker is allowed (next lower), but 240.4(B) lets you use a 90 A breaker because 85 A is not standard. You may not go to 100 A — only one step.

When 240.4(B) Does NOT Apply

When the conductor ampacity equals a standard rating — use that rating, no bump.

For equipment rated over 800 A — the OCPD cannot exceed the conductor ampacity.

For small conductors governed by 240.4(D) unless an exception (motor/A/C/welder) applies.

NEC 240.4(A), 240.21 — Tap Rules (Brief)

The general rule in 240.4(A) is that conductors are protected at ampacity. Tap rules in 240.21 allow shorter conductor runs to be sized smaller than the upstream OCPD when physical conditions limit fault duration. The common taps:

10 ft tap (240.21(B)(1)) — tap not less than 1/10 the rating of the upstream OCPD, in a raceway or cable, length not more than 10 ft.

25 ft tap (240.21(B)(2)) — tap not less than 1/3 the rating of the upstream OCPD, length not more than 25 ft, and the tap must terminate in a single set of fuses or breaker sized at not more than the tap ampacity.

Outdoor tap (240.21(B)(5)) — for outdoor line tap, with the OCPD at the building or structure per 225.

For 800 A+ feeders, the high-fault tap rule (240.21(B)(3)) applies, with specific minimum sizes and clearing-time requirements.

Tap rules are exam-relevant in the Calculations part for feeder and service-entrance questions. The 1/10 and 1/3 multipliers are the values to memorize.

Continuous Loads — 125% and the 210.19(A)/210.20(A) Link

A continuous load is defined in Article 100 as a load where the maximum current is expected to continue for 3 hours or more . When a load is continuous, two related rules apply.

210.19(A) — branch-circuit conductors are sized at 125% of the continuous load plus 100% of the noncontinuous load.

210.20(A) — the branch-circuit OCPD is sized at 125% of the continuous load plus 100% of the noncontinuous load.

The 125% factor and the next-size-up rule interact: you compute the OCPD at 125% of the continuous portion, then apply 240.4(B) if that value is not a standard rating. Chapter 6 covers full branch-circuit sizing; the key here is that overcurrent protection for continuous loads is always bumped by the 125% factor before any 240.4(B) adjustment.

Worked Example — Continuous Load + 240.4(B)

A 208 V single-phase branch circuit feeds a continuous load of 56 A . Size the OCPD.

Step 1 — Apply 210.20(A). OCPD = 125% × 56 A = 70 A.

Step 2 — Check 240.6(A). 70 A is a standard rating.

Result: Use a 70 A OCPD. No 240.4(B) bump is needed because 70 A is already standard. If the continuous load had been 60 A, then 125% × 60 = 75 A, which is not standard, and 240.4(B) would let you round up to 80 A .