Study guide
16.1 The Construction Team: Site Management, Trades & Site Visitors
City & Guilds 2365 Level 2 Diploma in Electrical Installations Exam
Track your progress as you read
Finished sections get a check mark.
1 Introduction & Qualification Overview
1.1 About the City & Guilds 2365 Level 2 Qualification 1.2 Study Strategy, Exam Technique & Resource Navigation
2 Health, Safety & Environmental Legislation, Risk Assessment & Permits
2.1 Statutory Framework & Health and Safety Law 2.2 Hazardous Substances, Incident Reporting & Welfare 2.3 Work Equipment, Manual Handling & PPE 2.4 Environmental Legislation, Pollution & Site Waste 2.5 Risk Assessments, Method Statements, Permits to Work & Safety Signs
3 Electrical Safety, Safe Isolation, Site Hazards & Emergencies
3.1 Safe Isolation Procedures & GS38 Compliance 3.2 Electrical Hazards & Electric Shock Physiology 3.3 Fire Safety, Site Supplies & Emergency Response 3.4 Accidents, First Aid, Emergency Procedures & Reporting
4 Working at Height & Access Equipment
4.1 Work at Height Regulations & Risk Management 4.2 Ladders, Stepladders & Podiums 4.3 Mobile Access Towers & Scaffolding Systems
5 Mathematical Principles, Units & Basic Mechanics
5.1 Mathematical Foundations & Transposition for Electricians 5.2 SI Units of Measurement in Electrotechnology 5.3 Basic Mechanics: Force, Work, Power & Mechanical Energy 5.4 Mass, Weight, Levers, Gears & Pulleys
6 Electron Theory, Resistance, Resistivity & DC Circuits
6.1 Resistance, Resistivity & Conductor Dimensions 6.2 Temperature Coefficient of Resistance 6.3 Ohm's Law, Power & Direct Current Calculations 6.4 Series, Parallel & Combination DC Circuits 6.5 Electron Theory, Conductors, Insulators & the Effects of Current
7 Magnetism, Electromagnetism & Transformers
7.1 Magnetic Fields, Flux & Solenoid Properties 7.2 Electromagnetic Induction & Motor/Generator Principles 7.3 Transformer Principles, Construction & Calculations
8 Alternating Current, Three-Phase Systems & Electronic Components
8.1 AC Waveform Generation & Key Values 8.2 AC Circuit Theory: Reactance, Impedance & Power Factor 8.3 Three-Phase Generation, Star-Delta & UK Distribution 8.4 Electronic Components in Electrical Systems
9 Industry Regulations, Technical Information & Drawings
9.1 Electrical Regulations, Standards & Part P 9.2 Electrical Drawings, Diagrams & BS EN 60617 Symbols 9.3 Technical Specifications, Schedules & Environmental Influences
10 Wiring Systems, Cables, Containment & Practical Installation
10.1 Thermoplastic, Armoured & Flexible Cables 10.2 Specialised Cables: MICC & Fire-Performance Cables 10.3 Conduit Systems: Steel & PVC 10.4 Trunking, Cable Tray & Cable Supports 10.5 Unit 204 Practical Skills: Tools, Preparation & Installing Wiring Systems
11 Final Circuits, Protective Devices, Alarm & Control Circuits
11.1 Lighting Circuits & Switching Arrangements 11.2 Power Circuits: Ring Final, Radial & Dedicated Circuits 11.3 Consumer Units, Distribution Boards & Protective Devices 11.4 Alarm, Emergency Lighting, Data & Control Circuits
12 Cable Selection & Structural Installation
12.1 Cable Current-Carrying Capacity & Correction Factors 12.2 Voltage Drop Principles & Calculations 12.3 Structural Integrity & Concealed Cable Routing
13 Supply Systems, Earthing, Shock Protection & Micro-Renewables
13.1 UK Electricity Supply Networks & Distribution 13.2 Earthing System Configurations: TN-S, TN-C-S (PME and PNB) & TT 13.3 Protective Conductors, Bonding & Earth Electrodes 13.4 Automatic Disconnection of Supply (ADS) & Maximum Zs 13.5 Micro-Renewable Energy Technologies
14 Electrical Inspection & Dead Testing Sequence
14.1 Inspection Principles & Testing Safety to GS38 14.2 Continuity Testing: Protective Conductors & Ring Circuits 14.3 Insulation Resistance & Polarity Verification
15 Live Testing, Certification & Handover
15.1 Live Testing: Earth Loop Impedance, PFC & RCD Testing 15.2 Certification, Handover & Commissioning
16 Communicating within Building Services Engineering (Unit 210)
16.1 The Construction Team: Site Management, Trades & Site Visitors 16.2 Information Sources: Legislation, Guidance & Workplace Documents 16.3 Customer Information, Company Policies & Limits of Authority 16.4 Communicating Effectively: Methods, Accessibility & Conflict
16.1 The Construction Team: Site Management, Trades & Site Visitors
Key Takeaways Explain This Topic AI
The site management team in the Unit 210 range includes the architect, project manager or clerk of works, structural engineer, surveyor, building services engineer, quantity surveyor, buyer, estimator, contracts manager and construction manager.
