5.3 The Texas Recordkeeping and Retention Map

Texas Fire Alarm Installer License Exam

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: Texas Insurance Code Chapter 6002 Foundations

1.1 Chapter 6002 Purpose, Scope & Statutory Definitions 1.2 State Preemption and the Limits of Local Regulation 1.3 Commissioner and SFMO Authority; Adopted Standards and Editions 1.4 Activities Not Regulated: The § 6002.155 Exemptions 1.5 Required Device Labels, Listings and Consumer Information

2 Chapter 2: Certificates of Registration and Company Operating Rules

2.1 Registration Certificates: Main Office, Branch Office and Single Station 2.2 Insurance Requirements for Registered Firms 2.3 Business Location, Designated Employee and Vehicle Identification (§ 34.610) 2.4 Ownership Changes, Officer Changes and Revised Certificates

3 Chapter 3: Individual Licenses, Qualifying Tests and Renewal

3.1 The Six Texas Fire Alarm Licenses and What Each May Do 3.2 License Applications, Fingerprinting and Criminal History 3.3 The Qualifying Tests: TFM11, TFM12, TFM13, TFM14 and Their References 3.4 NICET, ESA and Professional Engineer Substitutions 3.5 Fees, the Two-Year Renewal Cycle and Late Renewal 3.6 Training Schools, Instructors and the Residential Technician Course

4 Chapter 4: Texas Field Practice — Installation, Service, Monitoring and Certification

4.1 Sales, Installation and Service Rules (§ 34.616) 4.2 Monitoring Requirements for Registered Firms (§ 34.616(c)) 4.3 The Installation Certificate (SF035) and Its Distribution 4.4 The Three-Stage Installation Inspection (§ 34.618) 4.5 Fire Alarm Plans and Record Drawings (§ 34.619)

5 Chapter 5: Texas Labels, Records and Enforcement

5.1 Installation and Service Labels (§§ 34.620–34.621) 5.2 Inspection/Test, Yellow and Red Labels and Impairment Notice 5.3 The Texas Recordkeeping and Retention Map 5.4 Prohibited Practices, Discipline, Enforcement and Penalties

6 Chapter 6: NFPA 72 Fundamentals, Power, Signals and Pathways

6.1 Identifying the Applicable NFPA Standards for TFM12 6.2 NFPA 72 Scope, Organization & Core Life Safety Definitions 6.3 NFPA 72 Documentation and Personnel Qualifications 6.4 Types of Equipment and Circuits: IDC, NAC, SLC and System Architectures 6.5 Signal Priority, Annunciation and Monitoring Integrity 6.6 Primary & Secondary Power Supply Calculations 6.7 Principles of Electricity and Notification Circuit Voltage Drop 6.8 Initiating & Notification Circuit Pathways (Class A, B, N, X) 6.9 Pathway Survivability, Shared Pathways and Circuit Separation

7 Chapter 7: Initiating Devices and Detection

7.1 Smoke, Heat & Flame Detection Principles & Spacing Rules 7.2 Gas Detection, Carbon Monoxide Detection and Special-Application Devices 7.3 Detector Selection and Environmental Limits 7.4 Duct Smoke Detectors, HVAC Controls & Specialized Sensors 7.5 Manual Fire Alarm Boxes, Waterflow Switches & Supervisory Initiating Devices 7.6 Sprinkler, Suppression and Releasing Service Interface

8 Chapter 8: Notification Appliances, Emergency Communications and Control Functions

8.1 Audible Notification Requirements & Sound Level Standards 8.2 Visible Notification Spacing, Synchronization & Candela Ratings 8.3 Emergency Communications Systems & Mass Notification Integration 8.4 Emergency Control Functions: Elevators, HVAC, Doors and Egress 8.5 Protected Premises Systems and the Sequence of Operation

9 Chapter 9: Wiring Methods, Supervising Stations and Inspection, Testing and Maintenance

9.1 NEC Article 760 Wiring Methods, Cable Classes & Circuit Protection 9.2 NEC Article 300 Wiring Methods and Installation Workmanship 9.3 Supervising Station Monitoring Systems & Signal Transmission Methods 9.4 Public Emergency Alarm Reporting Systems and Auxiliary Systems 9.5 Periodic Inspection, Testing & Impairment Procedures 9.6 System Acceptance Testing, Commissioning & Maintenance Records

5.3 The Texas Recordkeeping and Retention Map

Key Takeaways Explain This Topic AI

Service, maintenance, and testing records must be kept complete for a minimum of two years and made available to the state fire marshal (§ 34.616(d)).

The certifying company's copy of the installation certificate is kept for the life of the system or ten years, whichever occurs first (§ 34.617(2)).

The completed installation inspection form is kept at the licensed firm's office for five years from the date of system certification (§ 34.618).

One- and two-family dwelling drawings are maintained by the installing registered firm for not less than one year after completion of the installation (§ 34.619(f)).

Every registration application includes written authorization for the state fire marshal or a representative to enter, examine, and inspect any premises used by the applicant while engaged in the business (§ 34.613(a)(2)).

