4.5 Inspection Methods: The Senses, Verifying Items & IP Classification

City & Guilds 2391-52 Combined Inspection & Testing of Electrical Installations Exam

Track your progress as you read

Finished sections get a check mark.

1 Introduction & Exam Overview

1.1 About the 2391-52 Exam 1.2 How to Use This Guide & Open-Book Exam Strategy

2 Chapter 2: Statutory & Non-Statutory Documents

2.1 Statutory Documents 2.2 Non-Statutory Documents 2.3 Roles, Responsibilities & the Statutory/Non-Statutory Relationship

3 Chapter 3: Certification & Documentation

3.1 The Electrical Installation Certificate (EIC) & Schedules 3.2 The Minor Electrical Installation Works Certificate (MEIWC) 3.3 The Electrical Installation Condition Report (EICR) & Schedules 3.4 Why the Documents Exist: Reasons, Information Needed, Recording & Retention

4 Chapter 4: Initial Verification & Safe Isolation

4.1 Safe Isolation & Safety Management 4.2 Visual Inspection Requirements 4.3 Initial Verification: Requirements & Process 4.4 Additions & Alterations to an Existing Installation 4.5 Inspection Methods: The Senses, Verifying Items & IP Classification

5 Chapter 5: Sequence of Tests & Test Instruments

5.1 The Correct Sequence of Tests 5.2 Test Instruments: Selection, Calibration & Accuracy 5.3 Factors That Affect Test Results & Tests That May Be Unnecessary at Periodic Inspection

6 Chapter 6: Continuity Testing

6.1 Continuity of Protective Conductors (R1+R2) 6.2 Continuity of Ring Final Circuits (r1, rn, r2) 6.3 Main & Supplementary Protective Bonding Continuity

7 Chapter 7: Insulation Resistance & Polarity

7.1 Insulation Resistance Testing 7.2 Polarity Verification 7.3 Verifying SELV, PELV & Electrical Separation

8 Chapter 8: Earth Fault Loop Impedance

8.1 Ze & Zs Measurement 8.2 Zs Limits, Disconnection Times & the 0.8 Rule 8.3 Prospective Fault Current (PFC/PSCC)

9 Chapter 9: RCD & Earth Electrode Testing

9.1 RCD Testing 9.2 Earth Electrode Resistance on TT Systems

10 Chapter 10: Periodic Inspection & EICR Reporting

10.1 Purpose, Scope & Limitations of Periodic Inspection 10.2 Sampling & Extent of Inspection 10.3 Observation Classification Codes C1/C2/C3/FI 10.4 Outcomes, Inspection Intervals & Completing the EICR

11 Chapter 11: Phase Sequence, Functional Testing & Voltage Drop

11.1 Check of Phase Sequence 11.2 Functional Testing 11.3 Verification of Voltage Drop

12 Chapter 12: The 2391-502 Practical Assignment

12.1 The Practical Assignment & Establishing a Safe System of Work 12.2 Carrying Out the Practical: Inspection, Tests, Verification & Documentation

4.5 Inspection Methods: The Senses, Verifying Items & IP Classification

Key Takeaways Explain This Topic AI

Inspection is carried out mainly by sight, supported by touch, smell and hearing; taste is never used, and touch is used only on parts that are safe to handle

On an EIC the schedule of inspections items are marked acceptable or not applicable; on an EICR they carry the observation codes C1, C2, C3, FI, plus LIM for a limitation

At initial verification an unsatisfactory item must be corrected and the affected inspection and tests repeated before the certificate is issued - there is no coding system for new work

At periodic inspection an unsatisfactory item is recorded as a coded observation; the inspector does not normally rectify, but a C1 requires immediate action to make safe

IP2X or IPXXB is the standard for basic protection by an enclosure or barrier; IP4X or IPXXD applies to a readily accessible horizontal top surface

Last updated: August 2026

Inspection Is a Sensory Examination

Assessment criterion 3.3 asks you to describe the appropriate human senses required for a particular inspection . It is a favourite exam item because the answer is short and precise.

Sense What it detects Notes

Sight The great majority of findings: damage, corrosion, missing barriers, incorrect cable type or routing, absent or illegible labelling, poor terminations, signs of overheating, IP degradation The primary sense — inspection is fundamentally a visual activity

Touch Loose accessories, insecure glands and enclosures, warm equipment indicating overload or a high-resistance joint Only on parts that are safe to touch ; the installation should be isolated, and a suspected hot part is checked with the back of the hand or a thermal instrument

Smell Overheated PVC or bakelite, burnt insulation, the sharp smell of ozone from arcing Often the first indication of a fault inside a sealed enclosure

Hearing Arcing or buzzing at a loose terminal, humming from loose laminations, a chattering RCD or contactor Useful on energised switchgear before isolation

Taste is never used. If an exam option offers it, that option is wrong.

Two practical points follow. First, most inspection is carried out with the installation isolated , which is why touch is available at all. Second, several of these senses are only useful before isolation — you cannot hear arcing in a dead board — so a walk-round of the energised installation, made safely and without opening anything, is a legitimate part of the process.

Verifying and Marking Each Item (AC3.2)

Every item on the schedule of inspections has to be resolved to an outcome. How you mark it depends on which document you are producing, and candidates lose marks by carrying the EICR codes onto an EIC.

On an Electrical Installation Certificate

New work either complies or it does not. Each item is marked as acceptable (a tick), or N/A where the item does not apply to this installation — for example supplementary bonding in a location that does not require it. There is no C1, C2, C3 or FI on an EIC. A deficiency is not coded; it is corrected.

On an Electrical Installation Condition Report

The installation already exists, so each item is judged on condition and marked with one of:

  • Mark Meaning
  • Acceptable condition The item was inspected and is satisfactory
  • C1 Danger present — risk of injury
  • C2 Potentially dangerous
  • C3 Improvement recommended
  • FI Further investigation advised
  • N/A The item does not apply to this installation
  • LIM The item was not inspected because of an agreed or operational limitation

LIM is not a pass. It records that the item was not examined, and it must be consistent with the limitations stated on the front of the report. Marking an item acceptable when it was never seen is a serious reporting failure. The coding system itself is covered in detail in section 10.3.