The quantity surveyor measures and values work and variations, the estimator prices work for tenders and quotations, and the buyer orders materials.
Trades such as groundworkers, bricklayers, joiners, plasterers, tilers, heating and ventilating fitters, gas fitters and decorators must be coordinated with electrical first and second fix.
Site visitors include building control inspectors (Building Regulations), water inspectors, HSE inspectors and electrical services inspectors, and they must sign in and follow site rules.
Last updated: October 2026
16.1 The Construction Team: Site Management, Trades & Site Visitors
Unit 210 (Understand how to communicate with others within building services engineering) is a 20-question, 40-minute test. Learning outcome 1 (5 questions) asks you to identify the key roles of the site management team , the people who report to that team, and site visitors . Knowing who does what tells you whom to ask, whom to report to and whose work affects yours.
The Site Management Team
Role What they do Why it matters to the electrician
Architect Designs the building's layout and appearance, prepares drawings and specifications, and may administer the building contract Produces the layout drawings; architect's instructions can change (vary) your work
Project manager Plans and controls the whole project: time, cost, quality and coordination of everyone involved Sets the programme and resolves clashes between trades
Clerk of works The client's on-site inspector, checking workmanship and materials against the drawings and specification Inspects your installation and records any defects for you to put right
Structural engineer Designs foundations, frames, beams and other load-bearing parts of the building Must approve any cutting or drilling of structural members beyond normal limits
Surveyor Measures and assesses land and buildings, sets out the site and reports on the condition of existing buildings Provides surveys, levels and information on existing structures
Building services engineer Designs the mechanical and electrical services: power, lighting, heating, ventilation and water Produces the electrical drawings, schedules and specifications you install from
Quantity surveyor Measures quantities, prepares bills of quantities, and manages costs, valuations and variations Values the work you complete and agrees the cost of changes
Buyer Orders materials and equipment at the best price and arranges deliveries Materials must be ordered in time to keep to the programme
Estimator Calculates the cost of a job (materials, labour and plant) to prepare a tender or quotation Accurate estimates make work profitable for your company
Contracts manager Manages one or more contracts for the contractor, overseeing supervisors, budgets and programmes across sites Your company's link between the site and the office
Construction (site) manager Runs the site day to day: safety, programme, trades, site rules and inductions Gives inductions, site rules and permits, and coordinates access to work areas
People Who Report to the Site Management Team
Sub-contractors : specialist firms employed by the main contractor, such as the electrical contractor, scaffolders and plasterers.
Site supervisor : manages the workforce on a site or part of it.
Trade supervisor : for example the electrical supervisor or chargehand, who allocates the electricians' work and checks its quality.
Trades : the skilled operatives listed below.
Trade What they do Coordination with the electrician
Ground workers Excavation, foundations, drainage and service trenches Lay ducts for incoming supplies and external cables before the ground is closed
Bricklayer Builds walls and blockwork Can build in boxes and conduits as walls go up, which saves chasing later
Joiner (carpenter) Floors, roofs, stud walls, doors and boxing-in Coordinate notching and drilling of joists and studs, and access traps
Plasterer Plastering and dry-lining First fix must be complete (and buried cables checked) before boards and plaster cover them
- Tiler Wall and floor tiling Agree box positions so accessories sit neatly within the tiling
- Electrician Electrical installation, inspection and testing Coordinates with all the others
Heating and ventilating (H&V) fitter Heating, ventilation and air conditioning systems Controls wiring, supplies to plant, and bonding where required
Gas fitter Gas pipework and appliances (must be Gas Safe registered) Keep electrical services apart from gas pipes; main bonding of metallic gas pipes
Decorator Painting and finishing Second fix accessories are usually fitted after decorating, or must be protected
A typical sequence on a new building is shown below. Delays or mistakes by one trade affect every trade that follows, which is why the programme and good communication matter so much.
Loading diagram... Typical Order of Trades on a New Building
Site Visitors
Visitor What they check
Building control inspector (local authority or registered approved inspector) That the work complies with the Building Regulations, including Part P electrical work where it has not been self-certified through a competent person scheme
Water inspector (from the water supplier) That plumbing and water fittings comply with the water fittings regulations, for example backflow prevention
HSE inspector Compliance with health and safety law; they can investigate accidents and serve improvement or prohibition notices
Electrical services inspector The electrical work itself, for example an assessor from a certification body or competent person scheme, or an inspector acting for the client
All visitors must sign in, receive a site induction, wear the required PPE and normally be escorted. Treat them courteously, answer their questions accurately within your knowledge, and refer anything you cannot answer to your supervisor.
The Client and the Principal Contractor
The client commissions and pays for the project. Under CDM 2015 the client appoints a principal designer and a principal contractor on projects with more than one contractor (Section 2.1). The principal contractor plans, manages and coordinates the construction phase, and the electrical contractor usually works for the principal contractor as a sub-contractor.
Tip
Test questions often describe a task and ask which person does it. Remember: the quantity surveyor measures and values, the estimator prices, the buyer orders, the clerk of works inspects for the client, and building control checks the Building Regulations.