Last updated: August 2026

Why This Section Matters

Retention questions look easy until four plausible numbers appear as answer choices. Texas uses one, two, five, and ten years for four different documents, plus two and five years as label dwell times. The only reliable way through is to attach each number to its rule.

1. The Master Retention Table

  • Document or label Rule Period Clock starts Kept by
  • Service, maintenance and testing records § 34.616(d) 2 years minimum — The firm

Installation certificate — company copy § 34.617(2) Life of the system or 10 years, whichever occurs first Completion of installation The certifying company

  • Installation certificate — AHJ copy § 34.617(3) Sent within 10 days Completion of installation The local AHJ
  • Installation certificate — original § 34.617(1) Kept at the site Completion of installation The site
  • Installation inspection form § 34.618 5 years Date of system certification The licensed firm's office

One- and two-family drawings § 34.619(f) Not less than 1 year Completion of the installation The installing registered firm

  • Record drawings § 34.619(c) Provided to the owner and kept current — The owner
  • Exempt-employee lesson plans and annual test results § 34.616(a)(2) Maintained (no fixed term) — The firm
  • Service label in place § 34.621(d) At least 2 years Attachment On the panel
  • Inspection/test label in place § 34.622(f) At least 5 years Attachment On the panel

Yellow / red label in place §§ 34.623(d), 34.624(d) Until corrected and a service label certifies the correction Attachment On the panel

Memory pattern: 1-2-5-10. One year — residential drawings. Two years — service/maintenance/testing records and service labels. Five years — installation inspection forms and inspection/test labels. Ten years (or life of system) — the installation certificate.

2. Availability for Inspection

Three provisions make records reachable by the state:

§ 34.616(d): service, maintenance and testing records "must be available for examination by the state fire marshal or the state fire marshal's representative."

§ 34.617(2): the company's installation certificate copy is retained "for access by the State Fire Marshal's Office."

§ 34.613(a)(2): every registration application must include written authorization permitting the state fire marshal or a representative "to enter, examine, and inspect any premises, building, room, or establishment used by the applicant while engaged in the business" to determine compliance.

That third item is the consent you give at application time — it is why an SFMO investigator does not need a separate warrant to review your job files during a compliance investigation under § 34.625(a).

3. Where the Records Must Live

  • Record Required location
  • Installation inspection form The licensed firm's office (§ 34.618)
  • Installation certificate original The site of installation (§ 34.617(1))
  • Record drawings With the building owner or representative (§ 34.619(c))
  • Plans, manuals and documents Anywhere except inside a fire alarm panel (§ 34.619(e))
  • Certificate of insurance On file in the State Fire Marshal's Office (§ 34.613(a)(5)(B))
  • Business records generally At the firm's physical business location shown on the certificate (§ 34.610(a))
  • 4. Documents Created at Each Job Stage PLANNING -> Signed plans with planner license no. + firm name, address,
  • phone, ACR no. (§ 34.619(b))
  • INSTALLATION -> Inspection form entries at 3 milestones (§ 34.618)
  • Installation label INSIDE the panel cover (§ 34.620)
  • CERTIFICATION -> Installation certificate (SF035): (§ 34.617)
  • original on site
  • AHJ copy within 10 days
  • company copy: life of system or 10 years
  • Record drawings incl. sequence of operation (§ 34.619(c))
  • SERVICE -> Service label, stacked over the previous one (§ 34.621)
  • Service/maintenance/testing records, 2 years (§ 34.616(d))
  • INSPECTION -> Blue inspection/test label after AHJ
  • acceptance for new systems (§ 34.622)
  • DEFICIENCY -> Yellow label + written notice, 5 business days (§ 34.623)
  • Red label + oral now / written next business
  • day (inoperable) or 3 business days (fault) (§ 34.624)
  • 5. Worked Fact Patterns

Pattern A. An SFMO investigator asks a firm for the installation certificate on a system certified 12 years ago. The firm no longer has it.

→ Compliant. Section 34.617(2) requires retention for the life of the system or ten years, whichever occurs first . Ten years occurred first.

Pattern B. The same investigator asks for the installation inspection form for a system certified four years ago, and the firm says it was left with the customer.

→ Non-compliant twice: the form must be kept five years from system certification , and it must be kept at the licensed firm's office .

Pattern C. A firm purges all service tickets after 18 months to save storage.

→ Non-compliant. Section 34.616(d) requires complete records of all service, maintenance and testing for a minimum of two years , available for examination by the state fire marshal.

Pattern D. A firm installed a monitored system in a single-family home 14 months ago and has kept nothing.

→ Non-compliant at the time , but the § 34.619(f) obligation runs not less than one year after completion, so a 14-month-old drawing may lawfully have been discarded — provided the firm actually kept it for the first year and made it available to the owner and AHJ on request during that period.

Pattern E. A technician keeps the record drawings in the firm's server and the panel manual folded inside the panel door.

→ The server copy is fine; the panel storage violates § 34.619(e) .